CN105928669A - Flange connection leakage early warning device - Google Patents
Flange connection leakage early warning device Download PDFInfo
- Publication number
- CN105928669A CN105928669A CN201610252909.5A CN201610252909A CN105928669A CN 105928669 A CN105928669 A CN 105928669A CN 201610252909 A CN201610252909 A CN 201610252909A CN 105928669 A CN105928669 A CN 105928669A
- Authority
- CN
- China
- Prior art keywords
- flange
- leakage
- early warning
- buffer tank
- metal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01M—TESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
- G01M3/00—Investigating fluid-tightness of structures
- G01M3/02—Investigating fluid-tightness of structures by using fluid or vacuum
- G01M3/26—Investigating fluid-tightness of structures by using fluid or vacuum by measuring rate of loss or gain of fluid, e.g. by pressure-responsive devices, by flow detectors
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Flanged Joints, Insulating Joints, And Other Joints (AREA)
Abstract
本发明涉及一种法兰连接泄漏预警装置,其特征在于:它包括法兰密封系统和泄漏保护预警系统;所述法兰密封系统主要由一对金属卡箍构成,所述金属卡箍为半圆环形,其内侧开设有截面为矩形的凹槽,所述一对金属卡箍相互配合将法兰的边缘密封卡住;所述泄漏保护预警系统包括缓冲罐,缓冲罐上设有压力表,其底部设有球形阀,压力表上还连接有一个报警装置;所述缓冲罐通过泄漏介质排放通道与一个金属卡箍连通连接。该装置能够应用于高温、高压、震动等复杂工况,长期保持良好的密封性,有效的防止法兰的泄漏,能够实时的对法兰的泄漏情况进行监测,在泄漏发生以后有预警装置预警,以提示人员撤离,并有缓冲罐作为泄漏的缓冲为人员撤离争取时间。
The invention relates to a flange connection leakage early warning device, which is characterized in that it includes a flange sealing system and a leakage protection early warning system; the flange sealing system is mainly composed of a pair of metal clamps, and the metal clamps are semicircular It is ring-shaped, and a groove with a rectangular cross-section is opened on the inner side, and the pair of metal clamps cooperate with each other to seal and hold the edge of the flange; the leakage protection early warning system includes a buffer tank, and a pressure gauge is provided on the buffer tank. A spherical valve is provided at the bottom, and an alarm device is connected to the pressure gauge; the buffer tank is communicated with a metal clamp through a leakage medium discharge channel. The device can be applied to complex working conditions such as high temperature, high pressure, vibration, etc. It can maintain good sealing performance for a long time, effectively prevent the leakage of the flange, and can monitor the leakage of the flange in real time. After the leakage occurs, there will be an early warning device. , to prompt personnel to evacuate, and a buffer tank is used as a buffer for leakage to buy time for personnel evacuation.
Description
技术领域 technical field
本发明涉及法兰的密封结构领域,具体涉及一种法兰连接泄漏预警装置。 The invention relates to the field of flange sealing structures, in particular to a flange connection leakage warning device.
背景技术 Background technique
法兰密封结构因其易拆装的优点被广泛的应用于石油化工。据统计一个大型石油化工厂中年产30万亿吨乙烯的五套主要装置、六套配套装置和七个辅助车间的静密封点数以万计。要对全厂区的重点部位法兰进行泄漏的保护和监测靠人力和增强巡逻是不合适的。由于化工厂处理的很多流体是易燃、易爆、有毒或腐蚀性的工作介质,而且通常有压力和温度,一旦发生泄漏将引起物质流失和能量损耗,造成环境污染,生产不能正常进行,增加非计划维修和停工,甚至危及人体健康与生命安全等后果。传统的法兰连接系统中螺栓受到的是拉伸载荷,而在高温条件下螺栓会产生应力松弛效应。传统的螺栓连接在高温、高压、震动等复杂的工况下很容易发生松动或预紧力不足而发生泄漏,且传统的法兰连接结构在泄漏发生以后很难进行监测和预警。 The flange sealing structure is widely used in petrochemical industry because of its easy disassembly and assembly. According to statistics, there are tens of thousands of static sealing points in five sets of main devices, six sets of supporting devices and seven auxiliary workshops with an annual output of 30 trillion tons of ethylene in a large petrochemical plant. It is not appropriate to rely on manpower and enhanced patrols to protect and monitor the leakage of flanges in key parts of the entire plant. Because many fluids handled by chemical plants are flammable, explosive, toxic or corrosive working media, and usually have pressure and temperature, once leakage occurs, it will cause material loss and energy loss, resulting in environmental pollution, and production cannot be carried out normally, increasing Unplanned maintenance and downtime, even endangering human health and life safety and other consequences. In the traditional flange connection system, the bolts are subjected to tensile loads, and the bolts will produce stress relaxation effects under high temperature conditions. Traditional bolted connections are prone to loosening or insufficient pre-tightening force and leakage under complex working conditions such as high temperature, high pressure, and vibration, and traditional flange connection structures are difficult to monitor and give early warning after leakage occurs.
发明内容 Contents of the invention
针对上述技术问题,本发明的目的在于提供一种法兰连接泄漏预警装置,该装置能够应用于高温、高压、震动等复杂工况,长期保持良好的密封性,有效的防止法兰的泄漏,能够实时的对法兰的泄漏情况进行监测,在泄漏发生以后有预警装置预警,以提示人员撤离,并有缓冲罐作为泄漏的缓冲为人员撤离争取时间。 In view of the above technical problems, the purpose of the present invention is to provide a flange connection leakage warning device, which can be applied to complex working conditions such as high temperature, high pressure, vibration, etc., maintain good sealing performance for a long time, and effectively prevent flange leakage. It can monitor the leakage of the flange in real time. After the leakage occurs, there will be an early warning device to remind personnel to evacuate, and a buffer tank will be used as a buffer for leakage to buy time for personnel to evacuate.
为实现上述目的,本发明所采取的技术方案是: For realizing above-mentioned purpose, the technical scheme that the present invention takes is:
一种法兰连接泄漏预警装置,其特征在于:它包括法兰密封系统和泄漏保护预警系统; A flange connection leakage early warning device is characterized in that it includes a flange sealing system and a leakage protection early warning system;
所述法兰密封系统主要由一对金属卡箍构成,所述金属卡箍为半圆环形,其内侧开设有截面为矩形的凹槽,所述一对金属卡箍相互配合将法兰的边缘密封卡住;所述法兰的上法兰盘和下法兰盘的表面周向分布有一圈定深盲孔,所述一对金属卡箍上设有与定深盲孔相对应的螺栓孔,螺栓孔内拧有定深螺栓,定深螺栓端头抵紧定深盲孔底部;所述金属卡箍内侧凹槽底部设有两个周向布置的矩形截面槽,一对金属卡箍内侧凹槽底部两个矩形截面槽内均设有O型密封圈,两个O型密封圈分别与上法兰盘和下法兰盘的外侧面挤压密封接触;所述金属卡箍两端的外侧均设有连接板,连接板上开设有螺栓孔,一对金属卡箍之间通过连接板和连接螺栓固定连接;所述金属卡箍两端的端面上分别设有相互匹配的凹槽和凸起,所述凹槽和凸起轴向分布,凹槽和凸起之间还设有条形垫; The flange sealing system is mainly composed of a pair of metal clamps, the metal clamps are semi-circular, and a groove with a rectangular cross-section is opened on the inner side, and the pair of metal clamps cooperate with each other to seal the edge of the flange. stuck; the surface of the upper flange and the lower flange of the flange is circumferentially distributed with a circle of fixed-depth blind holes, and the pair of metal clamps are provided with bolt holes corresponding to the fixed-depth blind holes. A depth-fixing bolt is screwed into the hole, and the end of the depth-fixing bolt presses against the bottom of the blind hole; the bottom of the inner groove of the metal clamp is provided with two circumferentially arranged rectangular cross-section grooves, and a pair of inner grooves of the metal clamp There are O-rings in the two rectangular cross-section grooves at the bottom, and the two O-rings are respectively in contact with the outer sides of the upper flange and the lower flange for extrusion and sealing; the outer sides of the two ends of the metal clamp are provided with There is a connecting plate with bolt holes, and a pair of metal clamps are fixedly connected through the connecting plate and connecting bolts; the end faces of the two ends of the metal clamps are respectively provided with matching grooves and protrusions. The above-mentioned grooves and protrusions are axially distributed, and there is also a strip pad between the grooves and the protrusions;
所述泄漏保护预警系统包括缓冲罐,缓冲罐上设有压力表,其底部设有球形阀,压力表上还连接有一个报警装置;所述缓冲罐通过泄漏介质排放通道与法兰密封系统中的一个金属卡箍连通连接。 The leakage protection early warning system includes a buffer tank, a pressure gauge is provided on the buffer tank, a spherical valve is provided at the bottom of the buffer tank, and an alarm device is connected to the pressure gauge; the buffer tank is connected to the flange sealing system through the leakage medium discharge channel A metal clamp connected through the connection.
所述球形阀为电子开关球形阀,压力表为电子压力表,并且两者之间通过数据线或无线电连接。 The spherical valve is an electronic switch spherical valve, the pressure gauge is an electronic pressure gauge, and the two are connected through a data line or a radio.
本发明所取得的有益效果为:本发明中的装置能够应用于高温、高压、震动等复杂工况,长期保持良好的密封性,有效的防止法兰的泄漏,能够实时的对法兰的泄漏情况进行监测,在泄漏发生以后有预警装置预警,以提示人员撤离,并有缓冲罐作为泄漏的缓冲为人员撤离争取时间。其中金属卡箍上用于预紧的定深螺栓受到压缩载荷而非传统的拉伸载荷,而一般高温螺栓在压缩条件下的松弛量小于拉伸条件下的松弛量,与传统法兰密封结构相比提高了螺栓的使用寿命。法兰的螺栓定位孔定深盲孔,未开通孔,增强了法兰的强度和刚度,并可采用大直径螺栓连接,这样可使螺栓承载力降低的同时,增加垫片压紧力,保证其连接紧密性。金属卡箍内侧安装有作为第二重密封的O型密封圈,二级密封结构使法兰的密封效果更好,减少非计划的维修与停工次数。预警装置可以快速准确的对泄漏做出反应,能够及时的预警以提示人员撤离。 The beneficial effects obtained by the present invention are: the device in the present invention can be applied to complex working conditions such as high temperature, high pressure, vibration, etc., maintain good sealing performance for a long time, effectively prevent the leakage of the flange, and can detect the leakage of the flange in real time After the leakage occurs, there will be an early warning device to warn the personnel to evacuate, and a buffer tank will be used as a buffer for the leakage to buy time for the personnel to evacuate. Among them, the fixed-depth bolts used for pre-tightening on the metal clamp are subjected to compressive loads instead of traditional tensile loads, and the relaxation of general high-temperature bolts under compression conditions is less than that under tension conditions, which is different from the traditional flange sealing structure. Compared with the service life of the bolt is improved. The bolt positioning hole of the flange is a blind hole with a fixed depth and no through hole, which enhances the strength and rigidity of the flange, and can be connected by large-diameter bolts, which can reduce the bearing capacity of the bolts and increase the pressing force of the gasket to ensure its connection. Tightness. The inner side of the metal clamp is installed with an O-ring as the second seal. The secondary seal structure makes the sealing effect of the flange better and reduces the number of unplanned maintenance and shutdowns. The early warning device can respond to the leakage quickly and accurately, and can give early warning in time to prompt personnel to evacuate.
附图说明 Description of drawings
图1为本发明的整体结构示意图。 Figure 1 is a schematic diagram of the overall structure of the present invention.
图2为本发明中法兰部分的俯视示意图。 Fig. 2 is a schematic top view of the flange part in the present invention.
图3为本发明中法兰密封系统结构示意图(即截面示意图)。 Fig. 3 is a structural schematic diagram (ie, a cross-sectional schematic diagram) of the flange sealing system in the present invention.
图中:1—连接板、2—金属卡箍、3—定深螺栓、4—防松垫片、5—上法兰盘、6—O型密封圈、7—矩形截面槽、8—泄漏介质排放通道、9—缓冲罐、10—压力表、11—报警装置、12—球形阀、13—垫片、14—下法兰盘、15—条形垫、16—连接螺栓、17—定深盲孔。 In the figure: 1—Connecting plate, 2—Metal clamp, 3—Fixed depth bolt, 4—Anti-loosening gasket, 5—Upper flange, 6—O-ring, 7—Rectangular section groove, 8—Leakage Medium discharge channel, 9—buffer tank, 10—pressure gauge, 11—alarm device, 12—spherical valve, 13—gasket, 14—lower flange, 15—strip pad, 16—connecting bolt, 17—fixed Deep blind holes.
具体实施方式 detailed description
为了更好地理解本发明,下面结合实施例和附图对本发明的技术方案做进一步的说明(如图1-3所示)。 In order to better understand the present invention, the technical solutions of the present invention will be further described below in conjunction with the embodiments and accompanying drawings (as shown in Figures 1-3).
一种法兰连接泄漏预警装置,它包括法兰密封系统和泄漏保护预警系统; A flange connection leakage early warning device, which includes a flange sealing system and a leakage protection early warning system;
所述法兰密封系统主要由一对金属卡箍2构成,所述金属卡箍2为半圆环形,其内侧开设有截面为矩形的凹槽(即金属卡箍2截面为“[”型),所述一对金属卡箍2相互配合将法兰(所述法兰由上法兰盘5、下法兰盘14以及垫片13组成)的边缘密封卡住(即将法兰的边缘完整的密封包裹住);所述法兰的上法兰盘5和下法兰盘14的表面(即上法兰盘5的上表面、下法兰盘14的下表面)周向分布有一圈定深盲孔17,所述一对金属卡箍2上设有与定深盲孔17相对应的螺栓孔(即数量、位置、大小相对应),螺栓孔内拧有定深螺栓3(定深螺栓3与金属卡箍2之间设有防松垫片4),定深螺栓3端头抵紧定深盲孔17底部(所述的上法兰盘5与下法兰盘14的法兰盘表面加工有定深盲孔17,在金属卡箍2卡紧上法兰盘5与下法兰盘14后通过定深螺栓3来为垫片13提供预紧力,形成第一级密封);所述金属卡箍2内侧凹槽底部设有两个周向布置的矩形截面槽7,一对金属卡箍2内侧凹槽底部两个矩形截面槽7内均设有O型密封圈6,两个O型密封圈6分别与上法兰盘5和下法兰盘14的外侧面挤压密封接触(所述金属卡箍2内侧安装有O型密封圈6在安装完成后挤压上法兰盘5与下法兰盘14的法兰盘外侧以形成第二级密封);所述金属卡箍2两端的外侧均设有连接板1,连接板1上开设有螺栓孔,一对金属卡箍2之间通过连接板1和连接螺栓16固定连接;所述金属卡箍2两端的端面上分别设有相互匹配的凹槽和凸起,所述凹槽和凸起轴向分布,凹槽和凸起之间还设有条形垫15(即凹槽内设有条形垫15,用于密封); The flange sealing system is mainly composed of a pair of metal clamps 2, the metal clamps 2 are semi-circular, and a groove with a rectangular cross section is opened on the inner side (that is, the cross section of the metal clamp 2 is "[" type), The pair of metal clamps 2 cooperate with each other to seal and hold the edge of the flange (the flange is composed of the upper flange 5, the lower flange 14 and the gasket 13) (that is, the edge of the flange is completely sealed. wrapped); the surface of the upper flange 5 and the lower flange 14 of the flange (that is, the upper surface of the upper flange 5 and the lower surface of the lower flange 14) is distributed with a circle of deep blind holes in the circumferential direction 17. The pair of metal clamps 2 are provided with bolt holes corresponding to the fixed depth blind holes 17 (that is, corresponding to the number, position and size), and the fixed depth bolts 3 are screwed in the bolt holes (the fixed depth bolts 3 and the An anti-loosening gasket 4 is provided between the metal clamps 2), and the ends of the depth-fixing bolts 3 are pressed against the bottom of the depth-fixing blind hole 17 (the flange surface processing of the upper flange 5 and the lower flange 14 is There is a fixed depth blind hole 17, and after the metal clamp 2 clamps the upper flange 5 and the lower flange 14, the gasket 13 is provided with a pretightening force through the fixed depth bolt 3 to form a first-level seal); The bottom of the inner groove of the metal clamp 2 is provided with two circumferentially arranged rectangular cross-sectional grooves 7, and a pair of metal clamps 2 are provided with O-rings 6 in the two rectangular cross-sectional grooves 7 at the bottom of the inner groove. The O-shaped seal ring 6 is in extrusion-seal contact with the outer sides of the upper flange 5 and the lower flange 14 respectively (the O-ring 6 is installed on the inner side of the metal clamp 2, and the upper flange 5 is extruded after the installation is completed. and the outer side of the flange of the lower flange 14 to form a second-level seal); the outer sides of the two ends of the metal clamp 2 are provided with a connecting plate 1, and a bolt hole is opened on the connecting plate 1, and a pair of metal clamps 2 The connecting plate 1 and the connecting bolt 16 are fixedly connected between them; the end faces of the two ends of the metal clip 2 are respectively provided with matching grooves and protrusions, and the grooves and protrusions are axially distributed, and the grooves and protrusions There is also a strip pad 15 between them (that is, a strip pad 15 is provided in the groove for sealing);
所述泄漏保护预警系统包括缓冲罐9,缓冲罐9上设有压力表10,其底部设有球形阀12,压力表10上还连接有一个报警装置11;所述缓冲罐9通过泄漏介质排放通道8与法兰密封系统中的一个金属卡箍2连通连接(即泄漏介质通过泄漏介质排放通道8进入缓冲罐9,缓冲罐9通过球形阀12泄压)。 The leakage protection early warning system includes a buffer tank 9, the buffer tank 9 is provided with a pressure gauge 10, and the bottom thereof is provided with a spherical valve 12, and the pressure gauge 10 is also connected with an alarm device 11; the buffer tank 9 is discharged through the leakage medium. The channel 8 communicates with a metal clamp 2 in the flange sealing system (that is, the leakage medium enters the buffer tank 9 through the leakage medium discharge channel 8, and the buffer tank 9 releases pressure through the ball valve 12).
所述球形阀12为电子开关球形阀,压力表10为电子压力表,并且两者之间通过数据线或无线电连接。 The spherical valve 12 is an electronic switch spherical valve, the pressure gauge 10 is an electronic pressure gauge, and the two are connected by a data line or a radio.
一种法兰连接泄漏预警装置的使用原理:1、压力表10将测得的压力经数据线或无线电的形式传递到报警装置11,当压力表10测得的缓冲罐9内的压力达到报警装置的预设值时,报警装置启动并响起警报声以通知人员撤离。2、当压力表10测得的缓冲罐9内的压力达到预设泄放值时会触发球形阀12的开关打开,对缓冲罐9进行泄压。 The principle of use of a flange connection leakage warning device: 1. The pressure gauge 10 transmits the measured pressure to the alarm device 11 in the form of a data line or radio, and when the pressure in the buffer tank 9 measured by the pressure gauge 10 reaches the alarm When the preset value of the device is reached, the alarm device will be activated and the alarm will sound to notify personnel to evacuate. 2. When the pressure in the buffer tank 9 measured by the pressure gauge 10 reaches the preset relief value, the switch of the spherical valve 12 will be triggered to release the pressure of the buffer tank 9 .
以上说明仅为本发明的应用实施例而已,当然不能以此来限定本发明之权利范围,因此依本发明申请专利范围所作的等效变化,仍属本发明的保护范围。 The above descriptions are only application examples of the present invention, and of course the scope of rights of the present invention cannot be limited by this. Therefore, equivalent changes made according to the patent scope of the present invention still belong to the protection scope of the present invention.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610252909.5A CN105928669A (en) | 2016-04-22 | 2016-04-22 | Flange connection leakage early warning device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610252909.5A CN105928669A (en) | 2016-04-22 | 2016-04-22 | Flange connection leakage early warning device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN105928669A true CN105928669A (en) | 2016-09-07 |
Family
ID=56839616
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610252909.5A Pending CN105928669A (en) | 2016-04-22 | 2016-04-22 | Flange connection leakage early warning device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105928669A (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107355611A (en) * | 2017-08-11 | 2017-11-17 | 慧感(上海)物联网科技有限公司 | A kind of online collecting mechanism of hoop type flange sealing leak |
| CN109340565A (en) * | 2018-11-09 | 2019-02-15 | 中国科学院合肥物质科学研究院 | Tank Replacement Device for Liquid Nitrogen Automatic Filling System |
| CN113834841A (en) * | 2020-06-23 | 2021-12-24 | 核工业西南物理研究院 | Liquid nitrogen thermal shock testing device for butt welding seam of metal pipeline |
| CN116907768A (en) * | 2023-08-04 | 2023-10-20 | 三峡金沙江川云水电开发有限公司 | Pressure gas pitcher advances people's door flange leak hunting structure |
| CN118564742A (en) * | 2024-07-30 | 2024-08-30 | 昆山艾森世华光电材料有限公司 | A wafer cleaning tank water inlet and outlet sealing assembly |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN203880274U (en) * | 2014-05-13 | 2014-10-15 | 武汉工程大学 | High-temperature pipeline flange |
| CN104101470A (en) * | 2014-06-25 | 2014-10-15 | 武汉工程大学 | Pipeline flange test system |
| CN104567747A (en) * | 2015-01-20 | 2015-04-29 | 武汉工程大学 | High-temperature flange leakage monitoring device based on laser rangefinder |
| CN204420390U (en) * | 2015-01-27 | 2015-06-24 | 武汉工程大学 | A kind of novel flange sealing configuration |
| CN105004493A (en) * | 2015-07-17 | 2015-10-28 | 武汉工程大学 | Leakage-detecting device for bolted flange connection system |
| CN105069208A (en) * | 2015-07-29 | 2015-11-18 | 武汉工程大学 | Method for evaluating tightness of high-temperature flange connection system |
| CN105423018A (en) * | 2016-01-08 | 2016-03-23 | 武汉工程大学 | Leakage detecting device of high-temperature flange connecting system |
-
2016
- 2016-04-22 CN CN201610252909.5A patent/CN105928669A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN203880274U (en) * | 2014-05-13 | 2014-10-15 | 武汉工程大学 | High-temperature pipeline flange |
| CN104101470A (en) * | 2014-06-25 | 2014-10-15 | 武汉工程大学 | Pipeline flange test system |
| CN104567747A (en) * | 2015-01-20 | 2015-04-29 | 武汉工程大学 | High-temperature flange leakage monitoring device based on laser rangefinder |
| CN204420390U (en) * | 2015-01-27 | 2015-06-24 | 武汉工程大学 | A kind of novel flange sealing configuration |
| CN105004493A (en) * | 2015-07-17 | 2015-10-28 | 武汉工程大学 | Leakage-detecting device for bolted flange connection system |
| CN105069208A (en) * | 2015-07-29 | 2015-11-18 | 武汉工程大学 | Method for evaluating tightness of high-temperature flange connection system |
| CN105423018A (en) * | 2016-01-08 | 2016-03-23 | 武汉工程大学 | Leakage detecting device of high-temperature flange connecting system |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107355611A (en) * | 2017-08-11 | 2017-11-17 | 慧感(上海)物联网科技有限公司 | A kind of online collecting mechanism of hoop type flange sealing leak |
| CN107355611B (en) * | 2017-08-11 | 2022-10-11 | 慧感(上海)物联网科技有限公司 | Clamp formula flange seal leaks on-line collection mechanism |
| CN109340565A (en) * | 2018-11-09 | 2019-02-15 | 中国科学院合肥物质科学研究院 | Tank Replacement Device for Liquid Nitrogen Automatic Filling System |
| CN113834841A (en) * | 2020-06-23 | 2021-12-24 | 核工业西南物理研究院 | Liquid nitrogen thermal shock testing device for butt welding seam of metal pipeline |
| CN116907768A (en) * | 2023-08-04 | 2023-10-20 | 三峡金沙江川云水电开发有限公司 | Pressure gas pitcher advances people's door flange leak hunting structure |
| CN118564742A (en) * | 2024-07-30 | 2024-08-30 | 昆山艾森世华光电材料有限公司 | A wafer cleaning tank water inlet and outlet sealing assembly |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105673966A (en) | Leakage protection and monitoring system for high-temperature flange | |
| CN105928669A (en) | Flange connection leakage early warning device | |
| CN201531594U (en) | Constant stress seal gasket capable of detecting leakage | |
| CN204459547U (en) | A kind of pipeline sealing device | |
| US7004470B2 (en) | Device for a pipe flange seal | |
| EP3049699B1 (en) | Metallic flange connection gasket | |
| CN207049512U (en) | Online plugging device for pipelines without firing | |
| CN205639960U (en) | High temperature flange joint structure | |
| CN209164874U (en) | A pipeline compensator fixing device | |
| CN204254095U (en) | Gasketless double seal flange | |
| CN205298899U (en) | Anti-static flange jumper | |
| CN206861104U (en) | Gas pipeline gasket | |
| CN203629758U (en) | Tool specialized for leakage test of corrugated tube | |
| CN209026188U (en) | A Novel Double-layer Sealed Early Warning Structure | |
| JP2011252577A (en) | Union joint and seal structure of union joint | |
| CN205534821U (en) | a plugging tool | |
| CN101692353B (en) | Leak Detectable Constant Stress Gaskets | |
| CN220435714U (en) | Oil gas warehousing and transportation pipeline | |
| CN205262696U (en) | Compress tightly load detectable seal assembly | |
| CN214274819U (en) | Metal seal ring gasket with leakage detection function | |
| CN219177136U (en) | Sealing structure for joint of oil delivery pipe | |
| CN112197608A (en) | Expansion plug for water pressure test of condenser cooling pipe and using method thereof | |
| US20140216716A1 (en) | Well cap assembly | |
| CN208041123U (en) | A kind of forging sealing element | |
| CN112681988A (en) | Friction welding type blowout prevention pipeline |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160907 |
|
| RJ01 | Rejection of invention patent application after publication |