Prior art keywords
control
data
terminal device
electric heating
heating equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610587120.5A
Other languages
Chinese (zh)
Other versions
CN106152249A (en
Inventor
王兴越
马文营
李鹤
袁丽
白淑玲
马振华
赵明杰
王彦楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Beijing Electric Power Co Ltd
Beijing Lead Electric Equipment Co Ltd
Beijing Huashang Sanyou New Energy Technology Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Beijing Electric Power Co Ltd
Beijing Lead Electric Equipment Co Ltd
Beijing Huashang Sanyou New Energy Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Beijing Electric Power Co Ltd, Beijing Lead Electric Equipment Co Ltd, Beijing Huashang Sanyou New Energy Technology Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610587120.5A priority Critical patent/CN106152249B/en
Publication of CN106152249A publication Critical patent/CN106152249A/en
Application granted granted Critical
Publication of CN106152249B publication Critical patent/CN106152249B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D19/00Details
    • F24D19/10Arrangement or mounting of control or safety devices
    • F24D19/1096Arrangement or mounting of control or safety devices for electric heating systems

Abstract

The invention discloses a kind of control method of electric heating equipment, device and system.Wherein, this method comprises: the control information that receiving platform area terminal device is sent, wherein control information includes: control instruction and control priority;Judge to control whether priority is highest priority;In the case where controlling priority is highest priority, according to control instruction, the operating status of electric heating equipment is controlled, wherein operating status includes at least any one following state: starting state, halted state and energy storage state.The present invention solves electric heating equipment in the prior art can access power grid at any time, cause to impact to power grid, lead to the technical problem of electrical network capacity deficiency.

Description

The control method of electric heating equipment, device and system
Technical field
The present invention relates to electric heating equipment control fields, in particular to a kind of control method of electric heating equipment, dress It sets and system.
Background technique
To reduce pollution of the coal heating to atmosphere, ensures human health, improves ambient air quality, many areas are close Gradually set about within several years improving existing warming mode, carried out the mode of using electricity instead of coal energetically, has reduced combustion to reach Coal pollution, improves the purpose of air quality.
Since " coal changes electricity " work is implemented, very positive effect has been played in terms of improving air quality.At the same time, More and more users access power grid, lead to the increase of network load, the specific gravity that electric heating load accounts for total load also greatly increases. For power-assisted " coal changes electricity " work, and realize power grid " peak load shifting ", government has put into effect a series of advantageous policies, carries out " peak valley The subsidies measures of step price ".Therefore, comprehensively consider user's heating habit and policy implication, during heating season, capacity is increasingly The electric heating load of growth exits power grid in " paddy valence electricity " initial time period concentration, unordered access power grid, " paddy valence electricity " processing completion time used for them, Huge impact will certainly be caused to power grid, and the problem of electrical network capacity deficiency very likely occurs.Therefore carry out extensive supply It is studied after warm load access power grid to the qualitative assessment of electric network influencing and to reduce negative effect as the heating control of target, As hot spot concerned by people, the concept orderly to heat also generates therewith.
Power grid can be accessed at any time for electric heating equipment in the prior art, and power grid is caused to impact, power grid is caused to hold Insufficient problem is measured, currently no effective solution has been proposed.
Summary of the invention
The embodiment of the invention provides a kind of control method of electric heating equipment, device and system are existing at least to solve Electric heating equipment in technology can access power grid at any time, cause to impact to power grid, lead to the technical problem of electrical network capacity deficiency.
According to an aspect of an embodiment of the present invention, a kind of control method of electric heating equipment is provided, comprising: receiving platform The control information that area's terminal device is sent, wherein control information includes: control instruction and control priority;Judgement control is preferential Whether grade is highest priority;In the case where controlling priority is highest priority, according to control instruction, controls electric heating and set Standby operating status, wherein operating status includes at least any one following state: starting state, halted state and energy storage shape State.
According to another aspect of an embodiment of the present invention, a kind of control device of electric heating equipment is additionally provided, comprising: receive Module, the control information sent for receiving platform area terminal device, wherein control information includes: that control instruction and control are preferential Grade;Judgment module controls whether priority is highest priority for judging;Control module, for being most in control priority In the case where high priority, according to control instruction, the operating status of electric heating equipment is controlled, wherein operating status includes at least Any one following state: starting state, halted state and energy storage state.
According to a third aspect of the embodiments of the present invention, a kind of control system of electric heating equipment is additionally provided, comprising: platform area Terminal device, for sending control information, wherein control information includes: control instruction and control priority;Monitor terminal is set It is standby, there is correspondence with platform area terminal device, whether the control priority for judging to receive is highest priority, is being controlled In the case that priority processed is highest priority, according to control instruction, the operating status of electric heating equipment is controlled, wherein operation State includes at least any one following state: starting state, halted state and energy storage state.
In embodiments of the present invention, collected temperature data and device data can be sent to platform area terminal device, Platform area terminal device generates control instruction according to temperature data, device data and default regulation rule, and according to the control received System instruction, control electric heating equipment are in starting state, halted state or energy storage state, to realize long-range control electric heating The orderly access and energy storage regulation of equipment, solve electric heating equipment in the prior art and concentrate, disorderly access power grid, to electricity Net causes the technical issues of impacting, leading to electrical network capacity.Therefore, scheme provided by the above embodiment through the invention, Ke Yitong Orderly heating is realized in the start and stop of avoiding the peak hour of process control user terminal too far, is negatively affected, is subtracted caused by power grid after reducing access power grid Few network load, promotes heat supply efficiency.
Detailed description of the invention
The drawings described herein are used to provide a further understanding of the present invention, constitutes part of this application, this hair Bright illustrative embodiments and their description are used to explain the present invention, and are not constituted improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is a kind of flow chart of the control method of electric heating equipment according to an embodiment of the present invention;
Fig. 2 is a kind of schematic diagram of the control device of electric heating equipment according to an embodiment of the present invention;And
Fig. 3 is a kind of schematic diagram of the control system of electric heating equipment according to an embodiment of the present invention.
Specific embodiment
In order to enable those skilled in the art to better understand the solution of the present invention, below in conjunction in the embodiment of the present invention Attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is only The embodiment of a part of the invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people The model that the present invention protects all should belong in member's every other embodiment obtained without making creative work It encloses.
It should be noted that description and claims of this specification and term " first " in above-mentioned attached drawing, " Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way Data be interchangeable under appropriate circumstances, so as to the embodiment of the present invention described herein can in addition to illustrating herein or Sequence other than those of description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that cover Cover it is non-exclusive include, for example, the process, method, system, product or equipment for containing a series of steps or units are not necessarily limited to Step or unit those of is clearly listed, but may include be not clearly listed or for these process, methods, product Or other step or units that equipment is intrinsic.
Embodiment 1
According to embodiments of the present invention, a kind of control method embodiment of electric heating equipment is provided, it should be noted that The step of process of attached drawing illustrates can execute in a computer system such as a set of computer executable instructions, also, It, in some cases, can be to be different from shown in sequence execution herein although logical order is shown in flow charts The step of out or describing.
Fig. 1 is a kind of flow chart of the control method of electric heating equipment according to an embodiment of the present invention, as shown in Figure 1, should Method includes the following steps:
Step S102, receiving platform area terminal device send control information, wherein control information include: control instruction and Control priority.
Specifically, above-mentioned area's terminal device can be the heating operation management area platform Zhong Tai intelligent terminal.
Step S104 judges to control whether priority is highest priority.
Specifically, above-mentioned control priority can be used for judging whether executing the control instruction that platform area intelligent terminal is sent, When controlling priority is highest priority, the control instruction for having to carry out the transmission of platform area intelligent terminal is determined.
Step S106, according to control instruction, controls electric heating equipment in the case where controlling priority is highest priority Operating status, wherein operating status includes at least any one following state: starting state, halted state and energy storage state.
Specifically, above-mentioned electric heating equipment can be electric boiler, electric heater, Electric radiant Heating Film etc., the present invention do not done this specifically It limits.
In a kind of optional scheme, platform area intelligent terminal can carry out electric heating equipment by intelligent monitoring terminal remote Process control sends control instruction and control priority to intelligent monitoring terminal.Intelligent monitoring terminal can pass through communication interface function Energy module is connected with corresponding area's intelligent terminal, receives corresponding area's terminal device by wireless private network or power carrier The control information of transmission judges to control whether priority is highest priority, in determining table area after receiving control information In the case that the control priority that intelligent terminal is sent is highest priority, intelligent monitoring terminal is carried out by control function module Starting, stopping and the energy storage control of electric heating equipment, control electric heating equipment are in starting, stopping and energy storage state.Together When, user can not start electric heating equipment by intelligent monitoring terminal, stop and energy storage control, the area Ji Tai intelligence In the case that the control priority that terminal is sent is highest priority, control that intelligent monitoring terminal is sent according to platform area intelligent terminal System instruction carries out corresponding pressure control to electric heating equipment.
Above-described embodiment through the invention can receive the control information of platform area terminal device transmission, and judge to receive Control priority whether be highest priority, in the case where determining control priority is highest priority, according to receiving Control instruction, control electric heating equipment be in starting state, halted state or energy storage state, to realize that pressure control is electric The operating status of heating equipment, avoids user from arbitrarily controlling electric heating equipment, solves electric heating equipment energy in the prior art It is enough to access power grid at any time, power grid is caused to impact, leads to the technical problem of electrical network capacity deficiency.Therefore, above-mentioned through the invention The scheme that embodiment provides can control the start and stop of user terminal by pressure, realize that orderly heating, reduction access after power grid to electricity It is negatively affected caused by net, reduces network load, promote heat supply efficiency.
Optionally, according to that above embodiment of the present invention, in the case where controlling priority is not highest priority, above-mentioned side Method further include:
Step S108 obtains control instruction set by user.
Step S110 controls the operating status of electric heating equipment according to control instruction set by user.
In a kind of optional scheme, it is not in the control priority that intelligent monitoring terminal determining table area's intelligent terminal is sent In the case where highest priority, user can be controlled electric heating equipment by intelligent monitoring terminal, and user can be manual Input control instruction, the control instruction that intelligent monitoring terminal receives user's input carry out the starting of electric heating equipment, stop control And energy storage control.
S108 to step S110 through the above steps, can be according to the case where control priority be not highest priority Under, the operating status of electric heating equipment is controlled according to control instruction set by user, to force control user terminal reaching While start and stop, meets user to the different demands for control of electric heating equipment, promote degree of intelligence and likability.
Optionally, according to that above embodiment of the present invention, the control information sent in step S102, receiving platform area terminal device Before, the above method further include:
Step S112, temperature collection data and device data, wherein temperature data includes at least: electric heating equipment it is interior Portion's temperature, environment temperature and set temperature, device data include: the status data and voltage and current data of electric heating equipment.
Specifically, above-mentioned temperature data may include: the internal temperature of electric heating equipment, such as: supplying heat source leaving water temperature, Return water temperature, thermal store internal temperature, environment temperature, such as: resident's room temperature, outdoor environment temperature, and setting Temperature, such as: the customized temperature of user's day part.Above equipment data may include: the status data of electric heating equipment, example Such as: electric heating equipment operating status, malfunction, energy storage and de-energized state, stored energy capacitance state and voltage and current data.
Collected temperature data and device data are sent to platform area terminal device by step S114, and receiving platform area is whole The control information that end equipment returns, wherein platform area terminal device generates control information according to temperature data and device data.
In a kind of optional scheme, the Real time Data Acquisition function module in intelligent monitoring terminal can be to temperature data It is acquired, can be sent out collected temperature data and device data by wireless private network or power carrier with device data Give corresponding area's intelligent terminal.Platform area intelligent terminal is after the data for receiving intelligent monitoring terminal transmission, Ke Yigen Corresponding control information is generated according to the data received, and returns to intelligent monitoring terminal.
Optionally, according to that above embodiment of the present invention, step S114, platform area terminal device is according to temperature data and number of devices Include: according to control information is generated
Step S1140, platform area terminal device receive temperature data and device data.
Step S1142, platform area terminal device judge whether the status data of electric heating equipment includes malfunction.
Specifically, can determine that event occurs in the electric heating equipment when the status data of electric heating equipment is malfunction Barrier, is unable to satisfy heating demands, needs to repair.
Step S1144, in the case where the status data of electric heating equipment includes malfunction, platform area terminal device is generated Stop control instruction and highest priority.
In a kind of optional scheme in the case that electric heating equipment breaks down, intelligent monitoring terminal can pass through Real time Data Acquisition function module collects the malfunction of electric heating equipment, and platform area intelligent terminal is receiving intelligent monitoring end After holding the temperature data and device data sent, it can be determined that the status data for the electric heating equipment for including in device data is No includes malfunction, is determining that status data includes platform Qu Zhi in the case that malfunction i.e. electric heating equipment breaks down Energy terminal determines that the electric heating equipment can not continue to run, and can be generated and stops control instruction and highest priority, avoids user The electric heating equipment is arbitrarily controlled by intelligent monitoring terminal.
S1140 to step S1144 through the above steps, platform area terminal device can be according to the status datas of electric heating equipment Control instruction and control priority are generated, not only can satisfy to electric heating equipment monomer start-up and shut-down control, but also can satisfy and adopted in electricity In the case that heating equipment breaks down, electric heating equipment is carried out forcing to stop control, forces control user terminal to reach The purpose of start and stop.
Optionally, according to that above embodiment of the present invention, in the case where device data is not malfunction, the above method is also Include:
Step S1146, platform area terminal device obtain rule of avoiding the peak hour.
Specifically, above-mentioned rule of avoiding the peak hour can be according to power grid electricity consumption demand and network load characteristic, determine The sub-load of power grid peak of power consumption period can be transferred to the low power consumption period, reduce the peak of power grid by peak load shifting mode Paddy load is poor, for example, can be according to power grid electricity consumption demand and network load characteristic, when determining the electricity consumption of different regions user Section.
Step S1148, platform area terminal device generate control and refer to according to temperature data, device data and rule of avoiding the peak hour Enable and control priority, control instruction include at least any one following instruction: starting control instruction stops control instruction and storage It can control instruction.
In a kind of optional scheme, platform area intelligent terminal is after receiving temperature data and device data, Ke Yigen According to temperature data, device data and pre-set rule of avoiding the peak hour, when determining the operation of user's electric heating equipment Section generates corresponding control instruction and control priority, controls corresponding electric heating equipment starting, stopping and energy storage.For example, When needing to carry out force start control to electric heating equipment, starting control instruction is can be generated in platform area intelligent terminal and highest is excellent First grade;When need to carry out electric heating equipment force stop control when, platform area intelligent terminal can be generated stop control instruction and Highest priority.
S1146 to step S1148 through the above steps, platform area terminal device rule and can be received according to avoiding the peak hour Data generate control instruction and control priority, not only can satisfy and integrally avoided the peak hour start-up and shut-down control to electric heating equipment, but also can be with Meet and start-up and shut-down control is forced to electric heating equipment, to achieve the purpose that the start and stop for forcing control user terminal.
Optionally, according to that above embodiment of the present invention, in the case where control instruction is to stop control instruction, control is preferential Grade is highest priority.
In a kind of optional scheme, when the control instruction that platform area intelligent terminal generates is to stop control instruction, determine User's electric heating equipment cannot access power grid, and user arbitrarily controls electric heating equipment starting in order to prevent, accesses power grid, can be with Highest priority is set by the corresponding control priority of the control instruction, control electric heating equipment is forced to be in halted state.
Optionally, according to that above embodiment of the present invention, step S106 controls the operating status of electric heating equipment, comprising:
Control instruction is sent to the control unit of electric heating equipment by step S1062, wherein the control of electric heating equipment The operating status of unit control electric heating equipment.
In a kind of optional scheme, it can be connected by communication interface functional module and the control unit of electric heating equipment It connects, by the control instruction that the platform area intelligent terminal received generates or the control instruction that user is manually entered, is transparent to electricity and adopts The control unit of heating equipment, the control unit of electric heating equipment control the operating status of electric heating equipment according to control instruction, and The communication message sent out by the control unit that communication interface functional module receives electric heating equipment.
S1062 through the above steps can be realized by sending control instruction to the control unit of electric heating equipment to electricity The control of heating equipment is promoted practical to realize long-range control electric heating equipment starting, stop control and energy storage control Degree.
Optionally, according to that above embodiment of the present invention, the control information sent in step S102, receiving platform area terminal device While or later, the above method further include:
Step S122, the clock synchronization order that receiving platform area terminal device is sent, and obtain at the first time.
Specifically, above-mentioned first time can be the current time of intelligent monitoring terminal.
Step S124 will be sent to platform area terminal device at the first time, and when the terminal of receiving platform area terminal device return Clock error.
Step S126, if the first waiting time for receiving terminal clock error was less than or equal to for the first effective time, At the first time according to terminal clock error transfer factor.
Specifically, above-mentioned first waiting time can be transmission at the first time to when the waiting for receiving terminal clock error Between, above-mentioned first effective time can be 10min, and the present invention is not specifically limited in this embodiment.
In a kind of optional scheme, intelligent monitoring terminal can have the function with platform area intelligent terminal clock synchronization, can be with Long-range clock synchronization is carried out by wireless private network, platform area intelligent terminal sends clock synchronization order, and intelligent monitoring terminal returns to current time Platform area intelligent terminal is given, platform area intelligent terminal returns to terminal clock error, and intelligent monitoring terminal can pass through time adjustment function module If judgement receives terminal clock error within the first effective time, i.e., missed from transmission current time to terminal clock is received The waiting time of difference was less than or equal to for the first effective time, then executed clock synchronization order, local clock is changed to current time+terminal Clocking error;Otherwise clock synchronization command expiration, and notify platform area intelligent terminal.
Herein it should be noted that intelligent monitoring terminal can have the control unit time adjustment function to electric heating equipment. The punctual every 24 hours errors of precision of intelligent monitoring terminal clock should be not more than 2 seconds, and in the power loss of intelligent monitoring terminal Afterwards, clock should be able to keep working normally.
Optionally, according to that above embodiment of the present invention, in step S124, will be sent at the first time platform area terminal device it Afterwards, the above method further include:
Step S132, platform area terminal device obtain the second local time.
Step S134, if the second waiting time for receiving first time is less than or equal to the second effective time, the area Ze Tai Terminal device determines at the first time be effective time, and calculates the time difference with the second time at the first time.
Specifically, above-mentioned second waiting time can be and send clock synchronization order to the waiting time for receiving first time, Above-mentioned second effective time can be 3s, and the present invention is not specifically limited in this embodiment.
Step S136, platform area terminal device judge whether time difference is more than or equal to preset value.
Specifically, above-mentioned preset value can be 3s, the present invention is not specifically limited in this embodiment.
Step S138, in the case where time difference is more than or equal to preset value, when platform area terminal device is waited according to second Between and time difference, obtain terminal clock error.
In a kind of optional scheme, platform area intelligent terminal can send clock synchronization order, if receiving intelligent monitoring end The waiting time of the first time returned is held to be less than or equal to for the second effective time, for example, platform area intelligent terminal is received in T1 < 3s Terminal return information is effective, the time difference of the first time that computational intelligence monitor terminal returns and local second time, i.e., Clocking error Δ T, if Δ T >=3s, platform area intelligent terminal is using Δ T+T1/2 as terminal clock error to write object command in real time Mode is handed down to intelligent monitoring terminal.
Optionally, according to that above embodiment of the present invention, if the second waiting time for receiving first time is greater than second Effective time, it is ineffective time that the area Ze Tai terminal device, which determines at the first time, and retransmits clock synchronization order.
In a kind of optional scheme, if T1 >=3s receive terminal return information be it is invalid, again to intelligent monitoring Terminal sends clock synchronization order, and receives the first time of intelligent monitoring terminal return.
It optionally, according to that above embodiment of the present invention, is more than preset times in the number for retransmitting clock synchronization order, or In the case that time difference is less than preset value, platform area terminal device stops sending terminal clock error.
Specifically, above-mentioned preset times can be 10 times, the present invention is not specifically limited in this embodiment.
In a kind of optional scheme, if continuous 10 times invalid or Δ T < 3s, Ze Tai area's intelligent terminal cancellation sheets Secondary clock synchronization, without clock synchronization.
Through the above scheme, the time adjustment function with platform area terminal device may be implemented, to guarantee the accurate of current time Property.
Embodiment 2
According to embodiments of the present invention, a kind of control device embodiment of electric heating equipment is provided, Fig. 2 is according to the present invention The schematic diagram of the control device of a kind of electric heating equipment of embodiment, as shown in Fig. 2, the device includes:
Receiving module 21, the control information sent for receiving platform area terminal device, wherein the control information includes: Control instruction and control priority.
Specifically, above-mentioned area's terminal device can be the heating operation management area platform Zhong Tai intelligent terminal.
Judgment module 23, for judging whether the control priority is highest priority.
Specifically, above-mentioned control priority can be used for judging whether executing the control instruction that platform area intelligent terminal is sent, When controlling priority is highest priority, the control instruction for having to carry out the transmission of platform area intelligent terminal is determined.
Control module 25, in the case where the control priority is the highest priority, according to the control Instruction, controls the operating status of the electric heating equipment, wherein the operating status includes at least any one following state: Starting state, halted state and energy storage state.
Specifically, above-mentioned electric heating equipment can be electric boiler, electric heater, Electric radiant Heating Film etc., the present invention do not done this specifically It limits.
In a kind of optional scheme, platform area intelligent terminal can carry out electric heating equipment by intelligent monitoring terminal remote Process control sends control instruction and control priority to intelligent monitoring terminal.Intelligent monitoring terminal can pass through communication interface function Energy module is connected with corresponding area's intelligent terminal, receives corresponding area's terminal device by wireless private network or power carrier The control information of transmission judges to control whether priority is highest priority, in determining table area after receiving control information In the case that the control priority that intelligent terminal is sent is highest priority, intelligent monitoring terminal is carried out by control function module Starting, stopping and the energy storage control of electric heating equipment, control electric heating equipment are in starting, stopping and energy storage state.Together When, user can not start electric heating equipment by intelligent monitoring terminal, stop and energy storage control, the area Ji Tai intelligence In the case that the control priority that terminal is sent is highest priority, control that intelligent monitoring terminal is sent according to platform area intelligent terminal System instruction carries out corresponding pressure control to electric heating equipment.
Above-described embodiment through the invention can receive the control information of platform area terminal device transmission, and judge to receive Control priority whether be highest priority, in the case where determining control priority is highest priority, according to receiving Control instruction, control electric heating equipment be in starting state, halted state or energy storage state, to realize that pressure control is electric The operating status of heating equipment, avoids user from arbitrarily controlling electric heating equipment, solves electric heating equipment energy in the prior art It is enough to access power grid at any time, power grid is caused to impact, leads to the technical problem of electrical network capacity deficiency.Therefore, above-mentioned through the invention The scheme that embodiment provides can control the start and stop of user terminal by pressure, realize that orderly heating, reduction access after power grid to electricity It is negatively affected caused by net, reduces network load, promote heat supply efficiency.
Embodiment 3
According to embodiments of the present invention, a kind of control system embodiment of electric heating equipment is provided, Fig. 3 is according to the present invention The schematic diagram of the control system of a kind of electric heating equipment of embodiment, as shown in figure 3, the system includes:
Platform area terminal device 31, for sending control information, wherein the control information includes: control instruction and control Priority.
Specifically, above-mentioned area's terminal device can be the heating operation management area platform Zhong Tai intelligent terminal.
Monitor terminal equipment 33 has correspondence with platform area terminal device 31, and the control for judging to receive is preferential Whether grade is highest priority, in the case where controlling priority is highest priority, according to control instruction, controls electric heating and sets Standby 35 operating status, wherein operating status includes at least any one following state: starting state, halted state and energy storage State.
Specifically, above-mentioned control priority can be used for judging whether executing the control instruction that platform area intelligent terminal is sent, When controlling priority is highest priority, the control instruction for having to carry out the transmission of platform area intelligent terminal is determined.Above-mentioned electric heating Equipment can be electric boiler, and electric heater, Electric radiant Heating Film etc., the present invention is not specifically limited in this embodiment.
In a kind of optional scheme, platform area intelligent terminal can carry out electric heating equipment by intelligent monitoring terminal remote Process control sends control instruction and control priority to intelligent monitoring terminal.Intelligent monitoring terminal can pass through communication interface function Energy module is connected with corresponding area's intelligent terminal, receives corresponding area's terminal device by wireless private network or power carrier The control information of transmission judges to control whether priority is highest priority, in determining table area after receiving control information In the case that the control priority that intelligent terminal is sent is highest priority, intelligent monitoring terminal is carried out by control function module Starting, stopping and the energy storage control of electric heating equipment, control electric heating equipment are in starting, stopping and energy storage state.Together When, user can not start electric heating equipment by intelligent monitoring terminal, stop and energy storage control, the area Ji Tai intelligence In the case that the control priority that terminal is sent is highest priority, control that intelligent monitoring terminal is sent according to platform area intelligent terminal System instruction carries out corresponding pressure control to electric heating equipment.
Above-described embodiment through the invention can receive the control information of platform area terminal device transmission, and judge to receive Control priority whether be highest priority, in the case where determining control priority is highest priority, according to receiving Control instruction, control electric heating equipment be in starting state, halted state or energy storage state, to realize that pressure control is electric The operating status of heating equipment, avoids user from arbitrarily controlling electric heating equipment, solves electric heating equipment energy in the prior art It is enough to access power grid at any time, power grid is caused to impact, leads to the technical problem of electrical network capacity deficiency.Therefore, above-mentioned through the invention The scheme that embodiment provides can control the start and stop of user terminal by pressure, realize that orderly heating, reduction access after power grid to electricity It is negatively affected caused by net, reduces network load, promote heat supply efficiency.
The serial number of the above embodiments of the invention is only for description, does not represent the advantages or disadvantages of the embodiments.
In the above embodiment of the invention, it all emphasizes particularly on different fields to the description of each embodiment, does not have in some embodiment The part of detailed description, reference can be made to the related descriptions of other embodiments.
In several embodiments provided herein, it should be understood that disclosed technology contents can pass through others Mode is realized.Wherein, the apparatus embodiments described above are merely exemplary, such as the division of the unit, Ke Yiwei A kind of logical function partition, there may be another division manner in actual implementation, for example, multiple units or components can combine or Person is desirably integrated into another system, or some features can be ignored or not executed.Another point, shown or discussed is mutual Between coupling, direct-coupling or communication connection can be through some interfaces, the INDIRECT COUPLING or communication link of unit or module It connects, can be electrical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple On unit.It can some or all of the units may be selected to achieve the purpose of the solution of this embodiment according to the actual needs.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated unit is realized in the form of SFU software functional unit and sells or use as independent product When, it can store in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially The all or part of the part that contributes to existing technology or the technical solution can be in the form of software products in other words It embodies, which is stored in a storage medium, including some instructions are used so that a computer Equipment (can for personal computer, server or network equipment etc.) execute each embodiment the method for the present invention whole or Part steps.And storage medium above-mentioned includes: that USB flash disk, read-only memory (ROM, Read-Only Memory), arbitrary access are deposited Reservoir (RAM, Random Access Memory), mobile hard disk, magnetic or disk etc. be various to can store program code Medium.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (10)

1. a kind of control method of electric heating equipment characterized by comprising
The control information that receiving platform area terminal device is sent, wherein the control information includes: that control instruction and control are preferential Grade;
Judge whether the control priority is highest priority;
In the case where the control priority is the highest priority, according to the control instruction, the electric heating is controlled The operating status of equipment, wherein the operating status includes at least any one following state: starting state, halted state and Energy storage state;
Wherein, before the control information that receiving platform area terminal device is sent, the method also includes:
Temperature collection data and device data, wherein the temperature data includes at least: the internal temperature of electric heating equipment, ring Border temperature and set temperature, the device data includes: the status data and voltage and current data of the electric heating equipment;
The collected temperature data and the device data are sent to platform area terminal device, and receive described area's terminal The control information that equipment returns, wherein described area's terminal device is raw according to the temperature data and the device data At the control information;
Wherein, described area's terminal device includes: according to the temperature data and the device data generation control information
Described area's terminal device receives the temperature data and the device data;
Described area's terminal device judges whether the status data of the electric heating equipment includes malfunction;
In the case where the status data of the electric heating equipment includes the malfunction, described area's terminal device generation stops Only control instruction and the highest priority;
Wherein, in the case where the status data of the electric heating equipment does not include the malfunction, the method also includes:
Described area's terminal device obtains rule of avoiding the peak hour;
Described area's terminal device is according to the temperature data, the device data and the rule of avoiding the peak hour, described in generation Control instruction and the control priority, the control instruction include at least any one following instruction: starting control instruction is stopped Only control instruction and energy storage control instruction.
2. the method according to claim 1, wherein not being the highest priority in the control priority In the case of, the method also includes:
Obtain control instruction set by user;
According to the control instruction set by user, the operating status of the electric heating equipment is controlled.
3. according to the method described in claim 1, the control instruction be the stopping control instruction in the case where, the control Priority processed is the highest priority.
4. the method according to claim 1, which is characterized in that control the fortune of the electric heating equipment Row state, comprising:
The control instruction is sent to the control unit of the electric heating equipment, wherein the control list of the electric heating equipment Member controls the operating status of the electric heating equipment.
5. the method according to claim 1, wherein receiving platform area terminal device send control information it is same When or later, the method also includes:
The clock synchronization order of described area's terminal device transmission is received, and is obtained at the first time;
The first time is sent to described area's terminal device, and receives the terminal clock of described area's terminal device return Error;
If the first waiting time for receiving the terminal clock error was less than or equal to for the first effective time, according to the end Clocking error is held to adjust the first time.
6. according to the method described in claim 5, it is characterized in that, being set the first time is sent to described area's terminal After standby, the method also includes:
Described area's terminal device obtains the second local time;
If the second waiting time for receiving the first time was less than or equal to for the second effective time, described area's terminal is set It is standby to determine that the first time is effective time, and calculate the time difference of the first time and second time;
Described area's terminal device judges whether the time difference is more than or equal to preset value;
In the case where the time difference is more than or equal to the preset value, described area's terminal device is waited according to described second Time and the time difference obtain the terminal clock error.
7. according to the method described in claim 6, it is characterized in that, if receiving the second waiting time of the first time Greater than second effective time, then described area's terminal device determines that the first time is ineffective time, and retransmits The clock synchronization order.
8. the method according to the description of claim 7 is characterized in that being more than default in the number for retransmitting the clock synchronization order In the case that number or the time difference are less than the preset value, described area's terminal device stops sending the terminal Clocking error.
9. a kind of control device of electric heating equipment characterized by comprising
Receiving module, the control information sent for receiving platform area terminal device, wherein the control information includes: that control refers to Enable and control priority;
Judgment module, for judging whether the control priority is highest priority;
Control module, for according to the control instruction, controlling in the case where the control priority is the highest priority Make the operating status of the electric heating equipment, wherein the operating status includes at least any one following state: starting shape State, halted state and energy storage state;
Wherein, before the control information that receiving platform area terminal device is sent, further includes:
Temperature collection data and device data, wherein the temperature data includes at least: the internal temperature of electric heating equipment, ring Border temperature and set temperature, the device data includes: the status data and voltage and current data of the electric heating equipment;
The collected temperature data and the device data are sent to platform area terminal device, and receive described area's terminal The control information that equipment returns, wherein described area's terminal device is raw according to the temperature data and the device data At the control information;
Wherein, described area's terminal device includes: according to the temperature data and the device data generation control information
Described area's terminal device receives the temperature data and the device data;
Described area's terminal device judges whether the status data of the electric heating equipment includes malfunction;
In the case where the status data of the electric heating equipment includes the malfunction, described area's terminal device generation stops Only control instruction and the highest priority;
Wherein, in the case where the status data of the electric heating equipment does not include the malfunction, further includes:
Described area's terminal device obtains rule of avoiding the peak hour;
Described area's terminal device is according to the temperature data, the device data and the rule of avoiding the peak hour, described in generation Control instruction and the control priority, the control instruction include at least any one following instruction: starting control instruction is stopped Only control instruction and energy storage control instruction.
10. a kind of control system of electric heating equipment characterized by comprising
Platform area terminal device, for sending control information, wherein the control information includes: control instruction and control priority;
Monitor terminal equipment has correspondence with described area's terminal device, and the control for judging to receive is preferential Whether grade is highest priority, in the case where the control priority is the highest priority, according to the control instruction, Control the operating status of the electric heating equipment, wherein the operating status includes at least any one following state: starting shape State, halted state and energy storage state;
Wherein, before the control information that receiving platform area terminal device is sent, further includes:
Temperature collection data and device data, wherein the temperature data includes at least: the internal temperature of electric heating equipment, ring Border temperature and set temperature, the device data includes: the status data and voltage and current data of the electric heating equipment;
The collected temperature data and the device data are sent to platform area terminal device, and receive described area's terminal The control information that equipment returns, wherein described area's terminal device is raw according to the temperature data and the device data At the control information;
Wherein, described area's terminal device includes: according to the temperature data and the device data generation control information
Described area's terminal device receives the temperature data and the device data;
Described area's terminal device judges whether the status data of the electric heating equipment includes malfunction;
In the case where the status data of the electric heating equipment includes the malfunction, described area's terminal device generation stops Only control instruction and the highest priority;
Wherein, in the case where the status data of the electric heating equipment does not include the malfunction, further includes:
Described area's terminal device obtains rule of avoiding the peak hour;
Described area's terminal device is according to the temperature data, the device data and the rule of avoiding the peak hour, described in generation Control instruction and the control priority, the control instruction include at least any one following instruction: starting control instruction is stopped Only control instruction and energy storage control instruction.
CN201610587120.5A 2016-07-22 2016-07-22 The control method of electric heating equipment, device and system Active CN106152249B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610587120.5A CN106152249B (en) 2016-07-22 2016-07-22 The control method of electric heating equipment, device and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610587120.5A CN106152249B (en) 2016-07-22 2016-07-22 The control method of electric heating equipment, device and system

Publications (2)

Publication Number Publication Date
CN106152249A CN106152249A (en) 2016-11-23
CN106152249B true CN106152249B (en) 2019-09-06

Family

ID=58060147

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610587120.5A Active CN106152249B (en) 2016-07-22 2016-07-22 The control method of electric heating equipment, device and system

Country Status (1)

Country Link
CN (1) CN106152249B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108151131A (en) * 2017-11-27 2018-06-12 国网北京市电力公司 The control method and system of electric heating equipment, storage medium, processor
CN108599162A (en) * 2018-07-27 2018-09-28 珠海格力电器股份有限公司 Peak regulation control method, device and system
CN111988206A (en) * 2020-07-23 2020-11-24 华帝股份有限公司 Control method of household appliance
CN113654102A (en) * 2021-09-08 2021-11-16 北京华远意通热力科技股份有限公司 Electric heating device and method
CN115616931B (en) * 2022-12-16 2023-04-14 广东美的暖通设备有限公司 Control method, control device, controller, control system, and storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103604162A (en) * 2013-12-05 2014-02-26 黑龙江隆宇科技开发有限责任公司 Intelligent public building electric heating control method and intelligent public building electric heating control system
CN103676814A (en) * 2012-10-11 2014-03-26 国网电力科学研究院 Remote power control method, system thereof and remote power management server
WO2014113505A1 (en) * 2013-01-15 2014-07-24 Andrew Butler Heat energy storage system and method for hot water systems
CN104654449A (en) * 2014-12-17 2015-05-27 东北大学 Distributed electric heat energy storage heating control system and method
CN105743094A (en) * 2016-04-22 2016-07-06 国网江苏省电力公司连云港供电公司 Power grid demand response control system

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103375873B (en) * 2012-04-20 2016-06-08 珠海格力电器股份有限公司 The control method of conditioner and device and conditioner
CN105650712A (en) * 2016-01-29 2016-06-08 兖矿东华建设有限公司 Air energy heating system and corresponding peak-load shifting heating method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103676814A (en) * 2012-10-11 2014-03-26 国网电力科学研究院 Remote power control method, system thereof and remote power management server
WO2014113505A1 (en) * 2013-01-15 2014-07-24 Andrew Butler Heat energy storage system and method for hot water systems
CN103604162A (en) * 2013-12-05 2014-02-26 黑龙江隆宇科技开发有限责任公司 Intelligent public building electric heating control method and intelligent public building electric heating control system
CN104654449A (en) * 2014-12-17 2015-05-27 东北大学 Distributed electric heat energy storage heating control system and method
CN105743094A (en) * 2016-04-22 2016-07-06 国网江苏省电力公司连云港供电公司 Power grid demand response control system

Also Published As

Publication number Publication date
CN106152249A (en) 2016-11-23

Similar Documents

Publication Publication Date Title
CN106152249B (en) The control method of electric heating equipment, device and system
CN106196266B (en) The control method of electric heating equipment, device and system
CN106091105B (en) Monitor terminal equipment and monitoring system
DK2503344T3 (en) Energy Management
CN105650886B (en) Storage-type electric water heater and its control method and control system
CN110056981A (en) A kind of heat-exchanging component, air-conditioner outdoor unit and its control method
CN203299668U (en) User comfort constraint-based household temperature control load demand response control structure
CN104137384A (en) On-demand power control system, on-demand power control system program, and computer-readable recording medium on which this program is recorded
KR20150043311A (en) On-demand multiple power source management system, on-demand multiple power source management system program and computer-readable recording medium on which said program is recorded
US20220352717A1 (en) Demand response of loads having thermal reserves
CN106642301B (en) Heating method and equipment
CN102969791B (en) Flexible load management system and method of power system based on bidirectional intelligent electric meter
CN108988467A (en) Electricity consumption strategy-generating method and device
CN108562020A (en) Air conditioner and its control method and computer readable storage medium
CN103471175B (en) Heat supply energy-saving control system and energy-saving control method
CN106196267A (en) The alarm method of electric heating equipment, device and system
WO2015166758A1 (en) Energy control system, energy control device, energy control method, and storage medium
CN109733247A (en) The control method and device of sanitation cart
Roche et al. A multi-agent model and strategy for residential demand response coordination
CN108063438A (en) The control method and device of DC micro power grid system
CN205606884U (en) Water storage formula water heater and control system
CN108151131A (en) The control method and system of electric heating equipment, storage medium, processor
CN106646254B (en) Battery temperature characteristic test method and apparatus and system
CN106545964B (en) A kind of compressor electric heating control device, method and air-conditioning
CN107702346B (en) A kind of electric heater duty control method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant