CN105908675A - Combined type emergency flood control wall between near, deep and large sub-docks - Google Patents

Combined type emergency flood control wall between near, deep and large sub-docks Download PDF

Info

Publication number
CN105908675A
CN105908675A CN201610381998.3A CN201610381998A CN105908675A CN 105908675 A CN105908675 A CN 105908675A CN 201610381998 A CN201610381998 A CN 201610381998A CN 105908675 A CN105908675 A CN 105908675A
Authority
CN
China
Prior art keywords
steel
control wall
flood
plain concrete
shaped steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610381998.3A
Other languages
Chinese (zh)
Inventor
何毅
彭再勇
李志军
崔玉国
王秋林
邵阳
赵康林
陈旺
邢永辉
邓彪
张伟
曾珂
柯斌
李社伟
田丽君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Erchu Co Ltd
Original Assignee
China Railway Tunnel Group Erchu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Erchu Co Ltd filed Critical China Railway Tunnel Group Erchu Co Ltd
Priority to CN201610381998.3A priority Critical patent/CN105908675A/en
Publication of CN105908675A publication Critical patent/CN105908675A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes

Abstract

The invention discloses a combined type emergency flood control wall between near, deep and large sub-docks. The combined type emergency flood control wall between the near, deep and large sub-docks structurally comprises a lower gravity type plain concrete wall, plain concrete, top pre-buried connection pieces, pre-buried plates, bolts, anchor bars, an upper steel structure flood control wall body, shape steel stand columns, steel angle frameworks, steel panels, lower anchor plates, stiffening plates, connecting bolts, a channel position steel structure flood control wall body, bottom ground beams and shape steel inclined struts. The simple combined type emergency flood control wall is adopted, pipe segment prefabricating in the flood season is achieved, noninterference of floating transportation is achieved, the combined type emergency flood control wall is safe and is guaranteed, and potential safety hazards to pipe segment floating transportation and prefabrication in the flood season are eliminated.

Description

One closes on combined emergency flood-control wall between deep big sub-depressed place
Technical field
The present invention relates to one and close on combined emergency flood-control wall between deep big sub-depressed place.
Background technology
At present, in immersed tube prefabrication of tube section is constructed, main is prefabricated place with dry-docking, dry-docking need to experience excavation, prefabricated, pour water, the complex working condition such as fitting-out, dock entrance are abolished, recover, backfill, owing to taking up an area, scale is big, engineering cost is high, seepage prevention system requires tight, big on duration impact, and dry-docking scale is still based on small-sized, medium-sized, and it is longer to cross river/river/seabed immersed tube tunnel, pipeline section quantity is many, needs the most prefabricated, transportation by driving, sinking, docking.
But, section floating, sinking are all selected flood season, Nanchang district persistently nearly half a year in flood season, and sequence of construction mostly is prefabricated limit, limit transportation by driving, so that, closing on sub-depressed place still in prefabrication phase flood season temporarily.Using long tube back-up sand or earth dam flood-control wall traditionally, long construction period, recovery utilization rate are low, civilized construction is poor.
Summary of the invention
The problem that it is an object of the invention to exist for existing flood-control wall, one is provided to be used for closing on combined emergency flood-control wall between deep big sub-depressed place, between two sub-depressed places, prefabrication of tube section, transportation by driving form line production, it does not interfere with each other, being effectively reduced the potential safety hazard that antithetical phrase in flood season depressed place is brought, Steel Structure Installation progress is fast, and steel recovery utilization rate is higher, remarkable in economical benefits, civilized construction is guaranteed.
Of the present invention close on combined emergency flood-control wall structure between deep big sub-depressed place and include: bottom gravity type plain concrete wall, plain concrete, top built-in connection, embedded board, bolt, steel construction flood-control wall, bottom grade beam, shaped steel diagonal brace at dowel, steel superstructure flood-control wall, shaped steel column, angle steel skeleton, steel facing, lower anchor slab, stiffener, connecting bolt, passage;
Described bottom gravity type plain concrete wall includes plain concrete, top built-in connection, and top built-in connection includes embedded board, bolt, dowel;Dowel and embedded board two-sided welding;
Described bottom gravity type plain concrete wall steel superstructure installed above flood-control wall;Its structure includes shaped steel column, horizontal corner steel skeleton, steel facing, lower anchor slab, stiffener, bolt, shaped steel column is connected by groove welding with lower anchor slab, stiffener, lower anchor slab is bolted with embedded board, and steel superstructure flood-control wall and bottom gravity type plain concrete wall are formed by bolt and be effectively connected.
Longitudinally disposed 2 road angle steel skeletons, angle steel skeleton is connected with Type of Welding with shaped steel column connecting portion, the every 5 butt head two root type steel column wing plate borings of shaped steel column, hole dimension is consistent with termination, steel facing both sides bore size, shaped steel column is bolted with steel facing, and steel facing and angle steel skeleton are by being welded to connect;
At described passage, steel construction flood-control wall is arranged at the roof panel docking sidewalk mouth of depressed place;
Outside at described passage, the structure of steel construction flood-control wall is identical with steel superstructure flood-control wall, also at passage, steel construction flood-control wall shaped steel column both sides increase by four root type steel diagonal braces, and shaped steel diagonal brace is welded to connect with shaped steel column, steel facing.
The invention has the beneficial effects as follows: use a kind of relatively simple combined emergency flood-control wall, it is achieved that in flood season, prefabrication of tube section, transportation by driving do not interfere with each other, safety is guaranteed, eliminates flood season to section floating, the prefabricated potential safety hazard brought.
Accompanying drawing explanation
Fig. 1 is that one of the present invention closes on combined emergency flood-control wall side view between deep big sub-depressed place;
Fig. 2 is that one of the present invention closes on combined emergency flood-control wall front view between deep big sub-depressed place;
Fig. 3 is that one of the present invention closes on gravity type plain concrete wall side view in combined emergency flood-control wall bottom between deep big sub-depressed place;
Fig. 4-1 closes on gravity type plain concrete wall top in combined emergency flood-control wall bottom between deep big sub-depressed place for one of the present invention and connects connector top view;
Fig. 4-2 closes on gravity type plain concrete wall top in combined emergency flood-control wall bottom between deep big sub-depressed place for one of the present invention and connects connector side view;
Fig. 5 is that one of the present invention closes on combined emergency flood-control wall steel superstructure flood-control wall front view between deep big sub-depressed place;
Fig. 6 is that one of the present invention closes on combined emergency flood-control wall steel superstructure flood-control wall side view between deep big sub-depressed place;
Fig. 7-1 closes on combined emergency flood-control wall steel superstructure flood-control wall and bottom gravity type plain concrete wall connector full-page proof side view between deep big sub-depressed place for one of the present invention;
Fig. 7-2 closes on combined emergency flood-control wall steel superstructure flood-control wall and bottom gravity type plain concrete wall connector full-page proof top view between deep big sub-depressed place for one of the present invention;
Fig. 8-1 for one of the present invention close between deep big sub-depressed place flood-control wall front view at combined emergency flood-control wall passage,
8-2 is that one of the present invention closes between deep big sub-depressed place flood-control wall top view at combined emergency flood-control wall passage;
8-3 is that one of the present invention closes between deep big sub-depressed place flood-control wall side view at combined emergency flood-control wall passage;
Shown in figure: 1-bottom gravity type plain concrete wall, 101-plain concrete, 102-top built-in connection, 10201-embedded board, 10202-bolt, 10203-dowel;2-steel superstructure flood-control wall, 201-shaped steel column, 202-angle steel skeleton, 203-steel facing, anchor slab under 204-, 205-stiffener, 206-connecting bolt;Steel construction flood-control wall at 3-passage, grade beam bottom 301-, 302-shaped steel diagonal brace.
Detailed description of the invention
Below in conjunction with the accompanying drawings and specific embodiment describe in detail the present invention.
Close on combined emergency flood-control wall structure between deep big sub-depressed place described in invention to include: bottom gravity type plain concrete wall, plain concrete, top built-in connection, embedded board, bolt, steel construction flood-control wall, bottom grade beam, shaped steel diagonal brace at dowel, steel superstructure flood-control wall, shaped steel column, angle steel skeleton, steel facing, lower anchor slab, stiffener, connecting bolt, passage;
Described bottom gravity type plain concrete wall includes plain concrete, top built-in connection, and top built-in connection includes embedded board, bolt, dowel;Dowel and embedded board two-sided welding;
Described bottom gravity type plain concrete wall steel superstructure installed above flood-control wall;Its structure includes shaped steel column, horizontal corner steel skeleton, steel facing, lower anchor slab, stiffener, bolt, shaped steel column is connected by groove welding with lower anchor slab, stiffener, lower anchor slab is bolted with embedded board, and steel superstructure flood-control wall and bottom gravity type plain concrete wall are formed by bolt and be effectively connected.
Longitudinally disposed 2 road angle steel skeletons, angle steel skeleton is connected with Type of Welding with shaped steel column connecting portion, the every 5 butt head two root type steel column wing plate borings of shaped steel column, hole dimension is consistent with termination, steel facing both sides bore size, shaped steel column is bolted with steel facing, and steel facing and angle steel skeleton are by being welded to connect;
At described passage, steel construction flood-control wall is arranged at the roof panel docking sidewalk mouth of depressed place;
Outside at described passage, the structure of steel construction flood-control wall is identical with steel superstructure flood-control wall, and steel construction flood-control wall shaped steel column both sides increase by four root type steel diagonal braces at passage, and shaped steel diagonal brace is welded to connect with shaped steel column, steel facing.
Concrete construction method is as follows:
Step one: as it is shown on figure 3, install, fixing top built-in connection 102, Guan Mo, pour bottom gravity type plain concrete wall 1 plain concrete 101.
Bottom gravity type plain concrete wall 1 is trapezoidal xoncrete structure, long 264m, high 2m, bottom width 2.2m, top width 0.5m.
Bottom gravity type plain concrete wall 1 includes plain concrete 101, top built-in connection 102.C25 plain concrete preferably used by plain concrete 101;Top built-in connection 102 includes embedded board 10201, bolt (containing nut, packing ring) 10202, dowel 10203.
In top built-in connection 102, embedded board 10201 preferably uses Q235-B, t=16mm steel plate, and M16*60 preferably used by bolt (containing nut, packing ring) 10202, and dowel 10203 is preferably with HRB400 φ 16 reinforcing bar.
In step (), as shown in Figure 4, dowel 10203 and embedded board 10201 two-sided welding, bolt 10202 is installed in advance to embedded board 10201, it is simple to later stage and steel superstructure flood-control wall, 2 times anchor slabs 204 were connected.
Step (two): install steel superstructure flood-control wall 2, first mount type steel column 201, weld horizontal angle steel skeleton 202, install, weld steel facing 203.
As shown in Figure 5,6, steel superstructure flood-control wall 2 includes shaped steel column 201, horizontal corner steel skeleton 202, steel facing 203, lower anchor slab 204, stiffener 205, bolt 206.
H175 shaped steel preferably used by described shaped steel column 201, high 2m, longitudinally arrange one every 1.5m, as shown in Figure 7, shaped steel column 201 is connected by groove welding with lower anchor slab 204, stiffener 205, lower anchor slab 204 and embedded board 10201 is connected by bolt 10202, and steel superstructure flood-control wall 2 is passed through bolt 10202 and formed and be effectively connected with bottom gravity type plain concrete wall 1.Described lower anchor slab 204 preferably uses Q235-B, t=16mm steel plate, and Q235-B, t=10mm steel plate preferably used by stiffener 205, and weld seam grade presses second-order weld.
As shown in Figure 5,6, longitudinally disposed 2 road angle steel skeletons 202, angle steel skeleton 202 preferably uses L125*80*10 angle steel, angle steel skeleton 202 to be connected with Type of Welding with shaped steel column 201 connecting portion.Steel facing 203 monolithic size: 2m height * 6m length, the every 5 butt head two root type steel column 201 wing plate borings of shaped steel column 201, hole dimension is consistent with termination, steel facing 203 both sides bore size, shaped steel column 201 is connected by bolt 206 with steel facing 203, and steel facing 203 and angle steel skeleton 202 are by being welded to connect.Described steel facing 203 is preferably with Q235-B, t=10mm steel plate, and bolt 206 is preferably with M14*40, and single shaped steel column 20101 is holed 22 holes.Welding all performs according to second-order weld.
So far, steel superstructure flood-control wall 2 forms one with bottom gravity type plain concrete wall 1.
Step (three): when flood situation has change, according to actual needs, pours grade beam 301, installs steel construction flood-control wall 3 at passage.
As shown in Figure 8, at passage, steel construction flood-control wall 3 is constructed with reference to steel superstructure flood-control wall 2, and steel construction flood-control wall shaped steel column both sides increase by four root type steel diagonal braces at passage, and shaped steel diagonal brace is welded to connect with shaped steel column, steel facing.
Difference is: 1. shaped steel column 201 is highly increased;2. angle steel skeleton 202 increases to 4;3. steel facing 203 adjusts upper and lower 2 pieces of splicings, splicing position groove welding;4. bottom gravity type plain concrete wall 1 is adjusted to bottom grade beam 301, and grade beam 301 structure is: 1m width * 0.5m is deep, preferably uses C25 plain concrete, and grade beam 301 top built-in connection 102 is identical with gravity type plain concrete wall 1 top, bottom built-in connection 102.5. at passage, steel construction flood-control wall 3 shaped steel column 201 both sides increase shaped steel diagonal brace 302, described shaped steel diagonal brace 302 one 4, preferably use H175 shaped steel, shaped steel diagonal brace 302 to be welded to connect with shaped steel column 201, steel facing 203.
Above-described embodiment is a specific embodiment of the present invention; the present invention is not limited to above-mentioned embodiment; made any conspicuously improved to above-mentioned embodiment of those skilled in the art or change, all without beyond the design of the present invention and the protection domain of claims.

Claims (1)

1. one kind is closed on combined emergency flood-control wall between deep big sub-depressed place, it is characterized in that: described in close on combined emergency flood-control wall structure between deep big sub-depressed place and include: bottom gravity type plain concrete wall, plain concrete, top built-in connection, embedded board, bolt, steel construction flood-control wall, bottom grade beam, shaped steel diagonal brace at dowel, steel superstructure flood-control wall, shaped steel column, angle steel skeleton, steel facing, lower anchor slab, stiffener, connecting bolt, passage;
Described bottom gravity type plain concrete wall includes plain concrete, top built-in connection, and top built-in connection includes embedded board, bolt, dowel;Dowel and embedded board two-sided welding;
Described bottom gravity type plain concrete wall steel superstructure installed above flood-control wall;Its structure includes shaped steel column, horizontal corner steel skeleton, steel facing, lower anchor slab, stiffener, bolt, shaped steel column is connected by groove welding with lower anchor slab, stiffener, lower anchor slab is bolted with embedded board, and steel superstructure flood-control wall and bottom gravity type plain concrete wall are formed by bolt and be effectively connected;
Longitudinally disposed 2 road angle steel skeletons, angle steel skeleton is connected with Type of Welding with shaped steel column connecting portion, the every 5 butt head two root type steel column wing plate borings of shaped steel column, hole dimension is consistent with termination, steel facing both sides bore size, shaped steel column is bolted with steel facing, and steel facing and angle steel skeleton are by being welded to connect;
At described passage, steel construction flood-control wall is arranged at the roof panel docking sidewalk mouth of depressed place;
Outside at described passage, the structure of steel construction flood-control wall is identical with steel superstructure flood-control wall, also at passage, steel construction flood-control wall shaped steel column both sides increase by four root type steel diagonal braces, and shaped steel diagonal brace is welded to connect with shaped steel column, steel facing.
CN201610381998.3A 2016-06-02 2016-06-02 Combined type emergency flood control wall between near, deep and large sub-docks Pending CN105908675A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610381998.3A CN105908675A (en) 2016-06-02 2016-06-02 Combined type emergency flood control wall between near, deep and large sub-docks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610381998.3A CN105908675A (en) 2016-06-02 2016-06-02 Combined type emergency flood control wall between near, deep and large sub-docks

Publications (1)

Publication Number Publication Date
CN105908675A true CN105908675A (en) 2016-08-31

Family

ID=56741854

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610381998.3A Pending CN105908675A (en) 2016-06-02 2016-06-02 Combined type emergency flood control wall between near, deep and large sub-docks

Country Status (1)

Country Link
CN (1) CN105908675A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109811721A (en) * 2019-03-25 2019-05-28 国网江苏省电力有限公司扬州供电分公司 A kind of modularization flood control baffle

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201896365U (en) * 2010-06-25 2011-07-13 国网直流工程建设有限公司四川工程建设部 Installing and fixing device for flat plate pre-embedded piece on surface of concrete
CN203729256U (en) * 2013-12-12 2014-07-23 陈志强 Assembled type anti-flood wall
US20150003915A1 (en) * 2012-06-05 2015-01-01 Deron Nettles System and Method for Shoreline Preservation
CN205662895U (en) * 2016-06-02 2016-10-26 中铁隧道集团二处有限公司 Close on emergent flood control wall of combination formula between dark big sub - depressed place

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201896365U (en) * 2010-06-25 2011-07-13 国网直流工程建设有限公司四川工程建设部 Installing and fixing device for flat plate pre-embedded piece on surface of concrete
US20150003915A1 (en) * 2012-06-05 2015-01-01 Deron Nettles System and Method for Shoreline Preservation
CN203729256U (en) * 2013-12-12 2014-07-23 陈志强 Assembled type anti-flood wall
CN205662895U (en) * 2016-06-02 2016-10-26 中铁隧道集团二处有限公司 Close on emergent flood control wall of combination formula between dark big sub - depressed place

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109811721A (en) * 2019-03-25 2019-05-28 国网江苏省电力有限公司扬州供电分公司 A kind of modularization flood control baffle

Similar Documents

Publication Publication Date Title
CN105386408B (en) Deep-water bridge pile foundation construction method
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN205742213U (en) Foundation pit supporting construction
CN105236275B (en) Soil lifting system and soil lifting method for building deep foundation pit construction in narrow zone
CN105133620B (en) Pit supporting construction and its construction method in local flow's modeling shape Muddy Bottoms soil body hole
CN107700366B (en) Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method
CN101338678A (en) Supporting arch hidden digging top-down construction method
CN104372743B (en) Trestle rapid constructing method
CN108589771A (en) One kind having runed underground station increasing layer transfer node construction method
CN102410031B (en) Underground space structure constructed by pile wall construction method
CN106351343A (en) Basement outer wall waterproof protection structure capable of realizing synchronous crossing construction and construction method thereof
CN203684108U (en) Fully-precast assembly type reinforced concrete bridge assembling structure
CN109630162B (en) Method for quickly connecting heavy steel and pipe curtain based on advanced support
CN205662895U (en) Close on emergent flood control wall of combination formula between dark big sub - depressed place
CN106193644B (en) Basement reconstruction structure with raft foundation building
CN105386779B (en) The counterfort method of large underground structure is built in shallow embedding rock stratum
CN207452738U (en) The deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone
CN106978814A (en) A kind of Fabricated Structure for Support of Excavation
CN206816278U (en) The new recyclable supporting steel arch-shelf of horizontal ground settlement and tunnel
CN208183643U (en) A kind of dock structure taking into account large ship and heavy mail mast and hanging
CN105908675A (en) Combined type emergency flood control wall between near, deep and large sub-docks
CN109594581A (en) Cross a river segment pipe structure and its installation method
CN206477341U (en) A kind of foundation pit support system
CN102477716A (en) Application of trestle type beam slab bridge in inland river with beaches at both sides
CN204851265U (en) Bearing structure in work well under high water pressure condition

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160831

WD01 Invention patent application deemed withdrawn after publication