一种接缝螺栓连接预制混凝土桥面板及预制方法 Download PDFInfo
- Publication number
- CN106087741A CN106087741A CN201610665114.7A CN201610665114A CN106087741A CN 106087741 A CN106087741 A CN 106087741A CN 201610665114 A CN201610665114 A CN 201610665114A CN 106087741 A CN106087741 A CN 106087741A
- Authority
- CN
- China
- Prior art keywords
- floorings
- side plate
- girder
- steel plate
- junction steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009408 flooring Methods 0.000 title claims abstract description 68
- 239000011178 precast concrete Substances 0.000 title claims abstract description 26
- 238000000034 method Methods 0.000 title claims abstract description 12
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 110
- 239000010959 steel Substances 0.000 claims abstract description 110
- 239000004567 concrete Substances 0.000 claims abstract description 38
- 238000010276 construction Methods 0.000 claims abstract description 29
- 238000010008 shearing Methods 0.000 claims abstract description 8
- 239000002689 soil Substances 0.000 claims description 3
- 230000015271 coagulation Effects 0.000 claims description 2
- 238000005345 coagulation Methods 0.000 claims description 2
- 238000009417 prefabrication Methods 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 5
- 238000013461 design Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000009940 knitting Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/12—Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
- E01D19/125—Grating or flooring for bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610665114.7A CN106087741B (zh) | 2016-08-12 | 2016-08-12 | 一种接缝螺栓连接预制混凝土桥面板及预制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610665114.7A CN106087741B (zh) | 2016-08-12 | 2016-08-12 | 一种接缝螺栓连接预制混凝土桥面板及预制方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106087741A true CN106087741A (zh) | 2016-11-09 |
CN106087741B CN106087741B (zh) | 2017-11-28 |
Family
ID=57456467
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610665114.7A Expired - Fee Related CN106087741B (zh) | 2016-08-12 | 2016-08-12 | 一种接缝螺栓连接预制混凝土桥面板及预制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106087741B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106835951A (zh) * | 2017-03-28 | 2017-06-13 | 宁波金蛟龙重工钢构有限公司 | 一种可替换式预制装配式组合梁结构及制造工艺 |
CN108625276A (zh) * | 2018-07-24 | 2018-10-09 | 中铁七局集团第二工程有限公司 | 一种装配式钢与混凝土组合梁栈桥及施工方法 |
CN115058985A (zh) * | 2022-06-30 | 2022-09-16 | 西安公路研究院有限公司 | 用于桥梁应急抢修的钢混组合结构及应急抢修方法 |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20100007300A (ko) * | 2008-07-14 | 2010-01-22 | 한국건설기술연구원 | 콘크리트 크로스 빔을 이용하여 강 주형을 연결한 강 합성교량 및 시공방법 |
KR20120013106A (ko) * | 2010-08-04 | 2012-02-14 | 세종대학교산학협력단 | Psc 거더와 프리캐스트 바닥판 연결 구조 |
KR20130123076A (ko) * | 2012-05-02 | 2013-11-12 | 한국건설기술연구원 | 루프철근의 연속화 이음구조를 가지는 프리캐스트 콘크리트 모듈의 이음구조 및 이를 구비한 프리캐스트 콘크리트 구조물 |
CN203320417U (zh) * | 2013-04-07 | 2013-12-04 | 同济大学 | 桥面板可更换的组合梁桥面结构 |
CN103590322A (zh) * | 2013-11-05 | 2014-02-19 | 上海市政工程设计研究总院(集团)有限公司 | 一种剪力连接件、含该剪力连接件的组合梁及其施工方法 |
CN203546589U (zh) * | 2013-10-24 | 2014-04-16 | 同济大学 | 钢梁-整体式挑臂预制混凝土桥面板组合梁桥 |
CN104131652A (zh) * | 2014-07-17 | 2014-11-05 | 湖南大学 | 装配式rpc-钢-混凝土混合梁结构 |
CN105350445A (zh) * | 2015-09-24 | 2016-02-24 | 中交第二航务工程局有限公司 | 一种新型高效装配式钢混组合梁 |
CN105421210A (zh) * | 2015-12-21 | 2016-03-23 | 华汇工程设计集团股份有限公司 | 一种快速拼装的钢箱-预制混凝土板桥梁结构及其施工方法 |
CN105803939A (zh) * | 2016-04-27 | 2016-07-27 | 长安大学 | 一种开孔钢管钢混组合梁桥结构 |
CN205934722U (zh) * | 2016-08-12 | 2017-02-08 | 长安大学 | 一种接缝螺栓连接预制混凝土桥面板 |
-
2016
- 2016-08-12 CN CN201610665114.7A patent/CN106087741B/zh not_active Expired - Fee Related
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20100007300A (ko) * | 2008-07-14 | 2010-01-22 | 한국건설기술연구원 | 콘크리트 크로스 빔을 이용하여 강 주형을 연결한 강 합성교량 및 시공방법 |
KR20120013106A (ko) * | 2010-08-04 | 2012-02-14 | 세종대학교산학협력단 | Psc 거더와 프리캐스트 바닥판 연결 구조 |
KR20130123076A (ko) * | 2012-05-02 | 2013-11-12 | 한국건설기술연구원 | 루프철근의 연속화 이음구조를 가지는 프리캐스트 콘크리트 모듈의 이음구조 및 이를 구비한 프리캐스트 콘크리트 구조물 |
CN203320417U (zh) * | 2013-04-07 | 2013-12-04 | 同济大学 | 桥面板可更换的组合梁桥面结构 |
CN203546589U (zh) * | 2013-10-24 | 2014-04-16 | 同济大学 | 钢梁-整体式挑臂预制混凝土桥面板组合梁桥 |
CN103590322A (zh) * | 2013-11-05 | 2014-02-19 | 上海市政工程设计研究总院(集团)有限公司 | 一种剪力连接件、含该剪力连接件的组合梁及其施工方法 |
CN104131652A (zh) * | 2014-07-17 | 2014-11-05 | 湖南大学 | 装配式rpc-钢-混凝土混合梁结构 |
CN105350445A (zh) * | 2015-09-24 | 2016-02-24 | 中交第二航务工程局有限公司 | 一种新型高效装配式钢混组合梁 |
CN105421210A (zh) * | 2015-12-21 | 2016-03-23 | 华汇工程设计集团股份有限公司 | 一种快速拼装的钢箱-预制混凝土板桥梁结构及其施工方法 |
CN105803939A (zh) * | 2016-04-27 | 2016-07-27 | 长安大学 | 一种开孔钢管钢混组合梁桥结构 |
CN205934722U (zh) * | 2016-08-12 | 2017-02-08 | 长安大学 | 一种接缝螺栓连接预制混凝土桥面板 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106835951A (zh) * | 2017-03-28 | 2017-06-13 | 宁波金蛟龙重工钢构有限公司 | 一种可替换式预制装配式组合梁结构及制造工艺 |
CN108625276A (zh) * | 2018-07-24 | 2018-10-09 | 中铁七局集团第二工程有限公司 | 一种装配式钢与混凝土组合梁栈桥及施工方法 |
CN115058985A (zh) * | 2022-06-30 | 2022-09-16 | 西安公路研究院有限公司 | 用于桥梁应急抢修的钢混组合结构及应急抢修方法 |
CN115058985B (zh) * | 2022-06-30 | 2023-03-10 | 西安公路研究院有限公司 | 用于桥梁应急抢修的钢混组合结构及应急抢修方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106087741B (zh) | 2017-11-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107354862B (zh) | 预制夹层钢管混凝土与空心钢筋混凝土拼装桥墩 | |
CN106013432B (zh) | 一种高延性装配整体式框架中节点连接结构及施工方法 | |
CN104947603B (zh) | 一种钢筋混凝土梁桥主梁加固构造及加固方法 | |
CN105133791A (zh) | 装配式厚板钢骨混凝土柱变截面转换节点结构的施工方法 | |
CN104831818B (zh) | 预制钢筋混凝土梁和叠合柱的连接节点 | |
CN104963415B (zh) | 一种圆钢管约束型钢混凝土柱与钢梁节点结构 | |
CN106759865B (zh) | 一种钢管混凝土柱-u型钢板组合梁框架 | |
CN109372130A (zh) | 一种新型全装配式混凝土型钢框架节点及其施工方法 | |
CN109372129A (zh) | 一种新型全装配式混凝土框架节点及其施工方法 | |
CN106121049B (zh) | 组合剪力墙与钢筋桁架组合梁连接耗能节点及其制备方法 | |
CN207079479U (zh) | 一种公路桥预制墩与基础连接定位构造 | |
CN106087741A (zh) | 一种接缝螺栓连接预制混凝土桥面板及预制方法 | |
CN107447901A (zh) | 抗震预制楼板及楼板抗震拼接结构 | |
CN110107134A (zh) | 装配式铰接混凝土框架-屈曲约束支撑结构 | |
CN205934722U (zh) | 一种接缝螺栓连接预制混凝土桥面板 | |
CN209670127U (zh) | 一种预制型钢混凝土剪力墙的装配式结构 | |
CN103195172A (zh) | 一种预制装配混凝土框架梁柱连接节点构造 | |
CN204112525U (zh) | 高强度混凝土预制框架内嵌带竖缝预制剪力墙结构 | |
CN103334580B (zh) | 一种悬挑式脚手架中的型钢三脚架以及脚手架系统 | |
CN208280454U (zh) | 双钢板钢筋混凝土组合梁 | |
CN109610654A (zh) | 预制装配式双钢板混凝土剪力墙连接组件及其使用方法 | |
CN206360399U (zh) | 一种类“双连梁”的既有钢筋混凝土连梁加固装置 | |
KR101029087B1 (ko) | 복합 콘크리트 축 구조물 | |
CN105951984A (zh) | 一种高延性装配整体式框架边节点连接结构及施工方法 | |
CN209408886U (zh) | 一种装配式多腔钢管混凝土构件 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Liu Yongjian Inventor after: Zhang Xuanyu Inventor after: Li Jiangjiang Inventor after: Liu Cheng Inventor before: Liu Yongjian Inventor before: Long Gang Inventor before: Li Jiangjiang Inventor before: Zhang Zejun |
|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Liu Yongjian Inventor after: Gao Yimin Inventor after: Zhang Xuanyu Inventor after: Li Jiangjiang Inventor after: Liu Cheng Inventor before: Liu Yongjian Inventor before: Zhang Xuanyu Inventor before: Li Jiangjiang Inventor before: Liu Cheng |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||