Summary of the invention
It is an object of the invention to provide a kind of waste material transportation and turn arranging device, to solve to transport present in prior art
Journey underaction and the relatively costly technical problem of discharge.
The invention provides a kind of waste material transportation for discharge field and turn arranging device, described discharge field has by level height
At least two-stage work platforms divided, including:
The most fixing belt feeder of high workload platform, feed end and institute in waste material transportation that stope is peeled off to discharge field
The delivery end stating fixing belt feeder coordinates the mobile belt unit of the discharging to receive described fixing belt feeder delivery end;
Conveying assembly, described conveying assembly includes chute and mobile belt unit, and described chute is arranged at adjacent two-stage
In side slope between work platforms, in each conveying assembly:
The described feed end of mobile belt unit coordinates with the delivery end of chute to receive the discharging of described chute delivery end,
And the described feed end of chute coordinates with the mobile belt unit on higher level's work platforms and moves on higher level's work platforms to receive
The waste material of belt unit downward level work platform conveying.
Further, each described mobile belt unit has a waste material transportation main road, each described conveying
In assembly:
Unloading of the waste material transportation main road of the feed end of described chute and the described mobile belt unit on higher level's work platforms
Material end coordinates.
Further, described mobile belt unit also has an at least one waste material transportation branch road, and each described useless
Material transport leg is provided with waste material diversion mechanism, to be connect by described mobile belt unit at the joint of described waste material transportation main road
A part in the waste material received branches to described waste material transportation branch road.
Further, described diversion mechanism includes the separatory funnel that support, described support support.
Further, each described mobile belt unit includes multiple mobile belt machine, along waste material transportation direction, after
The feed end of one-level mobile belt machine is positioned at the lower section of previous stage mobile belt machine delivery end.
Further, vertically, the feed end of each described mobile belt machine is less than delivery end.
Further, described chute has multiple circular hole, for coordinating described chute is fixed on row with fixture
In side slope between adjacent two the described work platformses in stock ground.
Further, between described fixing belt feeder delivery end and matched described mobile belt unit feed end
It is provided with dust-proof mechanism, and/or, the delivery end of the described mobile belt unit on higher level's work platforms and the feed end of described chute
Between be provided with dust-proof mechanism, and/or, the described mobile belt unit on the delivery end end of described chute and subordinate's work platforms
Be provided with dust-proof mechanism between feed end, and/or, the higher level's mobile belt machine delivery end in each described mobile belt unit with
It is provided with dust-proof mechanism between subordinate's mobile belt machine feed end.
Further, the shower nozzle arranged in described dust-proof mechanism includes dust cover, described dust cover.
Further, the blower fan arranged in described dust-proof mechanism includes dust cover, described dust cover and described blower fan are even
That connect and be positioned at the cleaner unit airduct outside described dust cover, the fiber bag precipitator being connected with described cleaner unit airduct.
The waste material transportation that the present invention provides turns arranging device can produce following beneficial effect:
The waste material transportation that the present invention provides turns in arranging device, and the waste material transportation that fixing belt is used for peeling off stope is to discharge
High workload platform on, the mobile belt unit being positioned on high workload platform is useless for the transport of fixing belt feeder come
Material is transported to the position that high workload platform needs;Further, between two the most adjacent work platformses, it is provided with a conveying assembly,
Setting, in two adjacent work platformses, the work platforms that level height is higher is referred to as higher level's work platforms, and level height is relatively low
Be referred to as subordinate's work platforms, the chute that conveying assembly has is arranged on the limit between higher level's work platforms and subordinate's work platforms
On slope, it is possible to receive mobile belt unit transhipment on higher level's work platforms, need to be delivered to the waste material of subordinate's work platforms, under
The waste material that this chute receives is transported on subordinate's work platforms the position needed by the mobile belt unit on level work platform.
Above-mentioned waste material transportation turns in arranging device, and the waste material that stope is peeled off is delivered to the senior engineer of discharge field by fixing belt feeder
After making platform, by the mobile belt unit being positioned on high workload platform waste material is transported on high workload platform corresponding
Position;When needing to transport the waste material downward level work platform on high workload platform, high workload platform is above-mentioned upper
Level work platform, now, the mobile belt unit on high workload platform can will need the useless of downward level work platform conveying
The material feed end by the chute in delivery end cross-docking to corresponding conveying assembly, and the mobile belt machine in this conveying assembly
The feed end of group receives the discharging of above-mentioned chute delivery end, and is turned by waste material by setting the transportation route of mobile belt unit
It is transported to the corresponding position of subordinate's work platforms, when some work platforms needs to drain in the side slope of work platforms waste material,
By mobile belt unit, waste material can be delivered to the neighbouring position of side slope, then directly waste material is drained into by load wagon etc.
Side slope.
Above-mentioned waste material transportation turns and have employed fixing belt feeder in arranging device and add the structure of mobile belt unit, it is not necessary to build fortune
Defeated road etc., and limited less by climbing height etc., and in the mobile belt unit on each work platforms, each moves
The position of dynamic belt feeder can adjust position as required, and then can arbitrarily change mobile belt unit at corresponding work platforms
On discharge position, flexible operation, and, relative in prior art use discharge conveying arrangement for, the present invention provide
Discharge conveying arrangement conveying cost and build cost relatively low.
Accompanying drawing explanation
In order to be illustrated more clearly that the specific embodiment of the invention or technical scheme of the prior art, below will be to specifically
In embodiment or description of the prior art, the required accompanying drawing used is briefly described, it should be apparent that, in describing below
Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not paying creative work
Put, it is also possible to obtain other accompanying drawing according to these accompanying drawings.
Same specification mobile belt machine is used on the two-layer FIX CHARGE RATE ABOUT THE WASTE stock ground work platforms that Fig. 1 provides for the embodiment of the present invention
Waste material transportation turn the front schematic view of arranging device;
Same specification mobile belt machine is used on the two-layer FIX CHARGE RATE ABOUT THE WASTE stock ground work platforms that Fig. 2 provides for the embodiment of the present invention
Waste material transportation turn the side schematic view of arranging device;
Different size mobile belt machine is used on the two-layer FIX CHARGE RATE ABOUT THE WASTE stock ground work platforms that Fig. 3 provides for the embodiment of the present invention
Waste material transportation turn the side schematic view of arranging device;
The simple waste material transportation on three layers of FIX CHARGE RATE ABOUT THE WASTE stock ground work platforms that Fig. 4 provides for the embodiment of the present invention turns arranging device
Front schematic view;
Close-up schematic view at the A that Fig. 5 provides for the embodiment of the present invention;
The dust-proof mechanism partial enlargement front schematic view that Fig. 6 provides for the embodiment of the present invention.
The plate brad supporting schematic diagram that Fig. 7 provides for the embodiment of the present invention.
Reference:
1-fixes belt feeder;2-the first mobile belt unit;
21-the first mobile belt machine;22-the second mobile belt machine;
23-the 3rd mobile belt machine;24-the 4th mobile belt machine;
3-conveying assembly;31-chute;
311-cement mortar;312-soil nailing;
313-C30 concrete;314-termination screw rod;
315-pad;316-nut;
32-the second mobile belt unit;321-the 5th mobile belt machine;
322-the 6th mobile belt machine;33-the 3rd mobile belt unit;
331-the 7th mobile belt machine;332-the 8th mobile belt machine;
333-the 9th mobile belt machine;334-the tenth mobile belt machine;
4-diversion mechanism;41-support;
42-separatory funnel;5-dust-proof mechanism;
51-dust cover;52-blower fan;
53--cleaner unit airduct;6-work platforms;
61-work platforms;62-work platforms;
7-load wagon;8-side slope.
Detailed description of the invention
Below in conjunction with accompanying drawing, technical scheme is clearly and completely described, it is clear that described enforcement
Example is a part of embodiment of the present invention rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill
The every other embodiment that personnel are obtained under not making creative work premise, broadly falls into the scope of protection of the invention.
In describing the invention, it should be noted that term " " center ", " on ", D score, "left", "right", " vertically ",
Orientation or the position relationship of the instruction such as " level ", " interior ", " outward " they are based on orientation shown in the drawings or position relationship, merely to
Be easy to describe the present invention and simplifying describe rather than instruction or the hint device of indication or element must have specific orientation,
With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.Additionally, term " first ", " second ",
" the 3rd " is only used for describing purpose, and it is not intended that indicate or hint relative importance.
In describing the invention, it should be noted that unless otherwise clearly defined and limited, term " is installed ", " phase
Even ", " connection " should be interpreted broadly, for example, it may be fixing connection, it is also possible to be to removably connect, or be integrally connected;Can
To be mechanical connection, it is also possible to be electrical connection;Can be to be joined directly together, it is also possible to be indirectly connected to by intermediary, Ke Yishi
The connection of two element internals.For the ordinary skill in the art, can understand that above-mentioned term is at this with concrete condition
Concrete meaning in invention.
Present embodiments provide a kind of waste material transportation and turn arranging device, including the waste material transportation for being peeled off by stope to discharge
In Chang, the most fixing belt feeder 1 of high workload platform, feed end coordinate with the delivery end of fixing belt feeder 1 to receive fixing belt feeder
The mobile belt unit of the discharging of 1 delivery end;Conveying assembly 3, conveying assembly 3 includes chute 31 and mobile belt unit, chute
31 are arranged between adjacent two-stage work platforms in the side slope 8 of 6, in each conveying assembly 3: the charging of mobile belt unit
End coordinates with the delivery end of chute 31 with the discharging of reception chute 31 delivery end, and the feed end of chute 31 and higher level's work platforms
On mobile belt unit coordinate to receive the waste material of mobile belt unit downward level work platform conveying on higher level's work platforms.
In order to clearly above-mentioned waste material transportation is turned the work process of arranging device and operation principle is retouched
State, specifically can be introduced as a example by the structure shown in Fig. 1 and Fig. 2;As depicted in figs. 1 and 2, discharge field has two work
Platform, respectively work platforms 61 and work platforms 62, wherein, work platforms 61 is the high workload platform of discharge field, and work
Making in platform 61 and work platforms 62, work platforms 61 is higher level's work platforms, and work platforms 62 is subordinate's work platforms, in work
Making to be placed with fixing belt feeder the 1, first mobile belt unit 2 and load wagon 7 on platform 61, the chute 31 of conveying assembly 3 is installed
In side slope 8 between work platforms 61 and work platforms 62, work platforms 62 is placed with the second mobile belt unit 32
With load wagon 7;Turn in arranging device at above-mentioned waste material transportation, when waste material to be delivered to work platforms 62 from work platforms 61,
The chute 31 that conveying assembly 3 has be able to receive that on work platforms 61 first mobile belt unit 2 transhipment, need to be delivered to down
The waste material of level work platform 62, the waste material that this chute 31 receives is transported to by the second mobile belt unit 32 on work platforms 62
The position needed on work platforms 62.Owing to conveying assembly 3 includes the second mobile belt unit 32, when work platforms 62 needs
When being drained into by waste material in the side slope of work platforms 62, by the second mobile belt unit 32, waste material can be delivered to the attached of side slope
Near position, then directly drains into the side slope of work platforms 62 by load wagon 7 grade by waste material.Above-mentioned waste material transportation turns row's dress
Put middle employing and fix the combination realization of belt feeder 1 and mobile belt unit and chute 31 transport to waste material, and can lead to
Cross the movement of each mobile belt machine in mobile belt unit and realize waste material each side on work platforms 6 residing for this mobile belt unit
The transport of position, it is not necessary to build transport routes etc., is limited less by climbing height etc., and the movement on each work platforms 6
In belt unit, the position of each mobile belt machine can adjust position as required, and then can arbitrarily change mobile belt machine
Group discharge position on corresponding work platforms 6, flexible operation, and, relative to the discharge transport dress used in prior art
For putting, discharge conveying arrangement conveying cost and build cost that the present invention provides are relatively low.
Wherein, as in figure 2 it is shown, for the multi-platform transport realizing waste material, each mobile belt unit has one and gives up
Material transport main road, in each conveying assembly 3: the feed end of chute 31 and the first mobile belt unit 2 on work platforms 61
Waste material transportation main road delivery end coordinate.
Further, as a kind of concrete can embodiment, when discharge field higher level's work platforms downward level work platform
When the waste material of transport is too much, mobile belt unit can also have the waste material transportation main road of one or more, on higher level's work platforms
Mobile belt unit by material transfer to multiple conveying assemblies so that waste material can by a plurality of waste material transportation main road by upper
Level work platform transports to subordinate's work platforms, accelerates waste material transportation speed.
Additionally, for the multi-direction transport realizing waste material, mobile belt unit also has at least one waste material transportation branch road,
As shown in Figure 4, discharge field has three work platformses, wherein, in the first mobile belt unit 2 on high workload platform, the
One mobile belt machine 21 and the 3rd mobile belt machine 23 have cooperatively formed one article of waste material transportation main road, and the second mobile belt machine 22
One article of waste material transportation branch road has been cooperatively formed, the 3rd mobile belt unit on subordinate's work platforms with the 4th mobile belt machine 24
In 33, the 7th mobile belt machine 331 and the 8th mobile belt machine 332 have cooperatively formed one article of waste material transportation main road, and the 9th moves
Dynamic belt feeder 333 and the tenth mobile belt machine 334 have cooperatively formed one article of waste material transportation branch road, and each waste material transportation branch road
With can be provided with waste material diversion mechanism 4 at the joint of waste material transportation main road, with in the waste material that received by mobile belt unit
A part branches to waste material transportation branch road, by diversion mechanism 4, the waste material on transport main line is transported to more a plurality of transport and props up
Lu Shang, it is achieved the trash discharge on different directions on work platforms 6.
Additionally, the delivery end of transport leg is unloaded to waste material on work platforms 6, then transferred to by 7 waste materials of load wagon
The side slope 8 of corresponding discharge field work platforms 6.
Wherein, as it is shown in figure 5, diversion mechanism 4 includes the separatory funnel 42 that support 41, support support, separatory funnel 42
First end is extended with funnel type flange, adds the end face cross-sectional area of separatory funnel 42 first end, it is ensured that waste material transportation is imitated
Rate, the second end of separatory funnel 42, the 3rd end coordinate transport waste material with main road and the branch road of mobile belt unit respectively.
Further, as a kind of concrete can embodiment, the second end, the 3rd end in diversion mechanism 4 can be provided with
Governor motion, is used for regulating the flow of the waste material being transported to mobile belt unit waste material transportation main road and waste material transportation branch road, makes
Transporting from transport main road of will not concentrating of waste material, better met on discharge field work platforms 6 different azimuth to useless
The discharge capacity of material.
Further, as a kind of concrete can embodiment, the support 41 in diversion mechanism 4 can be fixed on mobile skin
On band machine, it is also possible to support on the ground.
Further, as a kind of concrete can embodiment, diversion mechanism 4 be fixed on can have on mobile belt machine many
The mode of kind, can be welded on mobile belt machine, it is also possible to be fixed on mobile belt machine by bolt, nut.
Further, as a kind of concrete can embodiment, separatory funnel 42 is stainless steel material, and stainless steel material is firm
Spend, wear-resisting.
Further, as a kind of concrete can embodiment, when waste material needs transport to discharge field work platforms more than 6
During individual orientation, subordinate's transport leg of waste material can also be provided with waste material diversion mechanism at the joint of waste material higher level's transport leg
4, add waste material transportation branch road, it is achieved waste material multi-faceted discharge on discharge field work platforms 6.
Additionally, each mobile belt unit includes multiple mobile belt machine, along waste material conveying direction, rear stage moves skin
Feed end with machine is positioned at the lower section of previous stage mobile belt machine delivery end so that waste material transportation enhanced convenience, specifically, and can
With as in figure 2 it is shown, the feed end of the 3rd mobile belt machine 23 in the first mobile belt unit 2 is positioned at the first mobile belt machine 21
The lower section of delivery end so that material by gravity can cross-docking to the feed end of the 3rd mobile belt machine 23.
Further, as a kind of concrete can embodiment, mobile belt machine feed end both sides and feed end top
End is provided with baffle plate, and drop when reducing waste material transportation to mobile belt machine feed end the situation on work platforms 6.
Further, as a kind of concrete can embodiment, the delivery end of higher level's mobile belt machine moves with subordinate
The transport that in alignment can carry out waste material at the feed end cooperation of belt feeder can also the angled fortune carrying out waste material
Defeated, mobile belt machine direction, position flexibly changing, simple in construction and can quickly meet the waste material transportation in different azimuth, real
The quickest multi-platform transport.
Additionally, vertically, the feed end of each mobile belt machine is less than delivery end, and waste material is by mobile belt machine
Feed end liter be transported to delivery end can cross-docking to the feed end of the most identical subordinate's mobile belt machine, it is not necessary to buying is the most not
Same mobile belt machine carries out coordinating transhipment, so that the mobile belt in the mobile belt unit on each work platforms
Machine uses same specification, and purchase engineering amount is little, marker method is the most flexible.
As in figure 2 it is shown, the first mobile belt machine 21 and the 3rd in the first mobile belt unit 2 on work platforms 61 moves
The feed end of dynamic belt feeder 23 is less than delivery end, and the feed end of the 3rd mobile belt machine 23 is less than the first mobile belt machine 21
Delivery end so that the first mobile belt machine 21 and the 3rd mobile belt machine 23 can use same specification.
Or, the feed end of each mobile belt machine can be on same level line with delivery end, and along waste material
Transmission direction, the vertically height of previous stage mobile belt machine is higher than the vertical height of rear stage mobile belt machine, concrete such as Fig. 3 institute
Show, the first mobile belt unit 2 on work platforms 61 and the charging of the mobile belt machine in the second mobile belt unit 32
End and delivery end are in same level and the vertically height of previous stage mobile belt machine is higher than rear stage mobile belt machine
Vertically height so that waste material can transport on each mobile belt machine smoothly.
In a kind of detailed description of the invention, the chute 31 in above-mentioned conveying assembly 3 has multiple circular hole, for joining with fixture
Close chute is fixed in the side slope 8 between adjacent two work platformses 6 in discharge field.
Further, as a kind of concrete can embodiment, as it is shown in fig. 7, chute 31 in discharge field adjacent two
Soil-Nailing Wall Structure fixed form can be used, between adjacent two work platformses in discharge field in side slope 8 between work platforms 6
Side slope 8 on bore elongated hole, soil nailing 312 inserts the elongated hole in the side slope 8 between discharge field work platforms 6 by the circular hole of chute 31
In, pouring into cement mortar 311 between elongated hole and soil nailing, soil nailing 312 head installs pad 315, the termination screw rod 314 of soil nailing 312
Use nut 316 to tighten with chute 31, between nut 316 and chute 31, use C30 concrete 313 to close.
In the above-described embodiments, wherein, consolidating in the chute 31 side slope 8 between adjacent two work platformses 6 in discharge field
Determine mode and can also have other forms, such as: chute 31 can be adopted in the side slope 8 between adjacent two work platformses 6 in discharge field
Use suspension roof support structurally-fixed mode.
And for example: in the side slope 8 between adjacent two work platformses 6 in discharge field, imbed metal bar, metal bar and chute it
Between weld.
Further, as a kind of concrete can embodiment, the cross section of chute 31 is U-shaped.
Further, as a kind of concrete can embodiment, the feed end of chute 31 is by adjacent two works in discharge field
Making to extend in the side slope 8 between platform 6 immediately below the delivery end of higher level's mobile belt unit, the delivery end of chute 31 is by discharge
Extend in side slope 8 between adjacent two work platformses 6 in field, directly over the feed end of subordinate's mobile belt unit, prevent waste material
Transported to subordinate's mobile belt machine by the feed end of higher level's mobile belt unit transport to chute 31 and the delivery end of chute 31
The situation on discharge field work platforms 6 that drops during group occurs.
Set between belt feeder 1 delivery end and the first matched mobile belt unit 2 feed end as in figure 2 it is shown, fixing
There is dust-proof mechanism 5, and/or, between delivery end and the feed end of chute 31 of the first mobile belt unit 2 on work platforms 61
It is provided with dust-proof mechanism 5, and/or, the charging of the second mobile belt unit 32 on the delivery end end of chute 31 and work platforms 62
Dust-proof mechanism 5 it is provided with between end, and/or, the higher level's mobile belt machine delivery end in each mobile belt unit moves with subordinate
Being provided with dust-proof mechanism 5 between dynamic belt feeder feed end, including dust cover 51, the shower nozzle arranged in dust cover 51, at dust cover 51
Inside carry out watering and lowering dust, produce substantial amounts of dust during preventing waste material transportation, protect the working environment of workman.
Or, as shown in Figure 6, dust-proof mechanism 5 includes dust cover 51, the interior blower fan 52 arranged of dust cover 51 and blower fan 52
Connect and be positioned at the cleaner unit airduct 53 outside dust cover 51, the fiber bag precipitator being connected with cleaner unit airduct 53, waste material
Dust enter into cleaner unit airduct 53 by blower fan 52, then entered fiber bag precipitator by cleaner unit airduct and carry out dedusting.Logical
Cross above example, this waste material transportation turn the flexibility ratio of arranging device high, easy to use while, save time and cost.
It is briefly described as a example by the work platforms of two-layer FIX CHARGE RATE ABOUT THE WASTE stock ground below.
As depicted in figs. 1 and 2, the waste material transportation that the fixing belt feeder 1 on highest work platforms is peeled off from stope to
First end of separatory funnel 42, waste material shunts through separatory funnel 42, respectively from the second end of separatory funnel 42, the 3rd end
Transport the first mobile belt machine 21 to waste material transportation main road and the second mobile belt machine 22 on waste material transportation branch road, pass through
After dust-proof mechanism 5, the first mobile belt machine 21 is by waste material transportation to the 3rd mobile belt machine 23, and the second mobile belt machine 22 will be useless
Material transport is to the 4th mobile belt machine 24, and the delivery end of the 4th mobile belt machine 24 is unloaded to waste material on work platforms 61, then
Transferred to the side slope 8 of discharge field work platforms 61 by 7 waste materials of load wagon, waste material is passed through dust-proof machine by the 3rd mobile belt machine 23
Structure 5 transports the feed end to chute 31, and waste material transports the feed end to the 5th mobile belt machine 321 by chute 31, by the
The delivery end transport of five mobile belt machines 321, to the feed end of the 6th mobile belt machine 322, arrives on work platforms 62, loads
7 waste materials of car transfer to the side slope 8 of discharge field work platforms 62.
It is briefly described as a example by three layers of FIX CHARGE RATE ABOUT THE WASTE stock ground work platforms below.
As shown in Figure 4 and Figure 5, the waste material transportation that the fixing belt feeder 1 on highest work platforms is peeled off from stope to
First end of separatory funnel 42, waste material shunts through separatory funnel 42, respectively from the second end of separatory funnel 42, the 3rd end
Transport the first mobile belt machine 21 to waste material transportation main road and the second mobile belt machine 22 on waste material transportation branch road, pass through
After dust-proof mechanism 5, the first mobile belt machine 21 is by waste material transportation to the 3rd mobile belt machine 23, and the second mobile belt machine 22 will be useless
Material transport is to the 4th mobile belt machine 24, and the delivery end of the 4th mobile belt machine 24 is unloaded to waste material on work platforms 6, then by
7 waste materials of load wagon transfer to the side slope 8 of the discharge field work platforms 6 of correspondence, and waste material is passed through anti-by the 3rd mobile belt machine 23
Dirt mechanism 5 transports the feed end to chute 31, and waste material transports the feed end to the 7th mobile belt machine 331 by chute 31, logical
Crossing the delivery end transport of the 7th mobile belt machine 331 to the first end of separatory funnel 42, waste material is carried out point through separatory funnel 42
Stream, transports the 8th mobile belt machine 332 to waste material transportation main road from the second end of separatory funnel 42, the 3rd end and gives up respectively
The 9th mobile belt machine 333 on material transport leg, thus arrive subordinate's work platforms, the 9th mobile belt machine 333 is by waste material
Transport is to the tenth mobile belt machine 334, and the delivery end of the tenth mobile belt machine 334 is unloaded to waste material on work platforms 6, then by
7 waste materials of load wagon transfer to the side slope 8 of the discharge field work platforms 6 of correspondence, and waste material is passed through anti-by the 8th mobile belt machine 332
Dirt mechanism 5 transports the feed end to chute 31, and waste material transports the feed end to the 5th mobile belt machine 321 by chute 31, logical
Cross the delivery end transport feed end to the 6th mobile belt machine 322 of the 5th mobile belt machine 321, arrive afterbody work flat
On platform, 7 waste materials of load wagon transfer to the side slope 8 of the discharge field work platforms 6 of correspondence.
Last it is noted that various embodiments above is only in order to illustrate technical scheme, it is not intended to limit;To the greatest extent
The present invention has been described in detail by pipe with reference to foregoing embodiments, it will be understood by those within the art that: it depends on
So the technical scheme described in foregoing embodiments can be modified, or the most some or all of technical characteristic is entered
Row equivalent;And these amendments or replacement, do not make the essence of appropriate technical solution depart from various embodiments of the present invention technology