CN105986629A - Light wallboard installation method - Google Patents

Light wallboard installation method Download PDF

Info

Publication number
CN105986629A
CN105986629A CN201510051398.6A CN201510051398A CN105986629A CN 105986629 A CN105986629 A CN 105986629A CN 201510051398 A CN201510051398 A CN 201510051398A CN 105986629 A CN105986629 A CN 105986629A
Authority
CN
China
Prior art keywords
mortar
guipure
installation method
light trabs
seam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510051398.6A
Other languages
Chinese (zh)
Inventor
秦晓峰
周国兴
王磊
黄京新
陈晓东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHONGSHAN JIANHUA WALL MATERIALS CO Ltd
China Railway Construction Engineering Group Co Ltd
Original Assignee
ZHONGSHAN JIANHUA WALL MATERIALS CO Ltd
China Railway Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHONGSHAN JIANHUA WALL MATERIALS CO Ltd, China Railway Construction Engineering Group Co Ltd filed Critical ZHONGSHAN JIANHUA WALL MATERIALS CO Ltd
Priority to CN201510051398.6A priority Critical patent/CN105986629A/en
Publication of CN105986629A publication Critical patent/CN105986629A/en
Pending legal-status Critical Current

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The invention discloses a light wallboard installation method which includes the steps of splicing light wallboards provided with grooves and tongues, keeping joint slots wet and plastering interface treating mortar, preparing adhesive mortar from mortar, Dow latex and water, and adhering mesh belts at the joint slots by the adhesive mortar. According to specific implementation, the mesh belts are adhered at the joint slots by the adhesive mortar after the joint slots are plastered with the interface treating mortar since the light wallboards with the grooves and tongues are spliced. By the light wallboard installation method, the wallboard installation is achieved by a dry process, transverse stress concentration of the wallboards is reduced, and the primary adhesion between the wallboards is generated by the mesh belts which cover the joint slots between the wallboards integrally. Further, by the light wallboard installation method, engineering installation efficiency is increased, installation cost is reduced, contractility of the whole wallboard is decreased, wall cracks are decreased effectively, and impact resistance property of the whole wallboard is improved.

Description

A kind of Light trabs installation method
Technical field
The application relates to the realm of building construction, particularly relates to a kind of Light trabs installation method.
Background technology
In existing project installation, novel light body of wall, such as light partition board for building, steam pressure pottery material concrete wall etc., connect seam by operating personnel by manually after mortar spread by cloudy tenon and Yang Sunlianjiechu, shove connects again, and outside is the most directly smeared mortar and closed up, and installation effectiveness is relatively low.Meanwhile, when being operated by operating personnel, randomness is bigger, it is impossible to guarantee that the mortar of seam crossing is full, after completing to install, can be because of the impact of the factors such as seam crossing drying shrinkage, variations in temperature, and there is crackle in body of wall, makes shock resistance reduce.
Summary of the invention
The application to solve the technical problem that being for the deficiencies in the prior art, it is provided that a kind of Light trabs installation method.
The application to solve the technical problem that and to solve by the following technical programs:
A kind of Light trabs installation method, including:
To there is cloudy tenon and there is the Light trabs docking of positive tenon;
Make seam groove keep moistening, in described seam groove, spread boundary mortar;
Mortar, Tao Shi emulsion and water is used to prepare sticking mortar;
Sticking mortar is used to connect seam stickup guipure.
In said method, described use sticking mortar is connecing seam stickup guipure, including:
Seam stickup ground floor guipure, the size of described ground floor guipure and described seam slot fit was connect described in boundary mortar smearing.
In said method, described use sticking mortar is connecing seam stickup guipure, also includes:
Using described sticking mortar to paste second layer guipure on described ground floor guipure, described second layer guipure covers described ground floor guipure.
In said method, described second layer guipure is each side than described ground floor guipure wide 20~60mm.
In said method, paste the flatness deviation with overall metope of the metope after described second layer guipure less than or equal to 3.0mm.
In said method, described guipure includes glass fiber mesh.
In said method, the ratio of mud of described boundary mortar is 0.2~0.5.
In said method, the sand of described sticking mortar and the weight ratio of cement are 2.5~3.0:1.
In said method, the ratio of mud of described sticking mortar is 0.5~0.6.
In said method, weight is mortar weight 8%~the 10% of described Tao Shi emulsion.
Owing to have employed above technical scheme, make what the application possessed to have the beneficial effects that:
(1), in the detailed description of the invention of the application, owing to, after the Light trabs docking that will have cloudy tenon and there is positive tenon, spreading boundary mortar in seam groove, re-use sticking mortar and connecing seam stickup guipure.Using the present processes, wallboard installation process can be made to realize dry operation, reduce wallboard lateral stress and concentrate, the seam entirety by the plate of light weight wall with plate of guipure covers, and gives plate and the preliminary cohesive force of plate.The application not only increases project installation efficiency, reduces installation cost;Also reduce the contractility of integral wall simultaneously, be effectively improved the crackle that body of wall occurs, improve shock resistance.
(2), in the detailed description of the invention of the application, owing to also pasting second layer guipure on ground floor guipure, not only again increase cohesive force between plate and plate, and improve flexibly connecting between plate and plate.The setting of double-deck guipure add plate dock with plate between cohesive force, improve toughness and Stress Release that plate docks with plate, it is ensured that the stability that plate docks with plate.
Accompanying drawing explanation
Fig. 1 is the present processes flow chart in one embodiment.
Detailed description of the invention
Combine accompanying drawing below by detailed description of the invention the present invention is described in further detail.
As it is shown in figure 1, the Light trabs installation method of the application, its a kind of embodiment, comprise the following steps:
Step 102: will there is cloudy tenon and there is the Light trabs docking of positive tenon.The cloudy tenon of Light trabs seam crossing and sun tenon docking, without any mortar between cloudy tenon and sun tenon.
Step 104: make seam groove keep moistening, spread boundary mortar in seam groove.The Light trabs edge having cloudy tenon and have positive tenon is provided with step, forms seam groove after docking.Seam groove can be made to keep moistening by modes such as watering or trickles.Then being filled and led up by Light trabs seam groove with boundary mortar, the ratio of mud of boundary mortar is 0.2~0.5.
In one embodiment, boundary mortar can use strength grade to be not less than M7.5 ordinary mortar.
Step 106: use mortar, Tao Shi emulsion and water to prepare sticking mortar.Before it will be understood by those skilled in the art that step 106 is also placed in step 102, as long as being ready to before pasting guipure.
In one embodiment, the weight of Tao Shi emulsion is the 8%~10% of mortar weight.The sand of sticking mortar and the weight ratio of cement are 2.5~3.0:1.The ratio of mud of sticking mortar is 0.5~0.6.
Step 108: use sticking mortar connecing seam stickup guipure.Wherein guipure can use glass fiber mesh.
In one embodiment, step 108 may include that
Step 1082: paste ground floor guipure, the size of ground floor guipure and seam slot fit at the seam that connects smearing boundary mortar.Ground floor guipure can equal in magnitude with seam groove, or slightly larger than seam groove.The seam groove entirety by the plate of Light trabs with plate that ground floor guipure is complete covers, and can give plate and the preliminary cohesive force of plate.
In another embodiment, step 108 can also include:
Step 1082: using sticking mortar to paste second layer guipure on ground floor guipure, second layer guipure covers ground floor guipure.Second layer guipure is each side than ground floor guipure wide 20~60mm.Ground floor guipure the widest 40~80mm, if such as the guipure of ground floor guipure 60mm width, after ground floor guipure mortar is full, then carries out guipure wide for second layer 100mm on the first layer and puts up, until second layer guipure mortar is full.Paste the flatness deviation with overall metope of the metope after second layer guipure less than or equal to 3.0mm, the flatness overall to ensure wallboard.
After pasting second layer guipure, not only again increase cohesive force between the plate of Light trabs and plate, and improve flexibly connecting between plate and plate.The setting of double-deck guipure add plate dock with plate between cohesive force, improve toughness and Stress Release that plate docks with plate, it is ensured that the stability that plate docks with plate.
Above content is to combine specific embodiment further description made for the present invention, it is impossible to assert the present invention be embodied as be confined to these explanations.For general technical staff of the technical field of the invention, without departing from the inventive concept of the premise, it is also possible to make some simple deduction or replace.

Claims (10)

1. a Light trabs installation method, it is characterised in that including:
To there is cloudy tenon and there is the Light trabs docking of positive tenon;
Make seam groove keep moistening, in described seam groove, spread boundary mortar;
Mortar, Tao Shi emulsion and water is used to prepare sticking mortar;
Sticking mortar is used to connect seam stickup guipure.
2. Light trabs installation method as claimed in claim 1, it is characterised in that described use sticking mortar is connecing seam stickup guipure, including:
Seam stickup ground floor guipure, the size of described ground floor guipure and described seam slot fit was connect described in boundary mortar smearing.
3. Light trabs installation method as claimed in claim 2, it is characterised in that described use sticking mortar is connecing seam stickup guipure, also includes:
Using described sticking mortar to paste second layer guipure on described ground floor guipure, described second layer guipure covers described ground floor guipure.
4. Light trabs installation method as claimed in claim 3, it is characterised in that described second layer guipure is each side than described ground floor guipure wide 20~60mm.
5. Light trabs installation method as claimed in claim 3, it is characterised in that paste the flatness deviation with overall metope of the metope after described second layer guipure less than or equal to 3.0mm.
6. the Light trabs installation method as according to any one of claim 1 to 5, it is characterised in that described guipure includes glass fiber mesh.
7. the Light trabs installation method as according to any one of claim 1 to 5, it is characterised in that the ratio of mud of described boundary mortar is 0.2~0.5.
8. the Light trabs installation method as according to any one of claim 1 to 5, it is characterised in that the sand of described sticking mortar and the weight ratio of cement are 2.5~3.0:1.
9. Light trabs installation method as claimed in claim 8, it is characterised in that the ratio of mud of described sticking mortar is 0.5~0.6.
10. Light trabs installation method as claimed in claim 8, it is characterised in that weight is mortar weight 8%~the 10% of described Tao Shi emulsion.
CN201510051398.6A 2015-01-30 2015-01-30 Light wallboard installation method Pending CN105986629A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510051398.6A CN105986629A (en) 2015-01-30 2015-01-30 Light wallboard installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510051398.6A CN105986629A (en) 2015-01-30 2015-01-30 Light wallboard installation method

Publications (1)

Publication Number Publication Date
CN105986629A true CN105986629A (en) 2016-10-05

Family

ID=57037168

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510051398.6A Pending CN105986629A (en) 2015-01-30 2015-01-30 Light wallboard installation method

Country Status (1)

Country Link
CN (1) CN105986629A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2586754Y (en) * 2002-06-18 2003-11-19 广州大学 Wall anti-cracking mesh-belt
WO2009006647A2 (en) * 2007-07-05 2009-01-08 Hariram Naicker Building elements and a method of manufacture of preformed building products
CN202644829U (en) * 2012-03-23 2013-01-02 中山建华墙体材料有限公司 Novel lightweight narrow board
CN102850083A (en) * 2012-10-11 2013-01-02 祁振君 Energy-saving embedded type light inside and outside wall board
CN103074957A (en) * 2013-02-24 2013-05-01 彭泓越 Incomplete butt-type wallboard and construction method
CN103266689A (en) * 2013-05-24 2013-08-28 东莞市彩丽建筑维护技术有限公司 Construction method and elastic binders for bonding lightweight concrete board wall, and wallboards
US20140260058A1 (en) * 2013-03-15 2014-09-18 Heartwood Carving, Inc. Interlocking wall panel with machine carved decorative texture

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2586754Y (en) * 2002-06-18 2003-11-19 广州大学 Wall anti-cracking mesh-belt
WO2009006647A2 (en) * 2007-07-05 2009-01-08 Hariram Naicker Building elements and a method of manufacture of preformed building products
CN202644829U (en) * 2012-03-23 2013-01-02 中山建华墙体材料有限公司 Novel lightweight narrow board
CN102850083A (en) * 2012-10-11 2013-01-02 祁振君 Energy-saving embedded type light inside and outside wall board
CN103074957A (en) * 2013-02-24 2013-05-01 彭泓越 Incomplete butt-type wallboard and construction method
US20140260058A1 (en) * 2013-03-15 2014-09-18 Heartwood Carving, Inc. Interlocking wall panel with machine carved decorative texture
CN103266689A (en) * 2013-05-24 2013-08-28 东莞市彩丽建筑维护技术有限公司 Construction method and elastic binders for bonding lightweight concrete board wall, and wallboards

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
南京鼎昊建设工程设计有限公司: "《苏J/T15-2013(四)轻质墙板构造图集(四)》", 31 March 2013, 江苏科技出版社 *
甘伟等: "轻质条板墙体裂缝成因及防裂措施", 《2005年全国砌体结构基本理论与工程应用学术会议论文集》 *

Similar Documents

Publication Publication Date Title
CN103821296A (en) Wall plastering technique for aerated concrete block filler wall
CN103806609A (en) Construction method of double-faced self-adhesion waterproof roll
CN105349070B (en) A kind of tile paste peel reinforcing agent
CN204282576U (en) A kind of lightweight external wall structure
CN205677110U (en) A kind of wooden partition wall being easy for installation and removal
CN103790334A (en) Combined splicing floor tile and laying technology of combined splicing floor tile
CN104453011A (en) Light outer wall structure and construction method thereof
CN203729547U (en) Composite splicing floor tile
CN105986629A (en) Light wallboard installation method
CN204343623U (en) A kind of combined floor of ground decoration
CN102330477B (en) Paper honeycomb light wallboard joint treatment method
CN106436943A (en) Supporting-hanging type rock wool board/strip thin plastering external wall thermal-insulation system
CN104675092A (en) Method for adhering face brick of building
CN206769073U (en) A kind of compound insulation structure integration non-dismantling formwork
CN202152539U (en) Plastic building template
CN210369776U (en) Stair can install drip fast
CN107188507A (en) A kind of levelling patch block mortar material of indoor and outdoor
CN207499351U (en) A kind of external corner claying board for building
CN204645701U (en) Construction walling surface reconditioning structure
CN204040341U (en) A kind of exterior wall old ceramic tile face putty refurbishment system
CN208363468U (en) A kind of exterior wall leveling putty refurbishment system
CN106760286A (en) Plaster structure and its construction technology are exempted from a kind of Novel interior wall gypsum bottoming
CN106567464A (en) Thinly-plastered external wall thermal insulation system provided with composite sandwich vacuum insulation board
CN206465585U (en) A kind of transfer membrane structure that processing is transferred applied to concrete retarding
CN110878618A (en) Safe wall surface hanging and sticking process for ceramic large plate and rock plate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161005

RJ01 Rejection of invention patent application after publication