CN106081944B - A kind of abridged edition type hoisting test method of heavy lift carrier - Google Patents

A kind of abridged edition type hoisting test method of heavy lift carrier Download PDF

Info

Publication number
CN106081944B
CN106081944B CN201610295392.8A CN201610295392A CN106081944B CN 106081944 B CN106081944 B CN 106081944B CN 201610295392 A CN201610295392 A CN 201610295392A CN 106081944 B CN106081944 B CN 106081944B
Authority
CN
China
Prior art keywords
crane
test
propelled
self
hoist
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610295392.8A
Other languages
Chinese (zh)
Other versions
CN106081944A (en
Inventor
薛建新
卞广飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU HONGQIANG MARINE HEAVY INDUSTRY CO LTD
Original Assignee
JIANGSU HONGQIANG MARINE HEAVY INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU HONGQIANG MARINE HEAVY INDUSTRY Co Ltd filed Critical JIANGSU HONGQIANG MARINE HEAVY INDUSTRY Co Ltd
Priority to CN201610295392.8A priority Critical patent/CN106081944B/en
Publication of CN106081944A publication Critical patent/CN106081944A/en
Application granted granted Critical
Publication of CN106081944B publication Critical patent/CN106081944B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/36Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
    • B66C23/52Floating cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/16Applications of indicating, registering, or weighing devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The present invention relates to a kind of abridged edition type hoisting test methods of heavy lift carrier, method includes the following steps: (1) experiment of weighing hoist;(2) overload test;(3) load test;(4) wheels-locked testing;(5) safety feature test;(6) post-test-inspection.The present invention has the advantages that the abridged edition type hoisting test method of heavy lift carrier of the present invention, compared with conventional test methods, it does not need using extraneous weight, directly using hanging on heavy lift carrier/two deck of self-propelled hatchway cover and 1x hanging block, both it reduced costs, it has been greatly reduced labor intensity, and has been made easy to operate.

Description

A kind of abridged edition type hoisting test method of heavy lift carrier
Technical field
The invention belongs to technical field of ships, in particular to the abridged edition type hoisting test method of a kind of heavy lift carrier.
Background technique
With the needs that marine cause develops, operation on the sea is increasingly enlarged, this requires to get over to marine large lifting equipment Come higher.Rising on heavy lift carrier enables the manufacture requirement hung high, and difficulty is big, wherein acting enable the hoisting test hung be mostly important one Ring, the purpose of test are to examine the installation integrity of crane, correctness, functional reliability, and verify whether performance indicator accords with Close design and test program requirement.Therefore rising and enabling the hoisting test hung is a comprehensive complicated engineering.Existing heavy lift carrier Hoisting test method, be usually transported on ship from harbour by huge heavy weight, order then used to hang and match with huge heavy weight Conjunction is tested, but the test method have the defects that it is certain: in the test method, need to by huge heavy transporting heavy things to ship, Hoisting test is carried out again, process is more complicated, meanwhile, extraneous weight need to be used, will increase cost, and transports weight to enhance labor Fatigue resistance.
Therefore, a kind of abridged edition type hoisting test that can reduce cost, labor intensity and easily operated heavy lift carrier is researched and developed Method is necessary.
Summary of the invention
It can reduce cost, labor intensity the technical problem to be solved in the present invention is to provide a kind of and easily operated hang again The abridged edition type hoisting test method of ship.
In order to solve the above technical problems, the technical solution of the present invention is as follows: a kind of abridged edition type hoisting test method of heavy lift carrier, Method includes the following steps:
(1) experiment of weighing hoist: weighing examines the test hoist approved by shipowner's ship, hangs/self-propelled hatchway cover P25 hangs/self-propelled hatchway cover P26, and two deck D5, two deck D 12, two deck D 7, two deck D6 and several weight are not One 1x hanging block;
(2) overload test:
A.1# crane main hook load raising test: hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled cabin Cover board P26, two deck D 5, two deck D 6 and two deck D 12;To be hung using 1# crane/self-propelled hatchway cover P26 hangs To FR106, that is, hatchcover stop place is moved ,/self-propelled hatchway cover P25 block hoist superposition then will be hung by 1# crane On hatch coaming, and lock, then successively D6, D5 and D12 are added to by wharf crane and hung/self-propelled hatchway cover P25 on, make Loading Center is located at FR106, and 1# crane raising radius is 18m at this time;Suspender is hung, main hook, which slowly rises, rises to 5 meters of height, and by 5 The high position of rice is defined as position A;
B.1# crane main hook load luffing test: after step a, from position, A does luffing movement, reaches luffing movement To maximum functional angle, it is then back to position A;
C.1# crane main hook loads turning test: after step b, first rotating clockwise 360 ° from position A, then again Slowly 360 ° of revolution returns to position A counterclockwise, then slowly falls and removes hoist;
D.1# crane main hook load raising test: hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled cabin Cover board P26, the 1x hanging block of two deck D 5 and 13.5t;To be hung using 1# crane/self-propelled hatchway cover P25 is hung to FR106 Place, then successively two deck D6 and 1x hanging blocks are added to by wharf crane hang/self-propelled hatchway cover P25 on, make in prestowage The heart is located at FR106, hang at this time/self-propelled hatchway cover P25 raising radius be 18m;Suspender is hung, main hook is slow after rising to 5 meters Outboard is screwed out to boom and beam upright position, then slow luffing to minimum operating angle, and by the minimum operating angle of main hook The location of degree is defined as position B, then slow 5 meters of slow raising again after 5 meters of weight of decline, and the radius of gyration is 33 at this time Rice;
E.1# crane main hook load luffing test: after step d, from position B slowly do luffing move to touch less than 9 meters of the least radius of loop wheel machine ontology, then luffing returns to initial position B to 33 meters of maximum working radius again;
F.1# crane main hook loads turning test: after step e, first slowly rotating about 70 ° clockwise from position B simultaneously Stop, then counterclockwise slowly 140 ° of stoppings of rotation, then rotate clockwise 70 ° of stoppings, after rotating, boom is slow Luffing slowly returns back to initial position FR106 stopping to 18 meters of the radius of gyration, slowly falls and removes weight;
G.1# crane auxiliary hook raising is tested: by boom rotation direction harbour, with the 1x hanging block of auxiliary hook lifting 50t, auxiliary hook work 36.5 meters of radius, first auxiliary hook is slowly risen and rises to 5 meters of height, then slowly falls and removes hoist;Again with wharf crane by the 1x of 50t Hanging block is hung to 3.5 meters of the position away from FR127 on ship, and 1# crane lifts by crane the 1x hanging block of 50t, auxiliary hook working radius with auxiliary hook 5.1 meters, then auxiliary hook is slowly increased to 5 meters of height, it then slowly falls and removes hoist;
H. it uses 1# crane instead 2# crane, overload test is carried out using 2# crane, the test procedure repeats step (a) ~(g);
(3) load test:
A.1# crane is once tested: hoist includes hanging/self-propelled hatchway cover P25 and two deck D 5;Utilize 1# grams Order, which is hung, to be hung/and self-propelled hatchway cover P25 is hung at FR106, and then two deck D5 are added to and hang/self-propelled hatchway cover On P25, Loading Center is made to be located at FR106,1# crane raising radius is 18m at this time;
Hoist is hung, after boom rotates outboard to boom and beam upright position, boom position is defined as position C, with normal Speed does three raising, revolution, luffing movement joint operations, and lifting altitude peaks, and angle of revolution is controlled in position C70 °, luffing requires to accomplish 9 meters and 33 meters of maximum working radius of minimum working radius, continues 15 minutes, finally in initial position FR106 removes hoist;
B.1# crane second trial: hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled hatchway cover P26, Two deck D 5 and two deck D12;To be hung using 1# crane/self-propelled hatchway cover P26 is hung at FR106, then it will hang From/self-propelled hatchway cover P25, two deck D5 and two deck D12 be added to hang/self-propelled hatchway cover P26 on, make Loading Center Positioned at FR106,1# crane raising radius is 18m at this time;Hoist is hung, raising, revolution, luffing three movements are done with normal speed Joint operation, lifting altitude peak, 360 ° of angle of revolution, and luffing requires to accomplish 9 meters of minimum working radius and maximum work Make 33 meters of radius, continues 15 minutes, finally remove hoist in FR106;
C.1# crane auxiliary hook raising is tested: by boom rotation direction harbour, boom is vertical with captain direction, and by boom position It is defined as position D, hoist is lifted by crane with auxiliary hook, three raising, revolution, luffing movement joint operations is done with normal speed, rise and increase Degree peaks, and D70 ° of position, luffing requires to accomplish 9 meters of minimum working radius and maximum working radius for angle of revolution control 36.5 meters, continue 15 minutes, finally removes hoist in initial position FR106;
D. it uses 1# crane instead 2# crane, load test is carried out using 2# crane, the test procedure repeats step (a) ~(c);
(4) wheels-locked testing:
A. main hook loads a wheels-locked testing: in a in step (3), respectively maximum working radius, maximum raising and Brake when maximum falling speed, raising does 1 brake, and 3 brakes are done in decline, meanwhile, when maximum rotational speed, maximum luffing into Row stops test;
B. main hook load secondary braking test: in the b in step (3), respectively maximum working radius, maximum raising and It brakes when decrease speed, raising does 1 brake, and 3 brakes are done in decline, meanwhile, when maximum rotational speed, maximum luffing, is stopped Only test;
C. it uses 1# crane instead 2# crane, wheels-locked testing is carried out using 2# crane, the test procedure repeats step (a) ~(b);
(5) safety feature test:
A. emergency stop test: starting pumping plant, respectively at crane driver's cabin, main junction box, power unit, channel into The cutting test of row emergency button, guarantees pumping plant can be made to stop working immediately in these position emergency switching-ofves;
B. emergency manual operation test: cutting off the power, raising of being decided respectively with manual pump, secondary raising, luffing and rotation;
C. emergency load discharges test: first main hook is tested, starts pumping plant, is stopped after hoist is lifted by crane 0.5 meter, and Button release hoist is discharged by pressing emergency;Auxiliary hook is tested again, starts pumping plant, is stopped after hoist is lifted by crane 0.5 meter, and Button release hoist is discharged by pressing emergency;The hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled hatchcover Plate P26, two deck D5, two deck D6 and two deck D12.
(6) post-test-inspection: check that whether there is or not obvious deformation or damages for crane structure;The crane includes 1# grams of order It hangs and 2# crane.
The present invention has the advantages that the abridged edition type hoisting test method of heavy lift carrier of the present invention, compared with conventional test methods, It does not need using extraneous weight, directly using hanging on heavy lift carrier/two deck of self-propelled hatchway cover and 1x hanging block, both reduced Cost, has been greatly reduced labor intensity, and make easy to operate.
Detailed description of the invention
The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
Fig. 1 to Fig. 8 is the process schematic of the abridged edition type hoisting test method of heavy lift carrier of the present invention.
Specific embodiment
The following examples can make professional and technical personnel that the present invention be more fully understood, but therefore not send out this It is bright to be limited among the embodiment described range.
Embodiment
The abridged edition type hoisting test method of the heavy lift carrier of the present embodiment, method includes the following steps:
(1) experiment of weighing hoist: weighing examines the test hoist approved by shipowner's ship, and 90t's hangs/self-propelled hatchcover The hanging of plate P25,90t/self-propelled hatchway cover P26,34t two deck D5, the two deck D 7 of the two deck D 12 of 34t, 30t, The two deck D6 of 30t, the 1x hanging block of 13.5t, the 1x hanging block of 45t and the 1x hanging block of 50t.
(2) overload test:
A.1# crane main hook load raising test: hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled cabin Cover board P26, two deck D 5, two deck D 6 and two deck D 12;As shown in Figure 1 ,/self-propelled will be hung using 1# crane Hatchway cover P26 is hung at FR106, that is, moves hatchcover stop place, and P25 block hoist is then superimposed upon hatch by 1# crane It places, and locks, then successively two deck D6, two deck D5 and D12 are added to and hang/self-propelled hatchway cover by wharf crane On P25, Loading Center is made to be located at FR106,1# crane raising radius is 18m at this time;Suspender is hung, main hook, which slowly rises, rises to 5 meters Height, and this 5 meters of high positions are defined as position A;And log is in table 1;
B.1# crane main hook load luffing test: after step a, from position, A does luffing movement, reaches luffing movement To maximum functional angle, it is then back to position A;And log is in table 1;
C.1# crane main hook loads turning test: after step b, first rotating clockwise 360 ° from position A, then again Slowly 360 ° of revolution returns to position A counterclockwise, then slowly falls and removes hoist;And log is in table 1;
D.1# crane main hook load raising test: hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled cabin Cover board P26, the 1x hanging block of two deck D 5 and 13.5t;As shown in Fig. 2,/self-propelled hatchway cover will be hung using 1# crane P25 is hung at FR106, and then successively two deck D6 and hanging block are added to by wharf crane and hang/self-propelled hatchway cover P25 On, so that Loading Center is located at FR106, crane raising radius is 18m at this time;Suspender is hung, main hook slowly screws out after rising to 5 meters Outboard is to boom and beam upright position, then slow luffing to minimum operating angle, and by the minimum operating angle institute of main hook The position at place is defined as position B, then slow 5 meters of slow raising again after 5 meters of weight of decline, and the radius of gyration is 33 meters at this time;And Log is in table 1;
E.1# crane main hook load luffing test: after step d, from position B slowly do luffing move to touch less than 9 meters of the least radius of loop wheel machine ontology, then luffing returns to position B to 33 meters of maximum working radius again;And log in Table 1;
F.1# crane main hook loads turning test: after step e, first slowly rotating about 70 ° clockwise from position B simultaneously Stop, then counterclockwise slowly 140 ° of stoppings of rotation, then rotate clockwise 70 ° of stoppings, after rotating, boom is slow Luffing slowly returns back to initial position FR106 stopping to 18 meters of the radius of gyration, slowly falls and removes weight;And record examination Result is tested in table 1;
G.1# crane auxiliary hook raising is tested: by boom rotation direction harbour, with the 1x hanging block of auxiliary hook lifting 50t, auxiliary hook work 36.5 meters of radius, first auxiliary hook is slowly risen and rises to 5 meters of height, then slowly falls and removes hoist;Again with wharf crane by the 1x of 50t Hanging block is hung to 3.5 meters of the position away from FR127 on ship, and 1# crane lifts by crane the 1x hanging block of 50t, auxiliary hook working radius with auxiliary hook 5.1 meters, then auxiliary hook is slowly increased to 5 meters of height, it then slowly falls and removes hoist;And log is in table 1;
H. it uses 1# crane instead 2# crane, overload test is carried out using 2# crane, is as shown in Figure 3 superimposed hoist To such as figure position, the test procedure repeats step (a)~(c), and log is in table 1;Hoist is superimposed as shown in Figure 4 To such as figure position, the test procedure repeats step (d)~(f), and log is in table 1;The examination of 2# crane auxiliary hook raising It tests process and repeats step g.
(3) load test:
A.1# crane is once tested: hoist includes hanging/self-propelled hatchway cover P25 and two deck D 5;Such as Fig. 5 institute Show, will be hung using 1# crane/self-propelled hatchway cover P25 is hung at FR106, then two deck D5 are added to hang/from On line hatchway cover P25, Loading Center is made to be located at FR106, crane raising radius is 18m at this time;Hoist is hung, boom rotates the side of a ship Outside to behind boom and beam upright position, boom position is defined as position C, with normal speed do raising, revolution, luffing three it is dynamic Make joint operation, lifting altitude peaks, and C70 ° of position, luffing requires to accomplish minimum working radius for angle of revolution control 9 meters and 33 meters of maximum working radius, continue 15 minutes, finally remove hoist in initial position FR106, and records raising, returns Turn, derricking speed and hydraulic oil temperature are in table 2;
B.1# crane second trial: hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled hatchway cover P26, Two deck D 5 and two deck D12;As shown in fig. 6, will be hung using 1# crane/self-propelled hatchway cover P26 is hung at FR106, Then will hang/self-propelled hatchway cover P25, two deck D5 and two deck D12 be added to hang/self-propelled hatchway cover P26 on, make Loading Center is located at FR106, and crane raising radius is 18m at this time;Hoist is hung, raising, revolution, luffing three are done with normal speed A movement joint operation, lifting altitude peak, 360 ° of angle of revolution, luffing require to accomplish 9 meters of minimum working radius and 33 meters of maximum working radius, continue 15 minutes, finally removes hoist in initial position FR106, and record raising, revolution, change Amplitude velocity degree and hydraulic oil temperature are in table 2;
C.1# crane auxiliary hook raising is tested: by boom rotation direction harbour, boom is vertical with captain direction, and by boom position It is defined as position D, hoist is lifted by crane with auxiliary hook, three raising, revolution, luffing movement joint operations is done with normal speed, rise and increase Degree peaks, and D70 ° of position, luffing requires to accomplish 9 meters of minimum working radius and maximum working radius for angle of revolution control 36.5 meters, continue 15 minutes, finally remove hoist in initial position FR106, and record raising, revolution, derricking speed and Hydraulic oil temperature is in table 2;
D. it uses 1# crane instead 2# crane, load test is carried out using 2# crane, as shown in fig. 7, hoist is folded It is added to such as figure position, the test procedure repeats step (a), and records raising, revolution, derricking speed and hydraulic oil temperature in table 2; As shown in figure 8, being added to hoist such as figure position, the test procedure repeats step (b), and record raising, revolution, derricking speed with And hydraulic oil temperature is in table 2;2# crane auxiliary hook raising the test procedure repeats step (c), and records raising, revolution, luffing speed Degree and hydraulic oil temperature are in table 2.
(4) wheels-locked testing:
A. main hook loads a wheels-locked testing: in a in step (3), respectively maximum working radius, maximum raising and Brake when maximum falling speed, raising does 1 brake, and 3 brakes are done in decline, meanwhile, when maximum rotational speed, maximum luffing into Row stops test;
B. main hook load secondary braking test: in the b in step (3), respectively maximum working radius, maximum raising and It brakes when decrease speed, raising does 1 brake, and 3 brakes are done in decline, meanwhile, when maximum rotational speed, maximum luffing, is stopped Only test;
C. it uses 1# crane instead 2# crane, wheels-locked testing is carried out using 2# crane, the test procedure repeats step (a) ~(b).
(5) safety feature test:
A. emergency stop test: starting pumping plant, respectively at crane driver's cabin, main junction box, power unit, channel into The cutting test of row emergency button, guarantees pumping plant can be made to stop working immediately in these position emergency switching-ofves;
B. emergency manual operation test: cutting off the power, raising of being decided respectively with manual pump, secondary raising, luffing and rotation;
C. emergency load discharges test: first main hook is tested, starts pumping plant, is stopped after hoist is lifted by crane 0.5 meter, and Button release hoist is discharged by pressing emergency;Auxiliary hook is tested again, starts pumping plant, is stopped after hoist is lifted by crane 0.5 meter, and Button release hoist is discharged by pressing emergency;The hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled hatchcover Plate P26, two deck D5, two deck D6 and two deck D12.
(6) post-test-inspection: check that whether there is or not obvious deformation or damages for crane structure.The crane includes 1# grams of order It hangs and 2# crane.
1 overload test result of table
2 load test result of table
Basic principles and main features and advantages of the present invention of the invention have been shown and described above.The skill of the industry Art personnel it should be appreciated that the present invention is not limited to the above embodiments, the above embodiments and description only describe The principle of the present invention, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these Changes and improvements all fall within the protetion scope of the claimed invention.The claimed scope of the invention by appended claims and Its equivalent thereof.

Claims (1)

1. a kind of abridged edition type hoisting test method of heavy lift carrier, it is characterised in that: method includes the following steps:
(1) experiment of weighing hoist: weighing examines the test hoist approved by shipowner's ship, hangs/self-propelled hatchway cover P25, hangs From/self-propelled hatchway cover P26, two deck D5, two deck D 12, two deck D 7, two deck D6 and the different 1x of several weight Hanging block;
(2) overload test:
A.1# crane main hook load raising test: hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled hatchway cover P26, two deck D 5, two deck D 6 and two deck D 12;To be hung using 1# crane/self-propelled hatchway cover P26 is hung to At FR106, that is, hatchcover stop place is moved, then will be hung by 1# crane/self-propelled hatchway cover P25 block hoist is superimposed upon On hatch coaming, and lock, then successively D6, D5 and D12 are added to by wharf crane and hung/self-propelled hatchway cover P25 on, make to match Load center is located at FR106, and 1# crane raising radius is 18m at this time;Suspender is hung, main hook, which slowly rises, rises to 5 meters of height, and by 5 meters High position is defined as position A;
B.1# crane main hook load luffing test: after step a, from position, A does luffing movement, reaches luffing movement most Then big operating angle is back to position A;
C.1# crane main hook loads turning test: after step b, first rotating clockwise 360 °, then when another mistake from position A Needle slowly turns round 360 ° and returns to position A, then slowly falls and removes hoist;
D.1# crane main hook load raising test: hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled hatchway cover P26, the 1x hanging block of two deck D 5 and 13.5t;To be hung using 1# crane/self-propelled hatchway cover P25 is hung at FR106, Then successively two deck D6 and 1x hanging blocks are added to by wharf crane hang/self-propelled hatchway cover P25 on, make Loading Center position In FR106, hang at this time/self-propelled hatchway cover P25 raising radius be 18m;Suspender is hung, main hook slowly screws out after rising to 5 meters Outboard is to boom and beam upright position, then slow luffing to minimum operating angle, and by the minimum operating angle institute of main hook The position at place is defined as position B, then slow 5 meters of slow raising again after 5 meters of weight of decline, and the radius of gyration is 33 meters at this time;
E.1# crane main hook load luffing test: after step d, luffing is slowly done from position B move to and touch less than loop wheel machine 9 meters of the least radius of ontology, then luffing returns to initial position B to 33 meters of maximum working radius again;
F.1# crane main hook loads turning test: after step e, first slowly rotating about 70 ° clockwise from position B and stops Only, then counterclockwise slowly 140 ° of stoppings of rotation, then 70 ° of stoppings are rotated clockwise, after rotating, boom slowly becomes Width slowly returns back to initial position FR106 stopping to 18 meters of the radius of gyration, slowly falls and removes weight;
G.1# crane auxiliary hook raising is tested: by boom rotation direction harbour, with the 1x hanging block of auxiliary hook lifting 50t, auxiliary hook working radius 36.5 meters, first auxiliary hook is slowly risen and rises to 5 meters of height, then slowly falls and removes hoist;Again with wharf crane by the 1x hanging block of 50t It is hung to 3.5 meters of the position away from FR127 on ship, 1# crane lifts by crane the 1x hanging block of 50t with auxiliary hook, and 5.1 meters of auxiliary hook working radius, Auxiliary hook is slowly increased to 5 meters of height again, then slowly falls and removes hoist;
H. use 1# crane instead 2# crane, using 2# crane carry out overload test, the test procedure repeat step (a)~ (g);
(3) load test:
A.1# crane is once tested: hoist includes hanging/self-propelled hatchway cover P25 and two deck D 5;Utilize 1# crane To hang/self-propelled hatchway cover P25 is hung at FR106, then two deck D5 are added to hang/self-propelled hatchway cover P25 on, Loading Center is set to be located at FR106,1# crane raising radius is 18m at this time;
Hoist is hung, after boom rotates outboard to boom and beam upright position, boom position is defined as position C, with normal speed Three raising, revolution, luffing movement joint operations are done, lifting altitude peaks, and angle of revolution control becomes C70 ° of position Width requires to accomplish 9 meters and 33 meters of maximum working radius of minimum working radius, continues 15 minutes, finally incites somebody to action in initial position FR106 Hoist removes;
B.1# crane second trial: hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled hatchway cover P26, diformazan Plate D 5 and two deck D12;To be hung using 1# crane/self-propelled hatchway cover P26 is hung at FR106, then will hang/from Line hatchway cover P25, two deck D5 and two deck D12 be added to hang/self-propelled hatchway cover P26 on, be located at Loading Center FR106,1# crane raising radius is 18m at this time;Hoist is hung, three raising, revolution, luffing movement joints are done with normal speed Operation, lifting altitude peak, 360 ° of angle of revolution, and luffing requires to accomplish 9 meters of minimum working radius and maximum functional half 33 meters of diameter, continues 15 minutes, finally remove hoist in FR106;
C.1# crane auxiliary hook raising is tested: by boom rotation direction harbour, boom is vertical with captain direction, and boom position is defined For position D, hoist is lifted by crane with auxiliary hook, three raising, revolution, luffing movement joint operations are done with normal speed, lifting altitude reaches To highest point, D70 ° of position, luffing requires to accomplish 9 meters of minimum working radius and maximum working radius 36.5 for angle of revolution control Rice, continues 15 minutes, finally removes hoist in initial position FR106;
D. use 1# crane instead 2# crane, using 2# crane carry out load test, the test procedure repeat step (a)~ (c);
(4) wheels-locked testing:
A. main hook loads a wheels-locked testing: in a in step (3), respectively in maximum working radius, maximum raising and maximum It brakes when decrease speed, raising does 1 brake, and 3 brakes are done in decline, meanwhile, when maximum rotational speed, maximum luffing, is stopped Only test;
B. main hook load secondary braking test: in the b in step (3), respectively in maximum working radius, maximum raising and decline It brakes when speed, raising does 1 brake, and 3 brakes are done in decline, meanwhile, when maximum rotational speed, maximum luffing, carries out stopping examination It tests;
C. use 1# crane instead 2# crane, using 2# crane carry out wheels-locked testing, the test procedure repeat step (a)~ (b);
(5) safety feature test:
A. emergency stops test: starting pumping plant is answered at crane driver's cabin, main junction box, power unit, channel respectively Anxious button cutting test, guarantees pumping plant can be made to stop working immediately in these position emergency switching-ofves;
B. emergency manual operation test: cutting off the power, raising of being decided respectively with manual pump, secondary raising, luffing and rotation;
C. emergency load discharges test: first testing main hook, starts pumping plant, stops after hoist is lifted by crane 0.5 meter, and pass through It presses emergency and discharges button release hoist;Auxiliary hook is tested again, starts pumping plant, is stopped after hoist is lifted by crane 0.5 meter, and pass through It presses emergency and discharges button release hoist;The hoist includes hanging/self-propelled hatchway cover P25, hangs/self-propelled hatchway cover P26, two deck D5, two deck D6 and two deck D12;
(6) post-test-inspection: check that whether there is or not obvious deformation or damages for crane structure;The crane include 1# crane and 2# crane.
CN201610295392.8A 2016-05-06 2016-05-06 A kind of abridged edition type hoisting test method of heavy lift carrier Active CN106081944B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610295392.8A CN106081944B (en) 2016-05-06 2016-05-06 A kind of abridged edition type hoisting test method of heavy lift carrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610295392.8A CN106081944B (en) 2016-05-06 2016-05-06 A kind of abridged edition type hoisting test method of heavy lift carrier

Publications (2)

Publication Number Publication Date
CN106081944A CN106081944A (en) 2016-11-09
CN106081944B true CN106081944B (en) 2019-02-12

Family

ID=57229262

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610295392.8A Active CN106081944B (en) 2016-05-06 2016-05-06 A kind of abridged edition type hoisting test method of heavy lift carrier

Country Status (1)

Country Link
CN (1) CN106081944B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111483921B (en) * 2020-04-23 2021-11-16 武汉通联路桥机械技术有限公司 Load test device and test method for hoisting equipment with quasi-diamond structure
CN113247772B (en) * 2021-03-29 2022-08-26 中船澄西船舶修造有限公司 Load test method after crane real ship installation

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103303798A (en) * 2012-03-09 2013-09-18 利勃海尔-韦尔克嫩青有限公司 Crane controller, crane and method for controlling crane
CN103439135A (en) * 2013-09-09 2013-12-11 长沙东屋机电有限责任公司 Test weight modules of bridge crane, and method for forming test load by combining test weight modules
CN203624878U (en) * 2013-10-28 2014-06-04 宁波捷胜海洋开发有限公司 Gantry crane
CN103879904A (en) * 2014-03-17 2014-06-25 江苏华西村海洋工程服务有限公司 Ocean crane ship and moving method thereof
CN104016247A (en) * 2014-06-09 2014-09-03 中联重科股份有限公司 Hoisting device of weight frame and crane test equipment
CN105439003A (en) * 2015-12-31 2016-03-30 浙江三一装备有限公司 Crawler crane and hoisting testing device and hoisting method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103303798A (en) * 2012-03-09 2013-09-18 利勃海尔-韦尔克嫩青有限公司 Crane controller, crane and method for controlling crane
CN103439135A (en) * 2013-09-09 2013-12-11 长沙东屋机电有限责任公司 Test weight modules of bridge crane, and method for forming test load by combining test weight modules
CN203624878U (en) * 2013-10-28 2014-06-04 宁波捷胜海洋开发有限公司 Gantry crane
CN103879904A (en) * 2014-03-17 2014-06-25 江苏华西村海洋工程服务有限公司 Ocean crane ship and moving method thereof
CN104016247A (en) * 2014-06-09 2014-09-03 中联重科股份有限公司 Hoisting device of weight frame and crane test equipment
CN105439003A (en) * 2015-12-31 2016-03-30 浙江三一装备有限公司 Crawler crane and hoisting testing device and hoisting method thereof

Also Published As

Publication number Publication date
CN106081944A (en) 2016-11-09

Similar Documents

Publication Publication Date Title
CN201864494U (en) Marine hydraulic telescopic folding crane
CN107697242B (en) Automatic buoy recycling and laying device
CN102464270B (en) Overturning-preventing torque limiter and movable crane
CN201151466Y (en) Raft and cargo crane for ship
CN106081944B (en) A kind of abridged edition type hoisting test method of heavy lift carrier
CN103640987A (en) Folding arm hydraulic crane
CN203558761U (en) Hydraulic knuckle crane
CN106927369A (en) Lorry-mounted crane and its job safety guard method, device and system
WO2015113400A1 (en) Apparatus for steel wire rope swing detection, and hoisting machinery
US10875748B2 (en) Marine crane vessel and method of operation
EP2888193A1 (en) Method for lowering and hoisting of a load to or from an ocean floor
CN210825189U (en) Hydraulic crane with rescue boat crane
CN206033063U (en) Electronic change width of cloth loop wheel machine
CN201427842Y (en) Fully rotary crane for ship
US2361053A (en) Ship cargo rig
CN204714393U (en) The bull tower crane peculiar to vessel of safety
CN205933029U (en) Rope releasing protective device
CN110217699B (en) Method and device for judging state of deck crane and deck crane system
CN206051370U (en) A kind of hydraulic gyration crane
CN206940301U (en) A kind of hydraulic pressure oil transportation crane
CN110329908A (en) A kind of heavy lift carrier master hangs connection and hangs test method
CN201058794Y (en) Slinging matter weight monitoring system for shipboard floating crane
CN213171208U (en) Vehicle is davit for testing platform
CN108045527A (en) Process of jacking is played in a kind of large-scale crane span structure depressed place with hinge handoff functionality
CN203558782U (en) General hydraulic crane

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20221118

Address after: No. 1, Hongqiang Avenue, Offshore Ship Industrial Park, Qidong, Nantong, Jiangsu 226000

Patentee after: Jiangsu jiongqiang Marine Equipment Co.,Ltd.

Address before: 226200 No. 1, Hongqiang Avenue, Huiping Town, Nantong City, Jiangsu Province

Patentee before: JIANGSU HONGQIANG MARINE HEAVY INDUSTRY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231031

Address after: No. 1 Hongqiang Avenue, Huiping Town, Qidong City, Nantong City, Jiangsu Province, 226000

Patentee after: JIANGSU HONGQIANG MARINE HEAVY INDUSTRY Co.,Ltd.

Address before: No. 1, Hongqiang Avenue, Offshore Ship Industrial Park, Qidong, Nantong, Jiangsu 226000

Patentee before: Jiangsu jiongqiang Marine Equipment Co.,Ltd.

TR01 Transfer of patent right