CN106120850A - A kind of method for designing of ballastless track of high-speed railway stake plate type retaining wall - Google Patents

A kind of method for designing of ballastless track of high-speed railway stake plate type retaining wall Download PDF

Info

Publication number
CN106120850A
CN106120850A CN201610452887.7A CN201610452887A CN106120850A CN 106120850 A CN106120850 A CN 106120850A CN 201610452887 A CN201610452887 A CN 201610452887A CN 106120850 A CN106120850 A CN 106120850A
Authority
CN
China
Prior art keywords
state
foundation soil
soil
stake
design
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610452887.7A
Other languages
Chinese (zh)
Inventor
周成
罗强
张良
李安洪
曾永红
姚裕春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
Southwest Jiaotong University
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University, China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical Southwest Jiaotong University
Priority to CN201610452887.7A priority Critical patent/CN106120850A/en
Publication of CN106120850A publication Critical patent/CN106120850A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The method for designing of a kind of ballastless track of high-speed railway stake plate type retaining wall, to efficiently solve the control problem of the pile body anchoring section foundation soil lateral deformation time effect that cannot consider in a plate type retaining wall traditional design method.Carry out as follows: survey means by ground and obtain the undisturbed soil sample of design work point foundation soil, carry out indoor triaxial test record soil sample intensity index c andCarry out indoor long-term triaxial test simultaneously and record the state threshold parameter lambda that fast and stable state is corresponding;It is calculated state strength parameter c of foundation soil before stake according to gained state threshold parameter lambda1WithIt is calculated the lateral bearing capacity σ of foundation soil deformation state before stake according to gained state strength parameterp 1;Draft anchor pile sectional dimension and anchoring depth by traditional anchor pile design and calculation method, calculate anchor pile to ground earth lateral pressure σ before stakey;The relatively σ at below ground 1/3 anchoring depthyWith σp;Carry out the Reinforcement Design of anchor pile, complete design flow process.

Description

A kind of method for designing of ballastless track of high-speed railway stake plate type retaining wall
Technical field
Patent of the present invention relates to the method for designing of a kind of ballastless track of high-speed railway stake plate type retaining wall.Belong to Geotechnical Engineering to prop up Gear structure-design technique field.
Background technology
Stake plate type retaining wall is to utilize the anchoring section being anchored in ground to provide skid resistance opposing to fill out earth lateral pressure, and it is main Wall is high not by the limitation in height of general barricade to want advantage to be, cantilever segment may be up to 15m, foundation bearing capacity can not pass through anchor completely Gu the buried depth of section is compensated for.But, when anchor pile cantilever segment is longer, the lateral deformation that pile body anchoring section is small will be in stake Being exaggerated at top, if the soil body and barricade generation compatible deformation after wall, then the lateral deformation of barricade will certainly cause the additional of embankment Sedimentation.When pile plate wall be applied to ballastless track of high-speed railway embankment prop up gear time, it is desirable to the deformation of anchoring section foundation soil is in quickly Steady statue (deformation is without time effect), controls the additional settlement of roadbed, to meet non-fragment orbit putting down under the conditions of few maintenance Pliable requirement.China TB10025-2006 " railway bed retaining structure design specification " specifies: pile plate wall below ground anchoring section Resistant force in front of anti-sliding pile at length 1/3 should be not more than foundation soil horizontal permitted bearing capacity [σH], and require that the lateral displacement of stake top is less than outstanding The 1% of arm segment length, and no more than 100mm.The deformation state of this intensity and Bit andits control standard and anchoring section foundation soil " fast and stable " state of requirement is not mated, it is difficult to the requirement of high-speed railway under the conditions of adaptation non-fragment orbit.Therefore, research It is applicable to the peg board formula DESIGN OF RETAINING WALLS method that ballastless track of high-speed railway controls based on deformation state, is high-speed railway subgrade work The key technical problem that Cheng Jianshe is urgently to be resolved hurrily.
Patent of invention content
The main purpose of patent of the present invention is to provide the method for designing of a kind of ballastless track of high-speed railway stake plate type retaining wall, During to efficiently solve the pile body anchoring section foundation soil lateral deformation that cannot consider in a plate type retaining wall traditional design method Between the control problem of effect.
It is as follows that the present invention solves the technical scheme that above-mentioned technical problem used:
The method for designing of a kind of ballastless track of high-speed railway stake plate type retaining wall of the present invention, is carried out as follows:
(1) survey means with passing through and obtain the undisturbed soil sample of design work point foundation soil, carry out indoor triaxial test and record soil Intensity index c of sample andCarry out indoor long-term triaxial test simultaneously and record the state threshold parameter lambda that fast and stable state is corresponding, When unconditionally carrying out indoor long-term triaxial test, λ takes 15%;
(2) it is calculated state strength parameter c of foundation soil before stake according to gained state threshold parameter lambda1WithCalculate public affairs Formula is:
In formulaFoundation soil is in state strength parameter during the first state, internal friction angle, °;
c1Foundation soil is in state strength parameter during the first state, cohesion, kPa;
Foundation soil actual strength parameter, internal friction angle, °;
C foundation soil actual strength parameter, cohesion, kPa;
λ1It is in state threshold parameter during the first state;
(3) it is calculated the lateral bearing capacity σ of foundation soil deformation state before stake according to gained state strength parameterp 1, calculate Formula is:
σ in formulap 1Foundation soil is in lateral bearing capacity during the first state, kPa;
The severe of γ foundation soil, kN/m3
Y is away from the earth's surface degree of depth, m;
(4) draft anchor pile sectional dimension and anchoring depth by traditional anchor pile design and calculation method, calculate anchoring Stake is to ground earth lateral pressure σ before stakey
(5) σ at below ground 1/3 anchoring depth is comparedyWith σp 1If, σy≤σp 1Before showing stake, foundation soil is at anchor pile Effect under do not have the deformation having time effect, can carry out next step design calculate;If σyp 1Shi Zexu adjusts between stake Away from or the parameter such as sectional dimension of stake recalculate, until meeting σy≤σp 1
(6) Reinforcement Design of anchor pile, complete design flow process are carried out.
The invention has the beneficial effects as follows, before controlling stake, foundation soil has the lateral deformation of time effect, builds new The pile plate wall method for designing of type, the shortcoming overcoming traditional design method, the requirement of ballastless track of high-speed railway can be met.
Accompanying drawing explanation
Fig. 1 is deformation state intensive parameter calculation diagram;
Fig. 2 is work point cross-sectional view;
Fig. 3 is that anchor pile is to foundation soil lateral stress scattergram;
Fig. 4-1 is anchoring section shearing scattergram;
Fig. 4-2 is anchoring section Bending moment distribution figure;
Fig. 5 is foundation soil lateral stress σ before stakeyTry hard to deformation state carrying.
Detailed description of the invention
Below in conjunction with detailed description of the invention, patent of the present invention is described in further detail.
When ballastless track of high-speed railway is by sloped ground, often building retaining structure in descending side, pile plate wall is For one of conventional selection.But, post-construction settlement of subgrade value is required extremely strict by ballastless track of high-speed railway, i.e. requires roadbed Sedimentation and deformation under Gravitative Loads and High-speed Train Loads has no time effect.It is therefore desirable to pile plate wall can not produce sometimes Between the lateral deformation of effect.Traditional pile plate wall method for designing is to ensure that retaining structure stabilizes to core purpose, does not control Whether structure there will be the lateral deformation having time effect.This is by the control technique of settlement after construction band for ballastless track of high-speed railway roadbed Carry out hidden danger.Patent of the present invention foundation soil before controlling stake has the lateral deformation of time effect, builds novel pile plate wall Method for designing, the shortcoming overcoming traditional design method, meet the requirement of ballastless track of high-speed railway.
It is critical only that of lateral deformation time effect controlling non-fragment orbit stake plate type retaining wall controls pile body anchoring location The lateral pressure of pile body suffered by foundation soil not can exceed that the load level threshold value corresponding to soil layer " fast and stable " state itself, This threshold value can be expressed with the percentage ratio of ultimate load level (peak load level).For design work point, surveyed by ground Means obtain the undisturbed soil sample of work point foundation soil, carry out indoor triaxial test and record the intensity index of soil sample, carry out interior length Phase triaxial test records the state threshold parameter lambda that " fast and stable " state is corresponding, and substantial amounts of actual measurement shows the " the most steady of fine grained soil Calmly " the state threshold parameter lambda that state is corresponding is generally 15%, i.e. pile body anchoring section acts on the lateral pressure of soil layer less than soil Layer lateral extreme bearing capacity (maximum lateral load level) 15% time, the lateral deformation of foundation soil is in fast and stable shape State, does not have time effect, meets the requirement of ballastless track of high-speed railway.It is calculated stake according to gained state threshold parameter lambda State strength parameter c of front foundation soil1WithThe determination of soil deformation state strength parameter is according to Mohr-Column criterion, right Ultimate load carries out reduction by load level threshold value λ, thus obtain the soil deformation state corresponding with load level threshold value Intensive parameter c1WithCalculation diagram is as shown in Figure 1.
In Fig. 1, solid line represents Mohr-Coulomb shear-resistant intensity, dotted line represent by load level reduction after soil deformation State strength line, by geometrical relationship, can derive intensive parameter c of soil deformation state1With
Can be converted by above-mentioned formula and obtain formula:
According to gained state strength parameter c1WithIt is calculated the lateral bearing capacity σ of foundation soil deformation state before stakep 1, meter Calculation formula is
Draft anchor pile sectional dimension and anchoring depth by traditional anchor pile design and calculation method again, calculate anchor pile To ground earth lateral pressure σ before stakey.Relatively at below ground 1/3 anchoring depth, (at this, pile body gives the lateral of foundation soil Pressure is maximum) σyWith σp 1.If σy≤σp 1Before the bright stake of segment table, foundation soil does not haves under the effect of anchor pile time effect Deformation, can carry out next step design calculate;If σyp 1Shi Zexu adjusts the parameters such as the sectional dimension of pile spacing or stake again Calculate, until meeting σy≤σp 1.Then the Reinforcement Design complete design flow process of anchor pile is carried out.
Deriving according to above, the method for designing of a kind of ballastless track of high-speed railway stake plate type retaining wall of the present invention, by such as Lower step is carried out:
(1) survey means with passing through and obtain the undisturbed soil sample of design work point foundation soil, carry out indoor triaxial test and record soil Intensity index c of sample andCarry out indoor long-term triaxial test simultaneously and record the state threshold parameter lambda that fast and stable state is corresponding (referring to that under load action, the deformation of soil sample is quickly stable, extends and sustainable development the most in time, i.e. deforms and do not have time effect) Corresponding state threshold parameter lambda, when unconditionally carrying out indoor long-term triaxial test, λ takes 15%, i.e. soil body bearing load is less than Maxium load value 15% time its deformation will be in fast and stable state;
(2) it is calculated state strength parameter c of foundation soil before stake according to gained state threshold parameter lambda1
WithComputing formula is:
In formulaFoundation soil is in state strength parameter during the first state, internal friction angle, °;
c1Foundation soil is in state strength parameter during the first state, cohesion, kPa;
Foundation soil actual strength parameter, internal friction angle, °;
C foundation soil actual strength parameter, cohesion, kPa;
λ1It is in state threshold parameter during the first state;
(3) it is calculated the lateral bearing capacity σ of foundation soil deformation state before stake according to gained state strength parameterp 1, calculate Formula is:
σ in formulap 1Foundation soil is in lateral bearing capacity during the first state, kPa;
The severe of γ foundation soil, kN/m3
Y is away from the earth's surface degree of depth, m;
(4) draft anchor pile sectional dimension and anchoring depth by traditional anchor pile design and calculation method, calculate anchoring Stake is to ground earth lateral pressure σ before stakey
(5) σ at below ground 1/3 anchoring depth is comparedyWith σp 1If, σy≤σp 1Before showing stake, foundation soil is at anchor pile Effect under do not have the deformation having time effect, can carry out next step design calculate;If σyp 1Shi Zexu adjusts between stake Away from or the parameter such as sectional dimension of stake recalculate, until meeting σy≤σp 1
(6) Reinforcement Design of anchor pile, complete design flow process are carried out.
Embodiment
1, parameter is calculated
Certain ballastless track of high-speed railway work point, as shown in Figure 2.Rolling earth behind retaining wall is A, B group filler, unit weight γ1=23kN/m3,(equivalent friction angle);In the range of anchor pile anchoring section, foundation soil has two-layer composition, and ground floor is that opaque sticks Soil, thickness h2-1≈ 10m, natural unit weight γ2-1=18.7kN/m3, c2=40.3kPa,Liquidity index IL=0.1; The second layer is severely-weathered shale, saturation, thickness h2-2=6m, by ground floor soil under 0.95 compactness and saturation Under parameter value, i.e. γ2-2=19.8kN/m3, its mechanics parameter is less with ground floor soil difference, for convenience of calculating, and this layer of soil Physical and mechanical parameter and ground floor soil take identical value, but coefficient of subgrade reaction is with the proportionality coefficient m value relatively ground floor soil of change in depth Can properly increase.Tentatively draft anchor pile cantilever segment height h1=8m, anchoring section degree of depth h2=16m.
Before stake, coefficient of subgrade reaction presses TB10023-1006 " railway bed retaining structure design with the proportionality coefficient m of change in depth Specification " value, as listed in table 1.Tentatively drafting anchor pile cross section is rectangle, wide B=2m, depth of section 3m, and pile body is C35 steel Reinforced concrete pours and forms, bending rigidity EI ≈ 1.4 × 108kN·m2, pile center's spacing L=5m.
Table 1 coefficient of subgrade reaction is with the proportionality coefficient m reference value of change in depth
According to GB50021-2001 " Code for investigation of geotechnical engineering " (2009 revised edition), ground silty clay liquidity index 0 < ILWhen=0.1≤0.25, for hard plastic state, then coefficient of subgrade reaction is with the proportionality coefficient m of change in depth1Span be 2000~ 4200kN/m4, during calculating, take its meansigma methods, then m1=3100kN/m4, for severely-weathered shale, m relatively silty clay improves one grade Value, i.e. m2Span is 3000~7000kN/m4, during calculating, take its meansigma methods, then m2=5000kN/m4.According to specification, Anchoring section h2In the range of soil conversion m value be:
m = m 1 h 2 - 1 2 + m 2 ( 2 h 2 - 1 + h 2 - 2 ) h 2 - 2 h 2 2 = 3100 &times; 10 2 + 5000 &times; ( 2 &times; 10 + 6 ) &times; 6 16 2 &ap; 4258 k N / m 4
The horizontal λ of deviatoric stress takes 0.15 according to result of the test, can obtain according to formulac2 1, as listed in table 2.
The deformation state intensive parameter of table 2 deviatoric stress horizontal λ 1 correspondence
2, process and result are calculated
A) Wall back pressure
Bright gold coefficient of active earth pressure ka1=0.2, can obtain:
E 1 = E a = 1 2 &gamma; 1 h 1 2 k a 1 = 0.5 &times; 23 &times; 8 2 &times; 0.2 = 147.2 k N / m
B) rigid pile and the judgement of elastic pile
Determination methods according to TB10023-1006 " railway bed retaining structure design specification ", rigid pile and elastic pile For:
In formula: the deformation coefficient of α stake, m-1
The anchorage depth of h stake, m;
The proportionality coefficient of m foundation soil horizontal resist forces, kN/m4
BpThe calculating width of stake, m;Bp=B+1;
The width of B stake, m;
The elastic modelling quantity of E stake, kPa;
The cross sectional moment of inertia of I stake, m4
Then according to calculating parameter, can obtain:
&alpha; = mB p E I 5 = 4258 &times; ( 2 + 1 ) 1.4 &times; 10 8 5 = 0.155 m - 1 ;
αh2=0.155 × 16=2.48 < 2.5, belongs to rigid pile.
C) anchor pile internal force calculates
Center of rotation y0 of anchor pile and anchor pile corner φ:
y 0 = h 2 ( 9 h 2 + 4 h 1 ) 6 ( h 1 + 2 h 2 ) = 16 &times; ( 9 &times; 16 + 4 &times; 8 ) 6 &times; ( 8 + 2 &times; 16 ) = 11.7 m ;
&phi; = 12 E 1 L ( h 1 + 2 h 2 ) B p mh 2 4 = 12 &times; 147.2 &times; 5 &times; ( 8 + 2 &times; 16 ) ( 2 + 1 ) &times; 4258 &times; 16 4 = 4.2 &times; 10 - 4 r a d .
Anchoring section away from ground y depth anchor pile to foundation soil lateral stress σyFor:
σy=my (y0-y) φ=4258 × 4.2 × 10-4× (11.7-y) y=21y-1.8y2
Then anchor pile is to foundation soil maximum lateral stress σymax=61.2kPa, corresponding y=5.8m, divide along the anchoring section degree of depth Cloth is as shown in Figure 3.
Anchor pile anchoring section shearing and Bending moment distribution, as shown in Figure 4.
Anchoring section shearing Qy:
Q y = E 1 L - 1 6 B p m&phi;y 2 ( 3 y 0 - 2 y ) = 147.2 &times; 5 - 3 &times; 4258 &times; 4.2 &times; 10 - 4 &times; y 2 ( 3 &times; 11.7 - 2 y ) / 6 = 736 - 31.4 y 2 + 1.8 y 3
Anchoring section moment My:
M y = 1 3 E 1 Lh 1 + E 1 L y - 1 12 B p m&phi;y 3 ( 2 y 0 - y ) = 147.2 &times; 5 &times; 8 / 3 + 147.2 &times; 5 y - 3 &times; 4258 &times; 4.2 &times; 10 - 4 &times; y 3 ( 2 &times; 11.7 - y ) / 12 = 1963 + 736 y - 10.5 y 3 + 0.45 y 4
The calculated anchoring section maximal bending moment distance away from ground is 5.8m.
D) foundation deformation state evaluation before stake
Away from below ground (1/3) h2The degree of depth and h2Depth anchor pile is to ground lateral stress σy, result is as listed in table 3, different The σ of depthp1With soil lateral stress σyAlong the anchoring section degree of depth distribution as shown in Figure 5.Calculating process is as follows:
Y=1/3h2[the σ of depthH i];
Y=h2[the σ of depthH i];
Table 3 ground lateral stress σ y unit: kPa
From table 3 and Fig. 5, calculated deep less than this away from below ground anchor pile each depth Pile side soil stress σ y Foundation soil lateral bearing capacity σ p1 under fast and stable state at degree, it can thus be assumed that the Sizes of intended stake, ground before wall stake Soil deformation is in fast and stable state.Control requirement by pile strength again and carry out arrangement of reinforcement calculating, complete design.

Claims (1)

1. a method for designing for ballastless track of high-speed railway stake plate type retaining wall, is carried out as follows:
(1) survey means with passing through and obtain the undisturbed soil sample of design work point foundation soil, carry out indoor triaxial test and record soil sample Intensity index c andCarry out indoor long-term triaxial test simultaneously and record the state threshold parameter lambda that fast and stable state is corresponding, without bar When part carries out indoor long-term triaxial test, λ takes 15%;
(2) it is calculated state strength parameter c of foundation soil before stake according to gained state threshold parameter lambda1WithComputing formula is:
In formulaFoundation soil is in state strength parameter during the first state, internal friction angle, °;
c1Foundation soil is in state strength parameter during the first state, cohesion, kPa;
Foundation soil actual strength parameter, internal friction angle, °;
C foundation soil actual strength parameter, cohesion, kPa;
λ1It is in state threshold parameter during the first state;
(3) it is calculated the lateral bearing capacity σ of foundation soil deformation state before stake according to gained state strength parameterp 1, computing formula For:
σ in formulap 1Foundation soil is in lateral bearing capacity during the first state, kPa;
The severe of γ foundation soil, kN/m3
Y is away from the earth's surface degree of depth, m;
(4) draft anchor pile sectional dimension and anchoring depth by traditional anchor pile design and calculation method, calculate anchor pile pair Ground earth lateral pressure σ before stakey
(5) σ at below ground 1/3 anchoring depth is comparedyWith σp 1If, σy≤σp 1Show that foundation soil is at the work of anchor pile before stake Do not have the deformation having time effect under with, next step design can be carried out and calculate;If σyp 1Shi Zexu adjust pile spacing or The parameters such as the sectional dimension of stake recalculate, until meeting σy≤σp 1
(6) Reinforcement Design of anchor pile, complete design flow process are carried out.
CN201610452887.7A 2016-06-22 2016-06-22 A kind of method for designing of ballastless track of high-speed railway stake plate type retaining wall Pending CN106120850A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610452887.7A CN106120850A (en) 2016-06-22 2016-06-22 A kind of method for designing of ballastless track of high-speed railway stake plate type retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610452887.7A CN106120850A (en) 2016-06-22 2016-06-22 A kind of method for designing of ballastless track of high-speed railway stake plate type retaining wall

Publications (1)

Publication Number Publication Date
CN106120850A true CN106120850A (en) 2016-11-16

Family

ID=57470523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610452887.7A Pending CN106120850A (en) 2016-06-22 2016-06-22 A kind of method for designing of ballastless track of high-speed railway stake plate type retaining wall

Country Status (1)

Country Link
CN (1) CN106120850A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447774A (en) * 2017-06-21 2017-12-08 中铁二院工程集团有限责任公司 Double pile foundation cantilever retaining wall resistance to overturning computational methods
CN109902320A (en) * 2017-12-07 2019-06-18 中铁二院工程集团有限责任公司 A kind of steep slope subgrade chair form piled anchor consolidates depth design calculation method
CN111199070A (en) * 2020-01-27 2020-05-26 贵州星隆迪岩土工程有限公司 Design method of pile-supported two-layer retaining wall
CN111274695A (en) * 2020-01-17 2020-06-12 中铁二院工程集团有限责任公司 Design method of high-speed railway road shoulder pile slab wall structure
CN111539051A (en) * 2020-03-16 2020-08-14 中铁二院工程集团有限责任公司 Three-dimensional static force calculation method for overhead pile plate structure
CN111678810A (en) * 2020-06-18 2020-09-18 西南交通大学 Compacted soil horizontal residual stress estimation method based on direct shear test
CN113047335A (en) * 2021-04-18 2021-06-29 中铁二院工程集团有限责任公司 Method for determining wall top displacement control standard of railway shoulder retaining wall
CN113378283A (en) * 2021-07-01 2021-09-10 中铁二院工程集团有限责任公司 Calculation method for anchoring point reinforced pile structure
CN114372302A (en) * 2021-11-24 2022-04-19 中铁二院工程集团有限责任公司 Design method of road shoulder gravity type retaining wall of high-speed railway with speed per hour of 400km plus

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100313721B1 (en) * 1998-11-26 2001-12-28 김징완 Method for designing synthetic underground retaining wall by temporary soil protection structure and working process of underground retaining wall of structure
CN101691724A (en) * 2009-09-17 2010-04-07 西南交通大学 Liquefied soil foundation quake-proof road-bridge transition section structure of ballastless track of high-speed railway
CN202194037U (en) * 2011-08-26 2012-04-18 中铁一局集团有限公司 Laterally adjusting and positioning device for ballastless turnouts of high-speed railways

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100313721B1 (en) * 1998-11-26 2001-12-28 김징완 Method for designing synthetic underground retaining wall by temporary soil protection structure and working process of underground retaining wall of structure
CN101691724A (en) * 2009-09-17 2010-04-07 西南交通大学 Liquefied soil foundation quake-proof road-bridge transition section structure of ballastless track of high-speed railway
CN202194037U (en) * 2011-08-26 2012-04-18 中铁一局集团有限公司 Laterally adjusting and positioning device for ballastless turnouts of high-speed railways

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李浩: "高速铁路无砟轨道路肩桩板墙侧向位移特征及状态控制设计方法研究", 《中国博士学位论文全文数据库(工程科技Ⅱ辑)》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447774A (en) * 2017-06-21 2017-12-08 中铁二院工程集团有限责任公司 Double pile foundation cantilever retaining wall resistance to overturning computational methods
CN109902320A (en) * 2017-12-07 2019-06-18 中铁二院工程集团有限责任公司 A kind of steep slope subgrade chair form piled anchor consolidates depth design calculation method
CN109902320B (en) * 2017-12-07 2023-04-07 中铁二院工程集团有限责任公司 Design and calculation method for anchoring depth of chair type pile of steep slope roadbed
CN111274695B (en) * 2020-01-17 2022-11-18 中铁二院工程集团有限责任公司 Design method of high-speed railway road shoulder pile plate wall structure
CN111274695A (en) * 2020-01-17 2020-06-12 中铁二院工程集团有限责任公司 Design method of high-speed railway road shoulder pile slab wall structure
CN111199070A (en) * 2020-01-27 2020-05-26 贵州星隆迪岩土工程有限公司 Design method of pile-supported two-layer retaining wall
CN111199070B (en) * 2020-01-27 2024-04-26 贵州星隆迪岩土工程有限公司 Design method of pile support two-layer retaining wall
CN111539051A (en) * 2020-03-16 2020-08-14 中铁二院工程集团有限责任公司 Three-dimensional static force calculation method for overhead pile plate structure
CN111678810A (en) * 2020-06-18 2020-09-18 西南交通大学 Compacted soil horizontal residual stress estimation method based on direct shear test
CN111678810B (en) * 2020-06-18 2021-11-09 西南交通大学 Compacted soil horizontal residual stress estimation method based on direct shear test
CN113047335A (en) * 2021-04-18 2021-06-29 中铁二院工程集团有限责任公司 Method for determining wall top displacement control standard of railway shoulder retaining wall
CN113378283B (en) * 2021-07-01 2022-10-04 中铁二院工程集团有限责任公司 Calculation method for anchoring point reinforced pile structure
CN113378283A (en) * 2021-07-01 2021-09-10 中铁二院工程集团有限责任公司 Calculation method for anchoring point reinforced pile structure
CN114372302A (en) * 2021-11-24 2022-04-19 中铁二院工程集团有限责任公司 Design method of road shoulder gravity type retaining wall of high-speed railway with speed per hour of 400km plus

Similar Documents

Publication Publication Date Title
CN106120850A (en) A kind of method for designing of ballastless track of high-speed railway stake plate type retaining wall
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
US20140314497A1 (en) Polymer grouting method for constructing gravel pile
CN100371537C (en) Novel method for reinforcing deep soft foundition-cencrete core sand stone pile compound foundition method
Wang et al. Working characteristics of concrete-cored deep cement mixing piles under embankments
CN107604770A (en) Non-fragment orbit low embankment substrate swelled ground pile foundation reinforcement afterwale method for determination of amount
Finno et al. Saturated clay response during braced cut construction
Le Kouby et al. Subgrade improvement method for existing railway lines–an experimental and numerical study
CN107841908A (en) For eliminating the road structure of the high embankment lateral variation sedimentation in high-speed railway abrupt slope
CN208293531U (en) A kind of mini pile soil composite structure of controllable variance sedimentation
Zhan et al. Design method of pile-slab structure roadbed of ballastless track on soil subgrade
Zhang et al. Field study on performance of new technique of geosynthetic-reinforced and pile-supported embankment at bridge approach
CN102433887A (en) Construction method of sand replacement mixing pile impervious wall
CN206052770U (en) A kind of use cast-in-situ bored pile combines the retaining wall of compaction grouting
CN111395062B (en) Equal-load replacement light soil side wide roadbed structure, design and construction method
CN111676740B (en) Construction and design method of anti-arching roadbed structure of ballastless track of cutting section
Wei et al. Design parameter optimization of beam foundation on soft soil layer with nonlinear finite element
Chunshan et al. Selection of reasonable scheme of entering into a working well in shield construction
Karlsrud Geotechnical Engineering for Transportation Infrastructure, Barends et al.(eds)© 1999 Balkema, Rotterdam, ISBN 90 5809 047 7
Grindheim et al. Full-scale pullout tests of rock anchors in limestone testing rock mass uplift failure
Guo et al. Numerical Simulation of New Support Structure for High In-Situ Stress Tunnel of Sichuan—Tibet Railway
Heitz et al. Embankment project on soft subsoil with grouted stone columns and geogrids
Gautray Influence of smear and compaction zones on the performance of stone columns in lacustrine clay
CN101525883B (en) Method for preventing cyclone well from sinking when sealing bottom
Li et al. Control and evaluation for residual subgrade settlement of high speed railway

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161116