CN106121688A - A kind of shield tunnel segment bolt hole water proof structure and construction method - Google Patents

A kind of shield tunnel segment bolt hole water proof structure and construction method Download PDF

Info

Publication number
CN106121688A
CN106121688A CN201610708866.7A CN201610708866A CN106121688A CN 106121688 A CN106121688 A CN 106121688A CN 201610708866 A CN201610708866 A CN 201610708866A CN 106121688 A CN106121688 A CN 106121688A
Authority
CN
China
Prior art keywords
bolt
washer
waterproof
jurisdiction
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610708866.7A
Other languages
Chinese (zh)
Other versions
CN106121688B (en
Inventor
肖明清
孙文昊
刘浩
谢俊
石湛
孙峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201610708866.7A priority Critical patent/CN106121688B/en
Publication of CN106121688A publication Critical patent/CN106121688A/en
Application granted granted Critical
Publication of CN106121688B publication Critical patent/CN106121688B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Bolts, Nuts, And Washers (AREA)

Abstract

The open a kind of shield tunnel segment bolt hole water proof structure of the present invention and construction method, including the bolt washer between the bolt at bolt hole inner connection tube sheet, the bolt head at bolt and section of jurisdiction, the first waterproof washer between bolt washer and section of jurisdiction, the second waterproof washer between bolt head and bolt washer;The one side that first waterproof washer contacts with section of jurisdiction is plane, and the one side contacted with bolt washer is provided with at least one ring semi-cylindrical hill;Two end faces of the second waterproof washer are plane.The present invention can improve bolt hole waterproofing pressure, by changing waterproof washer and section of jurisdiction and the contact stress of bolt washer, thus can realize different waterproofing pressure requirements as desired to the size of regulation bolt pretightening, and have more preferable durability.

Description

A kind of shield tunnel segment bolt hole water proof structure and construction method
Technical field
The invention belongs to tunnel water proofing technical field, specifically a kind of shield tunnel segment bolt hole water proof structure and executing Work method.
Background technology
Shield tunnel is the structure formed by polylith prefabricated pipe section on-site consolidation, is bolted between section of jurisdiction, In order to prevent subsoil water from leaking in tunnel from segment joint, seam crossing is provided with waterproof sealing gasket outside section of jurisdiction, Bolt arranges hydro-expansive rubber sealing ring, and carries out filleting in inner side, in the engineering that waterproof requirement is higher, near connecing Second waterproof sealing gasket it is also provided with inside seam.In Practical Project, due to prefabricated pipe section quality, the assembled quality of construction, close The impact of the factors such as packing sticking Quality, outer side seal pad seepage is very difficult to avoid completely, and even in indivedual engineerings, seepage is very Seriously.
When, after outer side seal pad generation seepage, current may enter tunnel along bolt hole, therefore bolt hole is provided with anti- Water constructs.But from " certain crosses the percolating water analysis of causes of Shield-bored tunnels section of jurisdiction, river and Treatment process " (Chinese architecture is waterproof, 6th phase in 2015), " the shield tunnel percolating water analysis of causes and counter-measure " (urban architecture, the 8th phase in 2013) and " shield Structure Tunnel Water Leakage processes construction technology " document such as (urban architecture, o. 11th in 2015) is it can be seen that segment bolt aperture is oozed The phenomenon of leakage often occurs.
Waterproof all employing of duct pieces of shield tunnel link bolt hole arranges triangular-section in bolt chamfering position at present The mode of water swelling rubber ring.Owing to diameter of bolt hole is typically bigger about 6mm than the diameter of bolt, sealing ring water-swellable is backward In bolt hole, extrusion, owing to not having sidewise restraint, can not form the bulbs of pressure, therefore waterproof effect is very poor.It addition, hydro-expansive rubber Material is less stable under the conditions of long period of soaking, and absorbent material easily runs off from the elastomer network of rubber, shows as long Before and after phase or repeatedly immersion, bigger mass loss and physical property decline.The most commonly used water-swellable rubber Expansive force can not be produced during the water-swellable that cushion rubber exists, not have a due waterproof action, and stability and durability not enough.
Summary of the invention
For problem present in background technology, the present invention propose a kind of from waterproof sealing gasket material and operation principle, close The aspects such as packing structure, sealing gasket installation site carry out comprehensive improvement, thus solve the shield tunnel that prior art is not enough Segment bolt hole water proof structure and construction method.
For reaching above-mentioned purpose, the shield tunnel segment bolt hole water proof structure of present invention design, including being positioned at bolt The bolt of hole inner connection tube sheet, the bolt washer between the bolt head and section of jurisdiction of bolt, it is characterised in that: also include being positioned at The first waterproof washer between bolt washer and section of jurisdiction, the second waterproof washer between bolt head and bolt washer;Described The one side that first waterproof washer contacts with described section of jurisdiction is plane, and it is semicircle that the one side contacted with bolt washer is provided with at least one ring Protruding;Two end faces of described second waterproof washer are plane.
Preferably, the internal diameter of described first waterproof washer is more than the internal diameter of bolt washer, and external diameter is not more than bolt washer External diameter;The diameter of described semi-cylindrical hill is less than the external diameter of bolt washer more than the internal diameter of the first waterproof washer.
It is further preferred that described first waterproof washer is provided with multi-ring semi-cylindrical hill, two adjacent semi-circular projection The difference of diameter be 10~20mm.
Preferably, described first waterproof washer uses ethylene propylene diene monomer (EPDM) material to make.
Preferably, described section of jurisdiction is provided with the stopper slot of accommodating described first waterproof washer.
It is further preferred that the degree of depth of described stopper slot is 2~4mm.
Preferably, the internal diameter of described second waterproof washer is not less than the diameter of bolt, and external diameter is less than bolt head inscribed circle diameter.
Preferably, described second waterproof washer uses neoprene or EP rubbers material.
Use the shield tunnel segment bolt hole waterproof construction side of above-mentioned shield tunnel segment bolt hole water proof structure Method, comprises the following steps:
One) carry out stopper slot during prefabricated pipe section in the lump, use bonding agent to be glued by the first waterproof washer before going into the well in section of jurisdiction Being attached in stopper slot, section of jurisdiction, in pasting 12 hours of installing the first waterproof washer, must not be sent down-hole assembled, and must not connect with water Touch;
Two), during segment assembly, successively the second waterproof washer and bolt washer are set on bolt, by tools for bolts ' pretension pair First waterproof washer and the second waterproof washer carry out densification and then play waterproof action, and can realize by adjusting bolt pretightening The requirement of the different water pressure of opposing.
Preferably, step one) in binding agent use modified environment protection type polychloroprene tackifier, brushing binding agent on section of jurisdiction After, cool put a period of time, when finger contact adhesion, then the stopper slot that the first waterproof washer is entirely attached on section of jurisdiction In.
It is further preferred that the described cool time put is 10~15 minutes.
The invention has the beneficial effects as follows: 1. can improve bolt hole waterproofing pressure.The existing waterproof side of hydro-expansive rubber packing ring Formula, can expand in bolt hole along the gap between bolt hole and bolt after meeting water due to packing ring, and expanded rubber is without constraint In the case of can not produce the bulbs of pressure, when there being hydraulic pressure effect, do not have waterproof effect.The waterproof project that the present invention uses is By the second waterproof washer between the first waterproof washer and bolt head and the bolt washer between section of jurisdiction and bolt washer at spiral shell Produce compression stress under bolt pretightning force effect, thus realize the waterproof purpose of bolt hole.2. the scheme that the present invention proposes, can basis Need to regulate the size of bolt pretightening, by changing waterproof washer and section of jurisdiction and the contact stress of bolt washer, thus real Existing different waterproofing pressure requirement.Packing ring material the most of the present invention has more preferable durability with hydro-expansive rubber ratio.
Accompanying drawing explanation
Fig. 1 is the assembling schematic diagram of the present invention
Fig. 2 is the amplification explosive view in Fig. 1 at A
Fig. 3 is the front view of the present invention the first waterproof washer
Fig. 4 is the section B-B figure of Fig. 3
In figure: bolt hole 1, section of jurisdiction 2, bolt 3, bolt head 4, bolt washer the 5, first waterproof washer 6 (semi-cylindrical hill 6.1), the second waterproof washer 7.
Detailed description of the invention
Below by Fig. 1~Fig. 4 and the mode of some alternative embodiments enumerating the present invention, the technical side to the present invention Case (including optimal technical scheme) is described in further detail, any technical characteristic in the present embodiment and any technical side Case is all not intended to protection scope of the present invention.
As depicted in figs. 1 and 2, the shield tunnel segment bolt hole water proof structure of invention design, including being positioned at bolt hole 1 The bolt 3 of inner connection tube sheet 2, the bolt washer 5 between the bolt head 4 and section of jurisdiction 2 of bolt 3, be positioned at bolt washer 5 and pipe The first waterproof washer 6 between sheet 2, the second waterproof washer 7 between bolt head 4 and bolt washer 5;Described first waterproof The one side that packing ring 6 contacts with described section of jurisdiction 2 is plane, and the one side contacted with bolt washer 5 is provided with at least one ring semi-cylindrical hill 6.1;Two end faces of described second waterproof washer 7 are plane.
Again as in figure 2 it is shown, the internal diameter of described first waterproof washer 6 is more than the internal diameter of bolt washer 5, external diameter is not more than bolt The external diameter of packing ring;The diameter of described semi-cylindrical hill 6.1 is less than the external diameter of bolt washer 5 more than the internal diameter of the first waterproof washer 6.
As shown in Figure 3 and Figure 4, described first waterproof washer 6 is provided with multi-ring semi-cylindrical hill 6.1, adjacent two and half The difference of the diameter of circular protrusions 6.1 is 10~20mm.It is to say, be spaced apart 5 between adjacent two semi-cylindrical hills 6.1 ~10mm.
Preferably, described first waterproof washer 6 uses ethylene propylene diene monomer (EPDM) material to make.
Again as in figure 2 it is shown, described section of jurisdiction 2 is provided with the stopper slot 8 of accommodating described first waterproof washer 6.Preferably, described The degree of depth of stopper slot 8 is 2~4mm.
Again as in figure 2 it is shown, the internal diameter of described second waterproof washer 7 is not less than bolt 3 diameter, external diameter is less than in bolt head 4 Tangential circle diameter.
Preferably, described second waterproof washer 7 uses neoprene or EP rubbers material.
Use the shield tunnel segment bolt hole waterproof construction side of above-mentioned shield tunnel segment bolt hole water proof structure Method, comprises the following steps:
One) carry out stopper slot 8 during prefabricated pipe section 2 in the lump, use bonding agent by the first waterproof washer before going into the well in section of jurisdiction 2 6 are pasted onto in stopper slot 8, and section of jurisdiction 2, in pasting 12 hours of installing the first waterproof washer, must not send down-hole assembled, and must not Contact with water;
Two), during segment assembly 2, successively the second waterproof washer 7 and bolt washer 5 are set on bolt 3, by bolt 3 Pretension carries out densification to the first waterproof washer 6 and the second waterproof washer 7 and then plays waterproof action, and can be by adjusting bolt 3 Pretightning force realizes the requirement of the different water pressure of opposing.
Preferably, step one) in binding agent use modified environment protection type polychloroprene tackifier, brushing binding agent on section of jurisdiction 2 After, cool put 10~15 minutes, when finger contact adhesion, then the first waterproof washer 6 is entirely attached on section of jurisdiction 2 spacing In groove 8.

Claims (10)

1. a shield tunnel segment bolt hole water proof structure, including the bolt being positioned at bolt hole (1) inner connection tube sheet (2) (3) bolt washer (5), being positioned between the bolt head (4) of bolt (3) and section of jurisdiction (2), it is characterised in that: also include being positioned at spiral shell The first waterproof washer (6) between bolt packing ring (5) and section of jurisdiction (2), second be positioned between bolt head (4) and bolt washer (5) Waterproof washer (7);The one side that described first waterproof washer (6) contacts with described section of jurisdiction (2) is plane, connects with bolt washer (5) The one side touched is provided with at least one ring semi-cylindrical hill (6.1);Two end faces of described second waterproof washer (7) are plane.
Shield tunnel segment bolt hole the most according to claim 1 water proof structure, it is characterised in that: described first waterproof The internal diameter of packing ring (6) is more than the internal diameter of bolt washer (5), and external diameter is not more than the external diameter of bolt washer (5);Described semi-cylindrical hill (6.1) diameter is less than the external diameter of bolt washer (5) more than the internal diameter of the first waterproof washer (6).
3. according to the shield tunnel segment bolt hole water proof structure described in claim 2, it is characterised in that: described first collision mat Circle (6) is provided with multi-ring semi-cylindrical hill (6.1), and the difference of the diameter of two adjacent semi-circular projection (6.1) is 10~20mm.
4. according to the arbitrary described shield tunnel segment bolt hole water proof structure of claims 1 to 3, it is characterised in that: described the One waterproof washer (6) uses ethylene propylene diene monomer (EPDM) material to make.
5. according to the shield tunnel segment bolt hole water proof structure described in claim 1, it is characterised in that: on described section of jurisdiction (2) It is provided with the stopper slot (8) of accommodating described first waterproof washer (6).
6. according to the shield tunnel segment bolt hole water proof structure described in claim 5, it is characterised in that: described stopper slot (8) The degree of depth be 2~4mm.
7. according to the shield tunnel segment bolt hole water proof structure described in claim 1, it is characterised in that: described second collision mat The internal diameter of circle (7) is less than bolt head (4) inscribed circle diameter not less than bolt (3) diameter, external diameter.
8. use the shield tunnel segment bolt of shield tunnel segment bolt hole water proof structure described in claim 1~7 Hole waterproof construction method, comprises the following steps:
One) carrying out stopper slot (8) during prefabricated pipe section (2) in the lump, going into the well in section of jurisdiction (2) uses bonding agent by the first collision mat before Circle (6) is pasted onto in stopper slot (8), and section of jurisdiction (2), in pasting 12 hours of installing the first waterproof washer (6), must not send down-hole Assembly, and must not contact with water;
Two), during segment assembly (2), successively the second waterproof washer (7) and bolt washer (5) are set on bolt (3), pass through spiral shell Bolt pretension carries out densification to the first waterproof washer (6) and the second waterproof washer (7) and then plays waterproof action, and can be by adjusting Bolt pretightening realizes the requirement of the different water pressure of opposing.
9. according to the shield tunnel segment bolt hole waterproof construction method described in claim 8, it is characterised in that: step one) in Binding agent uses modified environment protection type polychloroprene tackifier, on section of jurisdiction after brushing binding agent, cool puts a period of time, treats that finger contacts During adhesion, then in the stopper slot (8) that the first waterproof washer (6) is entirely attached on section of jurisdiction.
10. according to the shield tunnel segment bolt hole waterproof construction method described in claim 9, it is characterised in that: described cool put Time be 10~15 minutes.
CN201610708866.7A 2016-08-23 2016-08-23 A kind of shield tunnel segment bolt hole water proof structure and construction method Active CN106121688B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610708866.7A CN106121688B (en) 2016-08-23 2016-08-23 A kind of shield tunnel segment bolt hole water proof structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610708866.7A CN106121688B (en) 2016-08-23 2016-08-23 A kind of shield tunnel segment bolt hole water proof structure and construction method

Publications (2)

Publication Number Publication Date
CN106121688A true CN106121688A (en) 2016-11-16
CN106121688B CN106121688B (en) 2019-02-26

Family

ID=57273614

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610708866.7A Active CN106121688B (en) 2016-08-23 2016-08-23 A kind of shield tunnel segment bolt hole water proof structure and construction method

Country Status (1)

Country Link
CN (1) CN106121688B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593488A (en) * 2016-11-23 2017-04-26 同济大学 Waterproof structure for sealing high-water-pressure shield tunnel bolt hole
CN108194090A (en) * 2018-01-16 2018-06-22 中铁二院工程集团有限责任公司 A kind of rock tunnel(ling) machine and method for tunnel construction that storehouse section is laid with waterproof membrane
CN110805460A (en) * 2019-10-10 2020-02-18 天津大学前沿技术研究院有限公司 Waterproof sealing method for bolt hole of shield tunnel segment
CN112761683A (en) * 2021-02-04 2021-05-07 西南交通大学 Inclined bolt hole waterproof structure of high-water-head shield tunnel segment
CN112761681A (en) * 2021-02-04 2021-05-07 西南交通大学 Bolt hole waterproof structure of high-head shield tunnel segment

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03208993A (en) * 1990-01-11 1991-09-12 Yoshitaka Masuda Structure of segment joint
JPH07279596A (en) * 1994-04-06 1995-10-27 Nishikawa Rubber Co Ltd Water swelling type annular water sealing member
JPH08177393A (en) * 1994-12-22 1996-07-09 Kajima Corp Shield segment
JP2662943B2 (en) * 1995-08-01 1997-10-15 大豊建設株式会社 Waterproof and seismic joints for segments in shield tunnels
CN102251784A (en) * 2011-05-30 2011-11-23 中铁第四勘察设计院集团有限公司 Double-layer lining shield tunnel duct piece and lining superposed structure
CN205936665U (en) * 2016-08-23 2017-02-08 中铁第四勘察设计院集团有限公司 Waterproof structure of shield method tunnel segment bolt hole

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03208993A (en) * 1990-01-11 1991-09-12 Yoshitaka Masuda Structure of segment joint
JPH07279596A (en) * 1994-04-06 1995-10-27 Nishikawa Rubber Co Ltd Water swelling type annular water sealing member
JPH08177393A (en) * 1994-12-22 1996-07-09 Kajima Corp Shield segment
JP2662943B2 (en) * 1995-08-01 1997-10-15 大豊建設株式会社 Waterproof and seismic joints for segments in shield tunnels
CN102251784A (en) * 2011-05-30 2011-11-23 中铁第四勘察设计院集团有限公司 Double-layer lining shield tunnel duct piece and lining superposed structure
CN205936665U (en) * 2016-08-23 2017-02-08 中铁第四勘察设计院集团有限公司 Waterproof structure of shield method tunnel segment bolt hole

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593488A (en) * 2016-11-23 2017-04-26 同济大学 Waterproof structure for sealing high-water-pressure shield tunnel bolt hole
CN106593488B (en) * 2016-11-23 2019-07-05 同济大学 A kind of high hydraulic pressure shield tunnel bolt hole hermetic water-proof structure
CN108194090A (en) * 2018-01-16 2018-06-22 中铁二院工程集团有限责任公司 A kind of rock tunnel(ling) machine and method for tunnel construction that storehouse section is laid with waterproof membrane
CN110805460A (en) * 2019-10-10 2020-02-18 天津大学前沿技术研究院有限公司 Waterproof sealing method for bolt hole of shield tunnel segment
CN112761683A (en) * 2021-02-04 2021-05-07 西南交通大学 Inclined bolt hole waterproof structure of high-water-head shield tunnel segment
CN112761681A (en) * 2021-02-04 2021-05-07 西南交通大学 Bolt hole waterproof structure of high-head shield tunnel segment
CN112761681B (en) * 2021-02-04 2022-04-22 西南交通大学 Bolt hole waterproof structure of high-head shield tunnel segment

Also Published As

Publication number Publication date
CN106121688B (en) 2019-02-26

Similar Documents

Publication Publication Date Title
CN106121688A (en) A kind of shield tunnel segment bolt hole water proof structure and construction method
CN107630717B (en) Coal bed permeability increasing method with electric pulse and coal bed water injection in cooperation
CN100572751C (en) A kind of using method of style shield tail sealing device of shield machine
CN205532640U (en) Elastic sealing pad for sealing seams among shield tunnel pipe segments
CN209762491U (en) Drainage pipeline connecting structure
CN201606084U (en) Waterproof structure of shield-structured tunnel segment
CN106703843B (en) A kind of two pass seam waterproof device with segment bolt connector box duct pieces of shield tunnel
CN105973724B (en) Rock discontinuum coupled shear-flow test box
CN205936665U (en) Waterproof structure of shield method tunnel segment bolt hole
CN203856484U (en) Tunnel segment sealing structure
CN206257359U (en) A kind of big cross section rectangle pipe jacking tube coupling made up joint
CN108678782B (en) High water pressure shield tunnel segment joint multichannel watertight fittings of slip casting hole is reserved
CN106593488A (en) Waterproof structure for sealing high-water-pressure shield tunnel bolt hole
CN112761683A (en) Inclined bolt hole waterproof structure of high-water-head shield tunnel segment
CN107504317A (en) A kind of non-stop plugging technique of gas pipeline crack formula leakage
CN208518682U (en) A kind of high hydraulic pressure duct pieces of shield tunnel seam multi layer waterproof device of reserved injected hole
CN112761681B (en) Bolt hole waterproof structure of high-head shield tunnel segment
CN107701201A (en) A kind of duct pieces of shield tunnel sealing gasket
CN102444409A (en) Elastic sealing pad for sealing seams among shield tunnel pipe segments by utilizing water pressure
CN106988279B (en) A kind of application method of the sluice with hydraulic lock
CN201902705U (en) Nonmetallic pipe baseplate-penetrating waterproof casing pipe
CN106906805B (en) A kind of construction method of sluice hydraulic lock system
CN215172857U (en) Back trompil wall bushing structure
CN204986039U (en) Buried sleeve organizes subassembly
CN102734573B (en) Waterproof structure for pipe-jacking method tunnel union joint

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant