CN106167229B - A kind of construction method of the underwater pipeline of dredging of marine lifting - Google Patents

A kind of construction method of the underwater pipeline of dredging of marine lifting Download PDF

Info

Publication number
CN106167229B
CN106167229B CN201610465425.9A CN201610465425A CN106167229B CN 106167229 B CN106167229 B CN 106167229B CN 201610465425 A CN201610465425 A CN 201610465425A CN 106167229 B CN106167229 B CN 106167229B
Authority
CN
China
Prior art keywords
pipeline
lifting
rope
lifting rope
initiating terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610465425.9A
Other languages
Chinese (zh)
Other versions
CN106167229A (en
Inventor
李兴建
马闯
邹锋
苑放
张岩
秦飞
包胜利
张鹏
余迪
闫志生
岳吉双
孙永奎
王兴博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Tianjin Harbour Engineering Co Ltd
Original Assignee
CCCC Tianjin Harbour Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Tianjin Harbour Engineering Co Ltd filed Critical CCCC Tianjin Harbour Engineering Co Ltd
Priority to CN201610465425.9A priority Critical patent/CN106167229B/en
Publication of CN106167229A publication Critical patent/CN106167229A/en
Application granted granted Critical
Publication of CN106167229B publication Critical patent/CN106167229B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • B66C1/16Slings with load-engaging platforms or frameworks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

The present invention relates to a kind of construction methods of the marine underwater pipeline of dredging of lifting, include the following steps:1), the ponding of remaining in-line is discharged using air compressor, makes pipeline interior full of air;2) lantern ring, is set in the initiating terminal of pipeline lifting, lantern ring connects single lifting rope;3), every piece auxiliary rope of 5~8m systems on lifting rope, the auxiliary rope other end is ined succession buoy;4), the lifting equipment of the other end connection anchor ship of lifting rope;5), anchor ship moves ahead a distance along the initiating terminal that pipeline lifts by crane, make lifting rope with pipeline shape in an angle;6) anchor ship, is at the uniform velocity opened, lifting rope cuts the mud layer on pipeline top, and mud groove pours into seawater, and the pipeline full of air is emerged by the buoyancy of seawater;7), after pipeline emerges completely, pipeline is drawn to the lifting operation on the bank, completing pipeline using equipment on the bank.This construction method construction is simple improves working efficiency, reduces labor intensity and pipeline is protected not to be damaged.

Description

A kind of construction method of the underwater pipeline of dredging of marine lifting
Technical field
The invention belongs to dredging and reclamation technical field, a kind of construction parties for pipeline of dredging under water more particularly to marine lifting Method
Background technology
At present, Dredger Filling Engineering is constructed, the long-term aerial drainage of discharge opening, covers thick layer silt above pipeline under water Mud, hardened through precipitation after a period of time, the soil body forms some strength, cause underwater line can not with normal mode by its Act the water surface.
Existing construction method, being inflated using air compressor machine makes underwater immersed tube float, then the underwater line floated is hauled out and is applied Work waters.After this method failure is implemented, begin to take on what the underwater immersed tube cooperation of station keeping ship system lifting rope auxiliary lifting was inflated Method, concrete operations are as follows:
1st, it is first inflated using air compressor machine and excludes totally, to make to be filled by air in the depot siding by the underwater immersed tube internal water accumulation of the section It is full;
2nd, a lifting rope is worn in its pole-climbing with a station keeping ship, after forming lock tube, is inserted in from the origin or beginning of underwater line The underwater line hoists lifting rope by motor on station keeping ship, makes to drag underwater line thereon.
The reason of such operating mode underground pipelines can not normally rise out is analyzed, native thick soil is larger, and blank pipe line is silted mud drum first, burying It encloses, without buoyancy;Second is that the soil body is hardened by precipitating for a long time, certain shearing strength is formed, integral strength is more than Pipeline bears intensity, and lifting process is easily destroyed pipeline, cause pipeline that cannot reuse.
However, after being operated using the method that above-mentioned routine plays underwater line, preferable effect is not obtained.Through excessive Analysis finds that main problem is as follows:
1st, covering mud layer is silt clay, and thickness is thicker, and the ballast above pipeline is excessive, and only input quantity is limited Station keeping ship lifting strength is not enough to sling underwater line;
2nd, it cannot effectively slide to and lock the end of next group of pipeline on station keeping ship or anchor ship by dead weight with lifting rope, cause Make station keeping ship during lifting, it is excessively high that upper one group of free end of pipeline acts the water surface, there are disconnected cable, touches and pounds the risk of ship machine, fixed Position ship dare not be lifted by crane, therefore there are some potential safety problemss with excessive strand power;
3rd, the fracture of disconnected or flange port is easily hung in gum cover position by excessive power of hanging, and prevents pipeline or gum cover from repeating profit With, and lifting rope rises and easily sludge discharge pipeline tube body and flange port is caused to scratch when dragging, and influences the follow-up use of pipeline;;
Once the 4th, the huge station keeping ship of input quantity, one side chartering is of high cost, on the other hand during the construction of this kind of method Between long, inefficiency.
Invention content
The present invention for solve known technology present in technical problem provide a kind of construction is simple, raising working efficiency, Reduce the marine construction method for lifting by crane pipeline of dredging under water of labor intensity, protection pipeline.
The present invention is adopted the technical scheme that solve technical problem present in known technology:
A kind of construction method of the underwater pipeline of dredging of marine lifting, it is characterised in that:The construction method includes the following steps:
1) initiating terminal of lifting, is set according to line layout position first;It will be remaining using air compressor in initiating terminal The ponding of in-line is discharged, and makes pipeline interior full of air, and is sealed the both ends of pipeline using plug members;
2) lantern ring, is set in the initiating terminal of pipeline lifting, sheath, the lantern ring connection are enclosed with outside the lantern ring Single lifting rope;
3) it, for the specific location of this clear and definite lifting rope, avoids and closes on the interference of dock vessels anchor hawser, lifting rope is from pipeline After initiating terminal extension certain distance, every piece auxiliary rope of 5~8m systems, the auxiliary rope other end is ined succession buoy, in the appearance of buoy Smear fluorescent material in face;
4), the lifting equipment of the other end connection anchor ship of the lifting rope;
5), the anchor ship moves ahead a distance along the initiating terminal that pipeline lifts by crane, and ensures that lifting rope forms one with pipeline Angle;
6) anchor ship, is at the uniform velocity opened, pipeline is lifted by crane using the lifting equipment of anchor ship, lifting rope is by the mud on pipeline top Layer is cut, and forms open mud groove, pipeline is detached with mud layer, with the traveling of anchor ship, seawater is along the mud groove of cutting It pours into, makes buoyancy of the pipeline full of air by seawater, pipeline emerges;
7), after pipeline emerges completely, pipeline is drawn to the lifting on the bank, completing pipeline using equipment on the bank Operation.
The invention has the advantages and positive effects that:Since the present invention is using above-mentioned technical proposal, has the following advantages:
1st, existing anchor ship or station keeping ship simply reequip, easy for construction, improvement expenses are low, and the time is short, Material therefor saves, easy to operate.
2nd, lifting rope is connected into lantern ring, protection pipeline surface and pipeline link can be played when cutting the soil body below pipeline The effect of flange protects tube body, improves secondary service efficiency;
3rd, this lifting rope is a plastic ties every 5 meters after extension certain distance at pipeline, and the plastic ties other end is ined succession Buoy, buoy are smeared by fluorescent material, on the one hand can instruct to carry on construction work at night, on the other hand in the construction process by indicating Lifting rope position can effectively avoid the interference of the objects such as underwater cable, improve construction efficiency, reduce unnecessary time loss.
4th, it is original using directly lifting by crane by the way of can not normally by pipeline mud extraction face, thereby result in largely by buried pipeline without Method secondary use causes great waste.And use after this construction method by effectively changing soil structures, make pipeline all Soil strength reduction is enclosed, then can pass through using conventional method, sludge discharge pipeline is made smoothly to rise out and is transported.
5th, entire cutting soil process does not have to pipeline is allowed to bear larger pulling force, especially to sebific duct, reduces pipeline and breaks Bad probability falls below also in work progress security risk minimum, has greatly enhanced the efficiency and pipeline of pipeline Recovery utilization rate.
Description of the drawings
Fig. 1 is constructing structure schematic diagram of the present invention;
Fig. 2 is buoy setting structure schematic diagram;
Fig. 3 is lantern ring and lifting rope attachment structure schematic diagram.
In figure:1st, pipeline;2nd, lantern ring;2-1, sheath;3rd, lifting rope;4th, anchor ship;5th, auxiliary rope;6th, buoy.
Specific embodiment
In order to further understand the content, features and effects of the present invention, the following examples are hereby given, and coordinate attached drawing Detailed description are as follows:
It please refers to Fig.1 to Fig.3, a kind of construction method of the marine underwater pipeline of dredging of lifting, which includes as follows Step:
1) initiating terminal of lifting, is set according to 1 installation position of pipeline first;It will be residual using air compressor in initiating terminal The ponding for depositing in-line is discharged, and makes pipeline interior full of air, and is sealed the both ends of pipeline using plug members;
2) lantern ring 2, is set in the initiating terminal of pipeline lifting, sheath 2-1, the lantern ring are enclosed with outside the lantern ring Connect single lifting rope 3;
3) it, for the specific location of this clear and definite lifting rope, avoids and closes on the interference of dock vessels anchor hawser, lifting rope is from pipeline After initiating terminal extension certain distance, every piece auxiliary rope of 5~8m systems, 5 other end of auxiliary rope is ined succession buoy 6, in the outer of buoy Surface smear fluorescent material;
4), the lifting equipment of the other end connection anchor ship 4 of the lifting rope;
5), the anchor ship moves ahead a distance along the initiating terminal that pipeline lifts by crane, and ensures that lifting rope forms one with pipeline Angle;
6) anchor ship, is at the uniform velocity opened, pipeline is lifted by crane using the lifting equipment of anchor ship, lifting rope is by the mud on pipeline top Layer is cut, and forms open mud groove, pipeline is detached with mud layer, with the traveling of anchor ship, seawater is along the mud groove of cutting It pours into, makes buoyancy of the pipeline full of air by seawater, pipeline emerges;
7), after pipeline emerges completely, pipeline is drawn to the lifting on the bank, completing pipeline using equipment on the bank Operation.
Using above-mentioned technical proposal, has the following advantages:
1st, existing anchor ship or station keeping ship simply reequip, easy for construction, improvement expenses are low, and the time is short, Material therefor saves, easy to operate.
2nd, lifting rope is connected into lantern ring, protection pipeline surface and pipeline link can be played when cutting the soil body below pipeline The effect of flange protects tube body, improves secondary service efficiency;
3rd, this lifting rope is a plastic ties every 5 meters after extension certain distance at pipeline, and the plastic ties other end is ined succession Buoy, buoy are smeared by fluorescent material, on the one hand can instruct to carry on construction work at night, on the other hand in the construction process by indicating Lifting rope position can effectively avoid the interference of the objects such as underwater cable, improve construction efficiency, reduce unnecessary time loss.
4th, it is original using directly lifting by crane by the way of can not normally by pipeline mud extraction face, thereby result in largely by buried pipeline without Method secondary use causes great waste.And use after this construction method by effectively changing soil structures, make pipeline all Soil strength reduction is enclosed, then can pass through using conventional method, sludge discharge pipeline is made smoothly to rise out and is transported.
5th, entire cutting soil process does not have to pipeline is allowed to bear larger pulling force, especially to sebific duct, reduces pipeline and breaks Bad probability falls below also in work progress security risk minimum, has greatly enhanced the efficiency and pipeline of pipeline Recovery utilization rate.
The above is only the preferred embodiments of the present invention, and not makees limitation in any form to the present invention, Any simple modification made to the above embodiment of every technical spirit according to the present invention, equivalent variations and modification, belong to In the range of technical solution of the present invention.

Claims (1)

  1. The construction method of pipeline 1. a kind of marine lifting is dredged under water, it is characterised in that:The construction method includes the following steps:
    1) initiating terminal of lifting, is set according to line layout position first;In initiating terminal pipe will be remained in using air compressor Ponding in line is discharged, and makes pipeline interior full of air, and is sealed the both ends of pipeline using plug members;
    2) lantern ring, is set in the initiating terminal of pipeline lifting, sheath is enclosed with outside the lantern ring, the lantern ring connection is single Lifting rope;
    3) it, for the specific location of this clear and definite lifting rope, avoids and closes on the interference of dock vessels anchor hawser, lifting rope is originated from pipeline After holding extension certain distance, every piece auxiliary rope of 5~8m systems, the auxiliary rope other end is ined succession buoy, is applied in the outer surface of buoy Smear fluorescent material;
    4), the lifting equipment of the other end connection anchor ship of the lifting rope;
    5), the anchor ship moves ahead a distance along the initiating terminal that pipeline lifts by crane, and ensures lifting rope with pipeline shape in an angle;
    6), at the uniform velocity open anchor ship, pipeline is lifted by crane using the lifting equipment of anchor ship, lifting rope by the mud layer on pipeline top into Row cutting, forms open mud groove, pipeline is detached with mud layer, and with the traveling of anchor ship, seawater is poured into along the mud groove of cutting, Make buoyancy of the pipeline full of air by seawater, pipeline emerges;
    7), after pipeline emerges completely, pipeline is drawn to the lifting on the bank, completing pipeline using equipment on the bank and is made Industry.
CN201610465425.9A 2016-06-21 2016-06-21 A kind of construction method of the underwater pipeline of dredging of marine lifting Active CN106167229B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610465425.9A CN106167229B (en) 2016-06-21 2016-06-21 A kind of construction method of the underwater pipeline of dredging of marine lifting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610465425.9A CN106167229B (en) 2016-06-21 2016-06-21 A kind of construction method of the underwater pipeline of dredging of marine lifting

Publications (2)

Publication Number Publication Date
CN106167229A CN106167229A (en) 2016-11-30
CN106167229B true CN106167229B (en) 2018-06-08

Family

ID=58064814

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610465425.9A Active CN106167229B (en) 2016-06-21 2016-06-21 A kind of construction method of the underwater pipeline of dredging of marine lifting

Country Status (1)

Country Link
CN (1) CN106167229B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109707911A (en) * 2019-01-17 2019-05-03 中交天航滨海环保浚航工程有限公司 A kind of underwater line sea traction construction

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB942218A (en) * 1960-04-09 1963-11-20 Electricite De France Improvements in or relating to the positioning or laying of submarine tubes
FR2461181B1 (en) * 1979-07-06 1985-10-04 Serra Freres Entr Sa ROLLING FLOAT DEVICE FOR SUBSEA PIPES
CN86108852A (en) * 1985-12-06 1987-10-28 斯纳姆普罗吉蒂公司 Large-scale underwater line, from the land phreatic method
EP1022501A1 (en) * 1999-01-21 2000-07-26 J.Ray McDermott, S.A. Marine pipeline installation method and apparatus
CN1589354A (en) * 2001-10-02 2005-03-02 全球海运业系统有限公司 Cable or pipe retrieval and burial apparatus and methods
CN1934332A (en) * 2004-03-16 2007-03-21 泰克尼普法国公司 Method and system for starting up a pipeline
CN102140803A (en) * 2010-02-02 2011-08-03 孔赟荣 Method for paving oil, gas and water pipelines by using water floating process
CN102454828A (en) * 2010-10-29 2012-05-16 中国海洋石油总公司 Pipeline recycling and discarding technology in deepwater S-shaped submarine pipeline laying process
CN102588675A (en) * 2012-03-14 2012-07-18 中国海洋石油总公司 Method for protectively recovering flexible tube from deep water
CN102667285A (en) * 2009-09-25 2012-09-12 塞彭公司 Hoisting method and assembly for abandoning and/or recovering an underwater pipeline from a laying vessel, and laying vessel equipped with such a hoisting assembly
CN103443518A (en) * 2011-03-21 2013-12-11 塞彭公司 A/r method and apparatus therefor
CN203686355U (en) * 2014-01-07 2014-07-02 中国海洋石油总公司 Submarine pipeline pipe abandoning, recycling and connecting device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3559413A (en) * 1968-02-07 1971-02-02 Pan American Petroleum Corp Adjustable stinger for use in laying pipeline in water covered areas
FR2790054B1 (en) * 1999-02-19 2001-05-25 Bouygues Offshore METHOD AND DEVICE FOR LOW-SURFACE LINKAGE BY SUBMARINE PIPELINE INSTALLED WITH LARGE DEPTH

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB942218A (en) * 1960-04-09 1963-11-20 Electricite De France Improvements in or relating to the positioning or laying of submarine tubes
FR2461181B1 (en) * 1979-07-06 1985-10-04 Serra Freres Entr Sa ROLLING FLOAT DEVICE FOR SUBSEA PIPES
CN86108852A (en) * 1985-12-06 1987-10-28 斯纳姆普罗吉蒂公司 Large-scale underwater line, from the land phreatic method
EP1022501A1 (en) * 1999-01-21 2000-07-26 J.Ray McDermott, S.A. Marine pipeline installation method and apparatus
CN1589354A (en) * 2001-10-02 2005-03-02 全球海运业系统有限公司 Cable or pipe retrieval and burial apparatus and methods
CN1934332A (en) * 2004-03-16 2007-03-21 泰克尼普法国公司 Method and system for starting up a pipeline
CN102667285A (en) * 2009-09-25 2012-09-12 塞彭公司 Hoisting method and assembly for abandoning and/or recovering an underwater pipeline from a laying vessel, and laying vessel equipped with such a hoisting assembly
CN102140803A (en) * 2010-02-02 2011-08-03 孔赟荣 Method for paving oil, gas and water pipelines by using water floating process
CN102454828A (en) * 2010-10-29 2012-05-16 中国海洋石油总公司 Pipeline recycling and discarding technology in deepwater S-shaped submarine pipeline laying process
CN103443518A (en) * 2011-03-21 2013-12-11 塞彭公司 A/r method and apparatus therefor
CN102588675A (en) * 2012-03-14 2012-07-18 中国海洋石油总公司 Method for protectively recovering flexible tube from deep water
CN203686355U (en) * 2014-01-07 2014-07-02 中国海洋石油总公司 Submarine pipeline pipe abandoning, recycling and connecting device

Also Published As

Publication number Publication date
CN106167229A (en) 2016-11-30

Similar Documents

Publication Publication Date Title
CN107339111B (en) The floating construction method of installation of more PE pipes in large-scale push pipe
CN102454176B (en) Sand fetching construction device
CN106337971B (en) A kind of buoyancy can be changed buoyancy tank and its application
CN103507109A (en) Underwater dry type cutting cabin and application method thereof
CN106167229B (en) A kind of construction method of the underwater pipeline of dredging of marine lifting
CN111636502A (en) Sand mining construction process based on cutter suction dredger
CN104975612A (en) Novel water open caisson construction technology
CN102758462A (en) Stem punching device for self-propelled trailing suction hopper dredgers and construction method thereof
CN101736706A (en) Underwater cutting construction method of low-pile bearing platform
CN106005312A (en) Underwater operation device for micro-tunnel excavation based on remote operated vehicle (ROV) and operation method thereof
CN204080839U (en) A kind of Yield rainfall relation device
CN202787354U (en) Self-propelled trailing suction dredger bow thrust device
CN106704705B (en) overwater pipeline assembling operation method and system
CN205707227U (en) The underwater working device of micro-tunneling is opened based on ROV
CN205873671U (en) Rings that rise of pipeline of dredging are lifted by crane under water at sea
CN206232308U (en) A kind of marine hoisting component for lifting by crane pipeline of dredging under water
CN205101675U (en) Long distance submarine pipe line is pipe laying construction system after ditching in advance
CN108005659B (en) A kind of diving excavation construction method for the construction of city vertical shaft
CN101509265A (en) Pull-type soil shifter smoothing technique for soft foundation field and pull-type soil shifter
CN205532599U (en) Ocean mining ship with device is refuted to dress
CN212294953U (en) Multi-functional environmental protection waterproof construction
CN105350592B (en) Big flow twists suction ship bull energy dissipating dress and refutes device
CN209353399U (en) A kind of band draws the pipe-line transportation system of slope structure
CN203996790U (en) Cable wire guiding, location sand pump dredger wet excavation system
CN105926679A (en) Dismounting method for pipe joints of immersed tube tunnel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant