CN106088130B - It is a kind of for the positioning device of high-voltage and ultra-high pipe pier bolt and the localization method of high-voltage and ultra-high pipe pier bolt - Google Patents
It is a kind of for the positioning device of high-voltage and ultra-high pipe pier bolt and the localization method of high-voltage and ultra-high pipe pier bolt Download PDFInfo
- Publication number
- CN106088130B CN106088130B CN201610709938.XA CN201610709938A CN106088130B CN 106088130 B CN106088130 B CN 106088130B CN 201610709938 A CN201610709938 A CN 201610709938A CN 106088130 B CN106088130 B CN 106088130B
- Authority
- CN
- China
- Prior art keywords
- bolt
- ultra
- voltage
- connecting plate
- embedded bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
Abstract
The invention discloses a kind of positioning devices for high-voltage and ultra-high pipe pier bolt, including upper positioning plate and lower positioning component, wherein one end of upper positioning plate and pre-embedded bolt is detachably connected;The connection of the other end of lower positioning component and pre-embedded bolt, lower positioning component include the first connecting plate, the second connecting plate and the gusset for connecting the first connecting plate and the second connecting plate.Positioning device for high-voltage and ultra-high pipe pier bolt of the invention pre-embedded bolt can be accurately positioned, and can satisfy the requirement of high-voltage and ultra-high support of pipelines installation accuracy.The localization method of high-voltage and ultra-high pipe pier bolt of the invention controls at the pre-embedded bolt center of high-voltage and ultra-high pipe pier in ± 1mm away from pipe pier center installation error, and pre-embedded bolt exposed length control errors are controlled in ± 1mm, pre-embedded bolt vertical error at 0.25 ° of ∠.Control is able to satisfy the requirement of high-voltage and ultra-high support of pipelines installation in this error range, to provide precondition to meet the smooth installation of high-voltage and ultra-high pipeline.
Description
Technical field
The present invention relates to high-voltage and ultra-high unit engineering construction fields, are used for high-voltage and ultra-high pipe pier more particularly to one kind
The positioning device of bolt further relates to the localization method of high-voltage and ultra-high pipe pier bolt.
Background technique
In the construction of high-voltage and ultra-high unit engineering, the installation of high-voltage and ultra-high support of pipelines is very important, directly
Influence the safety of device operation.High-voltage and ultra-high pipe pier bolt is up to 1500mm or more, can be by concreting process
To the influence of various aspects, it is special to find that the construction precision of bolt is difficult to meet if taking no action to direct pre-embedded bolt, after pouring
Required precision of the sharp quotient to bolt.Patent quotient is the pre-embedded bolt center of high-voltage and ultra-high pipe pier away from pipe pier center to required precision
Installation error control is controlled in ± 1mm, pre-embedded bolt vertical error in ∠ in ± 1mm, pre-embedded bolt exposed length control errors
0.25°.Being unsatisfactory for required precision will cause largely doing over again for construction work, human and material resources, financial resources investment waste.
Summary of the invention
In view of the deficiencies of the prior art, determine the purpose of the present invention is to provide a kind of for high-voltage and ultra-high pipe pier bolt
The localization method of position device and high-voltage and ultra-high pipe pier bolt, the present invention can effectively solve the problem that in high-voltage and ultra-high device
This problem of high-voltage and ultra-high support of pipelines ground pipe pier pre-embedded bolt precision, so that pre-embedded bolt precision is able to satisfy high pressure superelevation
The installation requirement of pressure pipeline bracket.
To achieve the goals above, the invention adopts the following technical scheme:
The present invention provides a kind of positioning device for high-voltage and ultra-high pipe pier bolt, including upper positioning plate and lower positioning group
Part, wherein
One end of upper positioning plate and pre-embedded bolt is detachably connected;
The connection of the other end of lower positioning component and pre-embedded bolt, lower positioning component include the first connecting plate, the second connecting plate
And the gusset of connection the first connecting plate and the second connecting plate.
Further, it is provided with positioning plate location hole on upper positioning plate, the size of upper positioning plate location hole, quantity and pre-
Size, the quantity for burying bolt are corresponding, the bolt of the bottom plate of the position and high-voltage and ultra-high support of pipelines of upper positioning plate location hole
The position in hole is corresponding, and upper positioning plate location hole is detachably connected to pre-embedded bolt by upper positioning crab bolt.
Further, it is provided with the first connecting plate location hole on the first connecting plate, is provided with the second company on the second connecting plate
Size, size, the quantity of quantity and pre-embedded bolt of fishplate bar location hole, the first connecting plate location hole and the second connecting plate location hole
It is corresponding.
Further, the first connecting plate location hole is connected to pre-embedded bolt, the second connecting plate by the first connection crab bolt
Location hole is connected to pre-embedded bolt by the second connection crab bolt.
Further, the first gasket is provided between the first connecting plate and the first connection crab bolt, the second connecting plate and the
The second gasket is provided between two connection crab bolts.
Further, upper positioning plate and lower positioning component are steel plates and have the strong of the force request for meeting pre-embedded bolt
Degree and rigidity.
The present invention also provides a kind of localization methods of high-voltage and ultra-high pipe pier bolt, comprising the following steps:
Step 1 provides the above-mentioned positioning device for high-voltage and ultra-high pipe pier bolt of the invention;
First connecting plate location hole is connect by step 2 by the first gasket and the first connection crab bolt with pre-embedded bolt,
The second connecting plate location hole connect with pre-embedded bolt by the second gasket and the second connection crab bolt, and then by lower positioning component
It is connect with pre-embedded bolt, while lower positioning component being adjusted to the levelness met the requirements;
Upper positioning plate location hole is connect by step 3 by upper positioning crab bolt with pre-embedded bolt, and then by upper positioning plate
It is connect with pre-embedded bolt;
Step 4 carries out location and installation according to centre spot.
Further, further comprise step 5, concreting is carried out to pre-embedded bolt.
It further, further comprise step 6, after completing concreting, by upper positioning plate and upper positioning crab bolt
High-voltage and ultra-high support of pipelines is installed again after dismounting.
Further, centralized positioning is carried out using theodolite.
Compared with prior art, advantageous effects of the invention are as follows:
(1) positioning device for high-voltage and ultra-high pipe pier bolt of the invention can carry out pre-embedded bolt accurately fixed
Position, can satisfy the requirement of high-voltage and ultra-high support of pipelines installation accuracy.
(2) localization method of high-voltage and ultra-high pipe pier bolt of the invention is by the pre-embedded bolt center of high-voltage and ultra-high pipe pier
It controls away from pipe pier center installation error in ± 1mm, pre-embedded bolt exposed length control errors are vertically missed in ± 1mm, pre-embedded bolt
Difference control is at 0.25 ° of ∠.Control is able to satisfy the requirement of high-voltage and ultra-high support of pipelines installation in this error range, to be
The smooth installation for meeting high-voltage and ultra-high pipeline provides precondition.Localization method of the invention accelerates high-voltage and ultra-high pipeline
Bracket and pressure piping installation progress.Pre-embedded bolt registration is high, and qualification rate is high, and high-voltage and ultra-high support of pipelines returns repair in shop and changes
Amount is reduced, and is greatly reduced investment, has been saved cost.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the positioning device for high-voltage and ultra-high pipe pier bolt of the invention;
Fig. 2 is the top view of upper positioning plate of the invention;
Fig. 3 is the structural schematic diagram of lower positioning component of the invention;
Fig. 4 is another structural schematic diagram of lower positioning component of the invention.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, right below with reference to examples and drawings
The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not
For limiting the present invention.
As shown in Figs 1-4, the positioning device for high-voltage and ultra-high pipe pier bolt of the invention, including 1 He of upper positioning plate
One end of lower positioning component 2, upper positioning plate 1 and pre-embedded bolt 3 is detachably connected.In a preferred embodiment, upper positioning plate 1
On be provided with positioning plate location hole 11, size, quantity phase of the size, quantity of upper positioning plate location hole 11 with pre-embedded bolt 3
It is corresponding, the position phase of the bolt hole (not shown) of the position and bottom plate of high-voltage and ultra-high support of pipelines of upper positioning plate location hole 11
Corresponding, upper positioning plate location hole 11 is detachably connected to pre-embedded bolt 3, upper positioning plate location hole by upper positioning crab bolt 12
The premise of 11 precision for being accurately to ensure that the construction of pre-embedded bolt 3.
Lower positioning component 2 is connect with the other end of pre-embedded bolt 3, and lower positioning component 2 connects including the first connecting plate 21, second
Fishplate bar 22 and the gusset 23 for connecting the first connecting plate 21 and the second connecting plate 22, by welding gusset 23 and the first connecting plate
21 and second connecting plate 22 connect.In a preferred embodiment, the first connecting plate location hole is provided on the first connecting plate 21
211, the second connecting plate location hole 221 is provided on the second connecting plate 22, the first connecting plate location hole 211 and the second connecting plate are fixed
Size, the quantity in position hole 221 are corresponding with the size of pre-embedded bolt 3, quantity.In a preferred embodiment, the first connecting plate is fixed
Position hole 211 is connected to pre-embedded bolt 3 by the first connection crab bolt 212, and the second connecting plate location hole 221 passes through the second connecting plate
Nut 222 is connected to pre-embedded bolt 3.In a preferred embodiment, it is set between the first connecting plate 21 and the first connection crab bolt 212
It is equipped with the first gasket 213, is provided with the second gasket 223 between the second connecting plate 22 and the second connection crab bolt 222.Of the invention
Upper positioning plate 1 and lower positioning component 2 are steel plate and the strength and stiffness with the force request for meeting pre-embedded bolt 3.
The present invention also provides a kind of localization methods of high-voltage and ultra-high pipe pier bolt, comprising the following steps:
Step 1 provides the above-described positioning device for high-voltage and ultra-high pipe pier bolt;
Step 2, by the first gasket 213 and the first connection crab bolt 212 by the first connecting plate location hole 211 with it is pre-buried
Bolt 3 connects, and connects crab bolt 222 for the second connecting plate location hole 221 and pre-embedded bolt 3 by the second gasket 223 and second
Connection, and then lower positioning component 2 is connect with pre-embedded bolt 3, while lower positioning component 2 is adjusted to the level met the requirements
Degree;
Upper positioning plate location hole 11 is connect by step 3 by upper positioning crab bolt 12 with pre-embedded bolt 3, and then will be upper fixed
Position plate 1 is connect with pre-embedded bolt 3;
Step 4 carries out location and installation according to centre spot 4, and the details according to drawing are constructed, Ke Yili
Centralized positioning is carried out with theodolite or other more advanced instruments known in the art;
Step 5 carries out concreting to pre-embedded bolt 3;
Step 6 after completing concreting, installs high pressure after upper positioning plate 1 and upper positioning crab bolt 12 are removed again
Ultra-high pressure pipeline bracket.
Embodiments of the present invention above described embodiment only expresses, the description thereof is more specific and detailed, but can not
Therefore limitations on the scope of the patent of the present invention are interpreted as.It should be pointed out that for those of ordinary skill in the art,
Without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection model of the invention
It encloses.
Claims (10)
1. a kind of positioning device for high-voltage and ultra-high pipe pier bolt, which is characterized in that including upper positioning plate and lower positioning group
Part, wherein
One end of the upper positioning plate and pre-embedded bolt is detachably connected, and the upper positioning plate is carried out to the pre-embedded bolt
It is disassembled after concreting;
The lower positioning component is connect with the other end of the pre-embedded bolt, and the lower positioning component includes the first connecting plate, the
The gusset of two connecting plates and connection first connecting plate and second connecting plate;
The pre-embedded bolt center is ± 1mm away from pipe pier center installation error;The pre-embedded bolt exposed length error be ±
1mm;The pre-embedded bolt vertical error is 0.25 °.
2. the positioning device according to claim 1 for high-voltage and ultra-high pipe pier bolt, which is characterized in that described fixed
Be provided with positioning plate location hole on the plate of position, the size of the upper positioning plate location hole, the size of quantity and the pre-embedded bolt,
Quantity is corresponding, the position of the upper positioning plate location hole and the position phase of the bolt hole of the bottom plate of high-voltage and ultra-high support of pipelines
Corresponding, the upper positioning plate location hole is detachably connected to the pre-embedded bolt by upper positioning crab bolt.
3. the positioning device according to claim 1 for high-voltage and ultra-high pipe pier bolt, which is characterized in that described first
It is provided with the first connecting plate location hole on connecting plate, is provided with the second connecting plate location hole on second connecting plate, described
The size of one connecting plate location hole and the second connecting plate location hole, quantity are opposite with the size of the pre-embedded bolt, quantity
It answers.
4. the positioning device according to claim 3 for high-voltage and ultra-high pipe pier bolt, which is characterized in that described first
Connecting plate location hole is connected to the pre-embedded bolt by the first connection crab bolt, and the second connecting plate location hole passes through second
Connection crab bolt is connected to the pre-embedded bolt.
5. the positioning device according to claim 4 for high-voltage and ultra-high pipe pier bolt, which is characterized in that described first
The first gasket, second connecting plate and the second connecting plate spiral shell are provided between connecting plate and the first connection crab bolt
The second gasket is provided between mother.
6. the positioning device according to claim 1-5 for high-voltage and ultra-high pipe pier bolt, which is characterized in that
The upper positioning plate and the lower positioning component be steel plate and have meet the pre-embedded bolt force request intensity and
Rigidity.
7. a kind of localization method of high-voltage and ultra-high pipe pier bolt, which comprises the following steps:
Step 1 provides the positioning device according to claim 1-6 for high-voltage and ultra-high pipe pier bolt;
First connecting plate location hole is connect with pre-embedded bolt by the first gasket and the first connection crab bolt, is passed through by step 2
Second connecting plate location hole is connect by the second gasket and the second connection crab bolt with the pre-embedded bolt, and then by the lower positioning
Component is connect with the pre-embedded bolt, while lower positioning component being adjusted to the levelness met the requirements;
Upper positioning plate location hole is connect by step 3 by upper positioning crab bolt with the pre-embedded bolt, and then by upper positioning plate
It is connect with the pre-embedded bolt;
Step 4 carries out location and installation according to centre spot.
8. the localization method of high-voltage and ultra-high pipe pier bolt according to claim 7, which is characterized in that further comprise step
Rapid five, concreting is carried out to the pre-embedded bolt.
9. the localization method of high-voltage and ultra-high pipe pier bolt according to claim 8, which is characterized in that further comprise step
Rapid six, after completing the concreting, high pressure is installed again after the upper positioning plate and the upper positioning crab bolt are removed
Ultra-high pressure pipeline bracket.
10. the localization method of high-voltage and ultra-high pipe pier bolt according to claim 7, which is characterized in that utilize theodolite
Carry out centralized positioning.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610709938.XA CN106088130B (en) | 2016-08-23 | 2016-08-23 | It is a kind of for the positioning device of high-voltage and ultra-high pipe pier bolt and the localization method of high-voltage and ultra-high pipe pier bolt |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610709938.XA CN106088130B (en) | 2016-08-23 | 2016-08-23 | It is a kind of for the positioning device of high-voltage and ultra-high pipe pier bolt and the localization method of high-voltage and ultra-high pipe pier bolt |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106088130A CN106088130A (en) | 2016-11-09 |
CN106088130B true CN106088130B (en) | 2019-05-10 |
Family
ID=57224751
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610709938.XA Active CN106088130B (en) | 2016-08-23 | 2016-08-23 | It is a kind of for the positioning device of high-voltage and ultra-high pipe pier bolt and the localization method of high-voltage and ultra-high pipe pier bolt |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106088130B (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005256559A (en) * | 2004-03-15 | 2005-09-22 | Ishikawajima Harima Heavy Ind Co Ltd | Anchor structure and anchor method |
CN202023199U (en) * | 2011-03-25 | 2011-11-02 | 国水投资集团包头风电科技有限公司 | Pre-stressed anchor plate and anchor bolt assembly for foundation |
CN102758445A (en) * | 2011-04-27 | 2012-10-31 | 华锐风电科技(集团)股份有限公司 | Foundation leveling device, foundation assembly and foundation forming method for wind driven generator tower |
CN102900098A (en) * | 2012-11-14 | 2013-01-30 | 河南省电力公司信阳供电公司 | Construction process for leveling basic embedded part |
CN203188117U (en) * | 2013-04-24 | 2013-09-11 | 山东科技大学 | Fixing device of bridge guardrail metal stand column base |
CN205917715U (en) * | 2016-08-23 | 2017-02-01 | 大庆石化工程有限公司 | A positioner that is used for high -pressure superhigh pressure pipe pier bolt |
-
2016
- 2016-08-23 CN CN201610709938.XA patent/CN106088130B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005256559A (en) * | 2004-03-15 | 2005-09-22 | Ishikawajima Harima Heavy Ind Co Ltd | Anchor structure and anchor method |
CN202023199U (en) * | 2011-03-25 | 2011-11-02 | 国水投资集团包头风电科技有限公司 | Pre-stressed anchor plate and anchor bolt assembly for foundation |
CN102758445A (en) * | 2011-04-27 | 2012-10-31 | 华锐风电科技(集团)股份有限公司 | Foundation leveling device, foundation assembly and foundation forming method for wind driven generator tower |
CN102900098A (en) * | 2012-11-14 | 2013-01-30 | 河南省电力公司信阳供电公司 | Construction process for leveling basic embedded part |
CN203188117U (en) * | 2013-04-24 | 2013-09-11 | 山东科技大学 | Fixing device of bridge guardrail metal stand column base |
CN205917715U (en) * | 2016-08-23 | 2017-02-01 | 大庆石化工程有限公司 | A positioner that is used for high -pressure superhigh pressure pipe pier bolt |
Also Published As
Publication number | Publication date |
---|---|
CN106088130A (en) | 2016-11-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202298628U (en) | Automatic steel pipe column perpendicularity adjusting device using reverse construction method | |
CN204899938U (en) | Tunnel secondary lining formworking jumbo bulkhead | |
CN107060075A (en) | A kind of supporting construction connected for fabricated construction beam slab and installation method | |
CN203247603U (en) | High-position foundation bolt positioning device | |
CN203891058U (en) | Built-in foundation bolt positioning tool for fixed type tower crane foundation | |
CN102589973B (en) | Pullout test auxiliary device for hook anchor rod and test method | |
CN103776767A (en) | Portable drawing-type testing device and drawing-type testing method for testing adhesive property steel bar and concrete | |
CN103669634B (en) | Construction method and the structure of after-pouring damping wall | |
CN203475806U (en) | Tool type anchoring bolt assembly used for fixing shape steel cantilever beam in construction sites | |
CN106088130B (en) | It is a kind of for the positioning device of high-voltage and ultra-high pipe pier bolt and the localization method of high-voltage and ultra-high pipe pier bolt | |
CN202047367U (en) | Integral cable clamp for stayed cables | |
CN202416881U (en) | Steel girder mounting auxiliary appliance | |
CN205917715U (en) | A positioner that is used for high -pressure superhigh pressure pipe pier bolt | |
CN201271845Y (en) | Rapid locating tool for changing pipeline flange | |
CN102528418B (en) | High-precision and large-diameter flange steel pipe segmenting and track-change installation method | |
CN108772540B (en) | Installation method of continuous casting crystallizer | |
CN204921558U (en) | A interim connecting device that is used for component and bracket to dock | |
CN207104135U (en) | Steel plate welds preheating zone ceramic backing bracing means | |
CN103174300B (en) | Viscous damper installation construction method | |
CN104727569B (en) | Large Towers equipment increase method | |
CN102720353A (en) | Post-construction one-side shear wall formwork for settlement joint of tower and construction method | |
CN206554526U (en) | A kind of built-in fitting fixing device | |
CN105387279A (en) | Pipeline wall-attaching fixing device and method | |
CN201458509U (en) | Combined hoisting tool for large-sized pipes | |
CN206663037U (en) | A kind of railway track displacement monitoring fixture |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |