CN106114757B - A kind of fore body three dimensional unit construction technology - Google Patents
A kind of fore body three dimensional unit construction technology Download PDFInfo
- Publication number
- CN106114757B CN106114757B CN201610741136.7A CN201610741136A CN106114757B CN 106114757 B CN106114757 B CN 106114757B CN 201610741136 A CN201610741136 A CN 201610741136A CN 106114757 B CN106114757 B CN 106114757B
- Authority
- CN
- China
- Prior art keywords
- fore body
- dimensional unit
- scaffold
- construction
- dimensional
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B73/00—Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B3/00—Hulls characterised by their structure or component parts
- B63B3/14—Hull parts
- B63B3/46—Stems
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Foundations (AREA)
Abstract
The present invention relates to shipbuilding field, and it is an object of the present invention to provide a kind of fore body three dimensional unit construction technology, the fore body three dimensional unit construction technology, include the following steps:Step 1 makes four support feets using pipe;Step 2, be open fore body three dimensional unit placed face down, sets up scaffold, and four support feets are averagely mounted on the three-dimensional surface at the top of fore body three dimensional unit;Step 3 removes scaffold, and by fore body three dimensional unit, transversely rib bit line overturns 180 °, and fore body three dimensional unit on the ground, fixation is raised, and set up scaffold by support feet to support feet by support downwards.The beneficial effects of the present invention are:The technique effectively reduces construction cost, raising construction continuity terminates only to need to set up scaffold three times, and the position after turn for fillet welding in the vertical position can all be constructed as flat fillet weld from construction to construction is started, the production efficiency of hull construction personnel is improved, reduces labor intensity.
Description
Technical field
The present invention relates to shipbuilding field, more particularly to a kind of fore body three dimensional unit construction technology.
Background technology
Fore body three dimensional unit is the class triangle of the three-dimensional surface composition with opening face and including two inclined-planes, applying before this
Work method is that respectively overturning is primary on the basis of opening face and two inclined-planes, and four foot hands need to be set up altogether to end from construction is started
Frame, cost is higher, and all fillets welding in the vertical position in position of welding, and construction is inconvenient, and difficulty of processing is high.
Invention content
It is an object of the invention to overcome drawbacks described above, a kind of simplified step, fore body solid point easy to process are provided
Section construction technology.
In order to solve the above-mentioned technical problem, the technical solution adopted by the present invention is:
A kind of fore body three dimensional unit construction technology, includes the following steps:
Step 1 makes four support feets using pipe;
Step 2, be open fore body three dimensional unit placed face down, sets up scaffold, four support feets are averagely mounted on
On three-dimensional surface at the top of fore body three dimensional unit;
Step 3 removes scaffold, and by fore body three dimensional unit, transversely rib bit line overturns 180 °, and support feet is supported on downwards
On ground, fore body three dimensional unit is raised, and set up scaffold by fixation by support feet;
Step 4 carries out fore body three dimensional unit weld job, and scaffold is removed after the completion of operation;
Step 5 sets up scaffold after fore body three dimensional unit is overturn 180 °, carry out reconditioning and painting operation, and operation is completed
After remove scaffold.
The beneficial effects of the present invention are:The technique effectively reduces construction cost, improves construction continuity, from starting to construct
Terminate only to need to set up scaffold three times, and the position after turn for fillet welding in the vertical position can all be applied as flat fillet weld to construction
Work improves the production efficiency of hull construction personnel, reduces labor intensity.
Description of the drawings
Fig. 1 is the Construction State figure of fore body three dimensional unit construction technology of the embodiment of the present invention.
Label declaration:
1st, fore body three dimensional unit;2nd, support feet;11st, be open face;12nd, three-dimensional surface;21st, VERTICAL TUBE;22nd, horizontal tube.
Specific embodiment
In order to describe the technical content, the structural feature, the achieved object and the effect of this invention in detail, below in conjunction with embodiment
And attached drawing is coordinated to be explained in detail.
The design of most critical of the present invention is:The technique effectively reduces construction cost, improves construction continuity, improves ship
The production efficiency of body construction personnel, reduces labor intensity.
Refering to Figure 1, the fore body three dimensional unit construction technology of the present embodiment, includes the following steps:
Step 1 makes four support feets 2 using pipe;
Step 2, face 11 that fore body three dimensional unit 1 is open are placed downward, set up scaffold, and four support feets 2 are averagely pacified
On the three-dimensional surface 12 at 1 top of fore body three dimensional unit;
Step 3 removes scaffold, and by fore body three dimensional unit 1, transversely rib bit line overturns 180 °, and support feet 2 supports downwards
On the ground, fore body three dimensional unit 1 is raised, and set up scaffold by fixation by support feet 2;
Step 4 carries out fore body three dimensional unit 1 weld job, and scaffold is removed after the completion of operation;
Step 5 sets up scaffold after fore body three dimensional unit 1 is overturn 180 °, carry out reconditioning and painting operation, and operation is completed
After remove scaffold.
As can be seen from the above description, the beneficial effects of the present invention are:The technique effectively reduces construction cost, improves construction and connects
Continuous property terminates only to need to set up scaffold three times from construction to construction is started, and all can be with for the position of fillet welding in the vertical position after turning over
It constructs as flat fillet weld, improves the production efficiency of hull construction personnel, reduce labor intensity.
Further, the support feet 2 includes VERTICAL TUBE 21 and horizontal tube 22, and 21 end of VERTICAL TUBE is three-dimensional with fore body
1 connection of segmentation, described 22 one end of horizontal tube are connect with 21 middle part of VERTICAL TUBE, 22 other end of horizontal tube and fore body three dimensional unit
1 connection.
Seen from the above description, the support feet 2 includes VERTICAL TUBE 21 and horizontal tube 22, and rational in infrastructure, stability is good.
Further, the support feet 2 is fixed by welding on fore body three dimensional unit 1.
Seen from the above description, support feet 2 is fixed by welding on fore body three dimensional unit 1, sound construction, construction party
Just.
It please refers to shown in Fig. 1, the embodiment of the present invention one is:
A kind of fore body three dimensional unit construction technology, includes the following steps:Step 1 makes four support feets 2 using pipe,
The support feet 2 includes VERTICAL TUBE 21 and horizontal tube 22, and 21 end of VERTICAL TUBE is connect with fore body three dimensional unit 1, the water
Flat 22 one end of pipe is connect with 21 middle part of VERTICAL TUBE, and 22 other end of horizontal tube is connect with fore body three dimensional unit 1, the support feet
2 are fixed by welding on fore body three dimensional unit 1;Step 2, face 11 that fore body three dimensional unit 1 is open are placed downward, set up foot hand
Four support feets 2 are averagely mounted on the three-dimensional surface 12 at 1 top of fore body three dimensional unit by frame;Step 3 removes scaffold, by bow
Transversely rib bit line overturns 180 ° to portion's three dimensional unit 1, and the support downwards of support feet 2 is on the ground, three-dimensional by fore body by support feet 2
Segmentation 1 raises fixation, and set up scaffold;Step 4 carries out fore body three dimensional unit 1 weld job, and foot is removed after the completion of operation
Hand cradle;Step 5 sets up scaffold after fore body three dimensional unit 1 is overturn 180 °, reconditioning and painting operation are carried out, after the completion of operation
Remove scaffold.
In conclusion fore body three dimensional unit construction technology provided by the invention, the technique effectively reduce construction cost, improve
It constructs continuity, terminates only to need to set up scaffold three times from construction to construction is started, and the position after turning over for fillet welding in the vertical position is complete
Portion can construct as flat fillet weld, improve the production efficiency of hull construction personnel, reduce labor intensity, the support feet
Rational in infrastructure including VERTICAL TUBE and horizontal tube, stability is good, and support feet is fixed by welding on fore body three dimensional unit, structure
Securely, it is easy for construction.
The foregoing is merely the embodiment of the present invention, are not intended to limit the scope of the invention, every to utilize this hair
The equivalent structure or equivalent flow shift that bright specification and accompanying drawing content are made directly or indirectly is used in other relevant skills
Art field, is included within the scope of the present invention.
Claims (3)
1. a kind of fore body three dimensional unit construction technology, which is characterized in that include the following steps:
Step 1 makes four support feets using pipe;
Step 2, be open fore body three dimensional unit placed face down, sets up scaffold, and four support feets are averagely mounted on fore body
On three-dimensional surface at the top of three dimensional unit;
Step 3 removes scaffold, and by fore body three dimensional unit, transversely rib bit line overturns 180 °, and support feet is supported on downwards ground
On, fore body three dimensional unit is raised, and set up scaffold by fixation by support feet;
Step 4 carries out fore body three dimensional unit weld job, and scaffold is removed after the completion of operation;
Step 5 sets up scaffold after fore body three dimensional unit is overturn 180 °, carry out reconditioning and painting operation, torn open after the completion of operation
Except scaffold.
2. fore body three dimensional unit construction technology according to claim 1, it is characterised in that:The support feet includes VERTICAL TUBE
And horizontal tube, the vertical pipe end are connect with fore body three dimensional unit, are connect in the middle part of described horizontal tube one end and VERTICAL TUBE, it is described
The horizontal tube other end is connect with fore body three dimensional unit.
3. fore body three dimensional unit construction technology according to claim 1, it is characterised in that:The support feet is solid by welding
It is scheduled on fore body three dimensional unit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610741136.7A CN106114757B (en) | 2016-08-26 | 2016-08-26 | A kind of fore body three dimensional unit construction technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610741136.7A CN106114757B (en) | 2016-08-26 | 2016-08-26 | A kind of fore body three dimensional unit construction technology |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106114757A CN106114757A (en) | 2016-11-16 |
CN106114757B true CN106114757B (en) | 2018-06-19 |
Family
ID=57271854
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610741136.7A Active CN106114757B (en) | 2016-08-26 | 2016-08-26 | A kind of fore body three dimensional unit construction technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106114757B (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101181926A (en) * | 2007-09-07 | 2008-05-21 | 沪东中华造船(集团)有限公司 | Sectionalized assembling method for ship bow luff part |
CN202879739U (en) * | 2012-10-16 | 2013-04-17 | 沪东中华造船(集团)有限公司 | Supporting tool for fore peak segmented carry positioning in ship construction |
CN104760662A (en) * | 2014-12-19 | 2015-07-08 | 华泰重工(南通)有限公司 | Process for manufacturing ice zone bulbous bow reinforcing structure by sections |
CN204548395U (en) * | 2015-01-22 | 2015-08-12 | 启东丰顺船舶重工有限公司 | A kind of band thruster stem sectional making technique |
CN105539769A (en) * | 2015-12-23 | 2016-05-04 | 江苏现代造船技术有限公司 | Method for building scaffolds in closing stage of bottom side tank of bulk cargo ship cargo hold |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101588716B1 (en) * | 2014-03-13 | 2016-01-26 | 삼성중공업 주식회사 | Ship construction method |
-
2016
- 2016-08-26 CN CN201610741136.7A patent/CN106114757B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101181926A (en) * | 2007-09-07 | 2008-05-21 | 沪东中华造船(集团)有限公司 | Sectionalized assembling method for ship bow luff part |
CN202879739U (en) * | 2012-10-16 | 2013-04-17 | 沪东中华造船(集团)有限公司 | Supporting tool for fore peak segmented carry positioning in ship construction |
CN104760662A (en) * | 2014-12-19 | 2015-07-08 | 华泰重工(南通)有限公司 | Process for manufacturing ice zone bulbous bow reinforcing structure by sections |
CN204548395U (en) * | 2015-01-22 | 2015-08-12 | 启东丰顺船舶重工有限公司 | A kind of band thruster stem sectional making technique |
CN105539769A (en) * | 2015-12-23 | 2016-05-04 | 江苏现代造船技术有限公司 | Method for building scaffolds in closing stage of bottom side tank of bulk cargo ship cargo hold |
Also Published As
Publication number | Publication date |
---|---|
CN106114757A (en) | 2016-11-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106114757B (en) | A kind of fore body three dimensional unit construction technology | |
CN204545736U (en) | A kind of assembling unit peculiar to vessel | |
CN110254623A (en) | A kind of production method of submerged body segmentation | |
CN202377693U (en) | Auxiliary welding tooling for special semitrailer | |
CN104526123B (en) | Passenger vehicle back wall assembly assembling-welding fixtures and use it to carry out the technique of back wall assembly welding equipment | |
CN203992859U (en) | A kind of for being interrupted the welding position scoring tool of fillet welding | |
CN203767025U (en) | Turnable cabin observation platform | |
CN202295224U (en) | Embedded bracket tool for positioning and mounting tail fin of ship | |
CN205147687U (en) | Supporting base | |
CN202879739U (en) | Supporting tool for fore peak segmented carry positioning in ship construction | |
CN203698610U (en) | Marine crane base | |
CN206883079U (en) | Code frock is drawn in a kind of board material splice positioning | |
CN201864019U (en) | Temporary scaffold device used in broadside subsection closure | |
CN206500783U (en) | A kind of industrial automatic soldering device | |
CN204075536U (en) | A kind of for boats and ships vertical electro-gas welding process servicing unit | |
CN205186469U (en) | Pitch ship stand alone type cargo hold structure of half UNICOM's type | |
CN206309032U (en) | A kind of plain form translation device | |
CN205259636U (en) | Combined pavilion | |
CN205324884U (en) | Processingequipment of hull bottom assembly pipe | |
CN107052668A (en) | Code frock and board joint method are drawn in board material splice positioning | |
CN202336861U (en) | Supporting tooling for linear section of bottom side tank | |
CN204978842U (en) | Concrete mixing semitrailer after -poppet structure | |
CN204279505U (en) | A kind of pigment bucket trammer dedicated | |
CN203936275U (en) | The pipe fitting jacking apparatus of automatic tube expanding machine | |
CN201589012U (en) | Device convenient for pipeline to pass through wall surface |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |