CN105887695A - Steel hoop support system applied to bottom of steel cylinder - Google Patents

Steel hoop support system applied to bottom of steel cylinder Download PDF

Info

Publication number
CN105887695A
CN105887695A CN201610355182.3A CN201610355182A CN105887695A CN 105887695 A CN105887695 A CN 105887695A CN 201610355182 A CN201610355182 A CN 201610355182A CN 105887695 A CN105887695 A CN 105887695A
Authority
CN
China
Prior art keywords
steel
support
hoop
cylinder
steel hoop
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201610355182.3A
Other languages
Chinese (zh)
Inventor
邵凯
张连江
徐波
孙建波
许琳丽
史虎彬
朱武华
冯宝强
杨龙
韩博文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201610355182.3A priority Critical patent/CN105887695A/en
Publication of CN105887695A publication Critical patent/CN105887695A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a steel hoop support system applied to the bottom of a steel cylinder. The steel hoop support system comprises six steel hoops, steel pipe supports, steel support beams and a steel cylinder coffer. The steel hoops cover a steel-pipe composite pile. Each steel hoop comprises two pieces of steel hoop bodies, and buckling plates with drill holes are mounted at two ends of each piece. Rib plates used for fastening the buckling plates are arranged the outer sides, on the backs of the buckling plates, of the steel hoop bodies. Bolts penetrate the drill holes of the buckling plates to lock every two pieces of steel hoop bodies. Holding plates are evenly arranged on rest portions of the steel hoop bodies besides the two ends. Rubber pads are adhered to the inner sides of the steel hoops. A main support frame of the steel support beams is an octagonal support frame internally connected with the steel cylinder coffer. The steel pipe supports are abutted between the outer sides of the steel hoops and separation beams as well as between the outer sides of the steel hoops and the octagonal support frame. The steel hoop support system has the advantages that the steel hoops, the steel pipe supports and the steel support beams can be used in a turnable mode, turnover rate can be increased, operation difficulty of operators can be lowered, and assembly work can be achieved; overall stability of steel members is high, and construction safety is guaranteed.

Description

It is applied to the steel hoop support system of steel bottom of cylinder
Technical field
The invention belongs to bridge technology field, particularly relate to a kind of steel hoop supporter being applied to steel bottom of cylinder System.
Background technology
Non-navigation bridge in the Zhuhai and Macao bridge deep water section of port is designed with embed-type prefabricated pier, and prefabricated pier is altogether There are 68.Pier installation uses prefabricated pier dry method construction technique, and shake heavy steel cylinder, enters it Row draws water and dredging operation, until it reaches pier mounting design absolute altitude.Steel pipe support needs supporting 68 times.
In predetermined scheme, by pouring 600mm thickness concrete cushion, 6 steel pipe composite piles are connected into entirety. When concrete reaches design strength, prop up with steel pipe support and stand in concrete cushion side, by steel cylinder cofferdam with Steel pipe composite pile connects.But long owing to considering mix ship holding time, cause boats and ships to use anxiety, boats and ships Putting into big, work efficiency reduces.
Summary of the invention
The present invention solves the problems referred to above, it is provided that a kind of steel hoop support system, be greatly increased construction efficiency, execute Work degree of progress speed is notable.
The technical solution used in the present invention:
It is applied to the steel hoop support system of steel bottom of cylinder, embraces including six steel being wrapped in outside steel pipe composite pile Hoop, steel pipe support, steel support beam and steel cylinder cofferdam, described steel hoop is divided into 2, and the two ends of every are installed There is the buckle with boring, the gusset reinforcing buckle is set outside the steel hoop at buckle back, is passed by bolt The boring of buckle, by 2 steel hoop lockings, steel hoop removes the remainder at two ends and is uniformly arranged supporting plate, steel Posting rubber blanket inside anchor ear, described steel support beam main support is to connect octagon support, eight limits in steel cylinder cofferdam On shape support, sequentially cutting off beam, octagon every the junction on two limits and the centre position overlap joint on two limits Overlap joint muscle beam straggly between support and partition beam, holds out against with steel pipe support between steel hoop and partition beam and octagon support.
Described steel pipe support and steel hoop contact jaw are provided with c-type supporting plate.
Described steel pipe support and steel support beam are diameter 400mm, the steel pipe of wall thickness 15mm.
The thickness of described rubber blanket is 5mm.
Beneficial effects of the present invention: the application present invention can have enough to meet the need use steel hoop, steel pipe support and steel support beam, Improving its turnover utilization rate, because of the age of concrete, the duration of making is not delayed, and alleviates the operation pressure of mix ship, Simplify workmen's operation easier, it is achieved assembling equalization, steel beam column stability in the large is preferable simultaneously, it is ensured that execute Work safety.
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention.
Fig. 2 is steel hoop structural representation in the present invention.
Wherein: 1-buckle;2-gusset;3-supporting plate;4-steel hoop;5-rubber blanket;6-cuts off beam;7-steel pipe props up Support;8-steel pipe composite pile;9-octagon support;10-muscle beam;11-C type supporting plate;12-steel cylinder cofferdam.
Detailed description of the invention
It is applied to the steel hoop support system of steel bottom of cylinder, including six steel being wrapped in outside steel pipe composite pile 8 Anchor ear 4, steel pipe support 7, steel support beam and steel cylinder cofferdam 12, described steel hoop 4 is divided into 2, every The two ends of steel hoop 4 are provided with the buckle 1 with boring, arrange reinforcing button outside buckle 1 back steel hoop 4 2 steel hoops 4, by bolt through the boring of buckle 1, are locked by the gusset 2 of plate 1, and steel hoop 4 removes The remainder going to two ends is uniformly arranged supporting plate 3, posts rubber blanket 5 inside steel hoop 4, described steel support beam Main support is the octagon support 9 connect in steel cylinder cofferdam 12, sequentially every two on octagon support 9 The centre position overlap joint on the junction on limit and two limits cuts off beam 6, straggly between octagon support 9 and partition beam 6 Overlap joint muscle beam 10, holds out against with steel pipe support 7 between steel hoop 4 and partition beam 6 and octagon support 9.
Described steel pipe support 7 is provided with c-type supporting plate 11 with steel hoop 4 contact jaw.
Described steel pipe support 7 and steel support beam are diameter 400mm, the steel pipe of wall thickness 15mm.
The thickness of described rubber blanket 5 is 5mm.
During use, steel hoop 4 is installed at outside steel pipe composite pile 8, between steel cylinder cofferdam 12 and steel hoop 4 Steel pipe hold out against, reach the purpose of firm steel cylinder cofferdam 12.
Above one embodiment of the present of invention is described in detail, but described content has been only the preferable of the present invention Embodiment, it is impossible to be considered the practical range for limiting the present invention.All according to the present patent application scope made equal Deng change and improvement etc., within all should still belonging to the patent covering scope of the present invention.

Claims (4)

1. it is applied to the steel hoop support system of steel bottom of cylinder, it is characterised in that include that six are wrapped in steel pipe Composite pile (8) steel hoop (4), steel pipe support (7), steel support beam and steel cylinder cofferdam (12) outward, described Steel hoop (4) be divided into 2, the two ends of every steel hoop (4) be provided with boring buckle (1), Outside, buckle (1) back steel hoop (4) arranges the gusset (2) reinforcing buckle (1), is passed by bolt 2 steel hoops (4) are locked by the boring of buckle (1), and the remainder that steel hoop (4) removes two ends is equal The even supporting plate (3) that arranges, posts rubber blanket (5) inside steel hoop (4), the main support of described steel support beam is steel The octagon support (9) connect in cylinder cofferdam (12), sequentially every two limits on octagon support (9) Junction and two limits centre position overlap joint cut off beam (6), octagon support (9) with cut off beam (6) Between overlap joint muscle beam (10) straggly, steel hoop (4) and cut off beam (6) and octagon support (9) between with steel pipe Support (7) to hold out against.
The steel hoop support system being applied to steel bottom of cylinder the most according to claim 1, it is characterised in that Described steel pipe support (7) and steel hoop (4) contact jaw are provided with c-type supporting plate (11).
The steel hoop support system being applied to steel bottom of cylinder the most according to claim 1, it is characterised in that Described steel pipe support (7) and steel support beam are diameter 400mm, the steel pipe of wall thickness 15mm.
The steel hoop support system being applied to steel bottom of cylinder the most according to claim 1, it is characterised in that The thickness of described rubber blanket (5) is 5mm.
CN201610355182.3A 2016-05-25 2016-05-25 Steel hoop support system applied to bottom of steel cylinder Withdrawn CN105887695A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610355182.3A CN105887695A (en) 2016-05-25 2016-05-25 Steel hoop support system applied to bottom of steel cylinder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610355182.3A CN105887695A (en) 2016-05-25 2016-05-25 Steel hoop support system applied to bottom of steel cylinder

Publications (1)

Publication Number Publication Date
CN105887695A true CN105887695A (en) 2016-08-24

Family

ID=56717460

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610355182.3A Withdrawn CN105887695A (en) 2016-05-25 2016-05-25 Steel hoop support system applied to bottom of steel cylinder

Country Status (1)

Country Link
CN (1) CN105887695A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512522A (en) * 2019-07-31 2019-11-29 中铁大桥局集团有限公司 A kind of compartment method and structure for steel boxed cofferdam large volume back cover
CN111501565A (en) * 2020-04-24 2020-08-07 中铁一局集团有限公司 Detachable hoop type bridge support steel pipe connecting device and method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201137151Y (en) * 2007-10-19 2008-10-22 山东高速集团青岛高速公路有限公司 Underwater bottom cover-free concrete case box
CN203429648U (en) * 2013-08-23 2014-02-12 中交第四航务工程勘察设计院有限公司 Large steel cylinder cofferdam structure
CN104727225A (en) * 2015-02-10 2015-06-24 中交一航局第一工程有限公司 Dry method installing construction method for offshore large-tonnage prefabricated abutment
CN204455847U (en) * 2015-02-10 2015-07-08 中交一航局第一工程有限公司 The marine positioning guiding device of the prefabricated pier of large-tonnage
CN204456152U (en) * 2015-02-10 2015-07-08 中交一航局第一工程有限公司 Steel cylinder cofferdam is used in waters viaduct construction
WO2015106679A1 (en) * 2014-01-15 2015-07-23 Cbj (Hong Kong) Ocean Engineering Limited Construction method for fixing hollow column for supporting marine structures and offshore platforms to a seabed
CN205775867U (en) * 2016-05-25 2016-12-07 中交第一航务工程局有限公司 It is applied to the steel hoop support system of steel bottom of cylinder

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201137151Y (en) * 2007-10-19 2008-10-22 山东高速集团青岛高速公路有限公司 Underwater bottom cover-free concrete case box
CN203429648U (en) * 2013-08-23 2014-02-12 中交第四航务工程勘察设计院有限公司 Large steel cylinder cofferdam structure
WO2015106679A1 (en) * 2014-01-15 2015-07-23 Cbj (Hong Kong) Ocean Engineering Limited Construction method for fixing hollow column for supporting marine structures and offshore platforms to a seabed
CN104727225A (en) * 2015-02-10 2015-06-24 中交一航局第一工程有限公司 Dry method installing construction method for offshore large-tonnage prefabricated abutment
CN204455847U (en) * 2015-02-10 2015-07-08 中交一航局第一工程有限公司 The marine positioning guiding device of the prefabricated pier of large-tonnage
CN204456152U (en) * 2015-02-10 2015-07-08 中交一航局第一工程有限公司 Steel cylinder cofferdam is used in waters viaduct construction
CN205775867U (en) * 2016-05-25 2016-12-07 中交第一航务工程局有限公司 It is applied to the steel hoop support system of steel bottom of cylinder

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512522A (en) * 2019-07-31 2019-11-29 中铁大桥局集团有限公司 A kind of compartment method and structure for steel boxed cofferdam large volume back cover
CN111501565A (en) * 2020-04-24 2020-08-07 中铁一局集团有限公司 Detachable hoop type bridge support steel pipe connecting device and method

Similar Documents

Publication Publication Date Title
CN106013172A (en) Double row pile and diagonal brace combined soft soil deep foundation pit supporting structure and construction method
CN201857618U (en) Floating guide platform and steel casing supported drilling platform deepwater pile foundation
CN106894420B (en) Basement construction method for supporting
CN105887695A (en) Steel hoop support system applied to bottom of steel cylinder
CN106869032B (en) A kind of bridge bearing platform constructing tie beam method
CN106120803A (en) Base pit stand construction in the case of artesian water
CN106193644B (en) Basement reconstruction structure with raft foundation building
CN205775867U (en) It is applied to the steel hoop support system of steel bottom of cylinder
CN106223355A (en) A kind of high bearing platform supported on piles in deep water Hold Hoop method has device and the construction method of end steel jacket box
CN211143050U (en) Grouting type underground continuous wall of prefabricated column and wall plate
CN104805828A (en) W-shaped steel sheet pile structure
CN208518679U (en) The supporting construction of template at a kind of shield well construction reserved opening ring beam
CN204040042U (en) A kind of super large ultra-deep support with manually dug piles structure
CN217325078U (en) Bearing platform cofferdam system suitable for bridge pier restoration of existing bridge
CN208965558U (en) Support component, foundation pit outer support system and foundation pit
CN108425374A (en) Complicated sea situation lower band binder dumbbell shape cushion cap steel suspended box cofferdam monolithic construction method
CN207245155U (en) A kind of composite shuttering of aluminium frame bamboo slab rubber
CN208650067U (en) Underground increasing layer excavates new supporting structure
CN204456152U (en) Steel cylinder cofferdam is used in waters viaduct construction
CN108978675B (en) Support assembly, foundation pit outer support system, foundation pit and construction method
CN103343529A (en) Movable steel pipe raft snorkeling over-water construction platform
CN217107041U (en) Underpinning structure for pile foundation in tunnel
CN211472597U (en) Prevention of seepage well lid
CN214697068U (en) Supporting device for suspended over-limit concrete single-beam construction
CN218624255U (en) Roadside reinforcing and supporting system for coal mine small coal pillar mining

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20160824

WW01 Invention patent application withdrawn after publication