CN105927153A - Control supporting frame applied to pile body and pile cap integrated construction for long spiral bored pile - Google Patents

Control supporting frame applied to pile body and pile cap integrated construction for long spiral bored pile Download PDF

Info

Publication number
CN105927153A
CN105927153A CN201610406133.8A CN201610406133A CN105927153A CN 105927153 A CN105927153 A CN 105927153A CN 201610406133 A CN201610406133 A CN 201610406133A CN 105927153 A CN105927153 A CN 105927153A
Authority
CN
China
Prior art keywords
pile
construction
support
pulley
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610406133.8A
Other languages
Chinese (zh)
Inventor
徐其新
徐涵
杨姣
孙鸿林
梁龙标
沈宇浈
江涛
明刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Chang Xin Foundation Works Co Ltd
Original Assignee
Jiangsu Chang Xin Foundation Works Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Chang Xin Foundation Works Co Ltd filed Critical Jiangsu Chang Xin Foundation Works Co Ltd
Priority to CN201610406133.8A priority Critical patent/CN105927153A/en
Publication of CN105927153A publication Critical patent/CN105927153A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/02Drilling rigs characterized by means for land transport with their own drive, e.g. skid mounting or wheel mounting
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/003Supports for the drilling machine, e.g. derricks or masts adapted to be moved on their substructure, e.g. with skidding means; adapted to drill a plurality of wells

Abstract

The invention belongs to the technical field of building construction foundation drilling tool accessory application, and particularly discloses a control supporting frame applied to pile body and pile cap integrated construction for a long spiral bored pile. The control supporting frame comprises a self-propelled vehicle, an electric distribution operation room, a pulley, a main winch, a support, a machine frame supporting rod and a horizontal head sliding part, wherein the electric distribution operation room, the pulley, the main winch and the support are arranged on the self-propelled vehicle; the two ends of the machine frame supporting rod are connected with the support; and the horizontal head sliding part is arranged on the support. The control supporting frame applied to pile body and pile cap integrated construction for the long spiral bored pile has the beneficial effects that the whole structure is reasonable in design, and the purpose of efficiently and precisely controlling and adjusting a drill rod and a drill bit can be achieved; meanwhile, positioning is firm after adjustment, and construction safety and construction quality stability are effectively guaranteed; the problems that an existing long spiral drilling machine is low in control adjustment efficiency and unstable in whole supporting structure are solved; and the control supporting frame is reasonable in design and meets the stable supporting and efficient adjustment construction requirements, positioning is firm, and therefore raw materials are saved, and production cost is lowered.

Description

It is applied to the control bracing frame of long screw auger drilling deposited pile pile jacking cap integrated construction
Technical field
The invention belongs to construction basis drilling tool accessory applied technical field, it is specifically related to be applied to the control bracing frame of long screw auger drilling deposited pile pile jacking cap integrated construction, the institute's bore position controlling long-spiral drilling machine can be adjusted accurately, it is ensured that construction pouring quality and raising efficiency of construction.
Background technology
Long-spiral drilling machine, it includes hydraulic moving mechanism pile frame and drilling system two parts.Pile frame uses hydraulic walking chassis, and automaticity is high, can walk voluntarily and 360 degree of revolutions, is provided with four hydraulic legs and a walking oil cylinder increases complete machine stability during construction with auxiliary walking and revolution simultaneously, can be transported through by complete machine.Column is folding box column, flange connection, and column uses two pieces high thickness masks and uses large-sized bender brake techniques, is welded with four reinforcements every 60cm and fixes through twice weld seam is welded while inside column, increases column torsion resistant and bending resistant.Column is controlled its landing by two luffing hydraulic jacks.Drilling system includes unit head and drilling tool, and the output shaft of unit head and spiral drill are hollow type, and stake machine uses long spire pore-forming, by drilling rod central canal, concrete or mud can be carried out pump concrete CFG pile driving construction.
In the construction operation of long-spiral drilling machine, for adjusting control drilling rod, the control bracing frame of drill bit is also its important component part, control the fixing of bracing frame, the high efficiency etc. controlling to adjust can directly affect construction quality and the efficiency of construction of long-spiral drilling machine, and the existing control bracing frame for being used in combination with long-spiral drilling machine, it is the most firm to position after adjusting in its structure complicated construction the most greatly and adjusting, thus reduce efficiency and the high standard prescription of perfusion drilling construction operation, when error is bigger need to do over again time, not only reduce construction speed and too increase the consumption of mixed earthy raw materials, and this is current urgently to be resolved hurrily.
Therefore, based on the problems referred to above, the present invention provides the control bracing frame being applied to long screw auger drilling deposited pile pile jacking cap integrated construction.
Summary of the invention
Goal of the invention: it is an object of the invention to provide the control bracing frame being applied to long screw auger drilling deposited pile pile jacking cap integrated construction, solve existing long-spiral drilling machine and control that regulated efficiency is low and integrated support structure supports instable phenomenon, its reasonable in design, satisfied stablizing supports and efficiently adjusts construction requirement, positions firm and then has saved raw material, reduced production cost.
Technical scheme: the present invention is provided to the control bracing frame of long screw auger drilling deposited pile pile jacking cap integrated construction, including automatic walking car, and it is arranged on the electric distribution operating room on automatic walking car, pulley, and it is arranged on the main turning hoisting machine on automatic walking car and between electric distribution operating room, pulley, and be arranged on automatic walking car and be positioned at the support outside pulley, and two ends connect the frame support bar of support, and the sleeping head saddle being arranged on support respectively.
The technical program, described pulley is three head pulleys.
The technical program, described support is barrel-type supporting structure.
Compared with prior art, the present invention is applied to having the beneficial effects that of the control bracing frame of long screw auger drilling deposited pile pile jacking cap integrated construction: 1, overall construction design is reasonable, can realize efficiently, control accurately to adjust drilling rod and the purpose of drill bit, to position after adjusting firm simultaneously, effective guarantee construction operation safety and construction quality stability;2, solve existing long-spiral drilling machine and control that regulated efficiency is low and integrated support structure supports instable phenomenon, its reasonable in design, satisfied stablizing supports and efficiently adjusts construction requirement, positions firm and then has saved raw material, reduced production cost (this control support frame structure is practical in the construction of the most luxuriant railway).
Accompanying drawing explanation
Fig. 1 is the structural representation controlling bracing frame being applied to long screw auger drilling deposited pile pile jacking cap integrated construction of the present invention;
Wherein, in figure, sequence number mark is as follows: 1-automatic walking car, 2-electric distribution operating room, the main turning hoisting machine of 3-, 4-pulley, 5-support, 6-frame support bar, 7-crouch head saddle.
Detailed description of the invention
Below in conjunction with the accompanying drawings and specific embodiment, it is further elucidated with the present invention.
The control bracing frame for long screw auger drilling deposited pile pile jacking cap integrated construction as shown in Figure 1, including automatic walking car 1, and it is arranged on the electric distribution operating room 2 on automatic walking car 1, pulley 4, and it is arranged on the main turning hoisting machine 3 on automatic walking car 1 and between electric distribution operating room 2, pulley 4, and be arranged on automatic walking car 1 and be positioned at the support 5 outside pulley 4, and two ends connect the frame support bar 6 of support 5, and the sleeping head saddle 7 being arranged on support 5 respectively.
Further preferred, pulley 4 is three head pulleys, and construction adjusts when controlling operation, and it is with main turning hoisting machine 3 and is connected rope and controls the position of sleeping head saddle 7 accurately, and the position after adjusting can be carried out stable location, and then ensure the quality of construction perfusion bore operation;Support 5 is barrel-type supporting structure, rational in infrastructure and install convenient, and it is used in combination with frame support bar 6, sleeping head saddle 7 is formed stable location and supports, it is ensured that angle that drilling rod and drill bit adjust and construction drill precision.
Embodiment
Further such as Fig. 1, when adjusting operation, utilize electric distribution operating room 2 to control main turning hoisting machine 3 counterclockwise or to turn clockwise, main turning hoisting machine 3 counterclockwise or turns clockwise and then is driven across the connection rope of pulley 4 and control sleeping head saddle 7 and rise or fall, and finally realizes accurate, efficient and stable control.
The above is only the preferred embodiment of the present invention, it is noted that for those skilled in the art, under the premise without departing from the principles of the invention, it is also possible to make some improvement, and these improvement also should be regarded as protection scope of the present invention.

Claims (3)

1. it is applied to the control bracing frame of long screw auger drilling deposited pile pile jacking cap integrated construction, it is characterised in that: include certainly
Dynamic walking car (1), and it is arranged on the electric distribution operating room (2) on automatic walking car (1), pulley (4), and be arranged on automatic walking car (1) and be positioned at the main turning hoisting machine (3) between electric distribution operating room (2), pulley (4), and be arranged on automatic walking car (1) and be positioned at the support (5) in pulley (4) outside, and two ends connect the frame support bar (6) of support (5), and the sleeping head saddle (7) being arranged on support (5) respectively.
The control bracing frame being applied to long screw auger drilling deposited pile pile jacking cap integrated construction the most according to claim 1, it is characterised in that: described pulley (4) is three head pulleys.
The control bracing frame being applied to long screw auger drilling deposited pile pile jacking cap integrated construction the most according to claim 1, it is characterised in that: described support (5) is barrel-type supporting structure.
CN201610406133.8A 2016-06-12 2016-06-12 Control supporting frame applied to pile body and pile cap integrated construction for long spiral bored pile Pending CN105927153A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610406133.8A CN105927153A (en) 2016-06-12 2016-06-12 Control supporting frame applied to pile body and pile cap integrated construction for long spiral bored pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610406133.8A CN105927153A (en) 2016-06-12 2016-06-12 Control supporting frame applied to pile body and pile cap integrated construction for long spiral bored pile

Publications (1)

Publication Number Publication Date
CN105927153A true CN105927153A (en) 2016-09-07

Family

ID=56833588

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610406133.8A Pending CN105927153A (en) 2016-06-12 2016-06-12 Control supporting frame applied to pile body and pile cap integrated construction for long spiral bored pile

Country Status (1)

Country Link
CN (1) CN105927153A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115324051A (en) * 2022-04-13 2022-11-11 中交第一航务工程局有限公司 Multifunctional auxiliary frame matched with cast-in-place pile drilling machine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1458383A (en) * 2003-06-18 2003-11-26 钱奂云 Multifunctional drill machine and its construction method
JP2005336702A (en) * 2004-02-27 2005-12-08 Hiromi Kuwahata Ground excavator
CN201546613U (en) * 2009-12-01 2010-08-11 河南省三力机械制造有限公司 Long spiral drilling machine
CN201851002U (en) * 2010-11-20 2011-06-01 威海市海泰起重机械有限公司 PLC (Programmable Logic Controller) controlled frequency conversion pile driver
CN202117556U (en) * 2011-03-01 2012-01-18 何庆林 Auger driller for moulding concrete piles with different depth and shapes
CN206053839U (en) * 2016-06-12 2017-03-29 江苏昌鑫基础工程有限公司 It is applied to the control bracing frame of long screw auger drilling deposited pile pile jacking cap integrated construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1458383A (en) * 2003-06-18 2003-11-26 钱奂云 Multifunctional drill machine and its construction method
JP2005336702A (en) * 2004-02-27 2005-12-08 Hiromi Kuwahata Ground excavator
CN201546613U (en) * 2009-12-01 2010-08-11 河南省三力机械制造有限公司 Long spiral drilling machine
CN201851002U (en) * 2010-11-20 2011-06-01 威海市海泰起重机械有限公司 PLC (Programmable Logic Controller) controlled frequency conversion pile driver
CN202117556U (en) * 2011-03-01 2012-01-18 何庆林 Auger driller for moulding concrete piles with different depth and shapes
CN206053839U (en) * 2016-06-12 2017-03-29 江苏昌鑫基础工程有限公司 It is applied to the control bracing frame of long screw auger drilling deposited pile pile jacking cap integrated construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115324051A (en) * 2022-04-13 2022-11-11 中交第一航务工程局有限公司 Multifunctional auxiliary frame matched with cast-in-place pile drilling machine

Similar Documents

Publication Publication Date Title
CN107988861B (en) Subway work complete set of equipments and method of laying a railway track
US20090000218A1 (en) Land rig
CN107988860A (en) A kind of rubber-tyred subway change paving machine and its become across method
CN207620714U (en) A kind of caterpillar track travelling both arms multi-angle jumbolter
CN101660357A (en) Machinery for installing light partition battens
CN103982200B (en) Slide rail Mobile steel mould trolley in tunneling boring
CN203546728U (en) Improved installation fixing device of top-down steel pipe column
CN105507833A (en) Derrick lifting type coiled tubing operation device
CN106436796B (en) A kind of construction of diaphragm wall equipment and construction method
CN105927154A (en) Spiral drilling and pouring device applied to pile top and pile cap integrated construction
CN105927153A (en) Control supporting frame applied to pile body and pile cap integrated construction for long spiral bored pile
CN107654191A (en) A kind of caterpillar track travelling both arms multi-angle jumbolter
CN206128158U (en) Underground continuous wall construction equipment
CN108798511A (en) A kind of crawler type hangs brill all-in-one machine
CN205154016U (en) Many rigs drill jumbo
CN206053839U (en) It is applied to the control bracing frame of long screw auger drilling deposited pile pile jacking cap integrated construction
CN102937004B (en) Coordinated hoisting control system of foldable type drilling machine base
CN105862732A (en) PLC-controlled (programmable logic controller controlled) integrated construction apparatus for long-spiral cast-in-place bored pile top cap
CN107964841B (en) A kind of rubber-tyred subway changes paving machine and method for automatically leveling
CN105862733A (en) Novel long spiral drilling hole cast-in-situ pile top and cap integrated construction device
CN208024369U (en) A kind of multifunctional tunnel arch Mobile workbench
CN104612154B (en) Afterburning self tapping stake stake machine
CN105888576A (en) Drilling assembly for integrated construction of long spiral bored perfusion pile top and cap
CN106320341A (en) Multifunctional installation equipment for steel pipe column
CN106437504A (en) All-orientation deep hole drilling machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160907