CN106149751A - Utilize the method that quick lime brick quarrel compaction pile reinforces building construction ground - Google Patents
Utilize the method that quick lime brick quarrel compaction pile reinforces building construction ground Download PDFInfo
- Publication number
- CN106149751A CN106149751A CN201510281705.XA CN201510281705A CN106149751A CN 106149751 A CN106149751 A CN 106149751A CN 201510281705 A CN201510281705 A CN 201510281705A CN 106149751 A CN106149751 A CN 106149751A
- Authority
- CN
- China
- Prior art keywords
- pile
- construction
- soil
- foundation
- brick
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明涉及一种对房屋建筑地基处理采取的加固施工方法,尤其涉及一种利用生石灰砖碴挤密桩加固房屋建筑地基的方法,采用生石灰、砖碴、土、水泥为原料,灌入地基的桩孔中,桩孔采用冲击成孔,桩端用砖碴夯实,采用工艺为:施工准备→施工放线→施工降水→冲击成孔→分层灌注→夯实封顶,在基础周围布孔,用冲击钻冲击成孔,成孔过程中桩间土得到挤密,把生石灰、砖碴、土、水泥原料混合后,打入地基土桩孔中,生石灰吸水膨胀使桩间土发生二次挤密效应,桩端用砖碴夯实,砖碴起硬骨料作用,使桩身直立挺拔,能有效增加地基土的强度,提高地基土承载力,改善了地基土的均匀性,防止地基基础因受力不均发生沉降变形,具有造价低,无环境污染,能缩短工期。The invention relates to a reinforcement construction method for building foundation treatment, in particular to a method for strengthening the foundation of a building by utilizing quicklime brick ballast compaction piles, using quicklime, brick ballast, soil, and cement as raw materials and pouring into the foundation In the pile hole, the pile hole is formed by impact, and the pile end is compacted with brick ballast. The adopted process is: construction preparation→construction setting out→construction precipitation→impact hole forming→layer pouring→tamping and capping. The percussion drill impacts the hole, and the soil between the piles is compacted during the hole formation process. After mixing quicklime, brick slag, soil, and cement raw materials, they are driven into the pile hole of the foundation soil. The quicklime absorbs water and expands to cause secondary compaction of the soil between the piles. effect, the pile end is rammed with brick ballast, and the brick ballast acts as a hard aggregate, making the pile upright and upright, which can effectively increase the strength of the foundation soil, improve the bearing capacity of the foundation soil, improve the uniformity of the foundation soil, and prevent the foundation from being damaged due to Settlement deformation occurs due to uneven force, low cost, no environmental pollution, and can shorten the construction period.
Description
技术领域 technical field
本发明属于地基加固处理技术领域,涉及一种对房屋建筑地基处理采取的加固施工方法,尤其涉及一种利用生石灰砖碴挤密桩加固房屋建筑地基的方法。 The invention belongs to the technical field of foundation reinforcement treatment, and relates to a reinforcement construction method adopted for the foundation treatment of a building, in particular to a method for reinforcing the foundation of a building by using quicklime brick compaction piles.
背景技术 Background technique
多年来建筑地基处理多采用砼灌注桩、水泥土搅拌桩,但是这些现有技术普遍存在如下缺点:1、工程造价比较高。例如一般6层住宅楼的基础造价当承载力fak=80~l00KPa采用砼灌注桩基础造价80元/m2;采用水泥土搅拌桩基础造价45元/m2,而采用生石灰砖碴挤密桩天然基础造价仅30元/m2;可见本发明可有效降低成本且又保证工程质量。2、施工进度慢。由于在现有技术中使用的机械设备庞大和沉重,工期较长,施工时不能做到机动灵活,且还受到场地、水、电、燃料等限制,所以施工进度受到一定影响。3、污染环境,有噪声。强烈的震动和噪音,泥浆外运和堆放,对周围群众的日常生活造成影响,存在噪声污染、环境污染和扰民现象。4、成桩质量受到一定限制。传统灌注桩、复合地基处理方法,多以摩擦力为主,施工时受地下水、土层、成桩工艺等影响,易产生缩颈、断桩、砼离析、沉渣过厚等工程质量问题。 Concrete pouring piles and cement-soil mixing piles have been mostly used in building foundation treatment for many years, but these prior art ubiquitous following shortcoming: 1, engineering cost is relatively high. For example, if the foundation cost of a general 6-story residential building has a bearing capacity of fak=80-l00KPa, the cost of concrete pouring pile foundation is 80 yuan/m2; the foundation cost of cement-soil mixing pile is 45 yuan/m2, and the natural foundation of quicklime brick compaction pile The construction cost is only 30 yuan/m2; it can be seen that the present invention can effectively reduce the cost and ensure the project quality. 2. The construction progress is slow. Because the mechanical equipment used in the prior art is huge and heavy, the construction period is long, the construction cannot be flexible, and it is also limited by the site, water, electricity, fuel, etc., so the construction progress is affected to a certain extent. 3. Pollution and noise. Strong vibrations and noises, mud transportation and stacking have affected the daily life of the surrounding people, resulting in noise pollution, environmental pollution and nuisance. 4. The pile quality is limited. Traditional cast-in-place piles and composite foundation treatment methods are mostly based on friction. During construction, affected by groundwater, soil layers, and pile-forming technology, etc., engineering quality problems such as necking, broken piles, concrete segregation, and excessive sediment thickness are prone to occur.
发明内容 Contents of the invention
本发明的目的在于克服现有技术中存在的不足而提供一种能有效增加地基土的强度,提高地基土承载力,改善地基土的均匀性,防止地基基础因受力不均发生沉降变形的利用生石灰砖碴挤密桩加固房屋建筑地基的方法。 The purpose of the present invention is to overcome the deficiencies in the prior art and provide a foundation soil that can effectively increase the strength of the foundation soil, improve the bearing capacity of the foundation soil, improve the uniformity of the foundation soil, and prevent the foundation from settlement deformation due to uneven force. The invention discloses a method for strengthening the foundation of a building by utilizing quicklime brick slag compaction piles.
本发明的目的是这样实现的:一种利用生石灰砖碴挤密桩加固房屋建筑地基的方法,其特征在于:采用生石灰、砖碴、土、水泥为原料,灌入地基的桩孔中,桩孔采用冲击成孔,桩端用砖碴夯实,采用如下工艺流程:施工准备→施工放线→施工降水→冲击成孔→分层灌注→夯实封顶,具体步骤如下: The purpose of the present invention is achieved in the following way: a method for reinforcing the foundation of a building by utilizing quicklime brick slag compaction piles, which is characterized in that: quicklime, brick slag, soil, and cement are used as raw materials to be poured into the pile holes of the foundation, and the piles The hole is formed by impact, and the pile end is compacted with brick ballast. The following process is adopted: construction preparation→construction setting out→construction precipitation→impact hole formation→layer pouring→tamping and capping. The specific steps are as follows:
步骤1)施工准备:备齐原材料,备齐施工机具:50型冲击钻机、洛阳铲、夯实设备、夯锤,通水、通电; Step 1) Construction preparation: Prepare raw materials and construction equipment: 50-type impact drilling rig, Luoyang shovel, compaction equipment, rammer, water supply and electricity supply;
步骤2)施工放线:按正方形、梅花形或等边三角形布置; Step 2) Construction setting out: arrange in square, quincunx or equilateral triangle;
步骤3)施工降水:为保证成孔及桩体质量,施工前应先降低施工地点的水位; Step 3) Dewatering during construction: In order to ensure the quality of holes and piles, the water level at the construction site should be lowered before construction;
步骤4)冲击成孔:按放好的桩位用50型冲击钻机,或场地狭窄无法机械施工时用洛阳铲成桩孔,先周边后中间; Step 4) Impact hole formation: Use a 50-type impact drill according to the pile position placed, or use a Luoyang shovel to form pile holes when the site is narrow and cannot be mechanically constructed, first at the periphery and then in the middle;
步骤5)分层填注:桩径和深度满足设计要求后开始填注,为了保证桩端承载力,桩端先填30 cm厚的碎砖块,用锤夯20--30次,提锤高度80-100cm;碎砖块都进入周围土中后,再填20 cm的碎砖碴,夯l5-20次;桩端夯实后,将拌和物灌入桩孔内,铺厚度30cm,夯l5-20次,提锤高度80-100cm;拌和物的配制重量比例为:在桩孔内地下水位以上,拌和物采用生石灰﹕砖碴﹕土=1﹕l﹕2,在桩孔内地下水位以下,拌和物采用生石灰﹕水泥﹕砖碴﹕土=1﹕0.5﹕1﹕3; Step 5) Filling in layers: Start filling after the pile diameter and depth meet the design requirements. In order to ensure the bearing capacity of the pile tip, first fill the pile tip with 30 cm thick broken bricks, tamp with a hammer 20-30 times, lift the hammer The height is 80-100cm; after all the broken bricks have entered the surrounding soil, fill in 20 cm of broken brick dregs and tamp l5-20 times; -20 times, the height of the hammer is 80-100cm; the weight ratio of the mixture is: above the groundwater level in the pile hole, the mixture is quicklime: brick ballast: soil = 1: l: 2, below the groundwater level in the pile hole , the mixture uses quicklime: cement: brick ballast: soil = 1:0.5:1:3;
步骤6)夯实封顶:封顶用素土分层夯填至地面封孔,厚度不少于30 cm。 Step 6) Ramming and capping: the capping layer shall be rammed and filled with plain soil to the ground to seal the hole, the thickness shall not be less than 30 cm.
在步骤5)中,向孔内填料前,孔底应夯实,并应抽样检查桩孔的直径、深度和垂直度;桩孔的垂直度偏差不大于1.5%;经检验合格后应按设计要求向孔内分层填入配合好的拌和物。 In step 5), before filling the hole, the bottom of the hole should be compacted, and the diameter, depth and verticality of the pile hole should be checked by sampling; the verticality deviation of the pile hole should not be greater than 1.5%; after passing the inspection, it should be in accordance with the design requirements Fill the well-mixed mixture into the hole layer by layer.
当整片处理时从里或中间向外间隔1-2孔进行,对大型工程采取分段施工,当局部处理时,从外向里间隔1-2孔进行;对大面积满足处理用等边三角形,对单独基础或条形基础用正方形,矩形或等腰三角形布置。 When processing the whole piece, it is carried out at intervals of 1-2 holes from the inside or the middle to the outside. For large-scale projects, the construction is carried out in sections. , use squares, rectangles or isosceles triangles for individual foundations or strip foundations.
在上述步骤完成后还需要进行地基检测与检验:具体是根据工程要求和当地经验采用开挖检查、静力触探或标准贯入试验、轻便触探试验、竖向抗压载荷试验方法进行检验,并应结合工程测试及观测资料综合评价加固效果;施工检测在施工后7-10天进行。 After the above steps are completed, foundation detection and inspection are required: specifically, excavation inspection, static penetration test or standard penetration test, portable penetration test, and vertical compressive load test are used for inspection according to engineering requirements and local experience. , and should be combined with engineering testing and observation data to comprehensively evaluate the reinforcement effect; construction testing should be carried out 7-10 days after construction.
采用静力触探或标准贯入试验、轻便触探试验检测时,检测部位为桩中心及桩间土,每两点为一组,检测组数应符合设计要求;载荷试验应在桩体强度满足试验荷载条件,且在成桩28天后进行。 When the static penetration test, standard penetration test, and portable penetration test are used for detection, the detection site is the pile center and the soil between the piles, and every two points are a group, and the number of detection groups should meet the design requirements; Satisfy the test load conditions and carry out 28 days after pile formation.
本发明在基础周围布孔,用冲击钻冲击成孔,成孔过程中桩间土得到挤密,然后把生石灰、砖碴、土、水泥等原料,按一定的比例混合后,打入地基土的桩孔中后,生石灰吸水膨胀使桩间土发生二次挤密效应,桩端用砖碴夯实,砖碴起硬骨料作用,使桩身直立挺拔,这样所形成的由地基土和增强体共同承担荷载的人工地基,能有效增加地基土的强度,提高地基土承载力,改善了地基土的均匀性,防止了地基基础因受力不均发生沉降变形。具有造价低,无环境污染,能缩短工期。具有良好的经济效益、社会效益和环境效益,在我国中小城市建设发展,特别是对多层房屋建筑地基的处理与应用有着较大的发展空间。 The invention arranges holes around the foundation, impacts the holes with a percussion drill, and compacts the soil between the piles during the hole forming process, then mixes quicklime, brick ballast, soil, cement and other raw materials in a certain proportion, and drives them into the foundation soil After the quicklime absorbs water and expands, the soil between the piles will undergo a secondary compaction effect, and the pile ends will be compacted with brick ballast, which acts as a hard aggregate to make the pile stand upright. The artificial foundation that bears the load jointly with the body can effectively increase the strength of the foundation soil, improve the bearing capacity of the foundation soil, improve the uniformity of the foundation soil, and prevent the foundation from settlement deformation due to uneven force. The utility model has the advantages of low cost, no environmental pollution, and can shorten the construction period. It has good economic benefits, social benefits and environmental benefits, and has a large development space in the construction and development of small and medium-sized cities in my country, especially for the treatment and application of multi-storey building foundations.
具体实施方式 detailed description
本发明的具体方法为在拟建建筑物基础周围布孔,用冲击钻冲击成孔,成孔过程中桩间土得到挤密,然后把生石灰、砖碴、土、水泥等原料,按一定的比例混合后,打入地基土的桩孔中后,生石灰吸水膨胀使桩间土发生二次挤密效应,桩端用砖碴夯实,砖碴起硬骨料作用,使桩身直立挺拔,这样所形成的由地基土和增强体共同承担荷载的人工地基,能有效增加地基土的强度,提高地基土承载力,改善了地基土的均匀性,防止了地基基础因受力不均发生沉降变形。 The specific method of the present invention is to arrange holes around the foundation of the building to be built, and impact the holes with a percussion drill. After being mixed in proportion and driven into the pile hole of the foundation soil, the quicklime absorbs water and expands to cause a secondary compaction effect on the soil between the piles. The formed artificial foundation, which is jointly borne by the foundation soil and the reinforcement, can effectively increase the strength of the foundation soil, improve the bearing capacity of the foundation soil, improve the uniformity of the foundation soil, and prevent the settlement and deformation of the foundation due to uneven force. .
本发明的生石灰砖碴挤密桩复合地基简称挤密生石灰桩,是采用生石灰、砖碴、土、水泥为原料,按一定的比例混合后,灌入地基的桩孔中,桩孔采用冲击成孔,该机械是佳木斯生产的50型钻机,桩端用砖碴夯实,由于采用的是冲击成孔,桩间土得到了挤密,生石灰吸水膨胀使桩间土二次挤密,砖碴起硬骨料作用,使桩身直立挺拔所形成的由地基土和增强体共同承担荷载的人工地基。能有效增加地基的强度和均匀性,提高地基承载力,从而满足基础设计的要求。采用如下工艺流程:施工准备→施工放线→施工降水(地下水位较浅时)→冲击成孔→分层灌注→夯实封顶。具体实施步骤如下: The quicklime brick ballast compacted pile composite foundation of the present invention is called compact quicklime pile for short. It uses quicklime, brick ballast, soil, and cement as raw materials. After mixing them in a certain proportion, they are poured into the pile holes of the foundation. hole, the machine is a 50-type drilling rig produced by Jiamusi, and the pile ends are compacted with brick ballast. Because the impact hole is used, the soil between the piles is compacted. The effect of hard aggregate makes the pile body upright and straight, forming an artificial foundation that bears the load jointly by the foundation soil and the reinforcement. It can effectively increase the strength and uniformity of the foundation, improve the bearing capacity of the foundation, so as to meet the requirements of foundation design. The following technological process is adopted: construction preparation→construction setting out→construction precipitation (when the groundwater table is relatively shallow)→impact hole formation→layered pouring→tamping and capping. The specific implementation steps are as follows:
步骤1)施工准备:①备齐原材料,按各项指标要求进行加工待用。②备齐施工机具:50型冲击钻机、洛阳铲、夯实设备、 夯锤(重量约12.5kg) 等。③通水、通电。 Step 1) Construction preparation: ① Raw materials are prepared and processed according to the requirements of various indicators for use. ②Preparation of construction equipment: Type 50 impact drilling rig, Luoyang shovel, compaction equipment, rammer (weight about 12.5kg), etc. ③ Connect water and electricity.
步骤2)施工放线:按正方形、梅花形或等边三角形布置; Step 2) Construction setting out: arrange in square, quincunx or equilateral triangle;
步骤3)施工降水:为保证成孔及桩体质量,施工前应先降低施工地点的水位; 因此如果地下水位较浅,为保证成孔及桩体质量,施工前应先降水。 Step 3) Precipitation during construction: In order to ensure the quality of holes and piles, the water level at the construction site should be lowered before construction; therefore, if the groundwater level is shallow, precipitation should be carried out before construction to ensure the quality of holes and piles.
步骤4)冲击成孔:按放好的桩位用50型冲击钻机,或场地狭窄无法机械施工时用洛阳铲成桩孔,先周边后中间; Step 4) Impact hole formation: Use a 50-type impact drill according to the pile position placed, or use a Luoyang shovel to form pile holes when the site is narrow and cannot be mechanically constructed, first at the periphery and then in the middle;
步骤5)分层填注:桩径和深度满足设计要求后开始填注, Step 5) Filling in layers: Start filling after the pile diameter and depth meet the design requirements,
①为了保证桩端承载力,桩端先填30 cm厚的碎砖块,用锤夯20--30次,提锤高度80-100cm; ①In order to ensure the bearing capacity of the pile end, the pile end is first filled with 30 cm thick broken bricks, rammed with a hammer for 20-30 times, and the height of the hammer is 80-100cm;
②碎砖块都进入周围土中后,再填20 cm的碎砖碴,夯l5-20次; ② After all the broken bricks have entered the surrounding soil, fill in 20 cm of broken brick ballast and tamp 15-20 times;
③桩端夯实后,将拌和物灌入桩孔内,铺厚度30cm,夯l5-20次,提锤高度80-100cm;拌和物的配制重量比例为:在桩孔内地下水位以上,拌和物采用生石灰﹕砖碴﹕土=1﹕l﹕2,在桩孔内地下水位以下,拌和物采用生石灰﹕水泥﹕砖碴﹕土=1﹕0.5﹕1﹕3; ③After the pile end is compacted, pour the mixture into the pile hole, pave the thickness of 30cm, tamp 15-20 times, lift the hammer height 80-100cm; the weight ratio of the mixture is: above the groundwater level in the pile hole, the mixture Quicklime: brick ballast: soil = 1: l: 2, below the groundwater level in the pile hole, quicklime: cement: brick ballast: soil = 1:0.5:1:3;
步骤6)夯实封顶:分层用锤夯实至设计标高,然后封顶,封顶用素土分层夯填至地面封孔,厚度不少于30 cm。 Step 6) Tamping and capping: use a hammer to compact the layers to the design elevation, and then cap the roof, and then ram and fill the roof with plain soil layer by layer to seal the hole on the ground, with a thickness of not less than 30 cm.
在步骤5)中,向孔内填料前,孔底应夯实,并应抽样检查桩孔的直径、深度和垂直度;桩孔的垂直度偏差不大于1.5%;经检验合格后应按设计要求向孔内分层填入配合好的拌和物。 In step 5), before filling the hole, the bottom of the hole should be compacted, and the diameter, depth and verticality of the pile hole should be checked by sampling; the verticality deviation of the pile hole should not be greater than 1.5%; after passing the inspection, it should be in accordance with the design requirements Fill the well-mixed mixture into the hole layer by layer.
当整片处理时从里或中间向外间隔1-2孔进行,对大型工程采取分段施工,当局部处理时,从外向里间隔1-2孔进行;对大面积满足处理用等边三角形,对单独基础或条形基础用正方形,矩形或等腰三角形布置。 When processing the whole piece, it is carried out at intervals of 1-2 holes from the inside or the middle to the outside. For large-scale projects, the construction is carried out in sections. , use squares, rectangles or isosceles triangles for individual foundations or strip foundations.
在上述步骤完成后还需要进行地基检测与检验:具体是根据工程要求和当地经验采用开挖检查、静力触探或标准贯入试验、轻便触探试验、竖向抗压载荷试验方法进行检验,并应结合工程测试及观测资料综合评价加固效果;施工检测在施工后7-10天进行。 After the above steps are completed, foundation detection and inspection are required: specifically, excavation inspection, static penetration test or standard penetration test, portable penetration test, and vertical compressive load test are used for inspection according to engineering requirements and local experience. , and should be combined with engineering testing and observation data to comprehensively evaluate the reinforcement effect; construction testing should be carried out 7-10 days after construction.
采用静力触探或标准贯入试验、轻便触探试验检测时,检测部位为桩中心及桩间土,每两点为一组,检测组数应符合设计要求;载荷试验应在桩体强度满足试验荷载条件,且在成桩28天后进行。 When the static penetration test, standard penetration test, and portable penetration test are used for detection, the detection site is the pile center and the soil between the piles, and every two points are a group, and the number of detection groups should meet the design requirements; Satisfy the test load conditions and carry out 28 days after pile formation.
施工要点及注意事项: Construction points and precautions:
1、施工要点: 1. Construction points:
①为了保证桩端承载力,桩端先填30cm厚的碎砖块,用锤夯20--30次,提锤高度80~1 00cm; ①In order to ensure the bearing capacity of the pile end, first fill the pile end with 30cm thick broken bricks, ram it with a hammer for 20-30 times, and lift the hammer height to 80-100cm;
②若碎砖块都进入周围土中,再填20cm的碎砖碴,夯l5--20次; ② If all the broken bricks have entered the surrounding soil, fill in 20cm of broken bricks and tamp 15-20 times;
③桩端夯实后,将拌和物(按一定的重量比例生石灰:砖碴:土=1:l:2和生石灰:水泥:砖碴:土=1:0.5:1:3(主要用于水下))填入孔内,铺厚度30cm左右,夯l5---20次,提锤高度80--100cm. ③ After the pile ends are compacted, mix the mixture (according to a certain weight ratio of quicklime: brick ballast: soil = 1: 1: 2 and quicklime: cement: brick ballast: soil = 1: 0.5: 1: 3 (mainly used for Underwater)) Fill in the hole, pave the thickness of about 30cm, tamp l5---20 times, lift the hammer height 80--100cm.
④封顶用素土分层夯填至地面封孔,厚度不少于30cm。 ④The roof shall be filled with plain soil layer by layer to seal the hole on the ground, the thickness shall not be less than 30cm.
2、注意事项: 2. Matters needing attention:
①向孔内填料前,孔底应夯实,并应抽样检查桩孔的直径、深度和垂直度; ①Before filling the hole, the bottom of the hole should be compacted, and the diameter, depth and verticality of the pile hole should be checked by sampling;
②桩孔的垂直度偏差不宜大于1.5%; ②The vertical deviation of the pile hole should not be greater than 1.5%;
③经检验合格后应按设计要求向孔内分层填入配合好的拌和物; ③ After passing the inspection, the well-fitted mixture should be filled into the hole layer by layer according to the design requirements;
④当整片处理时宜从里(或中间)向外间隔1-2孔进行。对大型工程可采取分段施工,当局部处理时,宜从外向里间隔1-2孔进行; ④ When processing the whole piece, it should be carried out from the inside (or the middle) to the outside at intervals of 1-2 holes. Segmented construction can be adopted for large-scale projects. When local treatment is carried out, it should be carried out at intervals of 1-2 holes from the outside to the inside;
⑤对大面积满足处理宜用等边三角形,对单独基础或条形基础宜用正方形,矩形或等腰三角形布置。 ⑤ Equilateral triangles should be used for large-area satisfactory treatment, and square, rectangular or isosceles triangle arrangements should be used for individual foundations or strip foundations.
3、试桩检测: 3. Pile test:
3.1复合地基检测与检验可根据工程要求和当地经验采用开挖检查、静力触探或标准贯入、轻便触探试验、竖向抗压载荷试验等方法进行检验,并应结合工程测试及观测资料综合评价加固效果。施工检测宜在施工后7-10天进行。 3.1 Composite foundation detection and inspection can be carried out by means of excavation inspection, static penetration or standard penetration, portable penetration test, vertical compressive load test and other methods according to engineering requirements and local experience, and should be combined with engineering testing and observation Comprehensive evaluation of reinforcement effect based on data. Construction testing should be carried out 7-10 days after construction.
3.2采用静力触探或标准贯入试验、轻便触探试验检测时,检测部位应为桩中心及桩间土,应每两点为一组。检测组数应符合设计要求。 3.2 When the static penetration test, standard penetration test, and portable penetration test are used for detection, the detection site should be the pile center and the soil between the piles, and every two points should be a group. The number of detection groups should meet the design requirements.
3.3载荷试验应在桩体强度满足试验荷载条件,且在成桩28天后进行。检测数量应符合设计要求。 3.3 The load test should be carried out after the pile strength meets the test load conditions and 28 days after the pile is formed. The number of tests shall meet the design requirements.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510281705.XA CN106149751B (en) | 2015-05-28 | 2015-05-28 | The method for reinforcing building construction ground using quick lime brick quarrel compaction pile |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510281705.XA CN106149751B (en) | 2015-05-28 | 2015-05-28 | The method for reinforcing building construction ground using quick lime brick quarrel compaction pile |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106149751A true CN106149751A (en) | 2016-11-23 |
| CN106149751B CN106149751B (en) | 2018-06-19 |
Family
ID=57348141
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510281705.XA Expired - Fee Related CN106149751B (en) | 2015-05-28 | 2015-05-28 | The method for reinforcing building construction ground using quick lime brick quarrel compaction pile |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106149751B (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108104106A (en) * | 2016-11-24 | 2018-06-01 | 神翼航空器科技(天津)有限公司 | Existing building essential bearing stratum reinforcement |
| CN111140199A (en) * | 2019-12-25 | 2020-05-12 | 北京正和恒基滨水生态环境治理股份有限公司 | Shaft plugging method |
| CN112609667A (en) * | 2020-12-22 | 2021-04-06 | 中铁三局集团有限公司 | Construction method for reinforcing earthwork compaction degree of lime-sand pile in small-span cross beam |
| CN113174951A (en) * | 2021-04-30 | 2021-07-27 | 福建永宏建设工程有限公司 | Construction device and method for reinforcing soft soil roadbed by self-expansion compaction pile with high bearing capacity |
| CN115822009A (en) * | 2022-11-30 | 2023-03-21 | 西安建科品匠工程技术有限公司 | A lime pile foundation deviation correction structure and its construction method |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| AU677908B2 (en) * | 1994-06-24 | 1997-05-08 | Qc Bricks Pty Ltd | Brick wall on piers |
| CN101798809A (en) * | 2010-03-16 | 2010-08-11 | 朱建新 | Non-borrow composite underreamed pile constructing method |
| CN102733376A (en) * | 2012-07-02 | 2012-10-17 | 朱建新 | Composite pile and construction method thereof |
| CN102864774A (en) * | 2012-10-10 | 2013-01-09 | 江苏南通六建建设集团有限公司 | Shrinkage treatment construction method for composite foundation- lime soil compaction piles |
-
2015
- 2015-05-28 CN CN201510281705.XA patent/CN106149751B/en not_active Expired - Fee Related
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| AU677908B2 (en) * | 1994-06-24 | 1997-05-08 | Qc Bricks Pty Ltd | Brick wall on piers |
| CN101798809A (en) * | 2010-03-16 | 2010-08-11 | 朱建新 | Non-borrow composite underreamed pile constructing method |
| CN102733376A (en) * | 2012-07-02 | 2012-10-17 | 朱建新 | Composite pile and construction method thereof |
| CN102864774A (en) * | 2012-10-10 | 2013-01-09 | 江苏南通六建建设集团有限公司 | Shrinkage treatment construction method for composite foundation- lime soil compaction piles |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108104106A (en) * | 2016-11-24 | 2018-06-01 | 神翼航空器科技(天津)有限公司 | Existing building essential bearing stratum reinforcement |
| CN111140199A (en) * | 2019-12-25 | 2020-05-12 | 北京正和恒基滨水生态环境治理股份有限公司 | Shaft plugging method |
| CN112609667A (en) * | 2020-12-22 | 2021-04-06 | 中铁三局集团有限公司 | Construction method for reinforcing earthwork compaction degree of lime-sand pile in small-span cross beam |
| CN113174951A (en) * | 2021-04-30 | 2021-07-27 | 福建永宏建设工程有限公司 | Construction device and method for reinforcing soft soil roadbed by self-expansion compaction pile with high bearing capacity |
| CN113174951B (en) * | 2021-04-30 | 2022-06-14 | 福建永宏建设工程有限公司 | Construction device and method for strengthening soft soil subgrade by self-expanding compaction piles with rich and high bearing capacity |
| CN115822009A (en) * | 2022-11-30 | 2023-03-21 | 西安建科品匠工程技术有限公司 | A lime pile foundation deviation correction structure and its construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106149751B (en) | 2018-06-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102080373B (en) | Construction method for jointly treating collapsibility of loess foundation by using DDC (Downhole Dynamic Compaction) pile and pile foundation | |
| CN108343102B (en) | Pile foundation settlement reinforcement jacking leveling structure and construction method thereof | |
| CN102277867B (en) | A construction method of collapsible loess foundation | |
| CN102535477B (en) | Safety construction method for cutting off anchor cables of support of excavating foundation pit | |
| CN109208625B (en) | A construction method for strengthening and strengthening karst caves of underground pile foundations | |
| CN106149751B (en) | The method for reinforcing building construction ground using quick lime brick quarrel compaction pile | |
| CN103422501B (en) | Anti-floating anchor rod structure in sand seam geology and construction method thereof | |
| CN102021906A (en) | Method for reinforcing soft soil foundation at deep mixing pile | |
| CN104404838B (en) | The above railway collapsible loess subgrade substrate treating method of speed 200km | |
| CN108797587A (en) | A kind of novel sinking construction technology of static pressed pile | |
| CN108560542B (en) | A kind of bidirectional reinforcement of waste tire covering building slag and construction method thereof | |
| CN101899828B (en) | Construction method of bagged rammed small-diameter soil-cement pile composite foundation | |
| CN103821139A (en) | Reamed carrier and stiffness core multi-component composite pile and soft soil foundation strengthening construction method | |
| CN110219300B (en) | Construction process of partially-bonded prestressed uplift anchor rod | |
| CN102400462A (en) | Secondary grouting small pile construction process in foundation anti-seismic reinforcement treatment | |
| CN103628508B (en) | The experimental rig of simulation stake rear flank slip casting uplift pile pile-soil interface physical property | |
| CN104762956B (en) | A pile-forming method based on recycled aggregate piles from construction waste | |
| CN104947648A (en) | Deep replacement dynamic compaction gravel pile foundation reinforcement method | |
| CN105735236B (en) | The soil body pre-add solid method that continuous wall trench underground is constructed in a kind of thick mud layer | |
| CN108571330A (en) | Method for treating leakage water of post-cast strip of subway bottom plate | |
| CN102605775A (en) | Combination pile of flexible pile and rigid pile concentrically arranged at upper end and lower end and pile forming method | |
| CN117364553A (en) | Karst cave piling method under complex geological conditions | |
| CN205224019U (en) | Stake of reinforcing bar fiber cement soil | |
| CN116446371A (en) | Construction method for soft soil foundation treatment by utilizing solid waste cementing recycled coarse aggregate | |
| CN203741824U (en) | Rammed carrier strong core multi-component composite pile |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180619 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |