CN106167229B - A kind of construction method of the underwater pipeline of dredging of marine lifting - Google Patents
A kind of construction method of the underwater pipeline of dredging of marine lifting Download PDFInfo
- Publication number
- CN106167229B CN106167229B CN201610465425.9A CN201610465425A CN106167229B CN 106167229 B CN106167229 B CN 106167229B CN 201610465425 A CN201610465425 A CN 201610465425A CN 106167229 B CN106167229 B CN 106167229B
- Authority
- CN
- China
- Prior art keywords
- pipeline
- lifting
- rope
- lifting rope
- initiating terminal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
- B66C1/16—Slings with load-engaging platforms or frameworks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
The present invention relates to a kind of construction methods of the marine underwater pipeline of dredging of lifting, include the following steps:1), the ponding of remaining in-line is discharged using air compressor, makes pipeline interior full of air;2) lantern ring, is set in the initiating terminal of pipeline lifting, lantern ring connects single lifting rope;3), every piece auxiliary rope of 5~8m systems on lifting rope, the auxiliary rope other end is ined succession buoy;4), the lifting equipment of the other end connection anchor ship of lifting rope;5), anchor ship moves ahead a distance along the initiating terminal that pipeline lifts by crane, make lifting rope with pipeline shape in an angle;6) anchor ship, is at the uniform velocity opened, lifting rope cuts the mud layer on pipeline top, and mud groove pours into seawater, and the pipeline full of air is emerged by the buoyancy of seawater;7), after pipeline emerges completely, pipeline is drawn to the lifting operation on the bank, completing pipeline using equipment on the bank.This construction method construction is simple improves working efficiency, reduces labor intensity and pipeline is protected not to be damaged.
Description
Technical field
The invention belongs to dredging and reclamation technical field, a kind of construction parties for pipeline of dredging under water more particularly to marine lifting
Method
Background technology
At present, Dredger Filling Engineering is constructed, the long-term aerial drainage of discharge opening, covers thick layer silt above pipeline under water
Mud, hardened through precipitation after a period of time, the soil body forms some strength, cause underwater line can not with normal mode by its
Act the water surface.
Existing construction method, being inflated using air compressor machine makes underwater immersed tube float, then the underwater line floated is hauled out and is applied
Work waters.After this method failure is implemented, begin to take on what the underwater immersed tube cooperation of station keeping ship system lifting rope auxiliary lifting was inflated
Method, concrete operations are as follows:
1st, it is first inflated using air compressor machine and excludes totally, to make to be filled by air in the depot siding by the underwater immersed tube internal water accumulation of the section
It is full;
2nd, a lifting rope is worn in its pole-climbing with a station keeping ship, after forming lock tube, is inserted in from the origin or beginning of underwater line
The underwater line hoists lifting rope by motor on station keeping ship, makes to drag underwater line thereon.
The reason of such operating mode underground pipelines can not normally rise out is analyzed, native thick soil is larger, and blank pipe line is silted mud drum first, burying
It encloses, without buoyancy;Second is that the soil body is hardened by precipitating for a long time, certain shearing strength is formed, integral strength is more than
Pipeline bears intensity, and lifting process is easily destroyed pipeline, cause pipeline that cannot reuse.
However, after being operated using the method that above-mentioned routine plays underwater line, preferable effect is not obtained.Through excessive
Analysis finds that main problem is as follows:
1st, covering mud layer is silt clay, and thickness is thicker, and the ballast above pipeline is excessive, and only input quantity is limited
Station keeping ship lifting strength is not enough to sling underwater line;
2nd, it cannot effectively slide to and lock the end of next group of pipeline on station keeping ship or anchor ship by dead weight with lifting rope, cause
Make station keeping ship during lifting, it is excessively high that upper one group of free end of pipeline acts the water surface, there are disconnected cable, touches and pounds the risk of ship machine, fixed
Position ship dare not be lifted by crane, therefore there are some potential safety problemss with excessive strand power;
3rd, the fracture of disconnected or flange port is easily hung in gum cover position by excessive power of hanging, and prevents pipeline or gum cover from repeating profit
With, and lifting rope rises and easily sludge discharge pipeline tube body and flange port is caused to scratch when dragging, and influences the follow-up use of pipeline;;
Once the 4th, the huge station keeping ship of input quantity, one side chartering is of high cost, on the other hand during the construction of this kind of method
Between long, inefficiency.
Invention content
The present invention for solve known technology present in technical problem provide a kind of construction is simple, raising working efficiency,
Reduce the marine construction method for lifting by crane pipeline of dredging under water of labor intensity, protection pipeline.
The present invention is adopted the technical scheme that solve technical problem present in known technology:
A kind of construction method of the underwater pipeline of dredging of marine lifting, it is characterised in that:The construction method includes the following steps:
1) initiating terminal of lifting, is set according to line layout position first;It will be remaining using air compressor in initiating terminal
The ponding of in-line is discharged, and makes pipeline interior full of air, and is sealed the both ends of pipeline using plug members;
2) lantern ring, is set in the initiating terminal of pipeline lifting, sheath, the lantern ring connection are enclosed with outside the lantern ring
Single lifting rope;
3) it, for the specific location of this clear and definite lifting rope, avoids and closes on the interference of dock vessels anchor hawser, lifting rope is from pipeline
After initiating terminal extension certain distance, every piece auxiliary rope of 5~8m systems, the auxiliary rope other end is ined succession buoy, in the appearance of buoy
Smear fluorescent material in face;
4), the lifting equipment of the other end connection anchor ship of the lifting rope;
5), the anchor ship moves ahead a distance along the initiating terminal that pipeline lifts by crane, and ensures that lifting rope forms one with pipeline
Angle;
6) anchor ship, is at the uniform velocity opened, pipeline is lifted by crane using the lifting equipment of anchor ship, lifting rope is by the mud on pipeline top
Layer is cut, and forms open mud groove, pipeline is detached with mud layer, with the traveling of anchor ship, seawater is along the mud groove of cutting
It pours into, makes buoyancy of the pipeline full of air by seawater, pipeline emerges;
7), after pipeline emerges completely, pipeline is drawn to the lifting on the bank, completing pipeline using equipment on the bank
Operation.
The invention has the advantages and positive effects that:Since the present invention is using above-mentioned technical proposal, has the following advantages:
1st, existing anchor ship or station keeping ship simply reequip, easy for construction, improvement expenses are low, and the time is short,
Material therefor saves, easy to operate.
2nd, lifting rope is connected into lantern ring, protection pipeline surface and pipeline link can be played when cutting the soil body below pipeline
The effect of flange protects tube body, improves secondary service efficiency;
3rd, this lifting rope is a plastic ties every 5 meters after extension certain distance at pipeline, and the plastic ties other end is ined succession
Buoy, buoy are smeared by fluorescent material, on the one hand can instruct to carry on construction work at night, on the other hand in the construction process by indicating
Lifting rope position can effectively avoid the interference of the objects such as underwater cable, improve construction efficiency, reduce unnecessary time loss.
4th, it is original using directly lifting by crane by the way of can not normally by pipeline mud extraction face, thereby result in largely by buried pipeline without
Method secondary use causes great waste.And use after this construction method by effectively changing soil structures, make pipeline all
Soil strength reduction is enclosed, then can pass through using conventional method, sludge discharge pipeline is made smoothly to rise out and is transported.
5th, entire cutting soil process does not have to pipeline is allowed to bear larger pulling force, especially to sebific duct, reduces pipeline and breaks
Bad probability falls below also in work progress security risk minimum, has greatly enhanced the efficiency and pipeline of pipeline
Recovery utilization rate.
Description of the drawings
Fig. 1 is constructing structure schematic diagram of the present invention;
Fig. 2 is buoy setting structure schematic diagram;
Fig. 3 is lantern ring and lifting rope attachment structure schematic diagram.
In figure:1st, pipeline;2nd, lantern ring;2-1, sheath;3rd, lifting rope;4th, anchor ship;5th, auxiliary rope;6th, buoy.
Specific embodiment
In order to further understand the content, features and effects of the present invention, the following examples are hereby given, and coordinate attached drawing
Detailed description are as follows:
It please refers to Fig.1 to Fig.3, a kind of construction method of the marine underwater pipeline of dredging of lifting, which includes as follows
Step:
1) initiating terminal of lifting, is set according to 1 installation position of pipeline first;It will be residual using air compressor in initiating terminal
The ponding for depositing in-line is discharged, and makes pipeline interior full of air, and is sealed the both ends of pipeline using plug members;
2) lantern ring 2, is set in the initiating terminal of pipeline lifting, sheath 2-1, the lantern ring are enclosed with outside the lantern ring
Connect single lifting rope 3;
3) it, for the specific location of this clear and definite lifting rope, avoids and closes on the interference of dock vessels anchor hawser, lifting rope is from pipeline
After initiating terminal extension certain distance, every piece auxiliary rope of 5~8m systems, 5 other end of auxiliary rope is ined succession buoy 6, in the outer of buoy
Surface smear fluorescent material;
4), the lifting equipment of the other end connection anchor ship 4 of the lifting rope;
5), the anchor ship moves ahead a distance along the initiating terminal that pipeline lifts by crane, and ensures that lifting rope forms one with pipeline
Angle;
6) anchor ship, is at the uniform velocity opened, pipeline is lifted by crane using the lifting equipment of anchor ship, lifting rope is by the mud on pipeline top
Layer is cut, and forms open mud groove, pipeline is detached with mud layer, with the traveling of anchor ship, seawater is along the mud groove of cutting
It pours into, makes buoyancy of the pipeline full of air by seawater, pipeline emerges;
7), after pipeline emerges completely, pipeline is drawn to the lifting on the bank, completing pipeline using equipment on the bank
Operation.
Using above-mentioned technical proposal, has the following advantages:
1st, existing anchor ship or station keeping ship simply reequip, easy for construction, improvement expenses are low, and the time is short,
Material therefor saves, easy to operate.
2nd, lifting rope is connected into lantern ring, protection pipeline surface and pipeline link can be played when cutting the soil body below pipeline
The effect of flange protects tube body, improves secondary service efficiency;
3rd, this lifting rope is a plastic ties every 5 meters after extension certain distance at pipeline, and the plastic ties other end is ined succession
Buoy, buoy are smeared by fluorescent material, on the one hand can instruct to carry on construction work at night, on the other hand in the construction process by indicating
Lifting rope position can effectively avoid the interference of the objects such as underwater cable, improve construction efficiency, reduce unnecessary time loss.
4th, it is original using directly lifting by crane by the way of can not normally by pipeline mud extraction face, thereby result in largely by buried pipeline without
Method secondary use causes great waste.And use after this construction method by effectively changing soil structures, make pipeline all
Soil strength reduction is enclosed, then can pass through using conventional method, sludge discharge pipeline is made smoothly to rise out and is transported.
5th, entire cutting soil process does not have to pipeline is allowed to bear larger pulling force, especially to sebific duct, reduces pipeline and breaks
Bad probability falls below also in work progress security risk minimum, has greatly enhanced the efficiency and pipeline of pipeline
Recovery utilization rate.
The above is only the preferred embodiments of the present invention, and not makees limitation in any form to the present invention,
Any simple modification made to the above embodiment of every technical spirit according to the present invention, equivalent variations and modification, belong to
In the range of technical solution of the present invention.
Claims (1)
- The construction method of pipeline 1. a kind of marine lifting is dredged under water, it is characterised in that:The construction method includes the following steps:1) initiating terminal of lifting, is set according to line layout position first;In initiating terminal pipe will be remained in using air compressor Ponding in line is discharged, and makes pipeline interior full of air, and is sealed the both ends of pipeline using plug members;2) lantern ring, is set in the initiating terminal of pipeline lifting, sheath is enclosed with outside the lantern ring, the lantern ring connection is single Lifting rope;3) it, for the specific location of this clear and definite lifting rope, avoids and closes on the interference of dock vessels anchor hawser, lifting rope is originated from pipeline After holding extension certain distance, every piece auxiliary rope of 5~8m systems, the auxiliary rope other end is ined succession buoy, is applied in the outer surface of buoy Smear fluorescent material;4), the lifting equipment of the other end connection anchor ship of the lifting rope;5), the anchor ship moves ahead a distance along the initiating terminal that pipeline lifts by crane, and ensures lifting rope with pipeline shape in an angle;6), at the uniform velocity open anchor ship, pipeline is lifted by crane using the lifting equipment of anchor ship, lifting rope by the mud layer on pipeline top into Row cutting, forms open mud groove, pipeline is detached with mud layer, and with the traveling of anchor ship, seawater is poured into along the mud groove of cutting, Make buoyancy of the pipeline full of air by seawater, pipeline emerges;7), after pipeline emerges completely, pipeline is drawn to the lifting on the bank, completing pipeline using equipment on the bank and is made Industry.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610465425.9A CN106167229B (en) | 2016-06-21 | 2016-06-21 | A kind of construction method of the underwater pipeline of dredging of marine lifting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610465425.9A CN106167229B (en) | 2016-06-21 | 2016-06-21 | A kind of construction method of the underwater pipeline of dredging of marine lifting |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106167229A CN106167229A (en) | 2016-11-30 |
CN106167229B true CN106167229B (en) | 2018-06-08 |
Family
ID=58064814
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610465425.9A Active CN106167229B (en) | 2016-06-21 | 2016-06-21 | A kind of construction method of the underwater pipeline of dredging of marine lifting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106167229B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109707911A (en) * | 2019-01-17 | 2019-05-03 | 中交天航滨海环保浚航工程有限公司 | A kind of underwater line sea traction construction |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB942218A (en) * | 1960-04-09 | 1963-11-20 | Electricite De France | Improvements in or relating to the positioning or laying of submarine tubes |
FR2461181B1 (en) * | 1979-07-06 | 1985-10-04 | Serra Freres Entr Sa | ROLLING FLOAT DEVICE FOR SUBSEA PIPES |
CN86108852A (en) * | 1985-12-06 | 1987-10-28 | 斯纳姆普罗吉蒂公司 | Large-scale underwater line, from the land phreatic method |
EP1022501A1 (en) * | 1999-01-21 | 2000-07-26 | J.Ray McDermott, S.A. | Marine pipeline installation method and apparatus |
CN1589354A (en) * | 2001-10-02 | 2005-03-02 | 全球海运业系统有限公司 | Cable or pipe retrieval and burial apparatus and methods |
CN1934332A (en) * | 2004-03-16 | 2007-03-21 | 泰克尼普法国公司 | Method and system for starting up a pipeline |
CN102140803A (en) * | 2010-02-02 | 2011-08-03 | 孔赟荣 | Method for paving oil, gas and water pipelines by using water floating process |
CN102454828A (en) * | 2010-10-29 | 2012-05-16 | 中国海洋石油总公司 | Pipeline recycling and discarding technology in deepwater S-shaped submarine pipeline laying process |
CN102588675A (en) * | 2012-03-14 | 2012-07-18 | 中国海洋石油总公司 | Method for protectively recovering flexible tube from deep water |
CN102667285A (en) * | 2009-09-25 | 2012-09-12 | 塞彭公司 | Hoisting method and assembly for abandoning and/or recovering an underwater pipeline from a laying vessel, and laying vessel equipped with such a hoisting assembly |
CN103443518A (en) * | 2011-03-21 | 2013-12-11 | 塞彭公司 | A/r method and apparatus therefor |
CN203686355U (en) * | 2014-01-07 | 2014-07-02 | 中国海洋石油总公司 | Submarine pipeline pipe abandoning, recycling and connecting device |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3559413A (en) * | 1968-02-07 | 1971-02-02 | Pan American Petroleum Corp | Adjustable stinger for use in laying pipeline in water covered areas |
FR2790054B1 (en) * | 1999-02-19 | 2001-05-25 | Bouygues Offshore | METHOD AND DEVICE FOR LOW-SURFACE LINKAGE BY SUBMARINE PIPELINE INSTALLED WITH LARGE DEPTH |
-
2016
- 2016-06-21 CN CN201610465425.9A patent/CN106167229B/en active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB942218A (en) * | 1960-04-09 | 1963-11-20 | Electricite De France | Improvements in or relating to the positioning or laying of submarine tubes |
FR2461181B1 (en) * | 1979-07-06 | 1985-10-04 | Serra Freres Entr Sa | ROLLING FLOAT DEVICE FOR SUBSEA PIPES |
CN86108852A (en) * | 1985-12-06 | 1987-10-28 | 斯纳姆普罗吉蒂公司 | Large-scale underwater line, from the land phreatic method |
EP1022501A1 (en) * | 1999-01-21 | 2000-07-26 | J.Ray McDermott, S.A. | Marine pipeline installation method and apparatus |
CN1589354A (en) * | 2001-10-02 | 2005-03-02 | 全球海运业系统有限公司 | Cable or pipe retrieval and burial apparatus and methods |
CN1934332A (en) * | 2004-03-16 | 2007-03-21 | 泰克尼普法国公司 | Method and system for starting up a pipeline |
CN102667285A (en) * | 2009-09-25 | 2012-09-12 | 塞彭公司 | Hoisting method and assembly for abandoning and/or recovering an underwater pipeline from a laying vessel, and laying vessel equipped with such a hoisting assembly |
CN102140803A (en) * | 2010-02-02 | 2011-08-03 | 孔赟荣 | Method for paving oil, gas and water pipelines by using water floating process |
CN102454828A (en) * | 2010-10-29 | 2012-05-16 | 中国海洋石油总公司 | Pipeline recycling and discarding technology in deepwater S-shaped submarine pipeline laying process |
CN103443518A (en) * | 2011-03-21 | 2013-12-11 | 塞彭公司 | A/r method and apparatus therefor |
CN102588675A (en) * | 2012-03-14 | 2012-07-18 | 中国海洋石油总公司 | Method for protectively recovering flexible tube from deep water |
CN203686355U (en) * | 2014-01-07 | 2014-07-02 | 中国海洋石油总公司 | Submarine pipeline pipe abandoning, recycling and connecting device |
Also Published As
Publication number | Publication date |
---|---|
CN106167229A (en) | 2016-11-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107339111B (en) | The floating construction method of installation of more PE pipes in large-scale push pipe | |
CN102454176B (en) | Sand fetching construction device | |
CN106337971B (en) | A kind of buoyancy can be changed buoyancy tank and its application | |
CN103507109A (en) | Underwater dry type cutting cabin and application method thereof | |
CN106167229B (en) | A kind of construction method of the underwater pipeline of dredging of marine lifting | |
CN111636502A (en) | Sand mining construction process based on cutter suction dredger | |
CN104975612A (en) | Novel water open caisson construction technology | |
CN102758462A (en) | Stem punching device for self-propelled trailing suction hopper dredgers and construction method thereof | |
CN101736706A (en) | Underwater cutting construction method of low-pile bearing platform | |
CN106005312A (en) | Underwater operation device for micro-tunnel excavation based on remote operated vehicle (ROV) and operation method thereof | |
CN204080839U (en) | A kind of Yield rainfall relation device | |
CN202787354U (en) | Self-propelled trailing suction dredger bow thrust device | |
CN106704705B (en) | overwater pipeline assembling operation method and system | |
CN205707227U (en) | The underwater working device of micro-tunneling is opened based on ROV | |
CN205873671U (en) | Rings that rise of pipeline of dredging are lifted by crane under water at sea | |
CN206232308U (en) | A kind of marine hoisting component for lifting by crane pipeline of dredging under water | |
CN205101675U (en) | Long distance submarine pipe line is pipe laying construction system after ditching in advance | |
CN108005659B (en) | A kind of diving excavation construction method for the construction of city vertical shaft | |
CN101509265A (en) | Pull-type soil shifter smoothing technique for soft foundation field and pull-type soil shifter | |
CN205532599U (en) | Ocean mining ship with device is refuted to dress | |
CN212294953U (en) | Multi-functional environmental protection waterproof construction | |
CN105350592B (en) | Big flow twists suction ship bull energy dissipating dress and refutes device | |
CN209353399U (en) | A kind of band draws the pipe-line transportation system of slope structure | |
CN203996790U (en) | Cable wire guiding, location sand pump dredger wet excavation system | |
CN105926679A (en) | Dismounting method for pipe joints of immersed tube tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |