CN105951859B - Base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method - Google Patents

Base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method Download PDF

Info

Publication number
CN105951859B
CN105951859B CN201610377009.3A CN201610377009A CN105951859B CN 105951859 B CN105951859 B CN 105951859B CN 201610377009 A CN201610377009 A CN 201610377009A CN 105951859 B CN105951859 B CN 105951859B
Authority
CN
China
Prior art keywords
basement bottom
concrete
dewatering well
bottom board
sealing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610377009.3A
Other languages
Chinese (zh)
Other versions
CN105951859A (en
Inventor
肖辉
张艳源
马恒力
陈世伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201610377009.3A priority Critical patent/CN105951859B/en
Publication of CN105951859A publication Critical patent/CN105951859A/en
Application granted granted Critical
Publication of CN105951859B publication Critical patent/CN105951859B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a kind of base pit dewatering well to wear concrete of basement bottom plate closure sealing construction processing method, comprises the following steps:Making sealing steel sleeve → pour basement bottom board blinding concrete → cutting bedding plane dewatering well filter pipe, water-stopping steel its lower end twines interior insertion dewatering well filter pipe after Bituminous hemp fiber, and shut → basement bottom board bedding plane construction of waterproof layer → colligation concrete floor reinforcing bar with cement mortar stuff up a crack, lasting precipitation → pour basement bottom board concrete, continue precipitation → dewatering well and terminate precipitation → closure dewatering well one by one.The present invention use double-vane ring sealing steel sleeve, insertion precipitation well head, and well head plugging structure is simple, scientific and reasonable, safe and reliable, water-stagnating effect is good, precipitation requirement when can adapt to basement construction of bottom plates difference operating mode very well;Solve the precipitation demand in basement reinforced concrete floor work progress, and solve terminate to wear concrete of basement bottom plate its dewatering well sealing closure problem during precipitation well.

Description

Base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method
Technical field
The present invention relates to deep basal pit foundation construction field, and in particular to a kind of base pit dewatering well is worn concrete floor closure and stopped Water construction treating methods.
Background technology
With the rapid development of economic construction of China, all kinds of public buildings and high residential building are increasing, its deep base The planar dimension in hole is increasing, substantially carries out deep foundation pit precipitation using the construction method of deep-well precipitation in hole at present.And The plugging construction technology of base pit dewatering well is a key point in whole foundation construction, and it directly influences base pit dewatering well The waterproof quality of water-stagnating effect and sole plate concrete, so as to influence to the construction of underground chamber base, this gives basement coagulation The closure that precipitation and precipitation during native construction of bottom plates terminate rear well head brings new difficulty and challenge.
Publication No. CN104711994A documents 1 disclose a kind of foundation-pit deep-well precipitation and plugging construction method, Using wellhead sealing steel plate and coating steel pipe, connection pulsating pump is absorbed water;Closing sealing is carried out using the valve on steel pipe, is solved Certainly plugging dewatering well problem, but do not solve valve, water suction steel pipe and sole plate concrete combination problem, and water check valve is wrapped in back In packing course, after long-time, because of pipe fitting corrosion, well head infiltration risk be present.Publication No. CN101148884B documents 2 are public The waterproof and plugging construction method of a kind of precipitation well in foundation pit have been opened, has been entered using steel sleeve, ring flange, connecting bolt, rubber ring Row closure well head, solves precipitation waterproof and closure problem, but does not solve the connectivity problem between steel sleeve and precipitation well head, more Do not solve the problems, such as the combination between dewatering well, steel sleeve, sole plate further, it is difficult to reach well head sealing and waterproof requirement. Publication No. CN204059380U documents 3 disclose in a kind of underground garage foundation ditch deep-well precipitation well head well-sealing device and Method, it is enclosed on using the steel cylinder of seal ring inside and outside band on well head, it is suitable for reading to seal steel bushing with steel plate, reaches closure precipitation well head mesh , solve deep-well precipitation well head shut-in well problem in foundation ditch, but sealing link is more, process is more, construction is complicated and need to also be in raft plate On the basis of doughnut-shaped steel plate waterstop is set, how the gap do not explained between clear steel bushing and well head outer wall to be handled, and infiltration be present Hidden danger.Publication No. CN103556644A documents 4 disclose a kind of basement bottom board dewatering well well head closure sleeve pipe and Construction method, using the steel cylinder with ring flange, it is placed on well head, first fixes steel cylinder with concrete, then covers flange sealing Water, solves dewatering well well head closure problem, but the working pit for the steel cylinder height that need to backbreak first pours concrete and fixes steel cylinder, volume It is outer to add foundation engineering amount, and sealing steel cylinder combined with pipe well it is not close.
At present dewatering well frequently with sealing method for blocking as described in above-mentioned patent searching, that is, wearing the drop of concrete floor The steel pipe that draws water is put into well, at well head(Typically in bottom plate lower position)Flange and gate valve are set, and sealing is closed when blocking Gate valve, the steel pipe that draws water of excision gate valve upper end, substantial amounts of standard is not only needed using underplate concrete by its environmental sealing, this method Tubing, difficulty of construction is larger, needs professional plumber's construction, and the concrete bottom plate at the position is thickeied downwards, changes bottom plate knot Structure, it adds additional construction cost.
The content of the invention
The technical problem to be solved in the present invention is, for deficiencies of the prior art, there is provided a kind of base pit dewatering Well wears concrete of basement bottom plate closure sealing construction processing method, and basement bottom board dewatering well uses double-vane ring sealing steel bushing Pipe, it is good to be inserted directly into progress sealing closure, plugging dewatering well construction is simple, water-stagnating effect in precipitation well head.
The present invention is that technical scheme is used by solving above-mentioned technical problem:
Base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method, comprises the following steps:
S1, make sealing steel sleeve;
S2, pour basement bottom board blinding concrete;
S3, after pouring basement bottom board blinding concrete, before construction of waterproof layer and concrete floor reinforcing bar colligation, The dewatering well filter pipe being higher by more than basement bottom board mat surface is cut off, in water-stopping steel outside of sleeve lower end winding pitch fiber crops Silk, and shut with cement mortar stuff up a crack, the sealing steel sleeve for winding Bituminous hemp fiber is placed in dewatering well filter pipe;Sealing Twice water-proof wing-ring, water-stopping steel cannula tip absolute altitude are higher by basement bottom board top surface 400mm, sealing up and down for welding on the outside of steel sleeve Steel sleeve lower end and dewatering well filter pipe lap of splice 600mm;
S4, in mounted water-stopping steel ferrule boot and basement bottom board junction with 1:2 cement mortar plugs are real, and surrounding is smeared Into arc-shaped, basement bottom board bedding plane construction of waterproof layer is carried out, pours pea gravel concreten fish tail and waterproof layer;
S5, colligation concrete floor reinforcing bar, continue precipitation;
S6, basement bottom board concrete is poured, continue precipitation;
S7, dewatering well terminate precipitation one by one;
S8, closure dewatering well.
By such scheme, the size of sealing steel sleeve is φ 273mm × 6mm in the step S3.
By such scheme, upper and lower twice water-proof wing ring width 200mm in the step S3, upper track water-proof wing-ring is away from basement bottom Plate top surface 100mm, lower road water-proof wing-ring is away from basement bottom board bottom surface 150mm.
By such scheme, in the step S5 when concrete floor reinforcing bar meets sealing steel pipe socket, concrete floor reinforcing bar Bypassed from periphery, at the same it is another plus four with diameter reinforcing bar, bend about 200mm with diameter reinforcing bar one end and welded with sealing steel pipe socket, The other end is horizontal and horizontal length is no less than 1.0m.
By such scheme, when it is determined that during closure dewatering well in the step S8, first under basement bottom board top surface at 80mm Sealing steel sleeve is cut off, filled with dewatering well dry powder inserts to sealing steel sleeve lower port position, then with basement bottom Plate is filled up to being poured onto under basement bottom board top surface at 80mm with the microdilatancy concrete of label, is welded with 6mm thickness sealing steel sleeve lamina tectis, Finally poured with C30 microdilatancy concretes flat.
By such scheme, dewatering well dry powder inserts is cement in the step S8:Sand is 1:1 mixture.
The operation principle of the present invention:After sole plate concrete bed course is poured, before construction of waterproof layer, by water-stopping steel outside of sleeve Lower end winds Bituminous hemp fiber, inserts in downcast well pipe, with cement mortar plug reality sealing steel sleeve surrounding and smears into arc-shaped;Then Construction waterproof layer, assembling reinforcement, until pouring underplate concrete;Basement construction is complete can stop precipitation when, using sand, water Mud, microdilatancy concrete block to dewatering well, effectively carry out sealing closure to dewatering well.
Compared with prior art, the beneficial effects of the invention are as follows:
1st, the present invention uses double-vane ring sealing steel sleeve, inserts the construction in precipitation well head as the closure of dewatering well sealing and arranges Apply, well head plugging structure is simple, scientific and reasonable, safe and reliable, water-stagnating effect is good, can adaptively descend the different constructions of chamber base very well Precipitation requirement during operating mode, solve the problems, such as that the valve in documents 1, water suction steel pipe and sole plate concrete do not combine very well It is wrapped in water check valve in backfill layer, after long-time, because of pipe fitting corrosion, the problem of well head infiltration risk is present;
2nd, the gap filling Bituminous hemp fiber and cement between dewatering well and steel sleeve, that is, blocked steel sleeve and dewatering well Between gap, secure sealing steel sleeve again, be easy to the installation of sealing steel sleeve and the construction of concrete floor, solve pair The problem of being difficult to reach well head sealing and waterproof requirement than the connection between the steel sleeve in file 2 and precipitation well head;
Double water-proof wing-rings, pipe on Bituminous hemp fiber, sealing steel sleeve between 3 while utilization sealing steel sleeve and dewatering well The multiple measures of preventing water collective effects such as interior filling concrete, that is, solve the precipitation demand in concrete floor work progress, and very well Ground, which solves, to be terminated to wear concrete floor dewatering well sealing closure problem during precipitation, and is had very with basement bottom board bed course waterproof layer It is good to combine, the construction of waterproof layer is not influenceed, solves that seal ring section in documents 3 is more, process is more, construction is complicated, need to also be The problem of doughnut-shaped steel plate waterstop is set on raft foundation, also solves steel cylinder working pit of being backbreak in documents 4, adds basis Quantities, and sealing steel cylinder is combined untight problem with pipe well.
Brief description of the drawings
Fig. 1 is that dewatering well well head sealing of the present invention blocks double-vane ring sealing steel sleeve processing dimension figure;
Dewatering well wears concrete bottom plate water stop construction method figure when Fig. 2 is precipitation state construction of bottom plates of the present invention;
Dewatering well wears concrete bottom plate water stop construction method figure when Fig. 3 terminates precipitation shut-in well for the present invention;
In figure, 1, sealing steel sleeve, 2, dewatering well filter pipe, 3, Bituminous hemp fiber, 4, cement mortar, 5, basement bottom board pad Layer, 6, waterproof layer, 7, concrete floor reinforcing bar, 8, dewatering well dry powder inserts, 9, microdilatancy concrete, 10, sealing steel sleeve top cover Plate, 11, C30 microdilatancy concretes, 12, upper water-proof wing-ring, 13, lower water-proof wing-ring.
Embodiment
The present invention is described in detail with reference to the accompanying drawings and examples.
Base pit dewatering well of the present invention wears concrete of basement bottom plate closure sealing construction processing method, including as follows Step:Making sealing steel sleeve 1 → pour basement bottom board blinding concrete → cutting bedding plane dewatering well filter pipe 2, sealing The lower end of steel sleeve 1 twines interior insertion dewatering well filter pipe 2 after Bituminous hemp fiber 3, and shuts → basement bottom board with the stuff up a crack of cement mortar 4 Bedding plane waterproof layer 6 is constructed → colligation concrete floor reinforcing bar 7, continues precipitation → pour basement bottom board concrete, continue precipitation → Dewatering well terminates precipitation → closure dewatering well one by one.
Specific workflow is as follows:
S1, make sealing steel sleeve 1:According to the sealing steel bushing of the double-vane ring for being used for the closure of dewatering well sealing shown in Fig. 1 The processing dimension of pipe 1 makes sealing steel sleeve 1(φ273mm×6mm);
S2, pour the concrete of basement bottom board bed course 5;
S3, after the concrete of basement bottom board bed course 5 is poured, waterproof layer 6 construct and the colligation of concrete floor reinforcing bar 7 it Before, the dewatering well filter pipe 2 being higher by more than the surface of basement bottom board bed course 5 is cut off, wound in the outside lower end of sealing steel sleeve 1 Bituminous hemp fiber 3, and shut with the stuff up a crack of cement mortar 4(Sealing is wiped one's face), the sealing steel sleeve 1 for winding Bituminous hemp fiber 3 is laid In dewatering well filter pipe 2;Twice water-proof wing-ring, water-proof wing ring width 200mm, weld seam will up and down for the welding of the outside of sealing steel sleeve 1 It is full, must not seamed crazing line, upper water-proof wing-ring 12 is away from basement bottom board top surface 100mm, and lower road water-proof wing-ring 13 is away from basement Bottom plate bottom surface 150mm, the elevation of top of sealing steel sleeve 1 are higher by basement bottom board top surface 400mm, the lower end of sealing steel sleeve 1 and drop The lap of splice 600mm of well filter pipe 3;
S4, in the mounted root of sealing steel sleeve 1 and basement bottom board junction with 1:2 cement mortar 4 fill in reality, surrounding Arc-shaped is smeared into, basement bottom board bedding plane waterproof layer 6 is carried out and constructs, pour pea gravel concreten fish tail and waterproof layer;
S5, colligation concrete floor reinforcing bar 7, continue precipitation:When concrete floor reinforcing bar 7 meets sealing steel pipe socket 1, coagulation Native baseplate reinforcing bar 7 is bypassed from periphery, while separately adds four with diameter reinforcing bar, and about 200mm and sealing are bent with diameter reinforcing bar one end Steel pipe socket 1 welds, and horizontal length horizontal with the diameter reinforcing bar other end is no less than 1.0m;
S6, basement bottom board concrete is poured, continue precipitation;
S7, dewatering well terminate precipitation one by one;
S8, closure dewatering well:When it is determined that closure dewatering well when, first under basement bottom board top surface at 80mm by sealing steel bushing Pipe 1 is cut off, with the cement mixed:Sand is 1:1 dewatering well dry powder inserts 8 is filled to the lower port position of sealing steel sleeve 1, Filled up again with basement bottom board with the microdilatancy concrete 9 of label to being poured onto under basement bottom board top surface at 80mm, be welded with 6mm thickness and stop Water steel sleeve lamina tecti 10, finally poured with C30 microdilatancies concrete 11 flat.
The above-described right model for being only presently preferred embodiments of the present invention, the present invention can not being limited with this certainly Enclose, dimensions length when especially constructing can be changed according to different basement bottom board demands adapt to optimum state completely, therefore The equivalence changes made according to scope of the present invention patent, still belong to protection scope of the present invention.

Claims (5)

1. base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method, it is characterised in that including following step Suddenly:
S1, make sealing steel sleeve;
S2, pour basement bottom board blinding concrete;
S3, after pouring basement bottom board blinding concrete, before construction of waterproof layer and concrete floor reinforcing bar colligation, by height The dewatering well filter pipe excision gone out more than basement bottom board mat surface, Bituminous hemp fiber is wound in water-stopping steel outside of sleeve lower end, The sealing steel sleeve for winding Bituminous hemp fiber is placed in dewatering well filter pipe;The welding of water-stopping steel outside of sleeve up and down stop by twice Hydrofoil ring, upper and lower twice water-proof wing ring width 200mm, upper track water-proof wing-ring is away from basement bottom board top surface 100mm, lower road water-proof wing-ring Away from basement bottom board bottom surface 150mm;Water-stopping steel cannula tip absolute altitude is higher by basement bottom board top surface 400mm, under sealing steel sleeve End and dewatering well filter pipe lap of splice 600mm;
S4, in mounted water-stopping steel ferrule boot and basement bottom board junction with 1:2 cement mortar plugs are real, and surrounding smears into circle Arcuation, basement bottom board bedding plane construction of waterproof layer is carried out, pours pea gravel concreten fish tail and waterproof layer;
S5, colligation concrete floor reinforcing bar, continue precipitation;
S6, basement bottom board concrete is poured, continue precipitation;
S7, dewatering well terminate precipitation one by one;
S8, closure dewatering well.
2. base pit dewatering well according to claim 1 wears concrete of basement bottom plate closure sealing construction processing method, its It is characterised by, the size of sealing steel sleeve is φ 273mm × 6mm in the step S3.
3. base pit dewatering well according to claim 1 wears concrete of basement bottom plate closure sealing construction processing method, its It is characterised by, in the step S5 when concrete floor reinforcing bar meets sealing steel pipe socket, concrete floor reinforcing bar bypasses from periphery, It is simultaneously another to add four with diameter reinforcing bar, welded with diameter reinforcing bar one end bending 200mm with sealing steel pipe socket, the other end is in horizontal Shape and horizontal length is no less than 1.0m.
4. base pit dewatering well according to claim 1 wears concrete of basement bottom plate closure sealing construction processing method, its Be characterised by, in the step S8 when it is determined that closure dewatering well when, first under basement bottom board top surface at 80mm by sealing steel bushing Pipe cut off, filled with dewatering well dry powder inserts to sealing steel sleeve lower port position, then with basement bottom board with label Microdilatancy concrete is filled up to being poured onto under basement bottom board top surface at 80mm, is welded with 6mm thickness sealing steel sleeve lamina tectis, is finally used C30 Microdilatancy concrete pours flat.
5. base pit dewatering well according to claim 4 wears concrete of basement bottom plate closure sealing construction processing method, its It is characterised by, dewatering well dry powder inserts is cement in the step S8:Sand is 1:1 mixture.
CN201610377009.3A 2016-05-31 2016-05-31 Base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method Active CN105951859B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610377009.3A CN105951859B (en) 2016-05-31 2016-05-31 Base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610377009.3A CN105951859B (en) 2016-05-31 2016-05-31 Base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method

Publications (2)

Publication Number Publication Date
CN105951859A CN105951859A (en) 2016-09-21
CN105951859B true CN105951859B (en) 2018-04-10

Family

ID=56908350

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610377009.3A Active CN105951859B (en) 2016-05-31 2016-05-31 Base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method

Country Status (1)

Country Link
CN (1) CN105951859B (en)

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836251A (en) * 2017-02-24 2017-06-13 中国十七冶集团有限公司 A kind of new pre-buried deformation joint anti-seepage structure of the pipe well borehole wall and its construction method
CN107100181A (en) * 2017-05-09 2017-08-29 黄坤坤 " being cheated in hole " two grades of relay precipitation systems and its method for blocking
CN109680698A (en) * 2017-10-18 2019-04-26 五冶集团上海有限公司 It is a kind of to block precipitation tube well construction method with pipe cap
CN109736355B (en) * 2019-01-19 2020-09-25 杭州联纵规划建筑设计院有限公司 Reverse construction method basement construction method in factory building transformation
CN110468862B (en) * 2019-09-06 2024-06-21 宁波市轨道交通集团有限公司建设分公司 Plugging structure for precipitation wellhead of subway station
CN112982461A (en) * 2019-12-14 2021-06-18 浙江建腾建设有限公司 Pipe well precipitation combined reducing steel sleeve plugging construction method
CN111608171A (en) * 2020-05-27 2020-09-01 中国一冶集团有限公司 Sandbar underground soft base pipe, well precipitation anti-floating pipe pile structure and construction method
CN112302714A (en) * 2020-10-23 2021-02-02 中国建筑第八工程局有限公司 Dewatering well sealing system and construction method thereof
CN112411588A (en) * 2020-11-10 2021-02-26 上海建工七建集团有限公司 Water seepage prevention device for dewatering well and construction method
CN112832279B (en) * 2021-01-05 2022-10-21 江苏凯伦建材股份有限公司 Waterproof structure and method for dewatering well of underground foundation pit
CN114427233B (en) * 2022-03-01 2024-07-26 中国建筑第八工程局有限公司 Dewatering wellhead plugging device and construction method thereof
CN115217163A (en) * 2022-06-06 2022-10-21 上海建工七建集团有限公司 Water drainage structure of basement bottom plate and construction method of basement bottom plate
CN115369900B (en) * 2022-08-12 2024-06-11 山西四建集团有限公司 Comprehensive atrial backfill dewatering well sealing method
CN115182371A (en) * 2022-08-24 2022-10-14 中建七局(上海)有限公司 Plugging structure of dewatering pipe well and construction method thereof
CN116695757A (en) * 2023-06-20 2023-09-05 中国十七冶集团有限公司 Foundation plate dewatering well plugging method based on rich pressure-bearing cement soil

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4260334A (en) * 1976-02-11 1981-04-07 Kelley Contract Dewatering Company Ground dewatering system
CN202124865U (en) * 2011-06-22 2012-01-25 南通海洲建设集团有限公司 Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN203145029U (en) * 2013-04-02 2013-08-21 中国建筑第七工程局有限公司 Plugging structure for deep foundation pit dewatering well
CN203188225U (en) * 2013-04-23 2013-09-11 中建八局第二建设有限公司 Novel dewatering-well sealing structure
CN103526766A (en) * 2013-10-12 2014-01-22 中建八局第三建设有限公司 Method for plugging relief well of deep foundation pit
CN204266220U (en) * 2014-11-24 2015-04-15 中国水利水电第十四工程局有限公司 A kind of plugging device of precipitation well in foundation pit

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4260334A (en) * 1976-02-11 1981-04-07 Kelley Contract Dewatering Company Ground dewatering system
CN202124865U (en) * 2011-06-22 2012-01-25 南通海洲建设集团有限公司 Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN203145029U (en) * 2013-04-02 2013-08-21 中国建筑第七工程局有限公司 Plugging structure for deep foundation pit dewatering well
CN203188225U (en) * 2013-04-23 2013-09-11 中建八局第二建设有限公司 Novel dewatering-well sealing structure
CN103526766A (en) * 2013-10-12 2014-01-22 中建八局第三建设有限公司 Method for plugging relief well of deep foundation pit
CN204266220U (en) * 2014-11-24 2015-04-15 中国水利水电第十四工程局有限公司 A kind of plugging device of precipitation well in foundation pit

Also Published As

Publication number Publication date
CN105951859A (en) 2016-09-21

Similar Documents

Publication Publication Date Title
CN105951859B (en) Base pit dewatering well wears concrete of basement bottom plate closure sealing construction processing method
CN102797266B (en) Well sealing waterproof construction method for dewatering well
CN107620312A (en) High hydraulic pressure precipitation well construction and hydrostatic slip casting method for blocking in a kind of Metro station excavation
CN107387123A (en) The construction method of pressure grouting leak stopping is carried out for shield duct piece piece Seepage
CN110725341B (en) Basement outer wall embedded sleeve and pipeline gap leakage treatment method
CN104929143B (en) A kind of bottom of foundation ditch dewatering well shut-in well method
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN105019404B (en) A kind of construction method of sealing rod and its water sealing structure and water sealing structure
CN102926770A (en) Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas
CN209339169U (en) A kind of precipitation well in foundation pit plugging device
CN109519150A (en) One kind being directed to the biggish plugging dewatering well device and method of water yield
CN106522252A (en) Seepage-proofing blocking mechanism and method for deep foundation pit raft dewatering well
CN107859064A (en) A kind of prefabricated piping lane is connected waterproof construction and construction method with cast-in-place piping lane
CN104895118A (en) Underground diaphragm wall internal corner position piping plug structure and grouting processing method thereof
CN108331026A (en) A kind of prefabricated assembling type reinforced concrete inspection shaft and its construction method
CN108166532A (en) A kind of groutable underground continuous wall connector and its construction method
CN105178342B (en) Precipitation well casing and method for blocking reserved hole of foundation pit through precipitation well casing
CN106522959A (en) Steel-structure waterproof jointing plate of well wall and construction process of steel-structure waterproof jointing plate
CN116857008B (en) Composite drilling method for mine water deep storage and ground drainage
CN203768925U (en) Seal device for dewatering well in foundation pit
CN206385557U (en) The water-impervious plugging mechanism of dewatering well on deep basal pit raft plate
CN109555140A (en) Foundation pit and Tunnel Base spring pump drainage method for blocking and device
CN209603062U (en) Change the concentrative seepage plugging structure that dynamic water is hydrostatic in gallery
CN209040133U (en) Well-covering device for dewatering well suitable for rich groundwater region
CN209444310U (en) A kind of plugging dewatering well structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant