CN105844426A - Grid-connected power plant technology supervision used quality assessing data processing method - Google Patents

Grid-connected power plant technology supervision used quality assessing data processing method Download PDF

Info

Publication number
CN105844426A
CN105844426A CN201610223566.XA CN201610223566A CN105844426A CN 105844426 A CN105844426 A CN 105844426A CN 201610223566 A CN201610223566 A CN 201610223566A CN 105844426 A CN105844426 A CN 105844426A
Authority
CN
China
Prior art keywords
scoring
power plant
project
closed loop
supervision
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610223566.XA
Other languages
Chinese (zh)
Inventor
李福兴
顾承昱
姜勇
陈洪兴
陈震
李晔
陈洪涛
袁和林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liandihengxing (nanjing) Information Systems Ltd
State Grid Shanghai Electric Power Co Ltd
East China Power Test and Research Institute Co Ltd
Original Assignee
Liandihengxing (nanjing) Information Systems Ltd
State Grid Shanghai Electric Power Co Ltd
East China Power Test and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liandihengxing (nanjing) Information Systems Ltd, State Grid Shanghai Electric Power Co Ltd, East China Power Test and Research Institute Co Ltd filed Critical Liandihengxing (nanjing) Information Systems Ltd
Priority to CN201610223566.XA priority Critical patent/CN105844426A/en
Publication of CN105844426A publication Critical patent/CN105844426A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Marketing (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a grid-connected power plant technology supervision used quality assessing data processing method which comprises the following steps: 1) building detection items for upcoming summer power consumption peak, closed loop self-detection items as well as corresponding technology supervision quality assessing standards for each item; 2) obtaining technology supervision reports of power plants on the upcoming summer power consumption peak and the technology supervision reports on the closed loop self detections; 3) based on the technology supervision reports of power plants on the upcoming summer power consumption peak and the technology supervision reports on the closed loop self detections, scoring the items respectively according to the technology supervision quality assessing standards so as to obtain the scores for the detection items for upcoming summer power consumption peak and the scores for closed loop self-detection items; 4) obtaining general assessing scores; and 5) listing the scores for the detection items for upcoming summer power consumption peak, the scores for the closed loop self-detection items and the general assessing scores in orders and outputting these lists; Compared to the prior art, the method helps better conduct grid-connected power plant technology supervision and is timely, convenient and through standardized operations.

Description

A kind of quality evaluation data processing method for factory's technical supervision of generating electricity by way of merging two or more grid systems
Technical field
The present invention relates to field of information processing, especially relate to a kind of quality for factory's technical supervision of generating electricity by way of merging two or more grid systems Evaluating data processing method.
Background technology
Power technology supervision is based on the standard of science, utilizes advanced measurement means and management method, to equipment In design, type selecting, manufacture, install, debug, produce as a trial and run, overhaul, stop (standby) use, technological transformation Technical supervision is carried out with power generation overall process and micro-variations Deng power construction;Grasp equipment, material and medium shape The variation tendency of condition, it is judged that its safe coefficient, it is thus possible to take preventive measures, prevents trouble before it happens, is to ensure that electrical network And power equipment safety, reliable, the important means of economical operation, it is lasting, quick, healthy to be that power industry realizes The important guarantee of development.
The more existing information systeies that can realize part technological supervision work function of present electric power enterprise make With, but these systems are owing to lacking a unified planning and effective design and tissue, and between these systems Being the most inaccessible, data mutually can not be linked up and share, and makes an original overall technological supervision work in information Become in change is imperfect.Therefore, in today that current power industry technology develops rapidly, electric power enterprise is in order to suitable Answer the development of technological supervision work, rely solely on traditional labor management and be clearly less to carry out technological supervision work Possible, power construction technical supervision information system is necessary, and by technological supervision work for many years, Have accumulated substantial amounts of technical supervision data to need an information platform and process, the most preferably Information platform is utilized to carry out technical supervision quality evaluation work significant.
Summary of the invention
Defect that the purpose of the present invention is contemplated to overcome above-mentioned prior art to exist and provide a kind of for grid-connected The quality evaluation data processing method of power plant's technical supervision, factory's technical supervision quality evaluation of can preferably generating electricity by way of merging two or more grid systems Work, the advantage such as have that promptness is good, convenience is good and standardization is strong.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of quality evaluation data processing method for factory's technical supervision of generating electricity by way of merging two or more grid systems comprises the following steps:
1) set up summer peak meeting and check project, closed loop self-inspection project and respective items purpose technical supervision quality evaluation Standard;
2) summer peak meeting technical supervision report and the supervision report of closed loop self-checking of each power plant are gathered;
3) according to summer peak meeting technical supervision report and the supervision report of closed loop self-checking of each power plant, supervise by technology Superintend and direct criteria of quality evaluation and carry out the scoring of projects respectively, it is thus achieved that summer peak meeting checks project scoring S1With closed loop self-inspection Project scoring S2
4) overall merit scoring S is obtainedz, meet below equation:
αS1+βS2=Sz
In formula, α, β correspond to summer peak meeting respectively and check project scoring and the weight factor of closed loop self-inspection project scoring;
5) summer peak meeting is checked project scoring, the scoring of closed loop self-inspection project, overall merit scoring order row respectively Row obtain comprehensive evaluation result, and export.
Described step 5) also include: according to step 3) scoring, contrast the technical supervision in projects of each power plant Score value in criteria of quality evaluation, using score value less than standard value respective items purpose technical supervision criteria of quality evaluation as Problem summary report exports.
The value of described α, β is directly proportional with the number in corresponding technical supervision criteria of quality evaluation.
Described summer peak meeting check project with closed loop self-inspection project by the special project corresponding with each specialty in power plant Detection project is constituted, and each specialty in power plant includes that insulation, relay protection, the quality of power supply, electrical measurement are professional, hot Working platform industry, steam turbine, energy-conservation, chemical, environmental protection and metal.
Described overall merit scoring SzAlso include power plant's basic management overall score, described power plant basic management overall score Comment including power plant's supervisory system scoring, power plant's work summary scoring, power plant's abnormal accident scoring, electric power factory equipment account Divide, power plant's experimental situation scoring, power plant's technical training scoring and the inspection plan of power plant's week are marked.
In described comprehensive evaluation result, each item rating shows with the form of search tree.
Compared with prior art, the invention have the advantages that
1) present invention establishes summer peak meeting and checks project, closed loop self-inspection project and respective items purpose technical supervision Criteria of quality evaluation, according to summer peak meeting technical supervision report and the supervision report of closed loop self-checking of power plant, it is achieved Summer peak meeting checks project scoring, the scoring of closed loop self-inspection project, overall merit scoring, and standardization is strong, and it is convenient to evaluate, From summer peak meeting, closed loop angle and comprehensive angle, factory's technical supervision quality of can preferably generating electricity by way of merging two or more grid systems is commented Valency works.
2) score value is also converged as problem by the present invention less than standard value respective items purpose technical supervision criteria of quality evaluation General report exports, and can exercise supervision power plant from summer peak meeting inspection management, closed loop inspection management, and Work can be checked oneself by the most conscientious the carrying out of problem summary report in net power plant, and report is checked oneself in establishment, formulates rectification Measure, and individual power plants can be carried out by power technology implementation and supervision unit related service personnel by problem summary report Centralized management examination & verification, it is ensured that the safe and stable operation of power plant.
3) summer peak meeting is checked that project scoring and closed loop self-inspection project are marked by respectively by the overall merit scoring of the present invention Number (i.e. number in project) in technical supervision criteria of quality evaluation carries out weight division, it is ensured that acquisition Overall merit scoring can the work ruuning situation of comprehensive assessment power plant, assessment result is more accurate.
4) the overall merit scoring of the present invention also includes power plant's basic management overall score, adds power plant's supervisory system and comments Point, power plant's work summary scoring, the scoring of the aspect such as power plant's abnormal accident scoring, promote each power plant reinforcement base pipe Reason, assesses more comprehensive.
5) present invention shows each item rating in comprehensive evaluation result with the form of search tree, it is simple to check scoring, directly Sight is more preferable.
Accompanying drawing explanation
Fig. 1 is the inventive method flow chart.
Detailed description of the invention
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.The present embodiment is with the technology of the present invention side Implement premised on case, give detailed embodiment and concrete operating process, but the protection model of the present invention Enclose and be not limited to following embodiment.
As it is shown in figure 1, a kind of quality evaluation data processing method for factory's technical supervision of generating electricity by way of merging two or more grid systems includes following Step:
1) set up summer peak meeting and check project, closed loop self-inspection project, power plant's basic management project and corresponding project Technical supervision criteria of quality evaluation.
Wherein, summer peak meeting check project with closed loop self-inspection project by the special project corresponding with each specialty in power plant Detection project is constituted, and each specialty in power plant includes that insulation, relay protection, the quality of power supply, electrical measurement are professional, hot Working platform industry, steam turbine, energy-conservation, chemical, environmental protection and metal.Such as: the quality of power supply includes checking that frequency, voltage are inclined Differences etc., i.e. check the frequency the most how frequency tolerance scope≤± 0.2Hz of power system, check power train Whether the busbar voltages at different levels of system meet voltage deviation area requirement etc..
Power plant's basic management project includes power plant's supervisory system project, power plant's work summary project, power plant's abnormal accident Project, electric power factory equipment account project, power plant's experimental situation project, power plant's technical training project and the inspection plan of power plant's week Project.Power plant's supervisory system project includes checking organization's network, supervisory system etc., power plant's work summary item Mesh includes checking quarterly or supervision report half a year, annual supervision work summary etc., power plant's abnormal accident item inspection Abnormal accident (including unit adjustment, generating set master-failure, electromotor main auxiliary equipment fault etc.) is reported Announcement, alarm notification list etc., electric power factory equipment account item inspection online electric measuring instrument account etc., power plant's experimental situation item Visual inspection looks into whether on-the-spot laboratory environment on the spot meets regulation requirement, power plant's technical training item inspection training program With record, electric detecting technology metrology and measurement certificate etc., power plant's week inspection planning item checks whether formulation portable type instrument instrument Table week inspection plan and drawing at wire tag master gage.
2) the summer peak meeting technical supervision report of each power plant, the supervision report of closed loop self-checking and power plant's base are gathered The supervision report of plinth management technique, summer peak meeting technical supervision report, the supervision report of closed loop self-checking and power plant basis Include that the technical supervision to each project is reported in management technique supervision report.
3) according to summer peak meeting technical supervision report, the supervision report of closed loop self-checking and power plant's base of each power plant The supervision report of plinth management technique, is carried out the scoring of projects respectively, it is thus achieved that meet peak by technical supervision criteria of quality evaluation Inspection project of aestivating scoring S1, closed loop self-inspection project scoring S2With power plant basic management overall score S0
Power plant basic management overall score S0Mark including power plant's supervisory system, power plant's work summary is marked, power plant is different Ordinary affair therefore scoring, the scoring of electric power factory equipment account, the scoring of power plant experimental situation, power plant's technical training scoring and power plant's week Inspection plan scoring.
4) overall merit scoring S is obtainedz, meet below equation:
αS1+βS2+γS0=Sz
In formula, α, β, γ correspond to summer peak meeting respectively and check project scoring, the scoring of closed loop self-inspection project and power plant's base Plinth management overall score weight factor, the value of α, β, γ with in corresponding technical supervision criteria of quality evaluation Number (the project number in i.e. summer peak meeting checks project, closed loop self-inspection project, power plant's basic management project) becomes Direct ratio.
5) summer peak meeting is checked project scoring, the scoring of closed loop self-inspection project, overall merit scoring order row respectively Row obtain comprehensive evaluation result, and export, and in comprehensive evaluation result, each item rating shows with the form of search tree, Comprehensive evaluation result can show with the form of icon, it is simple to looks into the evaluation situation of each power plant at a glance See, simultaneously always according to step 3) scoring, contrast each power plant in the technical supervision criteria of quality evaluation of projects Score value, using score value less than standard value respective items purpose technical supervision criteria of quality evaluation defeated as problem summary report Go out.
Data in whole evaluating data processing method are stored in cloud database, it is simple to data are uploaded and led Go out.Use the inventive method can conveniently realize technical supervision quality evaluation and relate to day-to-day supervision report submission, Summer peak meeting inspections etc., create a data processing platform (DPP) for preferably carrying out technical supervision quality evaluation work.

Claims (6)

1. the quality evaluation data processing method for factory's technical supervision of generating electricity by way of merging two or more grid systems, it is characterised in that bag Include following steps:
1) set up summer peak meeting and check project, closed loop self-inspection project and respective items purpose technical supervision quality evaluation Standard;
2) summer peak meeting technical supervision report and the supervision report of closed loop self-checking of each power plant are gathered;
3) according to summer peak meeting technical supervision report and the supervision report of closed loop self-checking of each power plant, supervise by technology Superintend and direct criteria of quality evaluation and carry out the scoring of projects respectively, it is thus achieved that summer peak meeting checks project scoring S1With closed loop self-inspection Project scoring S2
4) overall merit scoring S is obtainedz, meet below equation:
αS1+βS2=Sz
In formula, α, β correspond to summer peak meeting respectively and check project scoring and the weight factor of closed loop self-inspection project scoring;
5) summer peak meeting is checked project scoring, the scoring of closed loop self-inspection project, overall merit scoring order row respectively Row obtain comprehensive evaluation result, and export.
A kind of quality evaluation data for factory's technical supervision of generating electricity by way of merging two or more grid systems the most according to claim 1 process Method, it is characterised in that described step 5) also include: according to step 3) scoring, contrast each power plant respectively Score value in the technical supervision criteria of quality evaluation of project, by score value less than standard value respective items purpose technical supervision matter Amount evaluation criterion exports as problem summary report.
A kind of quality evaluation data for factory's technical supervision of generating electricity by way of merging two or more grid systems the most according to claim 1 process Method, it is characterised in that the value of described α, β becomes with the number in corresponding technical supervision criteria of quality evaluation Direct ratio.
A kind of quality evaluation data for factory's technical supervision of generating electricity by way of merging two or more grid systems the most according to claim 1 process Method, it is characterised in that described summer peak meeting check project and closed loop self-inspection project by with in power plant each specially Special detection project corresponding to industry is constituted, each specialty in power plant include insulation, relay protection, the quality of power supply, Electrical measurement specialty, thermal technology's specialty, steam turbine, energy-conservation, chemical, environmental protection and metal.
A kind of quality evaluation data for factory's technical supervision of generating electricity by way of merging two or more grid systems the most according to claim 1 process Method, it is characterised in that described overall merit scoring SzAlso include power plant's basic management overall score, described power plant Basic management overall score include the scoring of power plant supervisory system, power plant's work summary scoring, power plant's abnormal accident scoring, The scoring of electric power factory equipment account, power plant's experimental situation scoring, power plant's technical training scoring and the inspection plan scoring of power plant's week.
A kind of quality evaluation data for factory's technical supervision of generating electricity by way of merging two or more grid systems the most according to claim 1 process Method, it is characterised in that in described comprehensive evaluation result, each item rating shows with the form of search tree.
CN201610223566.XA 2016-04-12 2016-04-12 Grid-connected power plant technology supervision used quality assessing data processing method Pending CN105844426A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610223566.XA CN105844426A (en) 2016-04-12 2016-04-12 Grid-connected power plant technology supervision used quality assessing data processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610223566.XA CN105844426A (en) 2016-04-12 2016-04-12 Grid-connected power plant technology supervision used quality assessing data processing method

Publications (1)

Publication Number Publication Date
CN105844426A true CN105844426A (en) 2016-08-10

Family

ID=56597302

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610223566.XA Pending CN105844426A (en) 2016-04-12 2016-04-12 Grid-connected power plant technology supervision used quality assessing data processing method

Country Status (1)

Country Link
CN (1) CN105844426A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109711666A (en) * 2018-11-21 2019-05-03 武汉瑞莱保能源技术有限公司 A kind of technical supervision evaluation method and system based on criterion and quantity
CN110363383A (en) * 2019-06-03 2019-10-22 华东电力试验研究院有限公司 A kind of distributed power generation monitoring technology based under digital development
CN110738427A (en) * 2019-10-21 2020-01-31 广东电网有限责任公司 electric power part work quality scoring system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109711666A (en) * 2018-11-21 2019-05-03 武汉瑞莱保能源技术有限公司 A kind of technical supervision evaluation method and system based on criterion and quantity
CN110363383A (en) * 2019-06-03 2019-10-22 华东电力试验研究院有限公司 A kind of distributed power generation monitoring technology based under digital development
CN110738427A (en) * 2019-10-21 2020-01-31 广东电网有限责任公司 electric power part work quality scoring system

Similar Documents

Publication Publication Date Title
Peppanen et al. Leveraging AMI data for distribution system model calibration and situational awareness
CN114640173B (en) Early warning model of transformer and generator based on many characteristic quantities
KR101683256B1 (en) Asset management system and method for electric power apparatus
CN103793859B (en) A kind of wind power plant operation monitoring and event integrated evaluating method
CN105869074A (en) Technical supervision system for grid-connected power plant
CN105844426A (en) Grid-connected power plant technology supervision used quality assessing data processing method
CN109188082A (en) A kind of Transformer condition evaluation based on BP neural network
CN104732103A (en) Evaluation method for electric transmission line orientated forest fire approaching risk
CN109902447A (en) A kind of huge Condition Maintenance for Hydraulic Power Plant model and construction method
CN116014893A (en) Remote visual intelligent inspection system for transformer substation
CN116664763A (en) Automatic generation method of indication map of forbidden limit area of power construction site of three-dimensional point cloud
KR101200675B1 (en) Method for evaluating risk level of power system
JP2010239731A (en) Generation/transformation unit inspection-power outage planning support system, and planning support method of the same
Chow et al. Novel engineering techniques to overcoming traditional challenges in online condition monitoring systems for power transformer
CN205643673U (en) Metering device scraps alarm device based on measurement instrument follow -up of quality evaluation system
Ekisheva et al. North American transformer outages initiated by transmission equipment failures and human error
Sheppy et al. Metering Best Practices Applied in the National Renewable Energy Laboratory's Research Support Facility: A Primer to the 2011 Measured and Modeled Energy Consumption Datasets
CN108197814A (en) A kind of electric power enterprise security of system evaluation method and system
Aljumaili et al. Assessment of railway frequency converter performance and data quality using the IEEE 762 Standard
Teske Bridging the Gap between Energy-and Grid Models: developing an integrated infrastructural planning model for 100% renewable energy systems in order to optimize the interaction of flexible power generation, smart grids and storage technologies
CN108009772A (en) A kind of power sourcing equipment method based on equipment unit capacity value analysis
Darian et al. Electrical power equipment digital twins. Basic principles and technical requirements
Duenckel et al. An electrical reliability metric for preventive maintenance: Mean time between failure plus finds
Sanquist et al. Grid-APPS-D Evaluation Framework: A Systems Engineering Approach
CN106248144B (en) A kind of electric power maintenance system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160810