CN106121268A - The system and method for prestress rope integrative consolidation slab column - Google Patents
The system and method for prestress rope integrative consolidation slab column Download PDFInfo
- Publication number
- CN106121268A CN106121268A CN201610700586.1A CN201610700586A CN106121268A CN 106121268 A CN106121268 A CN 106121268A CN 201610700586 A CN201610700586 A CN 201610700586A CN 106121268 A CN106121268 A CN 106121268A
- Authority
- CN
- China
- Prior art keywords
- angle steel
- post
- wire rope
- plate
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
The invention discloses the system of a kind of prestress rope integrative consolidation slab column, including being anchored in the multiple big angle steel on post and plate/beam by split bolt and nut;That each big angle steel is connected with post while anchoring has multiple little angle steel, each little angle steel connects lay winding wire ropes by adjustable bolt respectively, and each lay winding wire ropes is wound in outside post respectively;Be arranged on that each big angle steel on the downside of plate/beam is connected with plate/beam is provided with multiple little angle steel, and each little angle steel connects screw shell by adjustable bolt respectively, and screw shell connects stretching wire rope;Lay winding wire ropes and stretching wire rope one end are anchored by extruding anchor head after screw shell.After steel wire rope Shi Hanzhang, the reinforcing to slab column can be realized efficiently, just can be realized steel wire rope Shi Hanzhang by twisting adjustable bolt, construct convenient, it is not necessary to main equipment.
Description
Technical field
The present invention relates to civil engineering reinforcement technique field, the system of a kind of prestress rope integrative consolidation slab column
And method.
Background technology
Due to material aging, construction quality, nature or the impact of the factor such as artificial, existing a lot of houses anxious the most to be repaired and
Reinforcing, countries in the world will expend huge fund every year for this.The reinforcement technique of existing reinforced concrete girder slab post mainly has increase to cut
Face method, reinforcement by sticking of sheets, stickup fibrous composite method for strengthening, setting support method for strengthening, steel strand wires mesh sheet-polymer mortar add
Gu method etc..Existing reinforcement means is primarily present problems with: there is Stress resort effect between (1) reinforcement material and original component,
Cooperation ability is poor, largely effects on consolidation effect;(2) reinforcement material end anchorage length is inadequate, easily finds anchored end
Stripping damage, it is impossible to give full play to the strength of materials;(3) increase the sectional dimension of original component, increase deadweight, impact sight and
Use.And current reinforcement means is each to reinforce plate and wall, it is impossible to effectively strengthen the globality of structure.Therefore, one it is badly in need of
Plant the system and method for integrative consolidation slab column to solve the problems referred to above.
Summary of the invention
Goal of the invention: in order to overcome the deficiencies in the prior art, the present invention provides a kind of prestress rope comprehensive
The system and method for reinforcement sheet-pile.
Technical scheme: for solving above-mentioned technical problem, a kind of prestress rope integrative consolidation slab column of the present invention
System, including being anchored in the multiple big angle steel on post and plate/beam by split bolt and nut;Each big angle steel is connected with post
While anchoring has multiple little angle steel, each little angle steel connects lay winding wire ropes by adjustable bolt respectively, and each lay winding wire ropes is respectively
It is wound in outside post;Be arranged on that each big angle steel on the downside of plate/beam is connected with plate/beam is provided with multiple little angle steel, each little angle
Steel connects screw shell by adjustable bolt respectively, and screw shell connects stretching wire rope;Lay winding wire ropes and stretching wire rope
One end is anchored by extruding anchor head after screw shell.
Wherein, position corresponding with each steel wire rope on plate/beam has groove, and steel wire rope is respectively placed in the groove of correspondence.
A kind of method of prestress rope integrative consolidation slab column, comprises the following steps:
(1) at floor/beam and column relevant position punching, fluting;
(2) split bolt is installed on floor/beam and column relevant position;
(3) big angle steel is installed at split bolt, big angle steel is installed little angle steel, little angle steel is installed adjustable spiral shell
Bolt, adjustable bolt connects screw shell;
(4) fixed by extruding anchor head after steel wire rope is each passed through the hole of screw shell, and winding post and paving respectively
It is located at the bottom of plate/beam;
(5) tighten adjustable bolt with instrument, make steel wire rope prestressing force reach design load;
(6) at the bottom of floor/beam and the outer surface shotcrete of post, reach to protect prestress rope smooth building
The purpose of plate/beam and column.
Beneficial effect: the system and method for a kind of prestress rope integrative consolidation slab column of the present invention, has following
Beneficial effect:
1, after to steel wire rope Shi Hanzhang, the reinforcing to slab column can be realized efficiently;
2, just can be realized steel wire rope Shi Hanzhang by twisting adjustable bolt dexterously, construct convenient, it is not necessary to
Main equipment;
3, this reinforcement means substantially increases the connection ultimate bearing capacity of joints of floor/beam and column, substantially increases the change of node
Shape ability;
4, achieving the integrative consolidation of floor/beam and column, effectively enhance the globality of structure, consolidation effect is the most excellent
In other reinforcement means.
Accompanying drawing explanation
Fig. 1 is the schematic three-dimensional top view of the system of prestress rope integrative consolidation slab column of the present invention;
Fig. 2 is the three dimensional bottom view of the system of prestress rope integrative consolidation slab column of the present invention;
Fig. 3 is the plane graph of the system of prestress rope integrative consolidation slab column of the present invention;
In figure: 1-split bolt, the little angle steel of 2-, 3-nut, 4-adjustable bolt, 5-screw shell, 6-extrudes anchor head, 7-steel
Cord, 8-post, 9-floor/beam, the big angle steel of 10-.
Detailed description of the invention
Below in conjunction with the accompanying drawings the present invention is further described.
Including as shown in Figure 1 to Figure 3 it is anchored in big angle steel 10 on post 8 and plate/beam 9 by split bolt 1, nut 3,
It is fixed on the little angle steel 2 on big angle steel 10;Adjustable bolt 4 is fixed on little angle steel 2 opposite side by nut;Steel wire rope 7 one end around
Being fixed by extruding anchor head 6 after crossing the hole of screw shell 5, the other end is anchored on plate/beam 9.Adjustable bolt 4 can be twisted with instrument
Tightly, and reach to control the stretching force of steel wire rope by controlling the torsion of instrument.Steel wire rope 7 part is used for reinforced column 8, another
Part is for securing plate/beam 9, and wherein the steel wire rope 7 of reinforced column 8 is wrapped on post 8, is anchored at the bottom of capital and post respectively, reinforces
The steel wire rope 7 of plate/beam 9 is arranged in plate/beam 9 end.
Position corresponding with each steel wire rope 7 on plate/beam 9 has groove, and steel wire rope 7 is respectively placed in the groove of correspondence.With
Adjustable bolt 4 tightened by instrument, after making steel wire rope 7 prestressing force reach design load, to plate/beam 9 surface shotcrete, cement bonded sand
Slurry covers the steel wire rope in plate/beam 9 surface and groove and groove, plays protection steel wire rope smooth floor/beam 9 and the work of post 8
With.
The present invention also provides for a kind of method of prestress rope integrative consolidation slab column, and the method comprises the following steps:
(1) punch at floor/beam 9 and post 8 relevant position, slot;
(2) split bolt 1 is installed on floor/beam 9 and post 8 relevant position;
(3) big angle steel 10, little angle steel 2, nut 3, adjustable bolt 4 and screw shell 5 are installed at split bolt;
(4) by steel wire rope winding post 8 respectively be laid on plate/beam 9 end, and walk around behind the hole of screw shell 5 by extruding
Anchor head 6 is fixed;
(5) tighten adjustable bolt 4 with instrument, make steel wire rope 7 prestressing force reach design load;
(6) at the outer surface shotcrete of floor/beam 9 end and post 8, reach to protect steel wire rope 7 smooth floor/
Beam 9 and the purpose of post 8.
The above is only the preferred embodiment of the present invention, it should be pointed out that: for the ordinary skill people of the art
For Yuan, under the premise without departing from the principles of the invention, it is also possible to make some improvements and modifications, these improvements and modifications also should
It is considered as protection scope of the present invention.
Claims (3)
1. the system of a prestress rope integrative consolidation slab column, it is characterised in that: include by split bolt and nut
It is anchored in the multiple big angle steel on post and plate/beam;It is that each big angle steel is connected with post while anchoring has multiple little angle steel, each little angle
Steel connects lay winding wire ropes by adjustable bolt respectively, and each lay winding wire ropes is wound in outside post respectively;It is arranged on the downside of plate/beam
Each big angle steel be connected with plate/beam be provided with multiple little angle steel, each little angle steel connects thread bush by adjustable bolt respectively
Cylinder, screw shell connects stretching wire rope;Extruding anchor is passed through after screw shell in lay winding wire ropes and stretching wire rope one end
Head anchoring.
The system of a kind of prestress rope integrative consolidation slab column the most according to claim 1, it is characterised in that: its
In, position corresponding with each steel wire rope on plate/beam has groove, and steel wire rope is respectively placed in the groove of correspondence.
3. the method for a prestress rope integrative consolidation slab column, it is characterised in that comprise the following steps:
(1) at floor/beam and column relevant position punching, fluting;
(2) split bolt is installed on floor/beam and column relevant position;
(3) big angle steel is installed at split bolt, big angle steel is installed little angle steel, little angle steel is installed adjustable bolt, can
Bolt is adjusted to connect screw shell;
(4) fixed by extruding anchor head after steel wire rope is each passed through the hole of screw shell, and winding post and being laid on respectively
At the bottom of plate/beam;
(5) tighten adjustable bolt with instrument, make steel wire rope prestressing force reach design load;
(6) at the bottom of floor/beam and the outer surface shotcrete of post, reach to protect prestress rope smooth floor/beam
Purpose with post.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610700586.1A CN106121268B (en) | 2016-08-22 | 2016-08-22 | The system and method for prestress rope integrative consolidation slab column |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610700586.1A CN106121268B (en) | 2016-08-22 | 2016-08-22 | The system and method for prestress rope integrative consolidation slab column |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106121268A true CN106121268A (en) | 2016-11-16 |
CN106121268B CN106121268B (en) | 2018-11-09 |
Family
ID=57279935
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610700586.1A Active CN106121268B (en) | 2016-08-22 | 2016-08-22 | The system and method for prestress rope integrative consolidation slab column |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106121268B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112412085A (en) * | 2020-10-15 | 2021-02-26 | 安徽寰宇建筑设计院 | Prestress reinforcing method for repairing expansion drum of box type steel column wall plate |
CN113790760A (en) * | 2021-09-18 | 2021-12-14 | 科顿环境科学股份有限公司 | Supervision method for installation of super-large-span steel structure planar truss |
CN117266620A (en) * | 2023-11-23 | 2023-12-22 | 北京工业大学 | Reinforcing device and reinforcing method for beam column joints |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010069376A (en) * | 2001-03-15 | 2001-07-25 | 이창남 | Reinforcing Method of RC Structure Applying Cone Bolts |
CN101696589A (en) * | 2009-10-13 | 2010-04-21 | 华侨大学 | Novel combined stone beam |
CN201883704U (en) * | 2010-12-20 | 2011-06-29 | 重庆中设工程设计有限公司 | External prestressed tensile base |
CN102477799A (en) * | 2010-11-30 | 2012-05-30 | 上海维固工程实业有限公司 | Masonry structure integrity reinforcing method |
CN102661055A (en) * | 2012-03-12 | 2012-09-12 | 河海大学 | Reinforcing device for reinforced concrete column using prestressing cable, and application method thereof |
CN203742193U (en) * | 2014-02-26 | 2014-07-30 | 华侨大学 | Reinforced concrete beam reinforcing device with prestressed steel wire rope |
CN206071086U (en) * | 2016-08-22 | 2017-04-05 | 东南大学 | The system of prestress rope integrative consolidation slab column |
-
2016
- 2016-08-22 CN CN201610700586.1A patent/CN106121268B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010069376A (en) * | 2001-03-15 | 2001-07-25 | 이창남 | Reinforcing Method of RC Structure Applying Cone Bolts |
CN101696589A (en) * | 2009-10-13 | 2010-04-21 | 华侨大学 | Novel combined stone beam |
CN102477799A (en) * | 2010-11-30 | 2012-05-30 | 上海维固工程实业有限公司 | Masonry structure integrity reinforcing method |
CN201883704U (en) * | 2010-12-20 | 2011-06-29 | 重庆中设工程设计有限公司 | External prestressed tensile base |
CN102661055A (en) * | 2012-03-12 | 2012-09-12 | 河海大学 | Reinforcing device for reinforced concrete column using prestressing cable, and application method thereof |
CN203742193U (en) * | 2014-02-26 | 2014-07-30 | 华侨大学 | Reinforced concrete beam reinforcing device with prestressed steel wire rope |
CN206071086U (en) * | 2016-08-22 | 2017-04-05 | 东南大学 | The system of prestress rope integrative consolidation slab column |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112412085A (en) * | 2020-10-15 | 2021-02-26 | 安徽寰宇建筑设计院 | Prestress reinforcing method for repairing expansion drum of box type steel column wall plate |
CN113790760A (en) * | 2021-09-18 | 2021-12-14 | 科顿环境科学股份有限公司 | Supervision method for installation of super-large-span steel structure planar truss |
CN117266620A (en) * | 2023-11-23 | 2023-12-22 | 北京工业大学 | Reinforcing device and reinforcing method for beam column joints |
Also Published As
Publication number | Publication date |
---|---|
CN106121268B (en) | 2018-11-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9657722B2 (en) | Method and sliding form for producing a structure and corresponding structure | |
CN102979221B (en) | Shear wall structure configured with crossed slant internal prestress and construction method of shear wall structure | |
CN105569331B (en) | A kind of simple support method of concrete cylindrical template | |
KR101570484B1 (en) | Half-PC Column using lightweight Encased Inner Form And Manufacturing Method Thereof, And Construction Method Using The Same | |
CN110206143B (en) | Construction method of post-tensioning prestressed assembly concrete frame structure | |
CN104746435A (en) | Wide-angle Y-shaped pier column construction method | |
CN202990170U (en) | Shear wall structure collocating cross oblique internal prestress | |
CN109750791B (en) | Assembled large cantilever steel structure | |
CN110468727B (en) | Temporary prestress tensioning pedestal and lifting point integrated structure of segmental beam and construction method | |
CN106121268A (en) | The system and method for prestress rope integrative consolidation slab column | |
CN113605771B (en) | Prestress assembly type frame structure system | |
CN208857720U (en) | A kind of prestressing force metal composite muscle reinforcement bridge structure | |
CN101498173A (en) | Anti-floating construction method for cast-in-place concrete hollow building roof | |
CN109057148A (en) | Ultra-high performance concrete is without regular reinforcement Prestressed U type beam and its construction method | |
CN106930436A (en) | A kind of reinforced concrete shear wall of built-in prestress steel diagonal brace | |
CN105887704A (en) | Prestressed steel wire rope anti-shearing reinforced concrete box girder and reinforcing method thereof | |
CN206071086U (en) | The system of prestress rope integrative consolidation slab column | |
KR101036748B1 (en) | Multi ribbed pc slab | |
CN111321807B (en) | Assembled frame construction post-post bundling reinforcing bar connection structure | |
CN107100322B (en) | Post stretching vertical prestressing cast-in-place concrete rod structure and construction method | |
CN102619338B (en) | Construction method for pre-stressed tendon of ultra-long ring beam | |
CN218622790U (en) | Antidetonation coincide wall | |
CN208907228U (en) | A kind of prestressing force modular retaining wall | |
CN206071088U (en) | The system of prestress rope integrative consolidation board wall | |
CN216884551U (en) | High-strength built-in post-tensioned reinforced concrete pole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |