CN105958353A - Transformer substation and layered transformer substation - Google Patents
Transformer substation and layered transformer substation Download PDFInfo
- Publication number
- CN105958353A CN105958353A CN201610411098.9A CN201610411098A CN105958353A CN 105958353 A CN105958353 A CN 105958353A CN 201610411098 A CN201610411098 A CN 201610411098A CN 105958353 A CN105958353 A CN 105958353A
- Authority
- CN
- China
- Prior art keywords
- equipment
- room
- substation
- grounding
- switchgear
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02B—BOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
- H02B7/00—Enclosed substations, e.g. compact substations
- H02B7/06—Distribution substations, e.g. for urban network
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Gas-Insulated Switchgears (AREA)
Abstract
一种变电站及一种分层式变电站,所述变电站包括:接地变消弧线圈设备和10kV配电装置室,所述10kV配电装置室包括:多组开关柜设备,其特征在于,所述接地变消弧线圈设备设置在所述10kV配电装置室内。实现了在放置接地变消弧线圈设备时无需再单独设置配电室,从而节省变电站的用地面积。
A substation and a layered substation, the substation includes: grounding substation arc suppressing coil equipment and a 10kV power distribution device room, the 10kV power distribution device room includes: multiple sets of switchgear equipment, characterized in that the The arc-suppressing coil equipment for grounding transformation is set in the 10kV power distribution device room. It realizes that there is no need to set up a separate power distribution room when placing the grounding substation arc suppressing coil equipment, thereby saving the land area of the substation.
Description
技术领域technical field
本发明涉及电力电网工程设计领域,具体涉及到一种变电站及层分式变电站。The invention relates to the field of power grid engineering design, in particular to a substation and a layered substation.
背景技术Background technique
国家电网公司从2011年开始大力推行《国家电网公司输变电工程通用设计》,从35kV至500kV均有对应电压等级的变电站通用设计方案作为基础指导施工图设计。《35kV—110kV变电站设计规范》规定:“按规划需装设消弧线圈补偿装置的变电站,采用接地变压器引出中性点时,接地变压器可作为站用变压器使用”。随着电力工程的发展,近年来,接地变消弧线圈成套设备在变电站中使用越来越广泛。Since 2011, the State Grid Corporation has vigorously promoted the "General Design of Power Transmission and Transformation Projects of the State Grid Corporation of China". From 35kV to 500kV, there are general design schemes for substations corresponding to voltage levels as the basis to guide the design of construction drawings. "35kV-110kV Substation Design Code" stipulates: "For substations that need to install arc suppression coil compensation devices according to the plan, when using grounding transformers to lead out the neutral point, the grounding transformers can be used as station transformers." With the development of electric power engineering, in recent years, the complete set of grounding substation arc suppression coils has been used more and more widely in substations.
在《110kV变电站通用设计》的A3-3方案中单独设置接地变消弧线圈室放置接地变消弧线圈成套设备,以便明确设备分区,但时也增大了变电站占地的面积,同时导致设备运输难度加大,致使变电站的建设成本增高,不能适应新形势下变电站的设计要求。In the A3-3 scheme of "General Design of 110kV Substation", the arc-suppression coil room of the grounding substation is separately set up to place the complete equipment of the arc-suppression coil of the grounding substation, so as to clarify the division of equipment, but it also increases the area occupied by the substation, and at the same time causes equipment The difficulty of transportation increases, resulting in an increase in the construction cost of the substation, which cannot meet the design requirements of the substation under the new situation.
因此,如何减小变电站的占地面积,降低变电站的建设成本成为亟待解决的问题。Therefore, how to reduce the footprint of the substation and reduce the construction cost of the substation has become an urgent problem to be solved.
发明内容Contents of the invention
本发明要解决的技术问题在于减小变电站的占地面积,降低变电站的建设成本。The technical problem to be solved by the invention is to reduce the occupied area of the substation and reduce the construction cost of the substation.
为此,根据第一方面,本发明实施例提供了一种变电站,包括:接地变消弧线圈设备和10kV配电装置室,10kV配电装置室包括:多组开关柜设备,接地变消弧线圈设备设置在10kV配电装置室内。Therefore, according to the first aspect, the embodiment of the present invention provides a substation, including: grounding substation arc suppression coil equipment and a 10kV power distribution device room, the 10kV power distribution device room includes: multiple sets of switch cabinet equipment, grounding substation arc suppression The coil equipment is set in the 10kV power distribution device room.
优选地,变电站还包括:一字排布的第一主变室、第二主变室和第三主变室,多组开关柜设备包括:第一开关柜设备、第二开关柜设备和第三开关柜设备,分别与第一主变室、第二主变室和第三主变室连接;第一开关柜设备的第一部分、第二开关柜设备和第三开关柜设备的第一部分一字排布;第一开关柜设备的第二部分和第三开关柜设备的第二部分分别位于10kV配电装置室的两侧,且分别靠近第一开关柜设备的第一部分的一侧和第三开关柜设备的第一部分的一侧。Preferably, the substation further includes: a first main transformer room, a second main transformer room and a third main transformer room arranged in a line, and multiple sets of switchgear equipment include: first switchgear equipment, second switchgear equipment and the first switchgear equipment Three switchgear equipment, respectively connected with the first main transformer room, the second main transformer room and the third main transformer room; the first part of the first switchgear equipment, the second switchgear equipment and the first part of the third switchgear equipment Word layout; the second part of the first switchgear equipment and the second part of the third switchgear equipment are located on both sides of the 10kV power distribution equipment room, and are respectively close to the side of the first part of the first switchgear equipment and the second One side of the first part of the three switchgear equipment.
优选地,接地变消弧线圈设备位于第一开关柜设备的第二部分和第三开关柜设备的第二部分之间。Preferably, the ground-changing arc suppression coil device is located between the second part of the first switchgear device and the second part of the third switchgear device.
优选地10kV配电装置室设置在与第一主变室、第二主变室和第三主变室并排的相对侧。Preferably, the 10kV switchgear room is arranged on the opposite side side by side with the first main transformer room, the second main transformer room and the third main transformer room.
优选地,接地变消弧线圈设备包括:本期第一接地变消弧线圈设备、本期第二接地变消弧线圈设备以及远期第三接地变消弧线圈设备;本期第一接地变消弧线圈设备、本期第二接地变消弧线圈设备和远期第三接地变消弧线圈设备依次并排设置。Preferably, the grounding variable arc suppression coil equipment includes: the first grounding variable arc suppression coil equipment in this period, the second grounding variable arc suppression coil equipment in this period, and the third grounding variable arc suppression coil equipment in the future; the first grounding variable arc suppression coil equipment in this period The arc-suppression coil equipment, the arc-suppression coil equipment of the second grounding transformer in the current phase and the arc-suppression coil equipment of the third grounding transformer in the long-term are arranged side by side in sequence.
优选地,开关柜设备和接地变消弧线圈设备共用通风系统。Preferably, the switchgear equipment and the grounding arc suppressing coil equipment share a ventilation system.
优选地,变电站还包括:上下排布的备品室和蓄电池室,设置在10kV配电装置室的左侧,且与第一电容器室和第二电容器室相对。Preferably, the substation further includes: a spare room and a battery room arranged up and down, arranged on the left side of the 10kV power distribution device room, and opposite to the first capacitor room and the second capacitor room.
根据第二方面,本发明实施例提供了一种层分式变电站,包括:上述的变电站,位于同一层;第三电容器室、二次设备室、GIS室以及备品备件室中的任意一种或任意组合,位于变电站的上层。According to the second aspect, an embodiment of the present invention provides a layered substation, including: the above-mentioned substation, located on the same floor; any one of the third capacitor room, secondary equipment room, GIS room, and spare parts room Any combination, located on the upper level of the substation.
本发明实施例提供的变电站,通过将变电站中的接地变消弧线圈设备从单独的配电室设置到10kV配电装置室中,与开关柜设备共用10kV配电装置室,实现了在放置接地变消弧线圈设备时无需再单独设置配电室,从而节省变电站的用地面积。In the substation provided by the embodiment of the present invention, the grounding substation arc suppressing coil equipment in the substation is installed in the 10kV power distribution device room from a separate power distribution room, and the 10kV power distribution device room is shared with the switchgear equipment, so as to achieve grounding There is no need to set up a separate power distribution room when changing the arc suppression coil equipment, thereby saving the land area of the substation.
此外,本发明实施例提供的变电站,通过将接地变消弧线圈设备设置在下层的10kV配电装置室中,相对于现有技术中,在上层为接地变消弧线圈设备单独配置配电室,节省变电站的用地面积,使得在设备安装时无需吊装,减少了接地变消弧线圈设备在吊装过程中引起的安全隐患,节省了吊装成本。In addition, in the substation provided by the embodiment of the present invention, by setting the grounding substation arc suppression coil equipment in the lower 10kV power distribution device room, compared with the prior art, the upper level is equipped with a separate power distribution room for the grounding substation arc suppression coil equipment , saving the land area of the substation, making it unnecessary to hoist when installing the equipment, reducing the safety hazards caused by the hoisting process of the grounding substation arc suppression coil equipment, and saving the hoisting cost.
附图说明Description of drawings
为了更清楚地说明本发明具体实施方式或现有技术中的技术方案,下面将对具体实施方式或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施方式,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the specific implementation of the present invention or the technical solutions in the prior art, the following will briefly introduce the accompanying drawings that need to be used in the specific implementation or description of the prior art. Obviously, the accompanying drawings in the following description The drawings show some implementations of the present invention, and those skilled in the art can obtain other drawings based on these drawings without any creative work.
图1示出了本发明实施例1的变电站的一层的框图;Fig. 1 shows the block diagram of one floor of the substation of embodiment 1 of the present invention;
图2示出了本发明实施例1的变电站的一层的平面结构图;Fig. 2 shows the plane structure diagram of one floor of the substation of Embodiment 1 of the present invention;
图3示出了本发明实施例2的变电站的二层的平面结构图;Fig. 3 shows the plane structure diagram of the second floor of the substation of Embodiment 2 of the present invention;
图4示出了本发明实施例2的变电站的第一综合断面图;Fig. 4 shows the first comprehensive sectional view of the substation of Embodiment 2 of the present invention;
图5示出了本发明实施例2的变电站的第二综合断面图;Fig. 5 shows the second comprehensive sectional view of the substation of Embodiment 2 of the present invention;
图6示出了本发明实施例2的变电站的第三综合断面图。Fig. 6 shows a third comprehensive sectional view of the substation according to Embodiment 2 of the present invention.
具体实施方式detailed description
下面将结合附图对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions of the present invention will be clearly and completely described below in conjunction with the accompanying drawings. Apparently, the described embodiments are some of the embodiments of the present invention, but not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
在本发明的描述中,需要说明的是,术语“对侧”、“边侧”、“左测”、“右测”、“上”、“下”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”、“第三”仅用于描述目的,而不能理解为指示或暗示相对重要性。In the description of the present invention, it should be noted that the orientation or positional relationship indicated by the terms "contraside", "side", "left side", "right side", "upper", "lower" etc. are based on the attached The orientation or positional relationship shown in the figure is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be construed as a reference to this invention. Invention Limitations. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and should not be construed as indicating or implying relative importance.
在本发明的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,还可以是两个元件内部的连通,可以是无线连接,也可以是有线连接。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should be noted that unless otherwise specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection. Connected, or integrally connected; it can be mechanically or electrically connected; it can be directly connected, or indirectly connected through an intermediary, or it can be the internal communication of two components, which can be wireless or wired connect. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.
实施例1Example 1
本实施例公开了一种变电站,如图1所示,该变电站包括:接地变消弧线圈设备62和10kV配电装置室6,10kV配电装置室6包括:多组开关柜设备61,接地变消弧线圈设备62设置在10kV配电装置室6内。通过对10kV配电装置室6整体规划和对多组开关柜设备进行设置,将接地变消弧线圈设备62设置在10kV配电装置室6内。在具体的实施例中,将开关柜设备61与接地变消弧线圈设备62共同设置在10kV配电装置室内,从而,无需对接地变消弧线圈设备62配置单独的配电室,并且,由于多组开关柜设备61与接地变消弧线圈设备62设置在同一10kV配电装置室6中,从而,可以使多组开关柜设备61与接地变消弧线圈设备62之间设置的电缆无需交叉跨越,能有效的避免接地变消弧线圈设备62设置在单独配电房时多组开关柜设备61与接地变消弧线圈设备62设置电缆出现的交叉跨越问题,例如,《国家电网公司输变电工程通用设计》的110-A3-3方案中多组开关柜设备61与接地变消弧线圈设备62分层布置设置在不同的配电室,且不在同一楼层,存在一次、二次电缆交叉跨越的问题。This embodiment discloses a substation, as shown in Figure 1, the substation includes: grounding substation arc suppressing coil equipment 62 and 10kV power distribution device room 6, 10kV power distribution device room 6 includes: multiple sets of switchgear equipment 61, grounding The variable arc suppressing coil equipment 62 is set in the 10kV power distribution device room 6 . Through the overall planning of the 10kV power distribution device room 6 and the installation of multiple sets of switchgear equipment, the grounding transformer arc suppression coil equipment 62 is arranged in the 10kV power distribution device room 6 . In a specific embodiment, the switchgear equipment 61 and the grounding transformer arc suppression coil equipment 62 are jointly installed in the 10kV power distribution device room, so that there is no need to configure a separate power distribution room for the grounding transformer arc suppression coil equipment 62, and because Multiple sets of switchgear equipment 61 and grounding transformer arc suppression coil equipment 62 are set in the same 10kV power distribution device room 6, so that the cables between multiple sets of switchgear equipment 61 and grounding transformer arc suppression coil equipment 62 do not need to cross Spanning can effectively avoid the cross-crossing problem that occurs when multiple sets of switchgear equipment 61 and grounding transformer arc suppression coil equipment 62 are installed in a separate power distribution room. For example, "State Grid Corporation of China In the 110-A3-3 scheme of General Design of Electrical Engineering, multiple sets of switchgear equipment 61 and grounding transformer arc suppression coil equipment 62 are arranged in different power distribution rooms in layers, and are not on the same floor, and there are primary and secondary cables crossing. crossing issues.
在优选的实施例中,变电站还包括:一字排布的第一主变室3、第二主变室4和第三主变室5,多组开关柜设备61包括:第一开关柜设备611、第二开关柜设备612和第三开关柜设备613,分别与第一主变室3、第二主变室4和第三主变室5连接;本实施例中,第一开关柜设备611拆分成两部分,第一开关柜设备611的第一部分和第一开关柜设备611的第二部分,第三开关设备613拆分成两部分,第三开关设备613的第一部分和第三开关设备613的第二部分,为了合理设置多组开关柜设备61为接地变消弧线圈设备预留足够、合理的设置空间。第一开关柜设备611的第一部分、第二开关柜设备612和第三开关柜设备613的第一部分一字排布;第一开关柜设备611的第二部分和第三开关柜设备613的第二部分分别位于10kV配电装置室6的两侧,且分别靠近第一开关柜设备611的第一部分的一侧和第三开关柜设备613的第一部分的一侧。In a preferred embodiment, the substation further includes: the first main transformer room 3, the second main transformer room 4 and the third main transformer room 5 arranged in a line, and the multiple sets of switchgear equipment 61 include: the first switchgear equipment 611. The second switchgear equipment 612 and the third switchgear equipment 613 are respectively connected to the first main transformer room 3, the second main transformer room 4 and the third main transformer room 5; in this embodiment, the first switchgear equipment 611 is split into two parts, the first part of the first switchgear device 611 and the second part of the first switchgear device 611, the third switchgear device 613 is split into two parts, the first part of the third switchgear device 613 and the third part The second part of the switchgear 613 is to reserve sufficient and reasonable setting space for the grounding transformer arc suppressing coil equipment in order to rationally arrange multiple groups of switchgear equipment 61 . The first part of the first switch cabinet device 611, the second switch cabinet device 612 and the first part of the third switch cabinet device 613 are arranged in a line; the second part of the first switch cabinet device 611 and the first part of the third switch cabinet device 613 The two parts are respectively located on both sides of the 10kV power distribution device room 6 , and are respectively close to one side of the first part of the first switchgear equipment 611 and one side of the first part of the third switchgear equipment 613 .
在具体的实施例中,第一主变室3、第二主变室4和第三主变室5分别用于设置主变压器,其排布方式如图1或图2所示,在平面图的上方成一字排布设置,在10kV配电装置室内6内的多组开关柜设备61例如可以是三组第一开关柜设备611、第二开关柜设备612和第三开关柜设备613分别与第一主变室3、第二主变室4和第三主变室5对应连接,如图1或图2所示,第一开关柜设备611的第一部分、第二开关柜设备612和第三开关柜设备613的第一部分一字排布,设置在平面图中的10kV配电装置室内6的上方,第一开关柜设备611的第二部分和第三开关柜设备613的第二部分分别位于10kV配电装置室6的两侧,并第一开关柜设备611的第二部分设置在第一开关柜设备611的第一部分的对侧,第三开关柜设备613的第二部分设置在第三开关柜设备613的第一部分的对侧。由于接地变消弧线圈设备62与开关柜设备61进行上述相应排布,使得空间紧凑有序,功能分区合理。In a specific embodiment, the first main transformation chamber 3, the second main transformation chamber 4 and the third main transformation chamber 5 are respectively used to set up main transformers, and their arrangement is shown in Fig. 1 or Fig. 2, in the plan view Arranged in a line at the top, the multiple sets of switchgear equipment 61 in the 10kV power distribution device room 6 can be, for example, three sets of first switchgear equipment 611, second switchgear equipment 612 and third switchgear equipment 613 respectively connected to the first switchgear equipment 613. One main transformer room 3, the second main transformer chamber 4 and the third main transformer chamber 5 are correspondingly connected, as shown in Fig. 1 or Fig. 2, the first part of the first switchgear equipment 611, the second switchgear equipment 612 and the third The first part of the switchgear equipment 613 is arranged in a line, and it is arranged above the 10kV power distribution device room 6 in the plan view. The second part of the first switchgear equipment 611 and the second part of the third switchgear equipment 613 are respectively located at 10kV On both sides of the power distribution device room 6, the second part of the first switchgear device 611 is arranged on the opposite side of the first part of the first switchgear device 611, and the second part of the third switchgear device 613 is arranged on the third switchgear device The opposite side of the first part of the cabinet device 613. Due to the corresponding arrangement of the grounding variable arc suppressing coil equipment 62 and the switch cabinet equipment 61, the space is compact and orderly, and the functional divisions are reasonable.
在优选的实施例中,接地变消弧线圈设备62位于第一开关柜设备611的第二部分和第三开关柜设备613的第二部分之间。在具体的实施例中,接地变消弧线圈设备62设置在第二开关柜设备613的对侧,并与第一开关柜设备611的第二部分和第三开关柜设备613的第二部分呈一字排布。In a preferred embodiment, the grounding arc suppression coil device 62 is located between the second part of the first switchgear device 611 and the second part of the third switchgear device 613 . In a specific embodiment, the grounding variable arc suppressing coil device 62 is arranged on the opposite side of the second switch cabinet device 613, and forms a shape with the second part of the first switch cabinet device 611 and the second part of the third switch cabinet device 613. Line up.
在优选的实施例中,10kV配电装置室6设置在与第一主变室3、第二主变室4和第三主变室5并排的对侧。In a preferred embodiment, the 10kV power distribution device room 6 is arranged on the opposite side to the first main transformer room 3 , the second main transformer room 4 and the third main transformer room 5 .
在优选的实施例中,接地变消弧线圈设备62可以包括:本期第一接地变消弧线圈设备621、本期第二接地变消弧线圈设备622以及远期第三接地变消弧线圈设备623,本期第一接地变消弧线圈设备621、本期第二接地变消弧线圈设备622和远期第三接地变消弧线圈设备623依次并排设置。远期第三接地变消弧线圈设备623可以是为未来增加接地变消弧线圈设备而预留的空间。在具体的实施例中,如图1所示,本期第一接地变消弧线圈设备621与第一开关柜设备611的第二部分的一侧,本期第一接地变消弧线圈设备621、本期第二接地变消弧线圈设备622以及远期第三接地变消弧线圈设备623依次并排放置。In a preferred embodiment, the grounding variable arc suppression coil device 62 may include: the first grounding variable arc suppression coil device 621 in the current period, the second grounding variable arc suppression coil device 622 in the current period, and the third grounding variable arc suppression coil device in the long term The equipment 623, the first grounding variable arc suppression coil device 621 of the current period, the second grounding variable arc suppression coil device 622 of the current period, and the third grounding variable arc suppression coil device 623 of the long term are arranged side by side in sequence. The third ground-to-arc suppression coil equipment 623 in the future may be a space reserved for adding ground-to-arc suppression coil equipment in the future. In a specific embodiment, as shown in FIG. 1 , the first grounding transformer arc suppression coil device 621 and the second part of the first switch cabinet device 611 are on one side, and the first grounding transformer arc suppression coil device 621 in this phase is , the current second grounding variable arc suppression coil device 622 and the long-term third grounding variable arc suppression coil device 623 are placed side by side in sequence.
在优选的实施例中,开关柜设备61和接地变消弧线圈设备62可以共用同一套通风系统,在具体的实施例中,将接地变消弧线圈设备62与开关柜设备61设置在同一间配电室中,复用通风系统,减少了通风系统的使用数量,节省了变电站建设的成本。In a preferred embodiment, the switchgear equipment 61 and the grounding transformer arc suppression coil equipment 62 can share the same set of ventilation system. In the power distribution room, the ventilation system is reused, which reduces the number of ventilation systems used and saves the cost of substation construction.
在优选的实施例中,左右排布的第一电容器室1和第二电容器室2,设置在一字排布的第一主变室3、第二主变室4和第三主变室5的左侧。In a preferred embodiment, the first capacitor chamber 1 and the second capacitor chamber 2 arranged left and right are arranged in the first main transformer chamber 3 , the second main transformer chamber 4 and the third main transformer chamber 5 arranged in a line on the left side.
在优选的实施例中,上下排布的备品室7和蓄电池室8,设置在10kV配电装置室6的左侧,且与第一电容器室1和第二电容器室2相对。In a preferred embodiment, the spare room 7 and battery room 8 arranged up and down are arranged on the left side of the 10kV power distribution device room 6 and are opposite to the first capacitor room 1 and the second capacitor room 2 .
通过将其中的接地变消弧线圈设备从单独的配电室重新设置到与开关柜设备公用10kV配电装置室中,实现了在放置接地变消弧线圈设备时无需再单独设置配电室,从而在进行变电站整体建造时节省了用地面积。By resetting the grounding transformer arc suppression coil equipment from a separate power distribution room to the common 10kV power distribution device room with the switchgear equipment, it is realized that there is no need to set up a separate power distribution room when placing the grounding transformer arc suppression coil equipment. Therefore, the land area is saved during the overall construction of the substation.
实施例2Example 2
本发明实施例还提供了一种层分式变电站,如图3至图6所示,该分层式变电站,包括:The embodiment of the present invention also provides a layered substation, as shown in Figure 3 to Figure 6, the layered substation includes:
上述实施例1中的变电站,位于同一层;辅助功能设备室,位于变电站的上层。在具体的实施例中,辅助功能设备室根据需要可以包括:第三电容器室9、二次设备室10、GIS室11以及备品备件室12中的任意一种或任意组合,二次设备室可以包括例如第一组二次设备101、第二组二次设备102以及第三组二次设备103;GIS室11可以包括例如GIS整套设备111,如图3所示,第三电容器室9可以设置在下层第一主变室3的左侧,如图5所示,第三电容器室9可以位于左右并排的第一电容器室1和第二电容器室2的空间上的上方;如图3所示,二次设备室10可以设置在第三电容器室9和第一主变室3的对侧,如图5所示,二次设备室10可以位于备品室7和蓄电池室8的空间上的上方;如图3所示,GIS室11可以设置在第一主变室3,第二主变室2,第三主变室3并排的对侧,如图4或图6所示,GIS室11可以设置在10kV配电装置室6的空间上的上方。需要说明的是,本领域技术人员应该理解,空间上的上、下是实际在建设过程中的上、下。The substation in the above-mentioned embodiment 1 is located on the same floor; the auxiliary function equipment room is located on the upper floor of the substation. In a specific embodiment, the auxiliary function equipment room may include: any one or any combination of the third capacitor room 9, the secondary equipment room 10, the GIS room 11, and the spare parts room 12, and the secondary equipment room may Including, for example, the first group of secondary equipment 101, the second group of secondary equipment 102 and the third group of secondary equipment 103; the GIS room 11 may include, for example, a complete set of GIS equipment 111, as shown in Figure 3, the third capacitor room 9 can be set On the left side of the first main transformer chamber 3 on the lower floor, as shown in Figure 5, the third capacitor chamber 9 can be located above the space of the first capacitor chamber 1 and the second capacitor chamber 2 side by side; as shown in Figure 3 , the secondary equipment room 10 can be arranged on the opposite side of the third capacitor room 9 and the first main transformer room 3, as shown in Figure 5, the secondary equipment room 10 can be located above the spare room 7 and the battery room 8 ; As shown in Figure 3, GIS room 11 can be arranged on the first main change room 3, the second main change room 2, the opposite side of the third main change room 3 side by side, as shown in Figure 4 or Figure 6, GIS room 11 It can be installed above the space of the 10kV distribution equipment room 6 . It should be noted that those skilled in the art should understand that the up and down in space are actually up and down in the construction process.
通过将接地变消弧线圈设备设置在下层的10kV配电装置室中,在设备安装时无需吊装,减少了接地变消弧线圈设备在吊装过程中引起的安全隐患节省了吊装成本。By installing the grounding transformer arc suppression coil equipment in the 10kV power distribution device room on the lower floor, there is no need for hoisting during equipment installation, which reduces the safety hazards caused by the grounding transformer arc suppression coil equipment during hoisting and saves hoisting costs.
图1至图6示出了本发明提供的变电站及分层式变电站的结构,本发明的各个设备室及装置室中的设备均为变电站内的常用设备,本领域技术人员可以理解各个设备之间的连接关系,故图中省略了各个设备间的连接电缆。Fig. 1 to Fig. 6 have shown the substation provided by the present invention and the structure of stratified substation, and the equipment in each equipment room and device room of the present invention is the common equipment in the substation, those skilled in the art can understand the difference between each equipment Therefore, the connection cables between each device are omitted in the figure.
虽然结合附图描述了本发明的实施方式,但是本领域技术人员可以在不脱离本发明的精神和范围的情况下作出各种修改和变型,这样的修改和变型均落入由所附权利要求所限定的范围之内。Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art can make various modifications and variations without departing from the spirit and scope of the present invention. Such modifications and variations all fall into the scope of the appended claims. within the limited range.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610411098.9A CN105958353A (en) | 2016-06-08 | 2016-06-08 | Transformer substation and layered transformer substation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610411098.9A CN105958353A (en) | 2016-06-08 | 2016-06-08 | Transformer substation and layered transformer substation |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN105958353A true CN105958353A (en) | 2016-09-21 |
Family
ID=56908764
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610411098.9A Pending CN105958353A (en) | 2016-06-08 | 2016-06-08 | Transformer substation and layered transformer substation |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105958353A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109888654A (en) * | 2019-02-28 | 2019-06-14 | 广东南海电力设计院工程有限公司 | A kind of novel transformer substation layout |
| CN110445047A (en) * | 2019-08-08 | 2019-11-12 | 苏州电力设计研究院有限公司 | A compact 220kV indoor substation |
| CN111416430A (en) * | 2020-05-19 | 2020-07-14 | 中国电建集团福建省电力勘测设计院有限公司 | Multi-station-in-one engineering off-station power fusion wiring method |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN204391512U (en) * | 2014-12-30 | 2015-06-10 | 鞍山电力勘测设计院 | A kind of control cables arrangement of intelligent substation 10kV Machine Room |
| CN204615230U (en) * | 2015-03-12 | 2015-09-02 | 国网山东省电力公司青岛供电公司 | A kind of complete indoor two-layer transformer station of 35kV split transformer |
| CN204615231U (en) * | 2015-03-12 | 2015-09-02 | 国网山东省电力公司青岛供电公司 | The full indoor substation of a kind of 110kV double winding split transformer |
| CN204760837U (en) * | 2015-05-14 | 2015-11-11 | 国网山东省电力公司青岛供电公司 | Complete indoor one deck transformer substation of 35kV components of a whole that can function independently transformer |
| CN204905731U (en) * | 2015-06-15 | 2015-12-23 | 国网山东省电力公司青岛供电公司 | Complete indoor transformer substation of three winding components of a whole that can function independently transformers of 110kV |
| CN205724593U (en) * | 2016-06-08 | 2016-11-23 | 国网山东省电力公司青岛供电公司 | Transformer station and a kind of layer fraction transformer station |
-
2016
- 2016-06-08 CN CN201610411098.9A patent/CN105958353A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN204391512U (en) * | 2014-12-30 | 2015-06-10 | 鞍山电力勘测设计院 | A kind of control cables arrangement of intelligent substation 10kV Machine Room |
| CN204615230U (en) * | 2015-03-12 | 2015-09-02 | 国网山东省电力公司青岛供电公司 | A kind of complete indoor two-layer transformer station of 35kV split transformer |
| CN204615231U (en) * | 2015-03-12 | 2015-09-02 | 国网山东省电力公司青岛供电公司 | The full indoor substation of a kind of 110kV double winding split transformer |
| CN204760837U (en) * | 2015-05-14 | 2015-11-11 | 国网山东省电力公司青岛供电公司 | Complete indoor one deck transformer substation of 35kV components of a whole that can function independently transformer |
| CN204905731U (en) * | 2015-06-15 | 2015-12-23 | 国网山东省电力公司青岛供电公司 | Complete indoor transformer substation of three winding components of a whole that can function independently transformers of 110kV |
| CN205724593U (en) * | 2016-06-08 | 2016-11-23 | 国网山东省电力公司青岛供电公司 | Transformer station and a kind of layer fraction transformer station |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109888654A (en) * | 2019-02-28 | 2019-06-14 | 广东南海电力设计院工程有限公司 | A kind of novel transformer substation layout |
| CN110445047A (en) * | 2019-08-08 | 2019-11-12 | 苏州电力设计研究院有限公司 | A compact 220kV indoor substation |
| CN110445047B (en) * | 2019-08-08 | 2024-06-04 | 苏州电力设计研究院有限公司 | 220KV all-indoor substation in compact arrangement |
| CN111416430A (en) * | 2020-05-19 | 2020-07-14 | 中国电建集团福建省电力勘测设计院有限公司 | Multi-station-in-one engineering off-station power fusion wiring method |
| CN111416430B (en) * | 2020-05-19 | 2024-04-02 | 中国电建集团福建省电力勘测设计院有限公司 | Multi-station integrated engineering station external power fusion wiring method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204155745U (en) | A kind of open-close type current transformer | |
| CN107634464B (en) | Mobile substation | |
| CN105958353A (en) | Transformer substation and layered transformer substation | |
| CN215267650U (en) | A low frequency power transmission system based on grounding structure | |
| CN205724593U (en) | Transformer station and a kind of layer fraction transformer station | |
| CN203932693U (en) | Rail traction substation 27.5kV main electrical scheme structure | |
| CN104009407A (en) | Compact-type totally-enclosed mobile transformer substation | |
| CN204067884U (en) | A kind of distribution line based on double bus scheme | |
| CN110459386B (en) | A DC isolation transformer with an expandable iron core structure | |
| CN205335056U (en) | Be total to box isolation transformer | |
| CN201918730U (en) | UHV DC converter station DC field | |
| CN205029223U (en) | Movable type transformer station | |
| CN104868391A (en) | Outdoor transformer substation | |
| CN204793780U (en) | Half indoor two -layer transformer substation in integrative transformer of 110kV duplex winding | |
| CN108879454B (en) | Combined electric vehicle and combined switch | |
| CN205029185U (en) | Movable substation's electrical connection structure | |
| CN204205380U (en) | Portable GIS transformer station | |
| CN204615231U (en) | The full indoor substation of a kind of 110kV double winding split transformer | |
| CN108183014A (en) | A kind of voltage transformer | |
| CN205724592U (en) | A kind of indoor intelligent substation of 110kV | |
| CN105977857A (en) | 110kV inner-bridge connection GIS equipment structure | |
| CN221530990U (en) | Prefabricated cabin for energy storage power station, prefabricated cabin group and energy storage power station network | |
| CN205335629U (en) | Outdoor arrangement structure of generating line high pressure parallel reactor | |
| CN205029226U (en) | Mobile substation's HGIS car and main combination that becomes car | |
| CN204720935U (en) | Terminal tower line interval arrangement |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160921 |