CN104131817A - 一种富水砂卵石地层盾构掘进施工渣土改良工艺 - Google Patents

一种富水砂卵石地层盾构掘进施工渣土改良工艺 Download PDF

Info

Publication number
CN104131817A
CN104131817A CN201410317338.XA CN201410317338A CN104131817A CN 104131817 A CN104131817 A CN 104131817A CN 201410317338 A CN201410317338 A CN 201410317338A CN 104131817 A CN104131817 A CN 104131817A
Authority
CN
China
Prior art keywords
shield
muck
stratum
polyacrylamide
rich water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410317338.XA
Other languages
English (en)
Inventor
张君
李人宪
徐润泽
杜飞龙
王国义
连逢逾
张卢学
杨亮亮
李小波
周双禧
麻俊辉
南庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Second Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Original Assignee
Southwest Jiaotong University
Second Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University, Second Engineering Co Ltd of China Railway 13th Bureau Group Co Ltd filed Critical Southwest Jiaotong University
Priority to CN201410317338.XA priority Critical patent/CN104131817A/zh
Publication of CN104131817A publication Critical patent/CN104131817A/zh
Pending legal-status Critical Current

Links

Abstract

本发明涉及一种富水砂卵石地层盾构掘进施工渣土改良工艺,在对富水砂卵石地层采用土压平衡盾构在对地层渣土特性进行改良的同时进行隧道工程施工作业。包含:1)渣土改良添加剂中增加聚丙烯酰胺组分,其配比浓度为1—3%质量百分比;2)在盾构台车内设置水箱,人工搅拌均匀1)渣土改良添加剂中后用水泵通过盾构机的膨润土通道加注到刀盘前部,从而对渣土特性进行改良。本发明利用聚丙烯酰胺能使悬浮物质通过电中和,架桥吸附,起絮凝作用;通过刀盘搅拌以及聚丙烯酰胺本身具有的物理、化学性质,对渣土起粘合作用。从而缓解盾构掘进施工时地层坍塌速率,有效控制地面沉降。

Description

一种富水砂卵石地层盾构掘进施工渣土改良工艺
技术领域
本发明涉及一种建筑隧道工程施工渣土改良,特别是一种富水砂卵石地层盾构掘进施工渣土改良。
背景技术
土压平衡盾构是利用安装在盾构最前面的全断面切削刀盘,将正面土体切削下来进入刀盘后面的贮留密封仓内,并使仓内具有适当压力与开挖面水土压力平衡,以减少盾构推进对地层土体的扰动,从而控制地表沉降,在出土时由安装在密封仓下部的螺旋运输机向排土口连续的将土渣排出。
富水砂卵石地层含水丰富,渗透系数大;岩体松散,无胶结,自稳能力差,单个石块强度高,卵石块在地层中起骨架作用,是一种典型的力学不稳定地层,颗粒之间的空隙大,没有粘聚力,砂卵石地层颗粒之间点对点传力,地层反应灵敏。刀盘旋转切削时,地层很易破坏原来的相对稳定或平衡状态而产生坍塌,引起较大的地层损失和围岩扰动,地面沉降反应速率快。针对富水砂卵石地层特殊性,必须对地层渣土特性进行改良,以适应土压平衡盾构法施工。良好的渣土改良有利于控制地面沉降,并且能减轻盾构机部件磨耗,提高施工进度。目前,富水砂卵石地层盾构施工主要是依靠“泡沫试剂+气+水”进行渣土改良,存在以下弊端:
(1)该地层地下水丰富、渗透系数大,单纯依靠泡沫气压、刀盘切削渣土建立土压,不能满足阻止地下水进入土仓从而减缓地层坍塌速率的要求。
(2)盾构掘进施工易发生“喷涌”现象,影响施工安全。
(3)盾构长时间停机,泡沫气压会在地层中散发,因此采用“泡沫+气+水”渣土改良方法不能起到固砂、泥的作用。
(4)采用“泡沫+气+水”渣土改良方法不能满足渣土流动性、和易性以及阻水功效,影响施工进度。
富水砂卵石地层对盾构刀盘、刀具、螺旋运输机等主要部件磨损严重。
发明内容
鉴于现有技术的以上不足,本发明旨为富水砂卵石地层盾构法施工控制地面沉降,减轻盾构机部件磨耗,提高施工进度。具体解决如下问题:
(1)减缓掘进施工中盾构刀盘扰动地层而产生的地层坍塌速率;
(2)解决富水砂卵石地层盾构施工发生“喷涌”现象的问题,保障施工安全;
减轻盾构刀盘、刀具、螺旋输送机等盾构机主要部件的磨耗。
本发明的目的是通过如下的手段实现的。
一种富水砂卵石地层盾构掘进施工渣土改良工艺,在对富水砂卵石地层采用土压平衡盾构在对地层渣土特性进行改良的同时进行隧道工程施工作业。包含:1)渣土改良添加剂中增加聚丙烯酰胺组分,其配比浓度为1—3%质量百分比;2)在盾构台车内设置水箱,人工搅拌均匀1)渣土改良添加剂中后用水泵通过盾构机的膨润土通道加注到刀盘前部,从而对渣土特性进行改良。
这样,采用本发明工艺,利用聚丙烯酰胺能使悬浮物质通过电中和,架桥吸附,起絮凝作用;通过刀盘搅拌以及聚丙烯酰胺本身具有的物理、化学性质,对渣土起粘合作用。从而缓解盾构掘进施工时地层坍塌速率,有效控制地面沉降。聚丙烯酰胺在中性和酸性条件下均有增稠作用,地下水不容易穿透渣土层,从而解决了富水砂卵石地层盾构施工发生“喷涌”现象。聚丙烯酰胺能有效地降低渣土流动时的摩擦阻力,从而减轻盾构刀盘、刀具、螺旋输送机等主要部件的磨耗。
本发明的优点和积极效果可归纳为
(1)利用聚丙烯酰胺能使悬浮物质通过电中和,架桥吸附,起絮凝作用;通过刀盘搅拌以及聚丙烯酰胺本身具有的物理、化学性质,对渣土起粘合作用。从而缓解盾构掘进施工时地层坍塌速率,有效控制地面沉降。
(2)聚丙烯酰胺在中性和酸性条件下均有增稠作用,地下水不容易穿透渣土层,成功地解决富水砂卵石地层盾构施工易发生“喷涌”现象。
(3)减轻盾构刀盘、刀具、螺旋输送机磨损,降低设备维修、换刀风险。
(4)实施简单,成本低。
掘进施工渣土变稠,成功降低渣土外运成本,保护城市环境。
具体实施方式
在对富水砂卵石地层采用土压平衡盾构在对地层渣土特性进行改良的同时进行隧道工程施工作业。包含:1)渣土改良添加剂中增加聚丙烯酰胺组分,其配比浓度为1—3%质量百分比;2)在盾构台车内设置水箱,人工搅拌均匀1)渣土改良添加剂中后用水泵通过盾构机的膨润土通道加注到刀盘前部,从而对渣土特性进行改良。本发明利用聚丙烯酰胺能使悬浮物质通过电中和,架桥吸附,起絮凝作用;通过刀盘搅拌以及聚丙烯酰胺本身具有的物理、化学性质,对渣土起粘合作用。从而缓解盾构掘进施工时地层坍塌速率,有效控制地面沉降。

Claims (1)

1.一种富水砂卵石地层盾构掘进施工渣土改良工艺,在对富水砂卵石地层采用土压平衡盾构在对地层渣土特性进行改良的同时进行隧道工程施工作业,其特征在于,包含:1)渣土改良添加剂中增加聚丙烯酰胺组分,其配比浓度为1—3%质量百分比;2)在盾构台车内设置水箱,人工搅拌均匀1)渣土改良添加剂中后用水泵通过盾构机的膨润土通道加注到刀盘前部,从而对渣土特性进行改良。
CN201410317338.XA 2014-07-04 2014-07-04 一种富水砂卵石地层盾构掘进施工渣土改良工艺 Pending CN104131817A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410317338.XA CN104131817A (zh) 2014-07-04 2014-07-04 一种富水砂卵石地层盾构掘进施工渣土改良工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410317338.XA CN104131817A (zh) 2014-07-04 2014-07-04 一种富水砂卵石地层盾构掘进施工渣土改良工艺

Publications (1)

Publication Number Publication Date
CN104131817A true CN104131817A (zh) 2014-11-05

Family

ID=51804652

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410317338.XA Pending CN104131817A (zh) 2014-07-04 2014-07-04 一种富水砂卵石地层盾构掘进施工渣土改良工艺

Country Status (1)

Country Link
CN (1) CN104131817A (zh)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105156122A (zh) * 2015-06-12 2015-12-16 北京城建设计发展集团股份有限公司 一种富水板岩与砂卵石复合地层盾构掘进用渣土改良方法
CN105201520A (zh) * 2015-09-09 2015-12-30 北京市市政四建设工程有限责任公司 砂卵石地层土压平衡盾构施工渣土改良工艺
CN106032755A (zh) * 2015-03-09 2016-10-19 北京市政路桥股份有限公司 复合地层土压平衡盾构施工添加剂选择及配比方法
CN106351665A (zh) * 2016-11-07 2017-01-25 成都建工路桥建设有限公司 砂卵石地层土压平衡矩形盾构顶掘渣土改良施工方法
CN106703820A (zh) * 2017-01-29 2017-05-24 邓军 一种预防螺旋机喷涌的膨润土改良剂及其制备方法
CN107327302A (zh) * 2017-07-20 2017-11-07 西南交通大学 高水压、高渗透砂性地层土压平衡盾构的渣土改良方法
CN108035722A (zh) * 2017-12-11 2018-05-15 上海市基础工程集团有限公司 土压平衡盾构强透水性砂土改良方法
CN109026040A (zh) * 2018-08-03 2018-12-18 中国电建集团铁路建设有限公司 一种用于土压平衡盾构的同步双材料渣土改良系统
CN109339799A (zh) * 2018-10-26 2019-02-15 中铁二十二局集团轨道工程有限公司 一种富水砂卵石地层浅埋段盾构施工工艺
CN109577993A (zh) * 2018-12-06 2019-04-05 中交公局第三工程有限公司 砂卵石地层土压盾构浓泥浆渣土改良经济配方的确定方法
CN110359918A (zh) * 2019-06-27 2019-10-22 中交一公局第三工程有限公司 砂卵石地层中盾构机开挖面的支护压力的控制方法
CN110436836A (zh) * 2019-08-21 2019-11-12 河海大学 Scap式土压平衡盾构开舱用泥浆及其配制方法
CN113756833A (zh) * 2021-09-26 2021-12-07 中交第三航务工程局有限公司 一种防止土压平衡盾构机的螺旋输送机喷涌的方法
CN113775345A (zh) * 2021-09-01 2021-12-10 浙江杭海城际铁路有限公司 一种联络通道顶管机施工粉砂土层中全断面渣土改良方法

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106032755A (zh) * 2015-03-09 2016-10-19 北京市政路桥股份有限公司 复合地层土压平衡盾构施工添加剂选择及配比方法
CN105156122A (zh) * 2015-06-12 2015-12-16 北京城建设计发展集团股份有限公司 一种富水板岩与砂卵石复合地层盾构掘进用渣土改良方法
CN105201520A (zh) * 2015-09-09 2015-12-30 北京市市政四建设工程有限责任公司 砂卵石地层土压平衡盾构施工渣土改良工艺
CN106351665A (zh) * 2016-11-07 2017-01-25 成都建工路桥建设有限公司 砂卵石地层土压平衡矩形盾构顶掘渣土改良施工方法
CN106703820A (zh) * 2017-01-29 2017-05-24 邓军 一种预防螺旋机喷涌的膨润土改良剂及其制备方法
CN107327302B (zh) * 2017-07-20 2019-10-18 西南交通大学 高水压、高渗透砂性地层土压平衡盾构的渣土改良方法
CN107327302A (zh) * 2017-07-20 2017-11-07 西南交通大学 高水压、高渗透砂性地层土压平衡盾构的渣土改良方法
CN108035722A (zh) * 2017-12-11 2018-05-15 上海市基础工程集团有限公司 土压平衡盾构强透水性砂土改良方法
CN109026040A (zh) * 2018-08-03 2018-12-18 中国电建集团铁路建设有限公司 一种用于土压平衡盾构的同步双材料渣土改良系统
CN109339799A (zh) * 2018-10-26 2019-02-15 中铁二十二局集团轨道工程有限公司 一种富水砂卵石地层浅埋段盾构施工工艺
CN109577993A (zh) * 2018-12-06 2019-04-05 中交公局第三工程有限公司 砂卵石地层土压盾构浓泥浆渣土改良经济配方的确定方法
CN110359918A (zh) * 2019-06-27 2019-10-22 中交一公局第三工程有限公司 砂卵石地层中盾构机开挖面的支护压力的控制方法
CN110436836A (zh) * 2019-08-21 2019-11-12 河海大学 Scap式土压平衡盾构开舱用泥浆及其配制方法
CN110436836B (zh) * 2019-08-21 2021-10-15 河海大学 Scap式土压平衡盾构开舱用泥浆及其配制方法
CN113775345A (zh) * 2021-09-01 2021-12-10 浙江杭海城际铁路有限公司 一种联络通道顶管机施工粉砂土层中全断面渣土改良方法
CN113756833A (zh) * 2021-09-26 2021-12-07 中交第三航务工程局有限公司 一种防止土压平衡盾构机的螺旋输送机喷涌的方法

Similar Documents

Publication Publication Date Title
CN104131817A (zh) 一种富水砂卵石地层盾构掘进施工渣土改良工艺
CN104265307B (zh) 软硬不均地层土压平衡盾构隧道下穿铁路既有线施工方法
CN108661705B (zh) 条采采空区四位一体综合治理施工方法
CN102767377B (zh) 黄土地层地铁隧道土压平衡盾构施工方法
CN103883350B (zh) 一种间隔跳采的充填采煤方法
AU2014344670A1 (en) Solid cementation backfill roadway type mining method for ultra-thick seam
CN101403307A (zh) 复合土压平衡盾构机穿越浅埋富水砂层的施工方法
CN109322699A (zh) 一种矿井下污染隔离封堵技术
CN102704936B (zh) 综采工作面端头回采巷道顶板控制垮落法
CN102146679A (zh) 复杂地质地段土压平衡盾构通过中间风井施工方法
CN103742146B (zh) 墩柱式充填法采煤工艺
CN101967978A (zh) 复合砂砾石地层中的盾构土体改良施工方法
CN104033160A (zh) 一种适用于软土地层的浅埋暗挖隧道新型支护方法
CN102733816A (zh) 一种盾构近距离穿越建筑物时的变形控制方法
CN102937011A (zh) 瓦斯抽采钻孔群区域性裂隙场二次注浆封堵装置及方法
CN102777185A (zh) 一种斜井井筒施工工艺
CN104632220A (zh) 缓倾斜中厚矿体条柱再造采场结构尺寸可调可控采矿方法
CN107975044B (zh) 一种崩落法矿山利用尾矿地表塌陷坑回填的方法
CN104564137A (zh) 双介质垛式支撑坚硬顶板的煤矿采空区处理方法及装置
CN102619515B (zh) 一种顶部充填的高端壁无底柱分段崩落法开采工艺
CN102619514B (zh) 一种顶部充填的无底柱挑檐端壁阶段崩落法开采工艺
CN104329093A (zh) 一种盾构区间隧道组段划分方法
CN109898992A (zh) 一种采用地面定向钻孔超前治理多灾源矿层安全开采方法
CN106381405A (zh) 一种稀土矿山集液系统及方法
CN111997640A (zh) 一种大直径盾构快速掘进施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20141105