CN106149903B - A kind of curtain wall first floor and structure are plugged into the application methods of the flashing devices at position - Google Patents
A kind of curtain wall first floor and structure are plugged into the application methods of the flashing devices at position Download PDFInfo
- Publication number
- CN106149903B CN106149903B CN201610620721.1A CN201610620721A CN106149903B CN 106149903 B CN106149903 B CN 106149903B CN 201610620721 A CN201610620721 A CN 201610620721A CN 106149903 B CN106149903 B CN 106149903B
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- stringer board
- splash guard
- transverse slat
- waterproof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/665—Sheets or foils impervious to water and water vapor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Building Environments (AREA)
- Load-Bearing And Curtain Walls (AREA)
- Finishing Walls (AREA)
Abstract
Plug into the flashing devices at position, including splash guard ontology the invention discloses a kind of curtain wall first floor and structure, splash guard ontology include transverse slat and with transverse slat the first stringer board connected vertically and the second stringer board;It is fixedly connected with the first stringer board above transverse slat side, the second stringer board is fixedly connected with below the other side;The transverse slat, the first stringer board and the second stringer board are integrated design;First stringer board is fixedly connected with curtain wall cross beam, and the second stringer board is fixed on structure outer, and splash guard outer body is equipped with waterproof roll.The present invention so that Curtain Wall and structure is formed organic waterproof is whole, strengthen the waterproof ability that curtain wall plate and structure are plugged at position, the maintenance process to build the later stage saves a large amount of manpower and material resources, also increases the service life of structure to a certain extent;Make the entire convenient and efficient one of work progress, effectively prevents the rain leakage problem at weak location, improve the weak link of curtain wall waterproof.
Description
Technical field
The present invention relates to the connecting elements of curtain wall, it particularly relates to which a kind of curtain wall first floor and structure are plugged at position
The application method of flashing devices.
Background technology
Curtain wall is modern large-scale and skyscraper commonly carries the lightweight wall of decorative effect, using various powerful, light
It is full of, the exterior wall engineering method that beautiful construction material replaces traditional masonry or window wall combines, keeps whole building beautiful, it is strong using function
It is complete and safe.Under normal circumstances, only paving is on external wall elevation for the external wall waterproof coiled material of the structure first floor, without being extended to curtain
In the system of wall, curtain wall is two entirety detached with structure, and in this way when rainy, rainwater is just easy to along curtain wall and structure
The location stream plugged into enters interior.Especially in the case where outdoor absolute altitude is not much different with indoor absolute altitude, rainwater is easier just to return
It fills into interior, influences normal use.
For the problems in the relevant technologies, currently no effective solution has been proposed.
Invention content
For above-mentioned technical problem in the related technology, the present invention proposes that a kind of curtain wall first floor and structure are plugged at position
Flashing devices can enhance the waterproof effect of curtain wall and structure connection.
To realize the above-mentioned technical purpose, the technical proposal of the invention is realized in this way:
A kind of curtain wall first floor and structure are plugged into the flashing devices at position, including splash guard ontology, the splash guard sheet
Body include transverse slat and with the transverse slat the first stringer board connected vertically and the second stringer board;It is fixedly connected above the transverse slat side
First stringer board, other side lower section are fixedly connected with the second stringer board;The transverse slat, the first stringer board and the second stringer board are integrated design;The
One stringer board is fixedly connected with curtain wall cross beam, and the second stringer board is fixed on structure outer, and the splash guard outer body is equipped with waterproof
Coiled material.
Preferably, the splash guard ontology uses material of the same race with Curtain wall frame crossbeam.
Preferably, splash guard ontology one end is fixed on using screw on crossbeam, and the other end is fixed on knot using nailing
On structure exterior wall.
Preferably, the splash guard ontology isType.
Beneficial effects of the present invention:It is mutual with structurally waterproof to change curtain wall waterproof by the waterproofing process of innovation by the present invention
The conventional construction method of phase separation so that Curtain Wall and structure form organic waterproof entirety, strengthen curtain wall plate and knot
Structure is plugged into the waterproof ability at position, is effectively prevented building in construction period rain leakage, the situation poured in down a chimney, to build the later stage
Maintenance process save a large amount of manpower and material resources, also increase the service life of structure to a certain extent;The peace of splash guard
The same curtain wall cross beam of load, waterproof roll laying are carried out at the same time so that the convenient and efficient one of entire work progress effectively prevents thin
Rain leakage problem at weak position, improves the weak link of curtain wall waterproof.
Description of the drawings
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment
Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the present invention
Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings
Obtain other attached drawings.
The flashing devices that Fig. 1, which is a kind of described according to embodiments of the present invention curtain wall first floor, to plug into structure at position
Structural schematic diagram;
Fig. 2 is a kind of described according to embodiments of the present invention curtain wall first floor and structure flashing devices at position of plugging into make
The node schematic diagram of used time.
In figure:
1, splash guard ontology;2, transverse slat;3, the first stringer board;4, the second stringer board;5, screw;6, curtain wall cross beam;7, waterproof is rolled up
Material.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained belong to what the present invention protected
Range.
As depicted in figs. 1 and 2, according to embodiments of the present invention a kind of curtain wall first floor and structure plug into it is anti-at position
Water panel assembly, including splash guard ontology 1, the splash guard ontology 1 include transverse slat 2 and with the transverse slat 2 connected vertically the
One stringer board 3 and the second stringer board 4;It is fixedly connected with the first stringer board 3 above 2 side of the transverse slat, second is fixedly connected with below the other side
Stringer board 4;The transverse slat 2, the first stringer board 3 and the second stringer board 4 are integrated design;First stringer board 3 is fixedly connected with curtain wall cross beam 6, the
Two stringer boards 4 are fixed on structure outer, and 1 outside of the splash guard ontology is equipped with waterproof roll 7.
The splash guard ontology 1 uses material of the same race with Curtain wall frame crossbeam.
Described 1 one end of splash guard ontology is fixed on using screw 5 on crossbeam, and the other end is fixed on structure outer using nailing
On.
The splash guard ontology 1 isType.
In order to facilitate understand the present invention above-mentioned technical proposal, below by way of in specifically used mode to the present invention it is above-mentioned
Technical solution is described in detail.
When specifically used, a kind of curtain wall first floor according to the present invention and the structure splash guard at position of plugging into fill
It sets, one piece is added in the crossbeam of curtain wall systemThe splash guard ontology of type, the splash guard ontology are adopted with Curtain wall frame crossbeam
With material of the same race, machined in advance in curtain wall producer.Curtain wall cross beam can install splash guard ontology, by it after installation is complete
One end is screwed on crossbeam, and the other end is fixed on using nailing on structure outer, then, then the waterproof of wall face is rolled up
On the splash guard ontology added, Curtain Wall is formed a unified waterproof entirety with structure, enhances curtain wall for material paving
With the waterproof effect of structure connection, pouring in down a chimney for rainy day rainwater is effectively blocked.
In conclusion by means of the above-mentioned technical proposal of the present invention, the invention has the advantages that:
Economic benefit:By the waterproofing process of innovation, changes the curtain wall waterproof routine disconnected from each other with structurally waterproof and apply
Work method so that it is whole that Curtain Wall and structure form organic waterproof, strengthens curtain wall plate and structure and plugs at position
Waterproof ability effectively prevents building in construction period rain leakage, the situation poured in down a chimney, and the maintenance process to build the later stage is saved
A large amount of manpower and material resources, also increase the service life of structure to a certain extent;
Social benefit:The installation of splash guard is laid in the same construction stage and carries out together with curtain wall cross beam, SBS coiled materials, makes
The entire convenient and efficient one of work progress is obtained, the rain leakage problem at weak location is effectively prevented, improves curtain wall waterproof
Weak link.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention
With within principle, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention god.
Claims (1)
- A kind of application method of flashing devices 1. curtain wall first floor and structure are plugged at position, the flashing devices include anti- Water plate ontology (1), the splash guard ontology (1) include transverse slat (2) and with the transverse slat (2) the first stringer board connected vertically (3) and the second stringer board (4);It is fixedly connected with the first stringer board (3) above transverse slat (2) side, the is fixedly connected with below the other side Two stringer boards (4);The transverse slat (2), the first stringer board (3) and the second stringer board (4) are integrated design;First stringer board (3) is fixedly connected Curtain wall cross beam, the second stringer board (4) are fixed on structure outer, and waterproof roll is equipped on the outside of the splash guard ontology (1), described Splash guard ontology (1) uses material of the same race, described splash guard ontology (1) one end fixed using screw (5) with Curtain wall frame crossbeam On crossbeam, the other end is fixed on using nailing on structure outer, and the splash guard ontology (1) isType;It is characterized in that, when specifically used, one piece is added in the crossbeam of curtain wall systemThe splash guard of type, curtain wall cross beam After installation is complete, splash guard can be installed, one end is screwed on crossbeam, the other end is fixed on structure using nailing On exterior wall, then, then by the waterproof roll paving of wall face on the splash guard added, Curtain Wall is formed one with structure A unified waterproof is whole, enhances the waterproof effect of curtain wall and structure connection, effectively blocks pouring in down a chimney for rainy day rainwater.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610620721.1A CN106149903B (en) | 2016-08-01 | 2016-08-01 | A kind of curtain wall first floor and structure are plugged into the application methods of the flashing devices at position |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610620721.1A CN106149903B (en) | 2016-08-01 | 2016-08-01 | A kind of curtain wall first floor and structure are plugged into the application methods of the flashing devices at position |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106149903A CN106149903A (en) | 2016-11-23 |
CN106149903B true CN106149903B (en) | 2018-10-16 |
Family
ID=57328254
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610620721.1A Active CN106149903B (en) | 2016-08-01 | 2016-08-01 | A kind of curtain wall first floor and structure are plugged into the application methods of the flashing devices at position |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106149903B (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201424764Y (en) * | 2009-05-27 | 2010-03-17 | 深圳市卓宝科技股份有限公司 | Warm-keeping and waterproof structure for decorative end |
CN202850224U (en) * | 2012-08-16 | 2013-04-03 | 原平市丰元彩钢结构有限公司 | Waterproof plate |
CN202899320U (en) * | 2012-10-08 | 2013-04-24 | 佛山市利铭蜂窝复合材料有限公司 | Waterproof component of portable house |
CN203603326U (en) * | 2013-12-10 | 2014-05-21 | 苏州苏明装饰股份有限公司 | Back-bolt type dry-hanging curtain wall system |
CN203924426U (en) * | 2014-06-19 | 2014-11-05 | 深圳市科源建设集团有限公司 | The window top waterproof construction of potter's clay curtain wall |
CN205894330U (en) * | 2016-08-01 | 2017-01-18 | 中铁十六局集团城市建设发展有限公司 | Plug into waterproof board device of position department of curtain first floor and structure |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09256487A (en) * | 1996-03-21 | 1997-09-30 | Riboole:Kk | Waterproof construction method for building |
-
2016
- 2016-08-01 CN CN201610620721.1A patent/CN106149903B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201424764Y (en) * | 2009-05-27 | 2010-03-17 | 深圳市卓宝科技股份有限公司 | Warm-keeping and waterproof structure for decorative end |
CN202850224U (en) * | 2012-08-16 | 2013-04-03 | 原平市丰元彩钢结构有限公司 | Waterproof plate |
CN202899320U (en) * | 2012-10-08 | 2013-04-24 | 佛山市利铭蜂窝复合材料有限公司 | Waterproof component of portable house |
CN203603326U (en) * | 2013-12-10 | 2014-05-21 | 苏州苏明装饰股份有限公司 | Back-bolt type dry-hanging curtain wall system |
CN203924426U (en) * | 2014-06-19 | 2014-11-05 | 深圳市科源建设集团有限公司 | The window top waterproof construction of potter's clay curtain wall |
CN205894330U (en) * | 2016-08-01 | 2017-01-18 | 中铁十六局集团城市建设发展有限公司 | Plug into waterproof board device of position department of curtain first floor and structure |
Also Published As
Publication number | Publication date |
---|---|
CN106149903A (en) | 2016-11-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104631857B (en) | Movable dwellings | |
CN206888294U (en) | A kind of glass curtain wall for being easy to splicing | |
CN204300966U (en) | Transformer station's optical lighting system | |
CN205840177U (en) | Steel structure canopy | |
CN203613645U (en) | Modular prefabricated movable house | |
CN106149903B (en) | A kind of curtain wall first floor and structure are plugged into the application methods of the flashing devices at position | |
CN204002293U (en) | Steel-structure factory building brick wall and color steel wall junction waterproof are received limit | |
CN209854922U (en) | Prefabricated assembled reinforced concrete prefabricated house | |
CN202831425U (en) | Plane roof with inner roof gutter drainage device | |
CN203613698U (en) | Roof for mobile house | |
CN205000360U (en) | Basement structure with waterproof structure | |
CN205894330U (en) | Plug into waterproof board device of position department of curtain first floor and structure | |
CN203932906U (en) | A kind of new antenna mounting structure | |
CN204266404U (en) | A kind of outer-wall crack-resisting anti-leakage structure | |
CN203613646U (en) | Prefabricated house convenient for wiring | |
CN203613675U (en) | Wall body for mobile house | |
CN204876217U (en) | Building decorative curtain wall convenient to drainage | |
CN203613826U (en) | Mobile house | |
CN208792537U (en) | A kind of prefabricated assembled exterior wall and prefabrication | |
CN207749687U (en) | A kind of Spliced type energy-saving curtain wall | |
CN205024953U (en) | Novel side fascia | |
CN205260000U (en) | Civil air defense engineering tubular well shutoff structure | |
CN202731319U (en) | Foldable horizontal protector between outer climb frame and building | |
CN219011910U (en) | Waterproof template system is strengthened to outer wall water-stop wing ring sleeve pipe | |
CN202787725U (en) | Waterproof structure for parapet wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |