CN105952045B - Floor construction method is poured after a kind of prestressing force - Google Patents

Floor construction method is poured after a kind of prestressing force Download PDF

Info

Publication number
CN105952045B
CN105952045B CN201610325452.6A CN201610325452A CN105952045B CN 105952045 B CN105952045 B CN 105952045B CN 201610325452 A CN201610325452 A CN 201610325452A CN 105952045 B CN105952045 B CN 105952045B
Authority
CN
China
Prior art keywords
construction
reinforcing bar
side pole
poured
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610325452.6A
Other languages
Chinese (zh)
Other versions
CN105952045A (en
Inventor
苏亮
余睿
吴奉蔚
向畅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University ZJU
Original Assignee
Zhejiang University ZJU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University ZJU filed Critical Zhejiang University ZJU
Priority to CN201610325452.6A priority Critical patent/CN105952045B/en
Publication of CN105952045A publication Critical patent/CN105952045A/en
Application granted granted Critical
Publication of CN105952045B publication Critical patent/CN105952045B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices
    • E04C5/125Anchoring devices the tensile members are profiled to ensure the anchorage, e.g. when provided with screw-thread, bulges, corrugations

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention discloses pouring floor construction method after a kind of prestressing force, it includes pre-buried anchorage and pipeline, is inserted into and anchor bar, sleeve connection tensioning, welded reinforcement truss, the outstanding sequences of construction such as take of template.The construction that the present invention pours reinforcing bar at floor by pre-buried anchorage and pipeline for after provides simply and easily method, higher without cost and the cumbersome complexity of construction bar planting or the reserved steel bar method for being difficult to control bending damage;The pulling force generated by sleeve connection balances the outstanding template taken to support, and avoids cumbersome successively formwork form removal process or angle steel pre-manufactured steel board method.Method simple economy of the present invention is practical, and the engineering demand of floor slab construction is poured after disclosure satisfy that.

Description

Floor construction method is poured after a kind of prestressing force
Technical field
The invention belongs to architectural engineering construction technique field more particularly to it is a kind of be suitable for after pour the construction method of floor.
Background technology
It is well known that during architectural engineering concreting, since special type requires, after pour floor slab construction and often occur In newly-built building engineering construction.The economy and practicability of technical method are directly related to the quality of construction method quality.Cause This, the simplicity, economy and practicality that floor slab construction process is poured after how realizing entirely are an important contents to merit attention.
After pour floor slab construction process and be broadly divided into two big steps:First is reinforcement construction, and second is pouring for floor.
For reinforcement construction, existing method is mainly bar planting or general contracting unit reserved steel bar.Although bar planting technique into It is ripe, but it the shortcomings that be that cost is higher and it is very big with bar planting material (anchor adhesive) degree of association, stress is complicated, construction Quality cannot be guaranteed.And the mode of general contracting unit reserved steel bar is limited in that and embedded bar is dug out from original structure, it can be through Go through one break it is curved break straight process again, uncontrollable fatigue damage can be caused and poured to after floor causing quality and safety it is hidden Suffer from.
For concrete floor slab placement, what emphasis was concentrated mainly on template builds mode.Conventionally employed method has the technique more normal The full hall scaffold of rule successively pours or precast floor slab concreting, but full hall scaffold is successively poured due to successively to take And if pour, each layer has the process of formwork form removal, and the duration is time-consuming longer.And for the method for precast floor slab, although being not required to Form removal is repeatedly taken, but needs to set up angle steel and is laid with floor support plate, vertical transport difficulty is bigger, and cost is relatively high. Still an alternative is that on the basis of existing structure angle steel and steel I-beam is set to be used as shuttering supporting, herein on basis Steel form is laid with, then using steel form as job platform, using movable Scaffold, one layer is continued up and sets up angle steel and I-shaped Girder steel, and so on.Although steel form speed of application is very fast and part girder steel will be left in after pour the inside of beam, the knot of beam is poured to after Structure is beneficial, but each component vertical transport difficulty of this method is big, will also destroy part steel form, and needs to set up fixed and remove A large amount of angle steel, I-steel, thus will generate more expense, cost is higher.
Based on above engineering background, quickly and easily to complete entire work progress and ensureing certain economy, profit With existing instrument and technological development it is a kind of it is new after to pour floor construction method be very valuable work.
The content of the invention
The purpose of the present invention is overcoming the shortcomings of existing method, prestressing technique is applied to and pours floor after building structure and applies Among work technology, floor construction method is poured after a kind of prestressing force is provided.This method is with faster construction efficiency and preferably Economy.
The purpose of the present invention is realized by following technical method:Floor construction method is poured after a kind of prestressing force, is mainly included Following working procedure:
(1) poured after floor both sides component pour before embedment improvement LM types thread anchorage and pipeline respectively, treat two After the pouring molding of side, tube drawing forms reserving hole channel.
(2) screw side pole is inserted by reserving hole channel in the concrete poured on both sides, and utilizes and improve LM type screws Side pole anchorage is anchored, and reinforcing bar is accessed on both sides respectively by butt joint.
(3) rotated since the reinforcing bar at both ends is inconvenient by anchoring, using positive and negative threaded ferrule to both sides bar connecting It draws, changes reinforcement stresses (it is made to generate certain pre-tensile stress).
(4) welded reinforcement truss mould plate by the use of the reinforcing bar with pre-tensile stress as the top boom of girder system, holds it By the weight of template;The template uses pre-manufactured steel board.
(5) concreting is completed.
The present invention has the advantages that compared with the prior art:
1st, access and anchoring are provided to pour the reinforcing bar at floor for after by the mode of pre-buried anchorage and pipeline, have it is low into Originally the characteristics of short, is taken, the step using the time used in bar planting and cumbersome specialty can be not only reduced, also avoid simultaneously The fatigue strength loss hidden danger of chisel reserved steel bar, has apparent economy and convenience.
2nd, by using the sleeve connection of positive and negative screw-thread both sides reinforcing bar is made to generate certain tensile stress and does steel afterwards to balance The compression (being similar to prestressing force) caused by the reinforcing bar of top boom is served as during muscle truss mould plate.It no longer needs to set up others such as The extra support of angle steel, I-steel etc..Greatly reduce the workload of construction personnel.
3rd, due to the method template set up dependence be this layer of reinforcing bar pre-tensile stress, it is possible to construction in layer, nothing Maintenance must be waited, can realize rapid construction.
4th, the present invention is economical and practical, and simple in structure, stress is clear and definite, and method is easy to operate, strong applicability.
Description of the drawings
Fig. 1 is the flow chart that floor construction method is poured after a kind of prestressing force of the present invention;
The reinforcing bar that Fig. 2 is the present invention accesses and anchoring schematic diagram, wherein, (a) is the schematic diagram before access reinforcing bar, and (b) is Access the schematic diagram after reinforcing bar;
Fig. 3 is the positive and negative screwed connection schematic diagram of sleeve of the present invention;
Fig. 4 is the steel bar truss floor system schematic diagram of the present invention;
Fig. 5 is the A-A side views of Fig. 4;
In figure, improvement LM types thread anchorage 1, pipeline 2, concrete 3, butt joint 4, reinforcing bar 5, positive and negative threaded ferrule 6th, template 7, side pole anchor nut 8, backing plate 9, anti-tampering shell 10, screw side pole 11, left hand thread 12, right-handed thread 13, bolt 14。
Specific embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings.The objects and effects of the present invention will become more significantly.
As described in Figure 1, floor construction method is poured after prestressing force of the present invention mainly includes following working procedure:
1st, poured after floor both sides component pour before embedment improvement LM types thread anchorage 1 and pipeline 2 respectively, treat two After the pouring molding of side, tube drawing forms reserving hole channel.
2nd, screw side pole 11 is inserted by reserving hole channel in the concrete 3 poured on both sides, and utilizes and improves LM type spiral shells Silk side pole anchorage 1 is anchored, and reinforcing bar 5 is accessed on both sides respectively by butt joint 4.
3rd, rotated since the reinforcing bar 5 at both ends is inconvenient by anchoring, using positive and negative threaded ferrule 6 to both sides bar connecting It draws, changes 5 stress of reinforcing bar (it is made to generate certain pre-tensile stress).
4th, welded reinforcement truss mould plate by the use of the reinforcing bar 5 with pre-tensile stress as the top boom of girder system, holds it By the weight of template 7;The template 7 uses pre-manufactured steel board.
5th, concreting is completed.
As shown in Fig. 2, anchorage selects the LM types thread anchorage 1 of improvement.With the LM types thread anchorage of market not It is side pole anchor nut 8 is welded on backing plate 9 in advance with part, and anti-tampering shell 10 is welded around.Treat itself and concrete After pouring together, among screw side pole 11 can be torqued into side pole anchor nut 8 from pre-buried pipeline one side, poured from opposite side mixed Coagulate the influence of soil.After screw side pole is torqued into and is fixed, reinforcing bar 5 is connected with side pole 11 using the form of butt welding.
As shown in figure 3, sleeve connection of two end bars in middle selects positive and negative threaded ferrule 6.Because reinforcing bar anchor Gu inconvenience is rotated further by, the stress of reinforcing bar 5 can be changed by the connection of positive and negative threaded ferrule 6, that is, generate certain pre-tensile stress.Its Step is that both sides reinforcing bar 5 is aligned to the two-port of positive and negative threaded ferrule 6, and rotatable connection sleeve makes two reinforcing bars smoothly enter sleeve. It finally determines positive and negative 6 both ends exposed threads of threaded ferrule and quantity is equal i.e. with the positive and negative threaded ferrule 6 of special spanner rotation, make two It locks and generates tensile stress in end.
As shown in figure 4, the welded reinforcement truss structure system on the basis of two rows reinforcing bar, while by welding and making Slab form is connected fixation with lower boom reinforcing bar and web member reinforcing bar intersection with the mode of bolt 14.This model meets simple purlin Frame Structure Calculation is theoretical, and template dead weight is considered as the vertical load that truss structure is born, and top boom will be by during model sheetinstallat Pressure.Balance portion is connected to caused pre-tensile stress on reinforcing bar 5 by this compression by sleeve 6 in installation process.

Claims (3)

1. pour floor construction method after a kind of prestressing force, it is characterised in that:It is mainly included the following steps that:
(1) poured after floor both sides component pour before respectively embedment improvement LM types thread anchorage (1) with pipeline (2), treat After the pouring molding of both sides, tube drawing forms reserving hole channel;
(2) screw side pole (11) is inserted by reserving hole channel in the concrete (3) poured on both sides, and utilizes and improves LM type spiral shells Silk side pole anchorage (1) is anchored, and reinforcing bar (5) is accessed on both sides respectively by butt joint (4);
(3) rotated since the reinforcing bar (5) at both ends is inconvenient by anchoring, using positive and negative threaded ferrule (6) to both sides bar connecting Tensioning changes reinforcing bar (5) stress;
(4) welded reinforcement truss mould plate by the use of the reinforcing bar (5) with pre-tensile stress as the top boom of girder system, holds it By the weight of template (7);The template (7) uses pre-manufactured steel board;
(5) concreting is completed.
2. pour floor construction method after a kind of prestressing force according to claim 1, it is characterised in that:Used improvement LM types thread anchorage is made of side pole anchor nut (8), side pole anchor plate (9), anti-tampering shell (10), side pole anchor nut (8) it is welded on backing plate (9), anti-tampering shell (1) covers side pole anchor nut (8), and is welded with backing plate (9).
3. pour floor construction method after a kind of prestressing force according to claim 1, it is characterised in that:It is used positive and negative The internal thread of threaded ferrule (6) is made of (13) two kinds of screw threads of left hand thread (12) and right-handed thread.
CN201610325452.6A 2016-05-17 2016-05-17 Floor construction method is poured after a kind of prestressing force Expired - Fee Related CN105952045B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610325452.6A CN105952045B (en) 2016-05-17 2016-05-17 Floor construction method is poured after a kind of prestressing force

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610325452.6A CN105952045B (en) 2016-05-17 2016-05-17 Floor construction method is poured after a kind of prestressing force

Publications (2)

Publication Number Publication Date
CN105952045A CN105952045A (en) 2016-09-21
CN105952045B true CN105952045B (en) 2018-05-29

Family

ID=56912884

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610325452.6A Expired - Fee Related CN105952045B (en) 2016-05-17 2016-05-17 Floor construction method is poured after a kind of prestressing force

Country Status (1)

Country Link
CN (1) CN105952045B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107013040A (en) * 2017-06-02 2017-08-04 杭州宥盛建筑科技有限公司 The construction method of floor is poured after a kind of sleeve built-in type
CN110630030A (en) * 2019-09-17 2019-12-31 湖南大学 P-UHPC reinforcing device for reinforced concrete structure and construction method thereof
CN111287486B (en) * 2020-02-19 2021-06-22 浙江固邦建筑特种技术有限公司 Construction method for underpinning hollow floor slab into cast-in-place floor slab

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10169066A (en) * 1996-12-06 1998-06-23 Tesuku:Kk Construction method for steel framed building
CN1904272A (en) * 2005-07-28 2007-01-31 邱则有 Structure force bearing type mould plate construction unit
CN101761000A (en) * 2009-12-30 2010-06-30 中铁二十三局集团有限公司 Nine-connecting-plate connective tensioning construction method for road bed
CN102535355A (en) * 2012-02-21 2012-07-04 朔黄铁路发展有限责任公司 Method for reinforcing bridge structure separated steel-concrete combined truss
CN104912204A (en) * 2015-07-07 2015-09-16 钟智谦 Connecting structure and connecting method
CN105040825A (en) * 2015-07-07 2015-11-11 钟智谦 Connecting structure and connecting method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10169066A (en) * 1996-12-06 1998-06-23 Tesuku:Kk Construction method for steel framed building
CN1904272A (en) * 2005-07-28 2007-01-31 邱则有 Structure force bearing type mould plate construction unit
CN101761000A (en) * 2009-12-30 2010-06-30 中铁二十三局集团有限公司 Nine-connecting-plate connective tensioning construction method for road bed
CN102535355A (en) * 2012-02-21 2012-07-04 朔黄铁路发展有限责任公司 Method for reinforcing bridge structure separated steel-concrete combined truss
CN104912204A (en) * 2015-07-07 2015-09-16 钟智谦 Connecting structure and connecting method
CN105040825A (en) * 2015-07-07 2015-11-11 钟智谦 Connecting structure and connecting method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
钢筋桁架楼承板在中瑞项目工程中的应用;吕强;《贵州大学学报( 自然科学版)》;20141031;第2节 *

Also Published As

Publication number Publication date
CN105952045A (en) 2016-09-21

Similar Documents

Publication Publication Date Title
CN207194146U (en) Prestressing force assembly concrete frame joint attachment structure
CN107165272A (en) Prestressing force assembly concrete frame joint attachment structure and its construction method
CN110528950B (en) Assembled hidden bracket type beam-column joint connecting device
CN107254884A (en) A kind of detachable prefabricated assembled concrete-filled steel square tubular column pin node
CN101984189B (en) Construction method of large steel concrete composite multi-terrace slope skewback
CN103422620A (en) Prefabricated hollow steel-reinforced concrete column and splicing structure and splicing method thereof
CN105952045B (en) Floor construction method is poured after a kind of prestressing force
CN109183607A (en) Precast spliced UHPC pipe-concrete super-high pier and construction method
CN113605771B (en) Prestress assembly type frame structure system
CN113653235A (en) Laminated slab, connecting structure of laminated slab and combination beam and construction method
CN203701334U (en) Reinforced and prefabricated type shear wall structure
CN202787099U (en) Reinforced concrete cap beam external prestressing structure
CN110905198B (en) Construction method of steel strand opposite-pull reinforcing template and reinforcing anchor device
CN209669688U (en) A kind of half assembled thin-wall piers
CN110905074A (en) Independent node assembly type frame structure and construction method
CN104790299B (en) Internal-span unsupported convenient construction support and method for bridge cast-in-place box beam
CN200999389Y (en) Panel point for steel pipe concrete column and reinforced concrete beam
CN100396868C (en) Prestressed anchoring system by high tensile steel wire pretension and construction method thereof
CN111608312A (en) Tensioning node of T-beam wing plate under post-tensioning method with bonded prestressed rib plate and construction method
CN208981316U (en) Variable-section steel pipe concrete column structure is connect on a kind of steel core concrete column
CN104453235B (en) Current conversion station fire wall construction technology
CN109853730A (en) A kind of novel precast reinforced concrete frame joint and its method of construction
CN109722984A (en) Half assembled thin-wall piers of one kind and its assembly method
CN108487506B (en) A kind of construction method of the assembled integral shear wall based on SP plate
CN208201892U (en) A kind of white-out tubular pole and soil nail wall composite supporting construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180529

CF01 Termination of patent right due to non-payment of annual fee