CN205724591U - A kind of transformer station - Google Patents
A kind of transformer station Download PDFInfo
- Publication number
- CN205724591U CN205724591U CN201620444778.6U CN201620444778U CN205724591U CN 205724591 U CN205724591 U CN 205724591U CN 201620444778 U CN201620444778 U CN 201620444778U CN 205724591 U CN205724591 U CN 205724591U
- Authority
- CN
- China
- Prior art keywords
- transformer
- chamber
- transformer chamber
- room
- transformer station
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000003990 capacitor Substances 0.000 claims description 12
- 230000008676 import Effects 0.000 claims description 6
- 230000005855 radiation Effects 0.000 claims 1
- 230000007812 deficiency Effects 0.000 abstract description 5
- 238000010276 construction Methods 0.000 description 6
- 230000009466 transformation Effects 0.000 description 5
- 230000005611 electricity Effects 0.000 description 3
- 239000002131 composite material Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000004146 energy storage Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
Abstract
The utility model proposes a kind of transformer station, including the first transformer chamber, the second transformer chamber, the 3rd transformer chamber, in each transformer chamber, it is respectively arranged with transformer body and carries out the radiator dispelled the heat for described transformer body, it is characterized in that: described first transformer chamber and the second transformer chamber are arranged on the same side, described 3rd transformer chamber is arranged on the offside of described second transformer chamber, offside, the side of described 3rd transformer chamber of described first transformer chamber are provided with GIS room, and described GIS room is used for arranging GIS device.This technical scheme overcome of the prior art because substation location expropriation of land length and width smaller and the technological deficiency of transformer station's universal design requirement cannot be met, optimize transformer station with achieving treatment in accordance with local conditions arrange, reached to improve land utilization ratio and shortened the purpose of completion time of project simultaneously.
Description
Technical field
This utility model relates to electricity power engineering design field, is specifically related to a kind of transformer station.
Background technology
Transformer station i.e. changes voltage, controls and distribute the place of electric energy, and transformator is the main of transformer station
Equipment, in addition transformer station also includes the plurality of devices such as controller switching equipment, energy storage device, secondary device.
Along with the development in city, the requirement to transformer station is more and more higher, due to the master being used in transformer station
Want equipment volume relatively big, so the floor space of transformer station is the biggest, this to electricity power engineering design and
Quality and the speed built are had higher requirement, and designer typically requires and takes a significant amount of time root
Design the structure of transformer station according to the land area planned in advance, thus make the structure between each transformer station poor
The biggest, and the transformer station designed may be unsuitable for periphery situation, in the prior art, full family
Interior transformer station typically uses two-layer to arrange, the completion time of project is longer, is additionally, since site land resource tight
, being affected by area planning, expropriation of land region can not meet far away the requirement of universal design, such as, pin
To State Grid Corporation of China's project of transmitting and converting electricity universal design " 110 (66)~500kV transformer station fascicle "
110-A2-4 scheme, it is desirable to transformer station arranges in the most indoor building, produces Composite Building First Floor and arranges main transformer
Depressor, 110kV power distribution equipment and 10kV power distribution equipment, two floor arrange secondary device room and capacitor chamber,
The site length that the program is given is to for 28 meters, and wide to for 9 meters, i.e. site length-width ratio is relatively large, right
Require less than the program 28 meters of Yu Changxiang, and the wide expropriation of land region to require more than the program 9 meters
Just cannot meet the requirement of this universal design, which limits the addressing scope of transformer station.
Therefore, how to overcome that cannot to meet transformer station general because substation location expropriation of land length and width are smaller
The technological deficiency that design requires, it is achieved treatment in accordance with local conditions ground optimizes transformer station and arranges, becomes an assistant officer and waits to solve
Technical problem certainly.
Utility model content
Therefore, the technical problems to be solved in the utility model is to overcome of the prior art because of transformer station
Site expropriation of land length and width are smaller and cannot meet the technological deficiency of transformer station's universal design requirement, because of ground system
Preferably optimize transformer station to arrange, reach to improve land utilization ratio and shorten the purpose of completion time of project simultaneously, from
And a kind of the most indoor one layer of transformer station of 110kV split transformator is provided.
To achieve these goals, the utility model proposes a kind of transformer station, including the first transformer chamber,
Second transformer chamber, the 3rd transformer chamber and electrical room, be respectively arranged with change in each transformer chamber
Depressor body and carry out the radiator that dispels the heat for described transformer body, it is characterised in that: described the
One transformer chamber and the second transformer chamber are arranged on the same side, and it is main that described 3rd transformer chamber is arranged on described second
Become the offside of room, offside, the side of described 3rd transformer chamber of described first transformer chamber are provided with GIS
Room, described GIS room is used for arranging GIS device.
Preferentially, described electrical room be arranged on described second transformer chamber and described 3rd transformer chamber it
Between, between described first transformer chamber and described GIS room.
Preferentially, also include: capacitor chamber, for arranging the capacitor compensating reactive power,
Described capacitor chamber is arranged on the side of described second transformer chamber.
Preferentially, also include: secondary device room, be used for arranging secondary device, described secondary device room
It is arranged on the side of described 3rd transformer chamber.
Preferentially, described transformer station is 110kV transformer station, and described transformer body is 110kV transformation
Device body.
Preferentially, described GIS room, described electrical room and each transformer chamber is equipped with and institute
It is provided with between the import and export stating transformer station's ft connection, the transformer body room being disposed adjacent and radiator chamber
Import and export, for passing through for personnel.
The transformer station that this utility model provides, uses a full layout layer scheme, by by the three of transformer station
Group main transformer wherein two groups arrange face-to-face, overcoming in prior art substation location expropriation of land cannot expire
In foot universal design three groups of main transformer the same sides arrange required for the technological deficiency of length-width ratio, make full use of
Expropriation of land resource, improves land utilization ratio, has adapted to urban planning requirement, becomes in prior art
The scheme that power station uses two-layer to arrange is compared, and the full layout layer of compact, not only the transport of equipment is more
Convenient, and save construction area, accelerate area power grid engineering design and construction speed, improve
Construction quality, and reduce transformer station's impact on the daylighting of Adjacent Buildings, promote resource
Economizing type, pro-environmental society.
Accompanying drawing explanation
In order to be illustrated more clearly that this utility model detailed description of the invention or technical side of the prior art
Case, will make simply the accompanying drawing used required in detailed description of the invention or description of the prior art below
Introduce, it should be apparent that, the accompanying drawing in describing below is embodiments more of the present utility model, right
From the point of view of those of ordinary skill in the art, on the premise of not paying creative work, it is also possible to according to
These accompanying drawings obtain other accompanying drawing.
Fig. 1 is a block diagram of transformer station in this utility model embodiment;
Fig. 2 is a plane structure chart of transformer station in this utility model embodiment;
Fig. 3 is a left view profile of transformer station in this utility model embodiment;
Fig. 4 is a front view of transformer station in this utility model embodiment;
Fig. 5 is another plane structure chart of transformer station in this utility model embodiment.
Detailed description of the invention
Below in conjunction with accompanying drawing, the technical solution of the utility model is clearly and completely described, aobvious
So, described embodiment is a part of embodiment of this utility model rather than whole embodiments.
Based on the embodiment in this utility model, those of ordinary skill in the art are not making creative work
The every other embodiment obtained under premise, broadly falls into the scope of this utility model protection.
In description of the present utility model, it should be noted that term " offside ", " avris ", " left ",
Orientation or the position relationship of the instruction such as " right " they are based on orientation shown in the drawings or position relationship, merely to
It is easy to describe this utility model and simplification description rather than instruction or the device of hint indication or element must
Must have specific orientation, with specific azimuth configuration and operation, therefore it is not intended that to this practicality
Novel restriction.Additionally, term " first ", " second ", " the 3rd " are only used for describing purpose, and can not
It is interpreted as instruction or hint relative importance.
In description of the present utility model, it should be noted that unless otherwise clearly defined and limited,
Term " is connected " and should be interpreted broadly, for example, it may be mechanically connected, it is also possible to be electrical connection;Can
Being to be joined directly together, it is also possible to be indirectly connected to by intermediary, it is also possible to be two element internals
Connection, can be wireless connections, it is also possible to be wired connection.For those of ordinary skill in the art
For, above-mentioned term concrete meaning in this utility model can be understood with concrete condition.
The present embodiment provides a kind of transformer station, and Fig. 1 to Fig. 5 shows the power transformation that this utility model provides
The structure stood, the equipment in each canyon described in the utility model and device room is in transformer station
Common equipment, it will be appreciated by those skilled in the art that the annexation between each equipment, Gu Tuzhong
Eliminate the connection cable of each equipment room.As it is shown in figure 1, described transformer station uses complete one layer of design,
It is mainly provided with: the first transformer chamber 13 of the 11, second transformer chamber the 12, the 3rd of transformer chamber, in each transformer chamber
Inside it is respectively arranged with transformer body 111 and carries out the radiator dispelled the heat for described transformer body 111
112, also include electrical room 14;Wherein said first transformer chamber 11 and the second transformer chamber 12 are arranged
In the same side, described 3rd transformer chamber 13 is arranged on the offside of described second transformer chamber 12, i.e. uses
Arrangement face-to-face.As in figure 2 it is shown, the concrete of each equipment of transformer station as shown in Figure 1 is divided
Cloth relation is made that more specific displaying.This programme taking into full account, to combine State Grid Corporation of China defeated
The basis of power transformation engineering universal design " 110 (66)~500kV transformer station fascicle " 110-A2-4 scheme
On, use module spliced to switch through shifting, treatment in accordance with local conditions ground uses main transformer to arrange face-to-face, such as Fig. 3 institute
Show, clearly show that the second transformer chamber 12 and the 3rd transformer chamber 13 position in left view profile
Relation and the particular location of transformer body 111, will wherein two groups of three groups of main transformers of transformer station
Arrange (the i.e. the 3rd transformer chamber 13 and the second transformer chamber 12 arrange face-to-face) face-to-face, overcome power transformation
Site expropriation of land cannot meet the length-width ratio required by three groups of transformer chamber's the same sides layouts of tradition transformer station
Defect, such as site expropriation of land is long to less than 28 meters of 110-A2-4 scheme, wide to more than 110-A2-4
During 9 meters (i.e. site expropriation of land length and width smaller) of scheme, the expropriation of land of this site just cannot set according to general
Transformer station is arranged in the requirement of meter, and the technical solution of the utility model makes the problems referred to above have been resolved.
It addition, arrange on the side of the offside of described first transformer chamber 11, described 3rd transformer chamber 13
GIS room 15, described GIS room 15 is had to be used for arranging GIS device.This GIS room 15 uses cable to enter
Outlet, as shown in Figure 4, in transformer station just clearly show that GIS room 15 and the 3rd transformer chamber 13
Position relationship in view.
As the preferred implementation of one, described electrical room 14 is arranged on described second transformer chamber
Between 12 and described 3rd transformer chamber 13, between described first transformer chamber 11 and described GIS room 15.
Wherein, power distribution equipment is indoor intermediate switchgear cabinet, specifically, and opening in described electrical room 14
Closing cabinet is that biserial is positioned opposite, the first transformer chamber 11 and the second transformer chamber the 12, the 3rd transformer chamber 13 and
GIS room 15 is separately positioned on the both sides of this electrical room 14, in order to transformer chamber is with power distribution equipment even
Connect.
Additionally, this transformer station also includes capacitor chamber 16, compensate reactive power for arranging
Capacitor, described capacitor chamber 16 is arranged on the side of described second transformer chamber 12.
Additionally, this transformer station also includes secondary device room 17, it is used for arranging secondary device, described two
Secondary device room 7 is arranged on described 3rd transformer chamber 13 side, as shown in Figure 4, clearly show that two
Secondary device room 7 and the 3rd transformer chamber 13 position relationship in transformer station's front view.
As it is shown in figure 1, in such scheme, capacitor chamber 16 and secondary device room 17 are positioned opposite,
Make full use of because of Liang Zu transformer chamber arrange face-to-face vacant go out site expropriation of land resource, need explanation
It is, on the arrangement of capacitor chamber 16 of the present utility model and secondary device room 17 is not limited to
The opposite positioning manner stated, as long as the arrangement that can realize the technical solution of the utility model is the suitableeest
For this utility model.
As a kind of concrete scheme, this transformer station can be 110kV transformer station, transformer body 111
For 110kV transformer body.The present embodiment preferentially selects 110kV transformer station and 110kV transformator
Body, it should be noted that the technical solution of the utility model is not limited to above-mentioned 110kV power transformation
Stand and 110kV transformer body, as long as the transformer station of the technical solution of the utility model can be realized,
All it is applicable to this utility model.
As further implementation, described GIS room 15, described electrical room 14 and each
The transformer body that individual transformer chamber is equipped with the import and export with described transformer station ft connection, is disposed adjacent
Import and export it are provided with, for passing through for personnel between room and radiator chamber.For the ease of equipment conveying, lifting,
Maintenance and operational inspection, can also arrange annular transport passage 18, such as Fig. 5 institute around described transformer station
Show, cable tunnel can be arranged on the lower section of annular transport passage 18, for cabling, and
Transformer station's enclosure wall 19 can also be built annular transport passage 18 is peripheral, it is achieved transformer station with outside every
From, to ensure the safe operation of transformer station.
The transformer station that this utility model provides, uses a full layout layer scheme, by by the three of transformer station
Group transformer chamber wherein two groups arrange face-to-face, overcoming in prior art substation location expropriation of land cannot
Meet in universal design three groups of transformer chamber and be arranged in the technological deficiency of the length-width ratio required for the same side, fill
Divide and make use of expropriation of land resource, improve land utilization ratio, adapted to urban planning requirement, with existing skill
The scheme that Shu Zhong transformer station uses two-layer to arrange is compared, the full layout layer of compact, the not only fortune of equipment
Defeated convenient, and save construction area, accelerate area power grid engineering design and construction speed,
Improve construction quality, and reduce transformer station's impact on the daylighting of Adjacent Buildings, promote
Resource-conserving and environment-friendly society builds.
Obviously, above-described embodiment is only for clearly demonstrating example, and not to embodiment party
The restriction of formula.For those of ordinary skill in the field, the most also may be used
To make other changes in different forms.Here without also all of embodiment being given
With exhaustive.And the obvious change thus extended out or variation are created still in this utility model
Protection domain among.
Claims (6)
1. a transformer station, fills including the first transformer chamber, the second transformer chamber, the 3rd transformer chamber and distribution
Put room, in each transformer chamber, be respectively arranged with transformer body and carry out for described transformer body
The radiator of heat radiation, it is characterised in that:
Described first transformer chamber and the second transformer chamber are arranged on the same side, and described 3rd transformer chamber is arranged on
The offside of described second transformer chamber, on offside, the side of described 3rd transformer chamber of described first transformer chamber
While be provided with GIS room, described GIS room is used for arranging GIS device.
Transformer station the most according to claim 1, it is characterised in that described electrical room is arranged on
Between described second transformer chamber and described 3rd transformer chamber, described first transformer chamber and described GIS room it
Between.
Transformer station the most according to claim 2, it is characterised in that also include:
Capacitor chamber, for arranging the capacitor compensating reactive power, described capacitor chamber is arranged
Side in described second transformer chamber.
Transformer station the most according to claim 3, it is characterised in that also include:
Secondary device room, is used for arranging secondary device, and it is main that described secondary device room is arranged on the described 3rd
Become the side of room.
Transformer station the most according to claim 4, it is characterised in that described transformer station is 110kV
Transformer station, described transformer body is 110kV transformer body.
Transformer station the most according to any one of claim 1 to 5, it is characterised in that
Described GIS room, described electrical room and each transformer chamber are equipped with and described transformer station
It is provided with import and export between the import and export of ft connection, the transformer body room being disposed adjacent and radiator chamber,
For passing through for personnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620444778.6U CN205724591U (en) | 2016-05-16 | 2016-05-16 | A kind of transformer station |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620444778.6U CN205724591U (en) | 2016-05-16 | 2016-05-16 | A kind of transformer station |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205724591U true CN205724591U (en) | 2016-11-23 |
Family
ID=57300385
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620444778.6U Expired - Fee Related CN205724591U (en) | 2016-05-16 | 2016-05-16 | A kind of transformer station |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205724591U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110318563A (en) * | 2019-06-18 | 2019-10-11 | 佛山电力设计院有限公司 | A kind of 3 buildings arrangement formula substation |
-
2016
- 2016-05-16 CN CN201620444778.6U patent/CN205724591U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110318563A (en) * | 2019-06-18 | 2019-10-11 | 佛山电力设计院有限公司 | A kind of 3 buildings arrangement formula substation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201667498U (en) | Box type transformer substation for open-pit mine | |
CN205622124U (en) | Prefabricated cabin formula transformer substation of 110kV | |
CN205724591U (en) | A kind of transformer station | |
CN103956763A (en) | Flexible DC converter station | |
CN204858370U (en) | Prefabricated storehouse of 110kV integrated transformer substation of formula | |
CN204927909U (en) | Pull whole flow box formula transformer substation | |
CN202423887U (en) | Distributor box for construction site | |
CN205583475U (en) | Integrated transformer substation of 110kV prepackage type | |
CN104967035A (en) | Special inverter and distribution transformer all-in-one intelligent integrated preassembled transformer station for photovoltaic power generation | |
CN102361241A (en) | Box type transformer station | |
CN204732755U (en) | A kind of frame-type transformer station | |
CN204905731U (en) | Complete indoor transformer substation of three winding components of a whole that can function independently transformers of 110kV | |
CN203826980U (en) | Flexible DC converter station | |
CN105391154A (en) | Container type energy supply system | |
CN204258114U (en) | A kind of 500kV substation equipment arrangement | |
CN209603568U (en) | Compound substation | |
CN204741208U (en) | Photovoltaic power generation becomes intelligent integrated form of integration pre -installation transformer substation special contrary joining in marriage | |
Chen et al. | Research on Key Technology and Technical and Economic Indicators of 220kV Prefabricated Cabin Substation | |
CN113241653A (en) | Integrated resonance-eliminating intelligent boosting transformer substation | |
CN204615231U (en) | The full indoor substation of a kind of 110kV double winding split transformer | |
CN113071347A (en) | Box-type charging station | |
CN205265332U (en) | Container formula energy supply system | |
CN105048324A (en) | L-shaped distribution structure of valve hall converter transformer of extra-high-voltage direct-current converter station | |
CN104538861A (en) | Intelligent simulation distribution box | |
CN205646453U (en) | Chassis bus duct |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161123 Termination date: 20180516 |