CN106129906B - A kind of Industrial Engineering cable process information processing method - Google Patents

A kind of Industrial Engineering cable process information processing method Download PDF

Info

Publication number
CN106129906B
CN106129906B CN201610504953.0A CN201610504953A CN106129906B CN 106129906 B CN106129906 B CN 106129906B CN 201610504953 A CN201610504953 A CN 201610504953A CN 106129906 B CN106129906 B CN 106129906B
Authority
CN
China
Prior art keywords
cable
information processing
next procedure
personnel
different
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610504953.0A
Other languages
Chinese (zh)
Other versions
CN106129906A (en
Inventor
贾隽
李少祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201610504953.0A priority Critical patent/CN106129906B/en
Publication of CN106129906A publication Critical patent/CN106129906A/en
Application granted granted Critical
Publication of CN106129906B publication Critical patent/CN106129906B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K19/00Record carriers for use with machines and with at least a part designed to carry digital markings
    • G06K19/06Record carriers for use with machines and with at least a part designed to carry digital markings characterised by the kind of the digital marking, e.g. shape, nature, code
    • G06K19/067Record carriers with conductive marks, printed circuits or semiconductor circuit elements, e.g. credit or identity cards also with resonating or responding marks without active components
    • G06K19/07Record carriers with conductive marks, printed circuits or semiconductor circuit elements, e.g. credit or identity cards also with resonating or responding marks without active components with integrated circuit chips

Abstract

The invention discloses a kind of Industrial Engineering cable process information processing methods, the following steps are included: S1, on cable be arranged ultrahigh frequency electronic tag as cable number plate, the setting flag position in ultrahigh frequency electronic tag, different marker bits correspond to different cable processes;S2, different process personnel log in hander software systems using default account, obtain different permissions.After hander identifies the ultra high frequency IC tag of cable, relevant information is shown according to permission;S3, process is completed to person number and deadline write-in label correspondence markings position;S4, by the analysis and statistics to previous process, instruction provided to the progress of next procedure and resource allocation from the background, and distribute to corresponding operating personnel;S5, complete cable laying all process steps after, count completion personnel and the deadline of all process steps, obtain integrated engineering scheduling network.The present invention can provide support for whole process information analysis, so that it is horizontal to improve the information processing of cable process.

Description

A kind of Industrial Engineering cable process information processing method
Technical field
The present invention relates to cable laying technical field more particularly to a kind of Industrial Engineering cable process information processing methods.
Background technique
Cable laying link is the emphasis link of electrical construction, and consumption resource is big, and holding time is long, output value accounting weight.Electricity Cable laying concerned process steps are more, such as: cable laying, cable connection, cable check and correction, monomer test run, linkage trial run.
The transmitting of traditional cable construction information is mostly carried out by artificial, more extensive, and real time monitoring process information is more difficult.It makes It is poor at procedure connection, increase duration consumption.The level of IT application of electrical construction entirety is lower, needs to think deeply solution. With the rapid development of BIM technology, also to the construction data of electric specialty, more stringent requirements are proposed, 4D, 5D in especially BIM And more advanced application, the requirement to process data is higher, needs to study the collection of bottom construction data and uploads mode.
Due to not forming information collection and processing to cable laying concerned process steps, going wrong cannot make in macroscopic view Specific aim adjustment, often result in progress monitoring cannot sufficiently flat peak cut paddy, idle lavishes labor on, and busy needs to consume more moneys Source.
Summary of the invention
The technical problem to be solved in the present invention is that low for the level of informatization in the prior art, process information monitors difficulty Big defect provides a kind of Industrial Engineering cable process information processing method that can be improved cable process processing level.
The technical solution adopted by the present invention to solve the technical problems is:
The present invention provides a kind of Industrial Engineering cable process information processing method, comprising the following steps:
S1, setting ultrahigh frequency electronic tag is as cable number plate on cable, the setting flag in ultrahigh frequency electronic tag Position, different marker bits correspond to different cable processes;
S2, the ultra high frequency IC tag that cable is identified by the way that numbered hander is arranged, the number of hander are corresponding different The different work personnel of process;
S3, after operating personnel completes process, process is completed into person number and deadline, label correspondence markings is written Position, as process information;
S4, process information is obtained, by the analysis and statistics to previous process, from the background to the progress of next procedure and resource Distribution provides instruction, and distributes to corresponding operating personnel;
S5, complete cable laying all process steps after, count completion personnel and the deadline of all process steps, obtain entirety Project progress network.
Further, the method for ultrahigh frequency electronic tag is set in step S1 of the invention are as follows:
The area Reserved, the area EPC, TID field and the area User are set in ultrahigh frequency electronic tag, are arranged in the area User different Marker bit correspond to different cable processes;Different cables are identified by critical field in marker bit.
Further, the method for critical field is set in step S1 of the invention are as follows:
Critical field includes process number, process label, time label and worker labels;Process number corresponds to different works Sequence;Process label record process completion status;Label record process deadline time;Worker labels record process and complete personnel Or personnel represent;
The electronic tag smaller for the area User only retains cable number using the set-up mode for simplifying marker bit Field, other fields change by recording from the background.
Further, method previous process analyzed and is counted in step S4 of the invention specifically:
The identical process of process number is counted, the process completion rate is calculated;
Process WnCompletion rate Rn=process W is completednCable count Nn/ cable sum N;
Process W in a certain systemn' completion rate RnProcess W is completed in '=n' cable count Nn'/cable sum N ';
Process W in a certain regionn" completion rate Rn"=be completed process Wn" cable count Nn"/cable sum N ".
Further, to process W in step S4 of the inventionnNext procedure Wn+1Progress provide the side of instruction Method specifically:
(1) R is setnThreshold value, start next procedure when the completion rate of process reaches threshold value;
(2) R of certain system is setn' threshold value starts next procedure when the completion rate of the system process reaches threshold value;
(3) R in certain region is setn" threshold value starts next procedure when the completion rate of the region process reaches threshold value;
(4) in the case where other particular/special requirements, start next procedure.
Further, for process W in step S4 of the inventionnNext procedure Wn+1Certain money is provided as follows Source Ren+1Instruction:
Statistics enters next procedure Wn+1Cable amount Nn+1, with following formula computing resource requirement:
Resource Ren+1Requirement=(cable amount Nn+1/ process resource efficiency En+1/ next procedure duration Tn+1)×Rn
Resource Ren+1Requirement only consider main resource, including personnel and main mechanical.
Further, the method for process information is obtained in step S4 of the invention specifically: high frequency is read by hander Electronic labeling information passes through manual operator and background synchronization.
The beneficial effect comprise that: Industrial Engineering cable process information processing method of the invention passes through correspondence The corresponding states word in the rewriting cable number plate of the system software in manual operator is logged in different work procedures personnel, to reach The function that personnel and deadline are completed to record flow chart, by read corresponding number plate status information or by manual operator with Background synchronization can reach the purpose for collecting complete cable process information;Guidance can be provided for subsequent handling construction later, it can also Support is provided for the analysis of whole process information, so that it is horizontal to improve the information processing of cable process.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples, in attached drawing:
Fig. 1 is the flow chart of the Industrial Engineering cable process information processing method of the embodiment of the present invention;
Fig. 2 is the label internal labeling position setting example of the Industrial Engineering cable process information processing method of the embodiment of the present invention Figure;
Fig. 3 is the hand-held set number setting example of the Industrial Engineering cable process information processing method of the embodiment of the present invention Figure.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not For limiting the present invention.
As shown in Figure 1, the Industrial Engineering cable process information processing method of the embodiment of the present invention, comprising the following steps:
S1, setting ultrahigh frequency electronic tag is as cable number plate on cable, the setting flag in ultrahigh frequency electronic tag Position, different marker bits correspond to different cable processes;
The method of ultrahigh frequency electronic tag is set are as follows:
The area Reserved, the area EPC, TID field and the area User are set in ultrahigh frequency electronic tag, are arranged in the area User different Marker bit correspond to different cable processes;Different cables are identified by critical field in marker bit.
The method of critical field is set are as follows:
Critical field includes process number, process label, time label and worker labels;Process number corresponds to different works Sequence;Process label record process completion status;Label record process deadline time;Worker labels record process and complete personnel Or personnel represent;
The electronic tag smaller for the area User only retains cable number using the set-up mode for simplifying marker bit Field, other fields change by recording from the background.
S2, the ultra high frequency IC tag that cable is identified by the way that numbered hander is arranged, the number of hander are corresponding different The different work personnel of process;
S3, after operating personnel completes process, process is completed into person number and deadline, label correspondence markings is written Position, as process information;
S4, process information is obtained, by the analysis and statistics to previous process, from the background to the progress of next procedure and resource Distribution provides instruction, and distributes to corresponding operating personnel;
The method that previous process is analyzed and is counted specifically:
The identical process of process number is counted, the process completion rate is calculated;
Process WnCompletion rate Rn=process W is completednCable count Nn/ cable sum N;
Process W in a certain systemn' completion rate RnProcess W is completed in '=n' cable count Nn'/cable sum N ';
Process W in a certain regionn" completion rate Rn"=be completed process Wn" cable count Nn"/cable sum N ".
To process WnNext procedure Wn+1The progress method that provides instruction specifically:
(1) R is setnThreshold value, start next procedure when the completion rate of process reaches threshold value;
(2) R of certain system is setn' threshold value starts next procedure when the completion rate of the system process reaches threshold value;
(3) R in certain region is setn" threshold value starts next procedure when the completion rate of the region process reaches threshold value;
(4) in the case where other particular/special requirements, start next procedure.
For process WnNext procedure Wn+1Certain resource Re is provided as followsn+1Instruction:
Statistics enters next procedure Wn+1Cable amount Nn+1, with following formula computing resource requirement:
Resource Ren+1Requirement=(cable amount Nn+1/ process resource efficiency En+1/ next procedure duration Tn+1)×Rn
Resource Ren+1Requirement only consider main resource, including personnel and main mechanical.
Obtain process information method specifically: by hander read ultra high frequency IC tag information or by manual operator with Background synchronization.
S5, complete cable laying all process steps after, count completion personnel and the deadline of all process steps, obtain entirety Project progress network.
As shown in Figures 2 and 3, in another specific embodiment of the invention:
User of the ultrahigh frequency electronic tag as cable number plate, in ultrahigh frequency electronic tag is arranged in step 1 on cable Area is provided with the process field of cable wiring.Cable number field is K-001, is the unique identification for distinguishing different cables;Process Number is 012;Process is labeled as 1 before process starts, and process label is changed to 2 after the completion of process;Simultaneously record process completion when Between the write time mark, such as 2016/6/2610:50;By wiring personnel number write-in worker labels' field of the cable, such as P- 023.The electronic tag smaller for the area User, can also be used the set-up mode of simplified marker bit, i.e., only retains cable number Field K-001, other fields change by recording from the background.
Step 2, wiring personnel P-023 log in hander software systems using default account, obtain corresponding authority.Hander After the ultra high frequency IC tag for identifying cable, the cable wiring information can be shown, such as: core wire size, core corresponding terminal number etc..
Step 3, after wiring personnel P-023 is completed with line procedures, process tag field can be changed by " 1 " with manual operator For " 2 ", the process has been completed in expression.Worker labels' field is written into wiring personnel number " P-023 ", by the deadline " 2016/6/26 10:50 " write time tag field, as process information;
Step 4 assumes that K-001 belongs to A system, which has 200 cables, numbers from K-001 to K-200;Cable is matched The next procedure of line is cable check and correction, number 013, it is assumed that the threshold value of the process is set as 60%.Then system accounting calculates A system Interior process W012' completion rate R012Process W is completed in '=012' cable count N012'/cable sum 100.Work as R012When ' >=60% It will start next procedure.The resource requirement of next procedure is calculated simultaneously.It is assumed that completion rate R012'=60%, i.e. cable are matched Line has completed 120.Assuming that the process resource efficiency of cable check and correction is 50 piece/day groups, the duration is 2 days.Resource Re013's Requirement=(cable amount N013/ process resource efficiency E013/ next procedure duration T013)×R012=1.2 groups, then firing cable school When to process, it may be considered that 1 group of school informant person is arranged first, then according to daily Re013Calculated value arranges second day school line Personnel's investment.
Step 5, the concerned process steps of cable laying generally have cable laying, cable wiring, cable check and correction, monomer assays, are System test etc..The relevant integrated engineering progress of cable then can be obtained in completion personnel and the deadline for counting above-mentioned all process steps Network.Data reference is provided for successive projects.
It should be understood that for those of ordinary skills, it can be modified or changed according to the above description, And all these modifications and variations should all belong to the protection domain of appended claims of the present invention.

Claims (7)

1. a kind of Industrial Engineering cable process information processing method, which comprises the following steps:
S1, setting ultrahigh frequency electronic tag is as cable number plate on cable, the setting flag position in ultrahigh frequency electronic tag, no Same marker bit corresponds to different cable processes;
S2, the ultra high frequency IC tag that cable is identified by the way that numbered hander is arranged, the number of hander correspond to different processes Different work personnel;
S3, after operating personnel completes process, process is completed into person number and deadline, label correspondence markings position is written, made For process information;
S4, process information is obtained, by the analysis and statistics to previous process, from the background to the progress of next procedure and resource allocation Instruction is provided, and is distributed to corresponding operating personnel;
S5, complete cable laying all process steps after, count completion personnel and the deadline of all process steps, obtain integrated engineering Scheduling network.
2. Industrial Engineering cable process information processing method according to claim 1, which is characterized in that be arranged in step S1 The method of ultrahigh frequency electronic tag are as follows:
The area Reserved, the area EPC, TID field and the area User are set in ultrahigh frequency electronic tag, different marks is set in the area User Note position corresponds to different cable processes;Different cables are identified by critical field in marker bit.
3. Industrial Engineering cable process information processing method according to claim 2, which is characterized in that be arranged in step S1 The method of critical field are as follows:
Critical field includes process number, process label, time label and worker labels;Process number corresponds to different processes;Work Sequence label record process completion status;Label record process deadline time;Worker labels record process and complete personnel or people Member represents;
The electronic tag smaller for the area User only retains cable number field using the set-up mode for simplifying marker bit, Other fields change by recording from the background.
4. Industrial Engineering cable process information processing method according to claim 1, which is characterized in that upper in step S4 The method that procedure is analyzed and counted specifically:
The identical process of process number is counted, the process completion rate is calculated;
Process WnCompletion rate Rn=process W is completednCable count Nn/ cable sum N;
Process W in a certain systemn' completion rate RnProcess W is completed in '=n' cable count Nn'/cable sum N ';
Process W in a certain regionn" completion rate Rn"=be completed process Wn" cable count Nn"/cable sum N ".
5. Industrial Engineering cable process information processing method according to claim 4, which is characterized in that work in step S4 Sequence WnNext procedure Wn+1The progress method that provides instruction specifically:
(1) R is setnThreshold value, start next procedure when the completion rate of process reaches threshold value;
(2) R of certain system is setn' threshold value starts next procedure when the completion rate of the system process reaches threshold value;
(3) R in certain region is setn" threshold value starts next procedure when the completion rate of the region process reaches threshold value;
(4) in the case where other particular/special requirements, start next procedure.
6. Industrial Engineering cable process information processing method according to claim 1, which is characterized in that in step S4 for Process WnNext procedure Wn+1Certain resource Re is provided as followsn+1Instruction:
Statistics enters next procedure Wn+1Cable amount Nn+1, with following formula computing resource requirement:
Resource Ren+1Requirement=(cable amount Nn+1/ process resource efficiency En+1/ next procedure duration Tn+1)×Rn
Resource Ren+1Requirement only consider main resource, including personnel and main mechanical.
7. Industrial Engineering cable process information processing method according to claim 1, which is characterized in that obtained in step S4 The method of process information specifically: ultra high frequency IC tag information is read by hander or passes through hander and background synchronization.
CN201610504953.0A 2016-06-30 2016-06-30 A kind of Industrial Engineering cable process information processing method Active CN106129906B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610504953.0A CN106129906B (en) 2016-06-30 2016-06-30 A kind of Industrial Engineering cable process information processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610504953.0A CN106129906B (en) 2016-06-30 2016-06-30 A kind of Industrial Engineering cable process information processing method

Publications (2)

Publication Number Publication Date
CN106129906A CN106129906A (en) 2016-11-16
CN106129906B true CN106129906B (en) 2019-01-11

Family

ID=57467582

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610504953.0A Active CN106129906B (en) 2016-06-30 2016-06-30 A kind of Industrial Engineering cable process information processing method

Country Status (1)

Country Link
CN (1) CN106129906B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102625551B1 (en) * 2018-06-19 2024-01-16 닛키 글로벌 가부시키가이샤 How to connect plant devices

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004005947A1 (en) * 2002-07-09 2004-01-15 Jin-Bae Park Time-frequency domain reflectometry apparatus and method
CN200979773Y (en) * 2006-11-16 2007-11-21 沈阳先达条码技术发展有限公司 A disposable electronic tag with a fragile encapsulation structure
CN101201905A (en) * 2007-12-21 2008-06-18 合肥工大高科信息技术有限责任公司 Low-power consumption active anticollision electronic label and operation method thereof
CN101482935A (en) * 2008-06-18 2009-07-15 上海秀派电子科技有限公司 Active RFID label used for container electronic seal and its reading device
CN101782958A (en) * 2009-01-15 2010-07-21 汉王科技股份有限公司 Digital display IC card system and operating method thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI372413B (en) * 2004-09-24 2012-09-11 Semiconductor Energy Lab Semiconductor device and method for manufacturing the same, and electric appliance

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004005947A1 (en) * 2002-07-09 2004-01-15 Jin-Bae Park Time-frequency domain reflectometry apparatus and method
CN200979773Y (en) * 2006-11-16 2007-11-21 沈阳先达条码技术发展有限公司 A disposable electronic tag with a fragile encapsulation structure
CN101201905A (en) * 2007-12-21 2008-06-18 合肥工大高科信息技术有限责任公司 Low-power consumption active anticollision electronic label and operation method thereof
CN101482935A (en) * 2008-06-18 2009-07-15 上海秀派电子科技有限公司 Active RFID label used for container electronic seal and its reading device
CN101782958A (en) * 2009-01-15 2010-07-21 汉王科技股份有限公司 Digital display IC card system and operating method thereof

Also Published As

Publication number Publication date
CN106129906A (en) 2016-11-16

Similar Documents

Publication Publication Date Title
WO2022094934A1 (en) Site location-based system and method for management of engineering quality acceptance
CN105139310A (en) Intelligent course scheduling system and method
CN108320127A (en) A kind of power engineering term computer management system
CN103426208A (en) Cell phone attendance system based on WiFi signals
CN106447156A (en) Attendance management method and system
CN107798489A (en) A kind of electric network operation site safety management method based on wechat platform
CN102693460A (en) Tester management system and method thereof
CN109658003A (en) A kind of property facility equipment management system and method
CN104933495A (en) Work task assessment system on Android-based mobile terminal
CN105225286A (en) A kind of Work attendance management system and method
CN111063144A (en) Abnormal behavior monitoring method, device, equipment and computer readable storage medium
CN105574666A (en) Method and device for evaluating credit level of enterprise based on key data modeling
WO2008071857A3 (en) Method and system for generating communication operations planned on information networks and systems, and implementation of said method in a billing verification process
CN106129906B (en) A kind of Industrial Engineering cable process information processing method
CN104281523A (en) Demand testability analysis method and system
CN111210535A (en) Intelligent inspection system for scheduling master station system equipment
CN112364145A (en) Work order processing method and device, electronic equipment and storage medium
CN107704771A (en) A kind of management system based on third party's online training platform
CN106887157A (en) Parking stall enters car, goes out car data correlating method and device
CN102332111A (en) Personnel management system
CN102437911A (en) Safety processing system and method for intelligent card (IC) card application
CN113326954B (en) Vehicle maintenance task scheduling method, device, equipment and storage medium
CN204856634U (en) Electron system of registering based on RFID wireless Intelligence card
ATE255753T1 (en) METHOD FOR CHECKING THE AUTHENTICITY OF OBJECTS
CN104216986A (en) Device and method for improving data query efficiency through pre-operation according to data update period

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant