CN106089222A - 一种用于砂岩泥岩单护盾tbm掘进方法 - Google Patents

一种用于砂岩泥岩单护盾tbm掘进方法 Download PDF

Info

Publication number
CN106089222A
CN106089222A CN201610477887.2A CN201610477887A CN106089222A CN 106089222 A CN106089222 A CN 106089222A CN 201610477887 A CN201610477887 A CN 201610477887A CN 106089222 A CN106089222 A CN 106089222A
Authority
CN
China
Prior art keywords
controls
driving
speed
water
tbm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610477887.2A
Other languages
English (en)
Other versions
CN106089222B (zh
Inventor
汪强宗
陈明
张志伟
邬叶飞
杨洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of Highway Engineering Bureau of CCCC
No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical No 1 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority to CN201610477887.2A priority Critical patent/CN106089222B/zh
Publication of CN106089222A publication Critical patent/CN106089222A/zh
Application granted granted Critical
Publication of CN106089222B publication Critical patent/CN106089222B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

一种用于砂岩泥岩单护盾TBM掘进方法属于隧道施工领域,通过控制TBM掘进参数,提高隧道掘进速度、质量,以及减少刀具消耗、改善施工环境;TBM掘进参数包括刀盘转速、刀盘扭矩、掘进速度、总推进力、每环加水量,具体如下:在砂岩中掘进时,刀盘转速控制在2.6~3.0r/min,掘进总推力控制在6500~8900kN,每环加水量控制在0.4~0.5m3,刀盘扭矩控制在1537~3014kNm,推进速度控制在35~53mm/min;在砂质泥岩中掘进时,刀盘转速控制在2.8~3.2r/min,掘进总推力控制在5600~7500kN,每环加水量控制在0.8~1.0m3,刀盘扭矩控制在2473~3267kNm,推进速度控制在28~42mm/min。

Description

一种用于砂岩泥岩单护盾TBM掘进方法
技术领域
本发明涉及砂岩泥岩地质单护盾TBM的掘进参数,适用于隧道施工的技术领域。
背景技术
近年来,各大城市相继发展地下公共交通设施,而TBM法施工已成为城市地铁施工的主要施工方法,但在目前的国内TBM掘进操作中,对掘进需要的各种参数都是边掘进边摸索,并没有确切的掘进参数范围,这样不仅使掘进速度过慢,而且容易出现错台、损坏刀盘刀具、施工现场粉尘大等一系列不利情况。为改善现状,现制定一种用于砂岩泥岩单护盾TBM掘进的参数范围。
发明内容
本发明的目的是提高隧道掘进速度、质量,以及减少刀具消耗、改善施工环境。
一种用于砂岩泥岩单护盾TBM掘进方法,其特征在于,通过控制TBM掘进参数,提高隧道掘进速度、质量,以及减少刀具消耗、改善施工环境;TBM掘进参数包括刀盘转速、刀盘扭矩、掘进速度、总推进力、每环加水量,具体如下:
1)在砂岩中掘进时,刀盘转速控制在2.6~3.0r/min,掘进总推力控制在6500~8900kN,每环加水量控制在0.4~0.5m3,刀盘扭矩控制在1537~3014kNm,推进速度控制在35~53mm/min;
2)在砂质泥岩中掘进时,刀盘转速控制在2.8~3.2r/min,掘进总推力控制在5600~7500kN,每环加水量控制在0.8~1.0m3,刀盘扭矩控制在2473~3267kNm,推进速度控制在28~42mm/min。
本发明通过对区间隧道地质情况分析、总结出单护盾TBM在此类砂岩泥岩中掘进所需范围,分析内容见下表:
由此总结出不同地质条件掘进参数选择:
1)砂质泥岩地层
在砂质泥岩中掘进时,刀盘切削岩层较容易,推力控制在5600~7500kN,推进速度在35~53mm/min。若推力过小,掘进速度低,施工进度慢,并且由于底层较软,掌子面对刀具产生的阻力小于刀具的启动扭矩,会导致刀具出现偏磨;若推力过大,掘进速度快,由于底层软,在掘进过程中,TBM姿态难以控制,效果不佳。
2)砂岩地层
在砂岩掘进时,刀盘切削岩层困难,推力控制在6500~8900kN,推进速度在28~42mm/min。若推力过小,推进速度低,施工进度慢、且刀具磨损快;若推力过大,由于底层硬,刀具切削岩体困难,超过刀具额定承载力,导致刀具损坏。
3)刀盘加水
刀盘加水是为了降低粉尘、刀盘温度及改变渣土的流塑性,在砂岩掘进时,将水量控制在0.4~0.5m3;在砂质泥岩掘进时,将水量控制在0.8~1.0m3
利用本发明,具有如下优点:
1)提高掘进速度与施工质量。
2)减少刀具以及TBM机各装置的消耗。
3)改善施工环境,降低粉尘。
具体实施方式
1)在砂岩中掘进时,刀盘转速控制在2.6~3.0r/min,掘进总推力控制在6500~8900kN,每环加水量控制在0.4~0.5m3,刀盘扭矩控制在1537~3014kNm,推进速度控制在35~53mm/min。
2)在砂质泥岩中掘进时,刀盘转速控制在2.8~3.2r/min,掘进总推力控制在5600~7500kN,每环加水量控制在0.8~1.0m3,刀盘扭矩控制在2473~3267kNm,推进速度控制在28~42mm/min。
具体参数见下表:单护盾TBM在砂岩泥岩中掘进参数表

Claims (1)

1.一种用于砂岩泥岩单护盾TBM掘进方法,其特征在于,通过控制TBM掘进参数,提高隧道掘进速度、质量,以及减少刀具消耗、改善施工环境;TBM掘进参数包括刀盘转速、刀盘扭矩、掘进速度、总推进力、每环加水量,具体如下:
1)在砂岩中掘进时,刀盘转速控制在2.6~3.0r/min,掘进总推力控制在6500~8900kN,每环加水量控制在0.4~0.5m3,刀盘扭矩控制在1537~3014kNm,推进速度控制在35~53mm/min;
2)在砂质泥岩中掘进时,刀盘转速控制在2.8~3.2r/min,掘进总推力控制在5600~7500kN,每环加水量控制在0.8~1.0m3,刀盘扭矩控制在2473~3267kNm,推进速度控制在28~42mm/min。
CN201610477887.2A 2016-06-27 2016-06-27 一种用于砂岩泥岩单护盾tbm掘进方法 Active CN106089222B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610477887.2A CN106089222B (zh) 2016-06-27 2016-06-27 一种用于砂岩泥岩单护盾tbm掘进方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610477887.2A CN106089222B (zh) 2016-06-27 2016-06-27 一种用于砂岩泥岩单护盾tbm掘进方法

Publications (2)

Publication Number Publication Date
CN106089222A true CN106089222A (zh) 2016-11-09
CN106089222B CN106089222B (zh) 2018-04-17

Family

ID=57253131

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610477887.2A Active CN106089222B (zh) 2016-06-27 2016-06-27 一种用于砂岩泥岩单护盾tbm掘进方法

Country Status (1)

Country Link
CN (1) CN106089222B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108386202A (zh) * 2018-03-30 2018-08-10 重庆大学 城市地铁区间隧道单护盾tbm施工工法
CN111079342A (zh) * 2019-11-29 2020-04-28 中铁工程装备集团有限公司 一种基于在线岩体等级分类的tbm掘进性能预测方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05106391A (ja) * 1991-10-14 1993-04-27 Penta Ocean Constr Co Ltd シールド掘削機の自動掘進方向制御方法
CN101915106A (zh) * 2010-08-05 2010-12-15 中山大学 一种盾构下穿已建隧道的最佳掘进速度控制方法
CN103870677A (zh) * 2014-02-07 2014-06-18 上海交通大学 一种掘进机的掘进参数设定方法
CN104632236A (zh) * 2014-12-26 2015-05-20 中铁二局股份有限公司 Tbm-epb双模式盾构在复合地层中的施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05106391A (ja) * 1991-10-14 1993-04-27 Penta Ocean Constr Co Ltd シールド掘削機の自動掘進方向制御方法
CN101915106A (zh) * 2010-08-05 2010-12-15 中山大学 一种盾构下穿已建隧道的最佳掘进速度控制方法
CN103870677A (zh) * 2014-02-07 2014-06-18 上海交通大学 一种掘进机的掘进参数设定方法
CN104632236A (zh) * 2014-12-26 2015-05-20 中铁二局股份有限公司 Tbm-epb双模式盾构在复合地层中的施工方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108386202A (zh) * 2018-03-30 2018-08-10 重庆大学 城市地铁区间隧道单护盾tbm施工工法
CN111079342A (zh) * 2019-11-29 2020-04-28 中铁工程装备集团有限公司 一种基于在线岩体等级分类的tbm掘进性能预测方法
CN111079342B (zh) * 2019-11-29 2023-04-07 中铁工程装备集团有限公司 一种基于在线岩体等级分类的tbm掘进性能预测方法

Also Published As

Publication number Publication date
CN106089222B (zh) 2018-04-17

Similar Documents

Publication Publication Date Title
Gong et al. Rock burst and slabbing failure and its influence on TBM excavation at headrace tunnels in Jinping II hydropower station
Barla et al. TBM tunnelling in difficult ground conditions
Bilgin An appraisal of TBM performances in Turkey in difficult ground conditions and some recommendations
CN107676100B (zh) 基于盾构掘进参数的不良地层预测方法
CN201588635U (zh) 一种在岩土复合地层使用的特殊盾构刀具组合
Gong et al. TBM tunneling in marble rock masses with high in situ stress and large groundwater inflow: a case study in China
CN104131817A (zh) 一种富水砂卵石地层盾构掘进施工渣土改良工艺
CN108256168B (zh) 一种复合地层盾构滚刀磨损量确定方法
CN104329093A (zh) 一种盾构区间隧道组段划分方法
CN104793261A (zh) 煤系地层构造、弱区识别及地层反演的钻进探测方法
CN102777185A (zh) 一种斜井井筒施工工艺
CN106869953A (zh) 土压平衡盾构上软下硬及全断面硬岩用压气平衡掘进方法
CN108643867A (zh) 一种卸压、水力喷射掏煤抽采煤层气工艺
CN106089222B (zh) 一种用于砂岩泥岩单护盾tbm掘进方法
Cao et al. Experimental study of the drilling process in debris-rich ice
CN106483197A (zh) 一种基于原位声波测试的巷道底鼓分类方法
CN204754762U (zh) 一种建筑用钻孔装置
CN204225772U (zh) 一种防卡钻钻头
CN102383803B (zh) 综合机械化岩巷掘进机的切削刀
CN204082157U (zh) 盾构用撕裂刀
CN106948860B (zh) 基于u型井与定向钻孔协同递进抽采煤层瓦斯的方法
Zhao et al. Rock mechanics and excavation by tunnel boring machine–issues and challenges
CN109268024A (zh) 用于软硬地层的磁力转换式智能换刀钻切装置
Xie et al. Mechanism and experiment of substituting high drainage roadway with directional long drilling group to extract pressure-relief gas
CN105863662B (zh) 一种隧道掘进机掘进方法及应用该方法的非开挖隧道掘进机

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant