CN202023199U - Pre-stressed anchor plate and anchor bolt assembly for foundation - Google Patents
Pre-stressed anchor plate and anchor bolt assembly for foundation Download PDFInfo
- Publication number
- CN202023199U CN202023199U CN2011200929950U CN201120092995U CN202023199U CN 202023199 U CN202023199 U CN 202023199U CN 2011200929950 U CN2011200929950 U CN 2011200929950U CN 201120092995 U CN201120092995 U CN 201120092995U CN 202023199 U CN202023199 U CN 202023199U
- Authority
- CN
- China
- Prior art keywords
- bolt
- anchor slab
- foundation
- anchor
- anchor plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Foundations (AREA)
Abstract
Description
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011200929950U CN202023199U (en) | 2011-03-25 | 2011-03-25 | Pre-stressed anchor plate and anchor bolt assembly for foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011200929950U CN202023199U (en) | 2011-03-25 | 2011-03-25 | Pre-stressed anchor plate and anchor bolt assembly for foundation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202023199U true CN202023199U (en) | 2011-11-02 |
Family
ID=44848155
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011200929950U Expired - Lifetime CN202023199U (en) | 2011-03-25 | 2011-03-25 | Pre-stressed anchor plate and anchor bolt assembly for foundation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202023199U (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103334496A (en) * | 2013-07-19 | 2013-10-02 | 中建八局第一建设有限公司 | Leveling bolt of embedded steel plate under isolation bearing and using method |
CN103866785A (en) * | 2014-03-31 | 2014-06-18 | 北京金风科创风电设备有限公司 | Anchor plate and anchor bolt assembly and anti-corrosion processing method of anchor bolt |
CN103967041A (en) * | 2014-05-21 | 2014-08-06 | 中冶天工集团有限公司 | Construction method of fan foundation ring |
CN104110353A (en) * | 2014-07-03 | 2014-10-22 | 中国电建集团华东勘测设计研究院有限公司 | Anti-overturning wind generator foundation ring structure and construction method thereof |
CN104404975A (en) * | 2014-11-22 | 2015-03-11 | 孙晨 | Universal five-point support loading type tower crane foundation and construction method |
CN104568589A (en) * | 2013-10-23 | 2015-04-29 | 江苏金海新能源科技有限公司 | Pre-stressed anchor bolt stretching and drawing detection equipment |
CN104942696A (en) * | 2015-06-09 | 2015-09-30 | 中石化第十建设有限公司 | Compressor pre-buried anchor plate grinding device |
CN106088130A (en) * | 2016-08-23 | 2016-11-09 | 大庆石化工程有限公司 | A kind of positioner for high-voltage and ultra-high pipe pier bolt and the localization method of high-voltage and ultra-high pipe pier bolt |
CN106272991A (en) * | 2015-05-26 | 2017-01-04 | 山西颐顺鑫科技有限公司 | A kind of crab-bolt set, back of the body bolt and punching head |
CN108442400A (en) * | 2018-04-09 | 2018-08-24 | 中国电建集团华东勘测设计研究院有限公司 | A kind of construction method of blower foundation bolt assembly and blower foundation with T-nut |
CN109372007A (en) * | 2018-11-28 | 2019-02-22 | 长江三峡集团福建能源投资有限公司 | A kind of Oversea wind unit installation anchor bolt cage sealing anchor bolt and its construction method |
CN110820792A (en) * | 2019-08-27 | 2020-02-21 | 西安理工大学 | Design method for lower plate of power transmission line combined plate-rod three-anchor-plate foundation structure |
CN113186969A (en) * | 2021-06-03 | 2021-07-30 | 华电重工股份有限公司 | Prestressed anchor bolt mounting structure and mounting method |
-
2011
- 2011-03-25 CN CN2011200929950U patent/CN202023199U/en not_active Expired - Lifetime
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103334496A (en) * | 2013-07-19 | 2013-10-02 | 中建八局第一建设有限公司 | Leveling bolt of embedded steel plate under isolation bearing and using method |
CN104568589A (en) * | 2013-10-23 | 2015-04-29 | 江苏金海新能源科技有限公司 | Pre-stressed anchor bolt stretching and drawing detection equipment |
CN103866785A (en) * | 2014-03-31 | 2014-06-18 | 北京金风科创风电设备有限公司 | Anchor plate and anchor bolt assembly and anti-corrosion processing method of anchor bolt |
CN103967041A (en) * | 2014-05-21 | 2014-08-06 | 中冶天工集团有限公司 | Construction method of fan foundation ring |
CN104110353A (en) * | 2014-07-03 | 2014-10-22 | 中国电建集团华东勘测设计研究院有限公司 | Anti-overturning wind generator foundation ring structure and construction method thereof |
CN104404975B (en) * | 2014-11-22 | 2016-08-24 | 孙晨 | Universal 5 support ballast formula foundation for tower crane and construction method |
CN104404975A (en) * | 2014-11-22 | 2015-03-11 | 孙晨 | Universal five-point support loading type tower crane foundation and construction method |
CN106272991B (en) * | 2015-05-26 | 2018-11-13 | 山西颐顺鑫科技有限公司 | A kind of punching head |
CN106272991A (en) * | 2015-05-26 | 2017-01-04 | 山西颐顺鑫科技有限公司 | A kind of crab-bolt set, back of the body bolt and punching head |
CN104942696B (en) * | 2015-06-09 | 2017-04-05 | 中石化第十建设有限公司 | The pre-buried anchor slab lapping device of compressor |
CN104942696A (en) * | 2015-06-09 | 2015-09-30 | 中石化第十建设有限公司 | Compressor pre-buried anchor plate grinding device |
CN106088130A (en) * | 2016-08-23 | 2016-11-09 | 大庆石化工程有限公司 | A kind of positioner for high-voltage and ultra-high pipe pier bolt and the localization method of high-voltage and ultra-high pipe pier bolt |
CN106088130B (en) * | 2016-08-23 | 2019-05-10 | 大庆石化工程有限公司 | It is a kind of for the positioning device of high-voltage and ultra-high pipe pier bolt and the localization method of high-voltage and ultra-high pipe pier bolt |
CN108442400A (en) * | 2018-04-09 | 2018-08-24 | 中国电建集团华东勘测设计研究院有限公司 | A kind of construction method of blower foundation bolt assembly and blower foundation with T-nut |
CN109372007A (en) * | 2018-11-28 | 2019-02-22 | 长江三峡集团福建能源投资有限公司 | A kind of Oversea wind unit installation anchor bolt cage sealing anchor bolt and its construction method |
CN109372007B (en) * | 2018-11-28 | 2023-11-07 | 长江三峡集团福建能源投资有限公司 | Sealing anchor bolt for installing anchor bolt cage of offshore wind turbine and construction method of sealing anchor bolt |
CN110820792A (en) * | 2019-08-27 | 2020-02-21 | 西安理工大学 | Design method for lower plate of power transmission line combined plate-rod three-anchor-plate foundation structure |
CN113186969A (en) * | 2021-06-03 | 2021-07-30 | 华电重工股份有限公司 | Prestressed anchor bolt mounting structure and mounting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202023199U (en) | Pre-stressed anchor plate and anchor bolt assembly for foundation | |
CN101812842B (en) | Tensionless filling pile structure | |
CN102704491B (en) | Sectional steel and reinforced concrete beam combination foundation pit supporting protection surrounding purlin and construction method of purlin | |
CN103422512B (en) | Replaceable pre-embedded bolt formula wind generation set concrete foundation and construction method thereof | |
CN106661856A (en) | Transmission tower foundation using micropile | |
CN203924104U (en) | A kind of blower foundation | |
CN206034345U (en) | Improved generation is steel cable cable guardrail for municipal garden | |
CN201447879U (en) | Steel column base calibrating and fine adjusting device | |
CN103114604A (en) | Prestressed concrete tubular type wind generating set foundation | |
CN102605783A (en) | Construction method for applying prestress to anchor jacked piles | |
CN204080849U (en) | A kind of cushion cap anchoring type blower foundation | |
CN101736751A (en) | Connecting structure between wind measurement tower and pile foundation of offshore wind power station | |
CN207538064U (en) | A kind of power transmission line iron tower foundation | |
KR101687972B1 (en) | Foundation for Wind Generator and Construction Method Thereof | |
CN203346897U (en) | Foundation raft embedded steel column positioning support | |
CN104405734A (en) | Buckle type flange connection structure and method for tower and base of wind turbine | |
CN208430522U (en) | The blower foundation of steel truss structure | |
CN208010018U (en) | A kind of extra-high compressed steel pylon connecting flange | |
CN204125957U (en) | Flange transition interconnection system single-pile foundation structure | |
CN204282394U (en) | A kind of blower foundation and the prestressing force assembly for blower foundation | |
CN203846490U (en) | Spiral ground pile and upright column connecting structure | |
CN203129565U (en) | Floor connecting device of external scaffolding rigid wall connecting piece | |
CN202040029U (en) | Base reversed balancing flange | |
CN104695468A (en) | Construction method of flat sphere-shaped electric power tower foundation | |
CN201314047Y (en) | Cast-in-situ triangular pile model sinking device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee |
Owner name: INNER MONGOLIA OF GIMHAE NEW ENERGY TECHNOLOGY CO. Free format text: FORMER NAME: BAOTOU WIND POWER SCIENCE + TECHNOLOGY CO., LTD. OF CHINA WATER INVESTMENT GROUP |
|
CP01 | Change in the name or title of a patent holder |
Address after: 014030, 85, happiness South Road, rare earth hi tech Zone, the Inner Mongolia Autonomous Region, Baotou Patentee after: INNER MONGOLIA OF GIMHAE NEW ENERGY TECHNOLOGY CO., LTD. Patentee after: JIANGSU JINHAI NEW ENERGY TECHNOLOGY CO., LTD. Address before: 014030, 85, happiness South Road, rare earth hi tech Zone, the Inner Mongolia Autonomous Region, Baotou Patentee before: Baotou Wind Power Science & Technology Co., Ltd. Of China Water Investment Group Patentee before: Jiangsu Jinhai Wind Power Technology Co., Ltd. |
|
CX01 | Expiry of patent term |
Granted publication date: 20111102 |
|
CX01 | Expiry of patent term |