CN106003364A - Method used for preventing concrete shear wall based on 3D printing from peeling - Google Patents
Method used for preventing concrete shear wall based on 3D printing from peeling Download PDFInfo
- Publication number
- CN106003364A CN106003364A CN201610489565.XA CN201610489565A CN106003364A CN 106003364 A CN106003364 A CN 106003364A CN 201610489565 A CN201610489565 A CN 201610489565A CN 106003364 A CN106003364 A CN 106003364A
- Authority
- CN
- China
- Prior art keywords
- precast concrete
- shell
- wall
- ground floor
- layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B1/00—Producing shaped prefabricated articles from the material
- B28B1/001—Rapid manufacturing of 3D objects by additive depositing, agglomerating or laminating of material
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
- E04B2/86—Walls made by casting, pouring, or tamping in situ made in permanent forms
- E04B2/8605—Walls made by casting, pouring, or tamping in situ made in permanent forms without spacers
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B33—ADDITIVE MANUFACTURING TECHNOLOGY
- B33Y—ADDITIVE MANUFACTURING, i.e. MANUFACTURING OF THREE-DIMENSIONAL [3-D] OBJECTS BY ADDITIVE DEPOSITION, ADDITIVE AGGLOMERATION OR ADDITIVE LAYERING, e.g. BY 3-D PRINTING, STEREOLITHOGRAPHY OR SELECTIVE LASER SINTERING
- B33Y10/00—Processes of additive manufacturing
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B33—ADDITIVE MANUFACTURING TECHNOLOGY
- B33Y—ADDITIVE MANUFACTURING, i.e. MANUFACTURING OF THREE-DIMENSIONAL [3-D] OBJECTS BY ADDITIVE DEPOSITION, ADDITIVE AGGLOMERATION OR ADDITIVE LAYERING, e.g. BY 3-D PRINTING, STEREOLITHOGRAPHY OR SELECTIVE LASER SINTERING
- B33Y80/00—Products made by additive manufacturing
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
- E04B2/86—Walls made by casting, pouring, or tamping in situ made in permanent forms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/12—Mounting of reinforcing inserts; Prestressing
Abstract
The invention discloses a method used for preventing a concrete shear wall based on 3D printing from peeling. The method used for preventing the concrete shear wall based on 3D printing from peeling comprises the following steps of a. manufacturing a first layer of a prefabricated concrete shell by using 3D printing and forming concave-convex lines on the surface of the prefabricated concrete shell; b. arranging a first layer of a tie bar and/or a horizontal bar at the top of the first layer of the prefabricated concrete shell; c. manufacturing a second layer of the prefabricated concrete shell at the top of the first layer of the prefabricated concrete shell to make two ends of the tie bar and/or the horizontal bar be arranged in the prefabricated concrete shells in an embedded way separately; and d. arranging a second layer of the tie bar and/or the horizontal bar at the top of the second layer of the prefabricated concrete shell and repeating step (3) until the prefabricated concrete shells is completed to the designed elevation, and then pouring concrete. According to the method, the tie bars are prefabricated between an inner wall surface and an outer wall surface of the prefabricated concrete shells, so that die expansion of the concrete can be prevented; moreover, the horizontal bars of the shear wall are embedded between the prefabricated concrete shells in advance, so that construction inconvenience caused by post-installation of the horizontal bars can be avoided and the construction can be simplified.
Description
The present invention is that the Chinese patent application of Application No. 201410437818.X is " based on mixing that 3D prints
Solidifying soil shear wall structure and construction method thereof " divisional application of (applying date: on 08 29th, 2014).
Technical field
The present invention relates to a kind of shear wall construction field, particularly relate to a kind of coagulation preventing and printing based on 3D
The method of soil shear wall shelling.
Background technology
Traditional shear wall construction uses cast-in-place concrete construction, first colligation shear force wall reinforcing steel bar cage, including cutting
Power wall horizontal bar and shear wall erect muscle, after steel reinforcement cage colligation completes, install shear wall formwork in steel reinforcement cage both sides,
And use the mode wearing tension rib to carry out drawknot, to prevent later stage concreting the template of both sides
During rise mould, in template, finally pour shear wall concrete, form removal after concrete final set,
Complete construction.
Traditional cast-in-place concrete shear wall working procedure is numerous and diverse, and cannot be adapted to fabricated reinforced concrete knot
Structure, the scope of application is little, is unfavorable for the development of building structure.
Assembled steel reinforced concrete structure is an important directions of building structure development, beneficially building industrialization
The energy and development Green environmental-protection building are saved in development, raising production efficiency.There is a kind of preferably assembled steel
Muscle concrete structure is to use the cast-in-place assembled steel reinforced concrete structure built of shell preformed core, and it is by assembled steel reinforced concrete
The beam of structure, post component concrete cover prefabricated together with stirrup, formed degree of lip-rounding precast concrete shell;
After shell assembling positions and configures main muscle, in shell, pour core concrete, the most both convenient construction
Save again template, beneficially building industrialization.
But, this precast reinforced concrete structure is owing to cannot install tension rib, it is impossible to be applicable to shearing
The construction of wall, therefore, how necessary proposition one installs tension rib in precast concrete shell is prevented
The modulus problem that rises only occurred during casting concrete.
Summary of the invention
The technical problem to be solved is to provide a kind of concrete shear force wall preventing from printing based on 3D and takes off
The method of shell, it is possible to prevent the mould that rises, and save on the premise of ensureing quality and safety material, manpower,
Time cost etc., meet green construction requirement.
For realizing above-mentioned technique effect, the invention discloses a kind of concrete shear force wall preventing and printing based on 3D
The method of shelling, including step:
A, employing 3D printing technique making ground floor shape adaptation are in the precast concrete shell of shear wall, described
Precast concrete shell includes an inner wall surface, a wall face and is located at described inner wall surface and described wall face both sides
Both sides metope;The surface of described precast concrete shell is formed with concave convex texture;
B, ground floor tension rib and/or horizontal bar are set in the top of ground floor precast concrete shell;
C, employing 3D printing technique make second layer precast concrete in the top of ground floor precast concrete shell
Shell, make the two ends of ground floor tension rib and/or horizontal bar be embedded in respectively ground floor precast concrete shell with
The junction of second layer precast concrete shell;
D, repetition step b, c, until completing all layer precast concrete shells to designed elevation;
E, in all layer precast concrete shells, plug perpendicular muscle, described perpendicular muscle colligation in described tension rib and/
Or on horizontal bar;
F, in all layer precast concrete shells casting concrete, complete the construction of shear wall;
Wherein, the top of precast concrete shell described at least one of which is provided with described tension rib, and described in draw
The two ends of knot muscle are respectively arranged on the top of described inner wall surface and described wall face.
The described method preventing the concrete shear force wall printed based on 3D from shelling further is improved by, described
The two ends of tension rib bend up or down.
The described method preventing the concrete shear force wall printed based on 3D from shelling further is improved by, described
Concave convex texture is consecutively formed at the described inner wall surface of described precast concrete shell, described wall face and institute
State on the inner surface of both sides metope.
The method of the described concrete shear force wall shelling preventing from printing based on 3D is further improved by, in the
The top of one layer of precast concrete shell arranges ground floor tension rib, uses 3D printing technique prefabricated in ground floor
The top of concrete casing makes second layer precast concrete shell, makes the two ends of ground floor tension rib bury respectively
It is located at the junction of ground floor precast concrete shell and second layer precast concrete shell;Then, in second
The top of layer precast concrete shell arranges ground floor horizontal bar.
The described method preventing the concrete shear force wall printed based on 3D from shelling further is improved by, described
Horizontal bar is parallel to described inner wall surface and described wall face, and the two ends of described horizontal bar are embedded in described two respectively
In side wall;Described perpendicular muscle is vertically inserted in described precast concrete shell, and colligation is in described horizontal bar
Inner side.
Due to the fact that and have employed above technical scheme so that it is have the advantages that
By using the construction of the reinforced concrete structure printed based on 3D, replace original pouring template construction, with
The integrated precast concrete shell of 3D printing technique, such as inner wall surface and the wall face of shear wall, not only may be used
Using the template as shear wall, itself also can be as a part for shear wall, therefore, it is to avoid at shearing
After wall concreting, the construction of form removal, save working procedure, save template, be conducive to building
Build industrialization.
By when making precast shear wall inner wall surface and wall face, arranging between inner wall surface and wall face and draw
Knot muscle, prevent from rising during concreting mould, and the horizontal bar of shear wall is embedded in the most in advance inner wall surface and
Between wall face, it is to avoid the construction inconvenience brought is installed after horizontal bar, simplifies construction.
By using the one-body molded precast concrete shell of 3D printing technique, at the interior table of precast concrete shell
Form continuous print concave convex texture on face, add the inner surface of precast concrete shell with its in note concrete it
Between contact surface, compare smooth inner surface, increase frictional force, improve bond strength, it is to avoid be de-
Shell phenomenon.
Accompanying drawing explanation
Fig. 1 is that the method using the present invention to prevent the concrete shear force wall printed based on 3D from shelling has made
The facade structures schematic diagram of the concrete shear wall structure printed based on 3D become.
Fig. 2 is the A-A sectional view of Fig. 1.
Fig. 3 is the construction schematic diagram of ground floor precast concrete shell of the present invention.
Fig. 4 is the construction schematic diagram of ground floor tension rib of the present invention.
Fig. 5 is the construction schematic diagram of second layer precast concrete shell of the present invention.
Fig. 6 is the construction schematic diagram of ground floor horizontal bar of the present invention.
Fig. 7 is the construction schematic diagram of third layer precast concrete shell of the present invention.
Fig. 8 is the schematic diagram after precast concrete shell of the present invention has been constructed.
Detailed description of the invention
Below in conjunction with the accompanying drawings and detailed description of the invention the present invention is further detailed explanation.
Referring initially to shown in Fig. 1, the concrete shear force wall printed based on 3D for using the present invention to prevent shells
Method complete based on 3D print concrete shear wall structure, should based on 3D print concrete
Shear wall structure mainly by precast concrete shell 11, shear wall tension rib 12, shear wall horizontal bar 13, cut
Power wall erects muscle 14, and pours the concrete composition in precast concrete shell 11.Coordinate shown in Fig. 2, in advance
The shape adaptation of concrete casing 11 processed is in shear wall, including the inner wall surface using the printing integrated molding of 3D
111, a wall face 112 and be located at the both sides metope 113 of inner wall surface 111 and wall face 112 both sides, concrete
The soil inner wall surface 111 of shell 11, wall face 112 and both sides metope 113 use 3D printing technique to make molding,
The surface of precast concrete shell 11 is formed with concave convex texture 15, adds the interior table of precast concrete shell 11
Contact surface between face and its interior note concrete, compares smooth inner surface, increases frictional force, improve
Bond strength, it is to avoid shelling phenomenon.Horizontal bar 13 is parallel to inner wall surface 111 and wall face 112, horizontal bar
The two ends of 13 are embedded in both sides metope 113 respectively, and perpendicular muscle 14 is vertically inserted in precast concrete shell 11,
And colligation is in the inner side of horizontal bar 13.The two ends of tension rib 12 are embedded in inner wall surface 111 and wall face 112 respectively
In, and the two ends of tension rib 12 bend, up or down for inner wall surface 111 and the wall face of drawknot both sides
112.By when making the precast concrete shell 11 of shear wall, in the inner wall surface of precast concrete shell 11
Arranging tension rib 12 between 111 and wall face 112, prevent from rising during concreting modulus problem.In system
When making the precast concrete shell 11 of shear wall, by horizontal bar 13 pre-plugged of shear wall in precast concrete
In the side wall 113 of shell 11, the construction inconvenience brought when installing after can avoiding horizontal bar 13, simplify construction.
Perpendicular muscle 14 is directly vertically inserted between inner wall surface 111 and wall face 112, and be embedded in inner wall surface 111 and outward in advance
Horizontal bar 13 and the mutual colligation of tension rib 12 between metope 112 are fixed.Use the reinforced concrete structure printed based on 3D
Construction, replace the construction of original pouring template, with the integrated precast concrete shell of 3D printing technique
Act not only as the template of shear wall, itself also can be as a part for shear wall, therefore, it is to avoid
After shear wall concreting, the construction of form removal, save working procedure, save template, have
It is beneficial to building industrialization.
In conjunction with shown in Fig. 3 to Fig. 8, the concrete shear force wall printed based on 3D for using the present invention to prevent shells
Method make the construction method of concrete shear force wall printed based on 3D, specific as follows:
A, use 3D printing technique make ground floor shape adaptation in the precast concrete shell 11 ' of shear wall,
This precast concrete shell 11 ' includes an inner wall surface 111 ' and the wall face using the printing integrated molding of 3D
112 ', and it is connected to two side walls of inner wall surface 111 ' and wall face 112 ' both sides, as shown in Figure 3;
B, arrange first in the inner wall surface 111 ' of ground floor precast concrete shell 11 ' and the top of wall face 112 '
Layer tension rib 12, tension rib 12 horizontal interval is arranged between inner wall surface 111 ' and wall face 112 ', and drawknot
The two ends of muscle 12 are folded upward at, as shown in Figure 2 and Figure 4;
C, employing 3D printing technique are prefabricated mixed in the top of ground floor precast concrete shell 11 ' the making second layer
Solidifying soil shell 11 ", it is pre-with the second layer that the two ends making ground floor tension rib 12 be folded upward at are embedded in ground floor respectively
The inner wall surface of concrete casing processed and the junction of wall face, with inner wall surface and the wall face of drawknot both sides, as
Shown in Fig. 5;
D, in second layer precast concrete shell 11 " the top of inner wall surface and wall face ground floor level is set
Muscle 13, the two ends of horizontal bar 13 are respectively arranged at the top of the side wall of both sides, as shown in Figure 6;
E, use 3D printing technique in second layer precast concrete shell 11 " to make third layer prefabricated mixed at top
Solidifying soil shell 11 " ', make the two ends of ground floor horizontal bar 13 be embedded in the second layer and third layer precast concrete respectively
The junction of the side wall of shell both sides, as shown in Figure 7;
Repeat above-mentioned construction, until completing precast concrete shell to designed elevation, as shown in Figure 8;
Perpendicular muscle 14 is plugged in precast concrete shell, and by the colligation of perpendicular muscle 14 in horizontal bar 13 and tension rib 12
On, make the outside that horizontal bar 13 is close to and is erected muscle 14, as shown in Figure 1;
After the colligation of perpendicular muscle 14 completes, casting concrete in precast concrete shell, complete shear wall construction.
Being described in detail the present invention above in association with accompanying drawing embodiment, those skilled in the art can
According to the above description the present invention is made many variations example.Thus, some details in embodiment should not be constituted
Limitation of the invention, the present invention by the scope that defines using appended claims as the protection model of the present invention
Enclose.
Claims (5)
1. the method preventing the concrete shear force wall shelling printed based on 3D, it is characterised in that
Including step:
A, use 3D printing technique make ground floor shape adaptation in the precast concrete shell of shear wall,
Described precast concrete shell include an inner wall surface, a wall face and be located at described inner wall surface with described outside
The both sides metope of metope both sides;The surface of described precast concrete shell is formed with concave convex texture;
B, ground floor tension rib and/or horizontal bar are set in the top of ground floor precast concrete shell;
C, employing 3D printing technique are prefabricated in the top of the ground floor precast concrete shell making second layer
Concrete casing, makes the two ends of ground floor tension rib and/or horizontal bar be embedded in ground floor respectively prefabricated mixed
Solidifying soil shell and the junction of second layer precast concrete shell;
D, repetition step b, c, until completing all layer precast concrete shells to designed elevation;
E, plugging perpendicular muscle in all layer precast concrete shells, described perpendicular muscle colligation is in described tension rib
And/or on horizontal bar;
F, in all layer precast concrete shells casting concrete, complete the construction of shear wall;
Wherein, the top of precast concrete shell described at least one of which is provided with described tension rib, and institute
The two ends stating tension rib are respectively arranged on the top of described inner wall surface and described wall face.
The method preventing the concrete shear force wall shelling printed based on 3D the most as claimed in claim 1,
It is characterized in that: the two ends of described tension rib bend up or down.
The method preventing the concrete shear force wall shelling printed based on 3D the most as claimed in claim 1,
It is characterized in that: described concave convex texture be consecutively formed at described precast concrete shell described inner wall surface,
On the inner surface of described wall face and described both sides metope.
The method preventing the concrete shear force wall shelling printed based on 3D the most as claimed in claim 1,
It is characterized in that: ground floor tension rib is set in the top of ground floor precast concrete shell, use 3D
Printing technique makes second layer precast concrete shell in the top of ground floor precast concrete shell, makes
The two ends of ground floor tension rib are embedded in ground floor precast concrete shell and second layer concrete respectively
The junction of soil shell;Then, the top in second layer precast concrete shell arranges ground floor level
Muscle.
The method preventing the concrete shear force wall shelling printed based on 3D the most as claimed in claim 4,
It is characterized in that: described horizontal bar is parallel to described inner wall surface and described wall face, described horizontal bar
Two ends are embedded in the metope of described both sides respectively;Described perpendicular muscle is vertically inserted in outside described precast concrete
In shell, and colligation is in the inner side of described horizontal bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610489565.XA CN106003364B (en) | 2014-08-29 | 2014-08-29 | The method for preventing the concrete shear force wall based on 3D printing from shelling |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610489565.XA CN106003364B (en) | 2014-08-29 | 2014-08-29 | The method for preventing the concrete shear force wall based on 3D printing from shelling |
CN201410437818.XA CN104153493B (en) | 2014-08-29 | 2014-08-29 | The concrete shear wall structure printed based on 3D and construction method thereof |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410437818.XA Division CN104153493B (en) | 2014-08-29 | 2014-08-29 | The concrete shear wall structure printed based on 3D and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106003364A true CN106003364A (en) | 2016-10-12 |
CN106003364B CN106003364B (en) | 2019-01-04 |
Family
ID=51879107
Family Applications (7)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410437818.XA Active CN104153493B (en) | 2014-08-29 | 2014-08-29 | The concrete shear wall structure printed based on 3D and construction method thereof |
CN201610490282.7A Active CN106121094B (en) | 2014-08-29 | 2014-08-29 | The precast concrete shell structure of concrete shear force wall based on 3D printing |
CN201610489562.6A Active CN106013529B (en) | 2014-08-29 | 2014-08-29 | The arrangement of reinforcement method of concrete shear force wall based on 3D printing |
CN201610490270.4A Active CN105937276B (en) | 2014-08-29 | 2014-08-29 | The production method of the precast concrete shell structure of 3D printing concrete shear force wall |
CN201610489565.XA Active CN106003364B (en) | 2014-08-29 | 2014-08-29 | The method for preventing the concrete shear force wall based on 3D printing from shelling |
CN201610490281.2A Active CN106013530B (en) | 2014-08-29 | 2014-08-29 | The reinforcement structure of concrete shear force wall based on 3D printing |
CN201610490313.9A Active CN106013531B (en) | 2014-08-29 | 2014-08-29 | The concrete shear wall structure based on 3D printing with concave convex texture |
Family Applications Before (4)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410437818.XA Active CN104153493B (en) | 2014-08-29 | 2014-08-29 | The concrete shear wall structure printed based on 3D and construction method thereof |
CN201610490282.7A Active CN106121094B (en) | 2014-08-29 | 2014-08-29 | The precast concrete shell structure of concrete shear force wall based on 3D printing |
CN201610489562.6A Active CN106013529B (en) | 2014-08-29 | 2014-08-29 | The arrangement of reinforcement method of concrete shear force wall based on 3D printing |
CN201610490270.4A Active CN105937276B (en) | 2014-08-29 | 2014-08-29 | The production method of the precast concrete shell structure of 3D printing concrete shear force wall |
Family Applications After (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610490281.2A Active CN106013530B (en) | 2014-08-29 | 2014-08-29 | The reinforcement structure of concrete shear force wall based on 3D printing |
CN201610490313.9A Active CN106013531B (en) | 2014-08-29 | 2014-08-29 | The concrete shear wall structure based on 3D printing with concave convex texture |
Country Status (1)
Country | Link |
---|---|
CN (7) | CN104153493B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108407040A (en) * | 2018-01-30 | 2018-08-17 | 南京肯信精密机器制造有限公司 | A kind of 3D printing technique having anchor slab component |
CN111015891A (en) * | 2019-12-02 | 2020-04-17 | 浙江大学 | Interlayer embedding and binding method for 3D printed concrete structure |
Families Citing this family (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104532986B (en) * | 2014-12-23 | 2017-10-31 | 中国建筑第八工程局有限公司 | 3D printing internal partition wall and its construction method |
CN105021470B (en) * | 2015-06-08 | 2017-12-15 | 中国建筑第八工程局有限公司 | The test structure and method of testing of 3D printing component interlaminar shear strength |
CN105003003A (en) * | 2015-06-13 | 2015-10-28 | 刘政辰 | 3D printing self heat insulation wall body and preparing method of 3D printing self heat insulation wall body |
CN105965664B (en) * | 2016-05-04 | 2018-03-20 | 河海大学 | A kind of prestressed pile 3D printing system and its application method |
CN106760532A (en) * | 2016-12-23 | 2017-05-31 | 浙江迅实科技有限公司 | A kind of architecture construction method based on 3D printing |
KR101911404B1 (en) | 2017-01-19 | 2018-12-19 | 연세대학교 산학협력단 | Concrete extrusion apparatus for 3d printing system |
KR101914523B1 (en) | 2017-01-19 | 2018-11-02 | 연세대학교 산학협력단 | Apparatus for 3d printed concrete binding redistribution |
KR101914524B1 (en) | 2017-01-19 | 2018-11-02 | 연세대학교 산학협력단 | Mobile Concrete Building 3D Printing System |
CN106968367A (en) * | 2017-05-03 | 2017-07-21 | 中国建筑股份有限公司 | A kind of new 3D printing reinforced wall and its construction method |
JP6993794B2 (en) * | 2017-05-26 | 2022-01-14 | 大成建設株式会社 | Laminated structure construction method, laminated structure and laminated structure construction equipment |
CN107780559A (en) * | 2017-09-06 | 2018-03-09 | 贵州益新装配式新型建材有限公司 | A kind of construction method of heat-insulation and heat-preservation gypsum partition wall |
CN107901185B (en) * | 2017-11-02 | 2019-10-22 | 中国建筑股份有限公司 | The method and its application on 3D printing concrete wall surface |
CN108193798A (en) * | 2018-01-29 | 2018-06-22 | 上海言诺建筑材料有限公司 | 3D printing wall element, walling system and its manufacturing method |
CN109881630A (en) * | 2019-04-09 | 2019-06-14 | 济南栋源水泥制品有限公司 | A kind of processing technology of assembled basin dam and basin dam monomer |
CN110370422A (en) * | 2019-06-28 | 2019-10-25 | 浙江大学 | A kind of method of reinforcement 3D mixing printing shear wall |
DE102019131051A1 (en) * | 2019-11-18 | 2021-05-20 | AEDITIVE GmbH | Process for the production of a reinforced concrete component, reinforced concrete component and production system |
CN111561081A (en) * | 2020-05-20 | 2020-08-21 | 张建国 | Concrete shear wall structure based on 3D printing and construction method thereof |
DE102020132141A1 (en) * | 2020-12-03 | 2022-06-09 | Universität Kassel, Körperschaft des öffentlichen Rechts | Wall structure of a building and method for producing such a wall structure |
CN114033041B (en) * | 2021-11-08 | 2023-10-13 | 欢颜创新科技(杭州)有限公司 | House construction method and house |
CN115217271B (en) * | 2022-05-31 | 2023-11-17 | 中国建筑材料科学研究总院有限公司 | A muscle material and device for strengthening 3D prints concrete wholeness |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101831970A (en) * | 2010-02-10 | 2010-09-15 | 黄靓 | Integrally assembled wallboard wall and construction method thereof |
EP2439352A1 (en) * | 2010-10-07 | 2012-04-11 | FEHR Groupe | Permanent formwork wall with connecting cablet |
CN202787577U (en) * | 2012-07-12 | 2013-03-13 | 南京工业大学 | Prefabricating wall outer shell structure of reinforced concrete superimposition shear wall |
Family Cites Families (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2891931B2 (en) * | 1996-03-29 | 1999-05-17 | 戸田建設株式会社 | Formwork for building concrete structures |
CN2527615Y (en) * | 2001-12-30 | 2002-12-25 | 北京城建耐泰安建材有限责任公司 | Heat insulating bearing wall construction member need no removal of mould |
CN1399047A (en) * | 2002-08-13 | 2003-02-26 | 张晶廷 | 3D structural building and its industrialized construction process |
CN1242136C (en) * | 2004-11-05 | 2006-02-15 | 朱秦江 | Composite heat insulation concrete shear wall and its construction method |
US8357323B2 (en) * | 2008-07-16 | 2013-01-22 | Siemens Energy, Inc. | Ceramic matrix composite wall with post laminate stitching |
CN102182317A (en) * | 2011-03-18 | 2011-09-14 | 北京华美科博科技发展有限公司 | Concrete spray steel mesh sandwich formwork cast-in-place shear wall construction method and shear wall |
CN102535841A (en) * | 2011-12-12 | 2012-07-04 | 中冶建工集团有限公司 | Construction technology of prefabricated wall panel |
CN102561585B (en) * | 2012-03-06 | 2014-10-29 | 程松林 | External wall slab of prefabricated cast-in-place composite concrete shear wall and manufacture and installation methods |
CN103334519B (en) * | 2013-07-26 | 2016-08-10 | 黑龙江宇辉新型建筑材料有限公司 | Overlaid plate type concrete shear wall and longitudinally connected method |
CN103422672B (en) * | 2013-08-29 | 2016-01-20 | 杜新智 | A kind of reinforced concrete precast assembling housing construction construction method |
CN203654462U (en) * | 2014-01-07 | 2014-06-18 | 马义和 | Middle section structure of flexible house and for 3D (three dimensional) printing |
CN103790266B (en) * | 2014-01-28 | 2016-04-13 | 江苏建筑职业技术学院 | Steel tube concrete core pillar is put more energy into prefabricated assembled shear-wall element |
CN103967276B (en) * | 2014-04-29 | 2016-03-02 | 同济大学 | Based on the building engineering construction device of 3D printing technique |
-
2014
- 2014-08-29 CN CN201410437818.XA patent/CN104153493B/en active Active
- 2014-08-29 CN CN201610490282.7A patent/CN106121094B/en active Active
- 2014-08-29 CN CN201610489562.6A patent/CN106013529B/en active Active
- 2014-08-29 CN CN201610490270.4A patent/CN105937276B/en active Active
- 2014-08-29 CN CN201610489565.XA patent/CN106003364B/en active Active
- 2014-08-29 CN CN201610490281.2A patent/CN106013530B/en active Active
- 2014-08-29 CN CN201610490313.9A patent/CN106013531B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101831970A (en) * | 2010-02-10 | 2010-09-15 | 黄靓 | Integrally assembled wallboard wall and construction method thereof |
EP2439352A1 (en) * | 2010-10-07 | 2012-04-11 | FEHR Groupe | Permanent formwork wall with connecting cablet |
CN202787577U (en) * | 2012-07-12 | 2013-03-13 | 南京工业大学 | Prefabricating wall outer shell structure of reinforced concrete superimposition shear wall |
Non-Patent Citations (2)
Title |
---|
S.LIM等: "Developments in construction-Scale additive manufacturing processes", 《AUTOMATION IN CONSTRUCTION》 * |
李志国等: "3D打印建筑材料相关概念辨析", 《天津建设科技》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108407040A (en) * | 2018-01-30 | 2018-08-17 | 南京肯信精密机器制造有限公司 | A kind of 3D printing technique having anchor slab component |
CN111015891A (en) * | 2019-12-02 | 2020-04-17 | 浙江大学 | Interlayer embedding and binding method for 3D printed concrete structure |
CN111015891B (en) * | 2019-12-02 | 2020-11-17 | 浙江大学 | Interlayer embedding and binding method for 3D printed concrete structure |
Also Published As
Publication number | Publication date |
---|---|
CN106013529B (en) | 2019-01-04 |
CN106121094A (en) | 2016-11-16 |
CN106013531A (en) | 2016-10-12 |
CN105937276A (en) | 2016-09-14 |
CN106121094B (en) | 2019-01-04 |
CN106013531B (en) | 2018-05-08 |
CN104153493A (en) | 2014-11-19 |
CN106013530A (en) | 2016-10-12 |
CN106013530B (en) | 2019-01-04 |
CN104153493B (en) | 2016-08-24 |
CN106013529A (en) | 2016-10-12 |
CN106003364B (en) | 2019-01-04 |
CN105937276B (en) | 2019-01-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104153493B (en) | The concrete shear wall structure printed based on 3D and construction method thereof | |
CN104264862B (en) | 3D printing reinforcement masonry shear wall structure and construction method thereof | |
CN105780935B (en) | Prefabricated assembled steel tube confinement energy consumption connecting node and construction method | |
CN104120788B (en) | A kind of reinforced concrete structure and construction method based on 3D printing | |
CN206267422U (en) | A kind of assembly concrete superposed column | |
CN101318350A (en) | Concrete cavity die component forming method | |
CN107762001A (en) | A kind of assembly concrete variable cross-section newel post type shearing wall member and its construction method | |
CN109868751A (en) | Notch, template and construction method are poured after a kind of assembled track girder concrete | |
CN102926534B (en) | Detachable building formwork for hollow floor slab and ribbed floor slab | |
CN211113137U (en) | Assembled reinforced concrete pier | |
CN210976322U (en) | Bracket superposed beam and forming equipment thereof | |
CN103628684A (en) | Construction method for casting floor slab and shear wall simultaneously | |
CN209686711U (en) | Prefabricated laminated superposed column, reinforced column and assembled architecture body | |
CN210217164U (en) | Concrete 3D prints component casing and structure | |
CN207436364U (en) | The outer enhanced prefabricated outer wall panel of impeller | |
CN103085160B (en) | Combined precast column base core die and method of manufacturing core body | |
CN217840575U (en) | Precast concrete constructional column | |
CN211523255U (en) | Manufacturing tool for foundation bearing platform template | |
CN107916749B (en) | Outer blade reinforced prefabricated external wall panel and production method thereof | |
CN104712140A (en) | Dissoluble concrete reserved-hole mold and construction method thereof | |
CN206267352U (en) | A kind of inclined hole grouting shear wall of L-shaped | |
JP2012192708A (en) | Method of manufacturing concrete pole | |
CN105926828A (en) | Prefabricated reinforced concrete member | |
CN107620400A (en) | A kind of assembly concrete variable cross-section is T-shaped to shear wall member and its construction method | |
CN105937287A (en) | Prefabricated part |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |