CN105839617A - High-stability building pile - Google Patents

High-stability building pile Download PDF

Info

Publication number
CN105839617A
CN105839617A CN201610350949.3A CN201610350949A CN105839617A CN 105839617 A CN105839617 A CN 105839617A CN 201610350949 A CN201610350949 A CN 201610350949A CN 105839617 A CN105839617 A CN 105839617A
Authority
CN
China
Prior art keywords
adjusting rod
pile body
column
stake
central hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610350949.3A
Other languages
Chinese (zh)
Other versions
CN105839617B (en
Inventor
丁洪
谈奇锋
洪晨
钱卓豪
王照国
杨洪忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG QIAOXING CONSTRUCTION GROUP Co Ltd
Original Assignee
ZHEJIANG QIAOXING CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG QIAOXING CONSTRUCTION GROUP Co Ltd filed Critical ZHEJIANG QIAOXING CONSTRUCTION GROUP Co Ltd
Priority to CN201610350949.3A priority Critical patent/CN105839617B/en
Publication of CN105839617A publication Critical patent/CN105839617A/en
Application granted granted Critical
Publication of CN105839617B publication Critical patent/CN105839617B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/48Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/72Pile shoes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/14Geometrical or physical properties resilient or elastic
    • E02D2200/146Springs
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/15Geometrical or physical properties including at least a hinge
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to the technical field of buildings, and particularly relates to a high-stability building pile. The high-stability building pile comprises a hollow pile body and a conical pile head. Side piles are arranged in the hollow pile body. The inner ends of the side piles are inserted into connecting plates located in the hollow pile body. Stand columns are arranged in the hollow pile body and can slide along the hollow pile body. The stand columns comprise the middle hollow stand column, the left stand column and the right stand column. The left stand column and the right stand column are located at the two sides of the middle hollow stand column. Inclined pushing faces which are close to the middle hollow stand column from top to bottom and are used for extruding the connecting plates are arranged on the sides, opposite to the connecting plates, of the left stand column and the right stand column. Pressed faces identical to the inclination directions of the pushing faces are arranged on the inner sides of the connecting plates. At least one set of adjusting structure for pushing the left stand column and the right stand column to be close to or far away from the connecting plates is arranged in the middle hollow stand column. The building pile has the beneficial effects of being good in strength and stability.

Description

The stake of a kind of high firm building
Technical field
The invention belongs to technical field of buildings, be specifically related to the stake of a kind of high firm building.
Background technology
It is known that building stake is a kind of building appliance, it is mainly used in squeezing in earth and carries out its upper building support Base apparatus, be therefore widely used in building engineering field.Whether building stake can keep in earth depths stablizing serious shadow Ring the safety of this building, and the stability building stake has an effect on the development in city later stage, as built subway etc., if building Stake generation loosens and will directly affect the life security of people.Existing building stake includes pile body and pile top, and pile top is arranged on pile body Bottom;During use, by hitting pile body, use pile top to run downwards in earth and be operated;But it finds in using, Because the structure of pile body and pile top is fixed form, therefore then cannot be carried out adapting in the building stake required for different size, Thus often occur that building stake is defective, or the situation do not arranged in pairs or groups.Although the diameter of some building stake pile crown can adjust, but It is that generally speaking building pilework is unstable, accident easily occurs.As Publication No. 204919532U discloses, one is novel builds Build stake, adjust left socle and the relative distance of right support by rotation adjustment device, thus adjust the distance between building pile crown, But the left and right of the building pile head of this structure divides point hinged, unstable when bearing huge gravity, there is potential safety hazard.And And this building stake is only by the frictional resistance of vertical direction, and not having the wedging function of horizontal direction, load ability to bear has Limit, when top load-bearing is the biggest, easily occurs.
Summary of the invention
It is an object of the invention to provide that a kind of intensity is good, the building stake of good stability.
The above-mentioned technical purpose of the present invention is achieved through the following technical solutions:
The stake of a kind of high firm building, including having the hollow pile body of left pile body and right pile body and having left pile crown and the cone of right pile crown Shape pile crown, hinged with left pile crown top bottom described left pile body, hinged with right pile crown top bottom described right pile body, its feature exists In: on described left pile body and right pile body, symmetrical offering is organized from inside to outside and downward-sloping side opening more, plugs in described side opening The side stake stretched out outside described side opening, stake the inner, described side is had to be inserted on the connecting plate being positioned at described hollow pile body;Described sky Being provided with column in heart pile body, described column includes central hollow column, is positioned at the left side column of central hollow column both sides, the right side Heel post, is positioned at central hollow column both sides and is positioned at the left slider above described left side column, right side uprights, right slide block, institute State left slider, right slide block is connected by spring between described central hollow column, the corresponding described left side of described left pile body, right pile body Slide block, right slide position are provided with left chute, right rail, and described left side column, right side uprights the most described connecting plate side set It is equipped with the skewed pushing face for extruding described connecting plate drawn close from top to bottom, described company to described central hollow column Be provided with the compression face identical with described pushing face incline direction inside fishplate bar, on described central hollow column at least provided with One group for promoting described left side column, right side uprights closer or far from the adjustment structure of described connecting plate.
Use and side stake is set in building stake, when building stake and squeezing in earth, slide downward column, column squeeze side Stake, makes side stake stretch into earth, which increases the wedging function of building stake horizontal direction, and load ability to bear is strengthened, and builds stake More stable.Arranging left and right slide block in central hollow column both sides, slide block is connected by spring with central hollow column, about correspondence Pile body position arranges chute, and middle hollow column is played correcting, supporting role by left and right slide block, makes central hollow column be not easy Offset, improve the stability of building stake on the whole.Slide block is connected by spring with central hollow column, when between building stake Away from the least, spring plays a cushioning effect.Connecting plate is respectively provided with consistent oblique of incline direction with left and right sides column opposite side Face, when connecting plate is displaced outwardly by the pushing of left and right sides column, the spacing between connecting plate and left and right sides column increases, and uses The setting of this downward slope, it is ensured that left and right sides column effectively contacts with connecting plate, thus advances side stake to enter the stake of earth side It is plugged in connecting plate.Adjustment structure is set simultaneously, regulation connecting plate and left side column or right side vertical between distance, Ke Yigeng Offside stake applies the active force of horizontal direction well, makes side stake enter earth smoothly.
As preferably, described adjustment structure includes being connected to described left side column, right side uprights near described central hollow Column side also penetrates the left connecting rod in described central hollow column, right connecting rod, described left connecting rod, right connecting rod interior End is hinged with downward-sloping left adjusting rod, right adjusting rod, hinged bottom described left adjusting rod, right adjusting rod, described left regulation The intermediate regulations having horizontally disposed and two ends can move up and down is connected along left adjusting rod and right adjusting rod between bar, right adjusting rod Bar.
As preferably, described left adjusting rod, right adjusting rod are all offered along described left adjusting rod, right adjusting rod length direction Arc chute, described middle tone pole two ends is had to be provided with the spherical slippery fellow that can slide along described arc chute.
As preferably, described middle tone pole is fixed with vertically arranged and described middle tone pole can be promoted along described circular arc The down-pressed pole that shape chute slides up and down, described down-pressed pole upper end is stretched out outside described central hollow column.
As preferably, described central hollow column top lateral symmetry offers entrance hole, and described down-pressed pole top is by upper Be disposed with multiple Horizontal limiting through hole under to, described central hollow column top with by being arranged in described entrance hole and water The gag lever post of flat limiting through hole connects.
As preferably, described gag lever post both sides be provided with for prevent described gag lever post from described entrance hole skid off spacing Block.
As preferably, on described central hollow column, Parallel Symmetric is provided with two groups of regulations of a shared described down-pressed pole Structure, connects between two middle tone poles of described two groups of adjustment structures and has even power lower platen, and described down-pressed pole is fixed on institute State the center of even power lower platen, be removably arranged with even power weight bucket post outside described down-pressed pole, in described even power weight bucket post From top to bottom at least provided with two spacing guiding collars, pass through between the described spacing guiding collar and even power weight bucket column wall Some spokes connect.
By arranging two groups of adjustment structures, two groups of adjustment structures are connected by even power lower platen, and down-pressed pole passes through
Even power lower platen applies active force to left and right sides column, and the area of even power lower platen is big, applies active force more high forces Evenly, left and right sides column lateral extrusion connecting plate is made.Outside down-pressed pole, sheathed even power weight bucket post considerably increases simultaneously The active force applying even power lower platen, makes side stake be easier to enter earth.
As preferably, bottom described down-pressed pole, centered by following depression bar axle center, it is provided with some radially
Firm stiffener, on described even power weight bucket post, the position of corresponding described entrance hole offers connecting hole.
Add the intensity of down-pressed pole by arranging firm stiffener bottom down-pressed pole, make down-pressed pole more stable.
Even power weight bucket post arranges connecting hole, can in the limiting through hole in connecting hole, entrance hole and down-pressed pole
It is fixed presses lever with insertion gag lever post.
As preferably, connected by axis of rotation bottom described left pile crown and right pile crown, described left pile crown and the right side
On pile crown, relative position is provided with screw, is provided with regulation screw in described screw, and described regulation screw is upper
It is arranged with back-moving spring between described left pile crown and right pile crown.
As preferably, described left pile body or right pile body top are provided with adjusting rod, and described adjusting rod includes rear end
The first adjusting rod offering hole, multiple location and the rear end that are articulated with on described left pile body or right pile body are socketed on
The second adjusting rod that can slide along the first adjusting rod in described first adjusting rod, described second adjusting rod front end
It is spirally connected with the contiguous block being arranged on described right pile body or left pile body top;It is provided with many on described second adjusting rod
Individual groove, is provided with locating piece in described groove, by spring and described groove bottom land bottom described locating piece
Connect.
When needing the distance shortening adjusting rod, press locating piece, advance the second adjusting rod to the first adjusting rod
Hole, location at, locating piece just be stuck in location hole in, it is achieved the shortening of adjusting rod.When needs elongation regulation
During bar, pull out the second adjusting rod by the locating piece fallen in hole, location.
In sum, the invention have the benefit that
1. use and side stake is set in building stake, when building stake and squeezing in earth, slide downward column, column squeeze side stake, Making side stake stretch into earth, which increase the wedging function of building stake horizontal direction, load ability to bear is strengthened, and building stake is more steady Fixed.Connecting plate is respectively provided with, with left and right sides column opposite side, the inclined-plane that incline direction is consistent, uses the setting of this downward slope, Connecting plate is respectively provided with, with left and right sides column opposite side, the inclined-plane that incline direction is consistent, when connecting plate is pushed away by left and right sides column Pressure is displaced outwardly, and the spacing between connecting plate and left and right sides column increases, and uses the setting of this downward slope, it is ensured that left and right sides Column effectively contacts with connecting plate, thus advances side stake to enter earth.
2. arranging left and right slide block in central hollow column both sides, slide block is connected by spring with central hollow column, corresponding Pile body position, left and right arranges chute, and middle hollow column is played correcting, supporting role by left and right slide block, makes central hollow column not It is susceptible to skew, improves the stability of building stake on the whole.Slide block is connected by spring with central hollow column, works as building Pile spacing is the least, and spring plays a cushioning effect.
3. column on the left of promotion, right side uprights be set in building stake closer or far from the adjustment structure of described connecting plate,
Two effects can be reached, on the one hand: when building stake enters in earth, if ambient earth is harder, only by a left side The right side uprights vertical direction extruding to connecting plate, it is impossible to make side stake enter earth, if now by left and right sides column toward overhanging Exhibition, carries out horizontal direction extruding and applies horizontal direction active force connecting plate, makes side stake be easier to enter earth;On the other hand, Cause spacing between left and right sides column and connecting plate the biggest when building stake because of width adjustment, it is impossible to contact with connecting plate, at this moment lead to Cross adjustment left and right sides column to stretch, reduce the distance between left and right sides column and connecting plate, it is achieved left and right sides column and connecting plate Extruding.
4. arranging two groups of adjustment structures, two groups of adjustment structures are connected by even power lower platen, and down-pressed pole is by pressing under even power Plate applies active force to left and right sides column, and the area of even power lower platen is big, applies active force more high forces evenly, makes left and right Heel post lateral extrusion connecting plate.Simultaneously outside down-pressed pole, sheathed even power weight bucket post considerably increases and executes even power lower platen The active force added, makes side stake be easier to enter earth.
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention;
Fig. 2 is central hollow column and left and right sides upright post connection structure figure;
Fig. 3 is even power lower platen and the top view of down-pressed pole connection;
Fig. 4 is adjusting rod top view;
Fig. 5 is adjusting rod front view;
The left pile body of 11-in figure, the right pile body of 12-, the left chute of 13-, 14-right rail, the left pile body of 21-, the right pile body of 22-, empty in the middle of 31- Heart column, column on the left of 32-, 33-right side uprights, the left connecting rod of 34-, the right connecting rod of 35-, the left adjusting rod of 36-, the right regulation of 37- Bar, 38-middle tone pole, 39-down-pressed pole, 391-spacing hole, 392-gag lever post, 393-stiffener, 394-even power weight bucket post, The 395-spacing guiding collar, 396-spoke, 4-side opening, 41-even power lower platen, the stake of 51-side, 52-connecting plate, 6-regulates screw, 71-the first adjusting rod, 72-the second adjusting rod, 711-positions hole, 721-groove, 722-locating piece, 8-back-moving spring, the left cunning of 91- Block, the right slide block of 92-.
Detailed description of the invention
Embodiment one
A kind of building stake with side stake, including having the hollow pile body of left pile body 11 and right pile body 12 and having left pile crown 21 He The taper pile crown of right pile crown 22, hinged with left pile crown 21 top bottom left pile body 11, with right pile crown 22 top bottom right pile body 12 Hinged, left pile body 11 and right pile body 12 symmetry offer organize from inside to outside and downward-sloping side opening 4 more, are inserted with in side opening 4 And stretch out the side stake 51 of side opening 4, side stake 51 the inner is inserted on the connecting plate 52 being positioned at hollow pile body;Arrange in hollow pile body Column, column is had to include central hollow column 31, be positioned at the left side column 32 of central hollow column 31 both sides, right side uprights 33, It is positioned at central hollow column 31 both sides and is positioned at the left slider 91 above left side column 32, right side uprights 33, right slide block 92, left cunning Block 91, right slide block 92 are connected by spring between central hollow column 31, the corresponding left slider 91 of left pile body 11, right pile body 12, Right slide block 92 position is provided with left chute 13, right rail 14, arranges left and right slide block in central hollow column both sides, and slide block is with middle Hollow column is connected by spring, and corresponding pile body position, left and right arranges chute, left and right slide block middle hollow column is played correcting, Supporting role, makes central hollow column that skew to be less likely to occur, improves the stability of building stake on the whole.Slide block is empty with centre Heart column is connected by spring, when building pile spacing is the least, and spring plays a cushioning effect.Left side column 32, right side uprights 33 relative connecting plate 52 sides be provided with from top to bottom to central hollow column 31 draw close for extruding described connecting plate 52 Skewed pushing face, is provided with the compression face identical with pushing face incline direction, when column slide downward inside connecting plate 52 Time, the pushing face of left and right sides column contacts laminating compression face and extrudes compression face, making connecting plate move outward.Middle empty One group it is provided with for promoting described left side column 32, right side uprights 33 closer or far from the tune of connecting plate 52 on heart column 31 Nodule structure.
Adjustment structure includes being connected to left side column 32, right side uprights 33 is near central hollow column 31 side and penetrates Between left connecting rod 34 in hollow column 31, right connecting rod 35, left connecting rod 34, the inner of right connecting rod 35 are hinged with and dip down Left adjusting rod 36 tiltedly, right adjusting rod 37, hinged bottom left adjusting rod 36, right adjusting rod 37, left adjusting rod 36, right adjusting rod 37 Between connect the middle tone pole 38 having horizontally disposed and two ends can move up and down along left adjusting rod 36 and right adjusting rod 37, left Arc chute 371 is all offered along left adjusting rod 36, right adjusting rod 37 length direction on adjusting rod 36, right adjusting rod 37, in Between adjusting rod 38 two ends be provided with can along arc chute 371 slide spherical foxy 381.It is fixed with in the middle part of middle tone pole 38 Vertically arranged and that middle tone pole 38 can be promoted to slide up and down along described arc chute 371 down-pressed pole 39, on down-pressed pole 39 End stretches out outside described central hollow column 31.When moving down of presses lever, drive the slide downward of middle tone pole, middle The left and right adjusting rod of adjusting rod extruding both sides, promotes left and right connecting rod to stretch out, and drives left and right side column towards connecting plate Extruding, makes side stake enter earth.Central hollow column 31 top lateral symmetry offers entrance hole 311, down-pressed pole 39 top by It is disposed with down multiple Horizontal limiting through hole 391, between entrance hole 311 and Horizontal limiting through hole 391, passes through gag lever post 392 connect, and gag lever post 392 both sides are provided with the limited block for preventing gag lever post 392 from skidding off from entrance hole 311.
Being connected by axis of rotation bottom left pile crown 21 and right pile crown 22, left pile crown 21 is relative with on right pile crown 22
Position is provided with screw, is provided with regulation screw 6 in screw, regulation screw 6 is positioned at left pile crown 21 and right pile crown 22 it Between be arranged with back-moving spring 8.By the size rotating regulation pile crown of left and right pile crown, regulation screw can fix pile crown makes building Stake is more stable.
Left pile body 11 top is provided with adjusting rod, and offering that adjusting rod includes that rear end is articulated with on right pile body 12 is multiple fixed The second tune that can slide along the first adjusting rod 71 that first adjusting rod 71 in hole 711, position and rear end are socketed in the first adjusting rod 71 Pole 72, the second adjusting rod 72 front end and the contiguous block being arranged on left pile body 11 top are spirally connected, and the second adjusting rod 72 is provided with Multiple grooves 721, are provided with locating piece 722 in groove, be connected with described groove bottom land by spring bottom locating piece 722.When When needing the distance shortening adjusting rod, press locating piece, advance at the hole, location of the second adjusting rod to the first adjusting rod, locating piece Just it is stuck in hole, location, it is achieved the shortening of adjusting rod.When needs elongation adjusting rod, by the locating piece fallen in hole, location Pull out the second adjusting rod.
Embodiment two
Other structures are with embodiment one, and difference is: be provided with two groups on central hollow column 31 for promoting left side Column 32, right side uprights 33 are closer or far from the adjustment structure of connecting plate 52.
Adjustment structure includes that on central hollow column 31, Parallel Symmetric is provided with two groups of regulations of a shared down-pressed pole 39 Structure, connects between two middle tone poles 38 of two groups of adjustment structures and has even power lower platen 41, and down-pressed pole 39 is fixed on even power The center of lower platen 41, down-pressed pole 39 is outer is removably arranged with even power weight bucket post 394, by upper in even power weight bucket post 394 Down-set have two spacing guiding collars 395, by some between the spacing guiding collar and even power weight bucket post 394 inwall Spoke 396 connects.Some firm stiffeners 393 it are provided with centered by following depression bar axle center radially bottom down-pressed pole 39, On even power weight bucket post 394, the position of corresponding described entrance hole offers connecting hole, the limit in connecting hole, entrance hole and down-pressed pole Position through hole may be inserted into gag lever post be fixed.Two groups of adjustment structures are connected by even power lower platen, and down-pressed pole is by even power Lower platen applies pressure to middle adjusting rod, and intermediate regulations pole pair left and right sides column applies active force, promotes connecting plate to move.Even The area of power lower platen is big, applies active force more high forces evenly, makes left and right sides column lateral extrusion connecting plate.Exist simultaneously Outside down-pressed pole, sheathed even power weight bucket post considerably increases the active force applying even power lower platen, makes side stake be easier to enter Earth.
The using method of embodiment one, two building stake is: according to using environment to determine distance before using, adjust left and right Distance between pile crown meets the requirements, and building stake is inserted in earth subsequently, is put into by column in building stake, and column passes through slide block Slipping in building stake, left and right side column, by extruding connecting plate, makes side stake stretch into earth.In the process can by down-pressed pole To adjust the distance between left and right side column and connecting plate, make left and right side column contact with connecting plate, apply one to connecting plate The active force of individual horizontal direction, makes side stake be easier to enter earth.Finally adjust the length of adjusting rod, make between the pile body of left and right Distance between distance and pile crown adapts.
This specific embodiment is only explanation of the invention, and it is not limitation of the present invention, people in the art The present embodiment can be made after reading this specification by member as required does not has the amendment of creative contribution, but as long as at this All protected by Patent Law in the right of invention.

Claims (10)

1. a high firm building stake, including having the hollow pile body of left pile body (11) and right pile body (12) and having left pile crown (21) and the taper pile crown of right pile crown (22), described left pile body (11) bottom is hinged with left pile crown (21) top, described right pile body (12) bottom is hinged with right pile crown (22) top, it is characterised in that: described left pile body (11) and the upper symmetry of right pile body (12) are offered There is organize from inside to outside and downward-sloping side opening (4) more, in described side opening (4), be inserted with the side stake stretching out described side opening (4) outward (51), described side stake (51) the inner is inserted on the connecting plate (52) being positioned at described hollow pile body;Set in described hollow pile body Be equipped with column, described column include central hollow column (31), the left side column (32) being positioned at central hollow column (31) both sides, Right side uprights (33), is positioned at central hollow column (31) both sides and is positioned at described left side column (32), right side uprights (33) top Left slider (91), right slide block (92), logical between described left slider (91), right slide block (92) and described central hollow column (31) Crossing spring to connect, described left pile body (11), the corresponding described left slider of right pile body (12) (91), right slide block (92) position are provided with a left side Chute (13), right rail (14), described left side column (32), right side uprights (33) the most described connecting plate (52) side are provided with The skewed pushing face for extruding described connecting plate (52) drawn close to described central hollow column (31) from top to bottom, institute State connecting plate (52) inner side and be provided with the compression face identical with described pushing face incline direction, on described central hollow column (31) In be used for promoting described left side column (32), right side uprights (33) closer or far from described connecting plate (52) at least provided with one group Adjustment structure.
A kind of high firm building the most according to claim 1 stake, it is characterised in that: described adjustment structure includes being connected to institute State left side column (32), right side uprights (33) is near described central hollow column (31) side and penetrates described central hollow column (31) the left connecting rod (34) in, right connecting rod (35), described left connecting rod (34), right connecting rod (35) the inner hinged oriented The left adjusting rod (36) of lower inclination, right adjusting rod (37), hinged bottom described left adjusting rod (36), right adjusting rod (37), described Connecting between left adjusting rod (36), right adjusting rod (37) has the horizontally disposed and two ends can be along left adjusting rod (36) and right adjusting rod (37) the middle tone pole (38) moved up and down.
A kind of high firm building the most according to claim 2 stake, it is characterised in that: described left adjusting rod (36), right regulation Arc chute, described middle tone is all offered along described left adjusting rod (36), right adjusting rod (37) length direction on bar (37) Pole (38) two ends are provided with the spherical slippery fellow that can slide along described arc chute.
A kind of high firm building the most according to claim 3 stake, it is characterised in that: described middle tone pole (38) is fixed with Vertically arranged and that described middle tone pole (38) can be promoted to slide up and down along described arc chute down-pressed pole (39), described under Described central hollow column (31) is stretched out outward in depression bar (39) upper end.
A kind of high firm building the most according to claim 4 stake, it is characterised in that: described central hollow column (31) top Lateral symmetry offers entrance hole, and described down-pressed pole (39) top is from top to bottom disposed with multiple Horizontal limiting through hole (391), described central hollow column (31) top with by being arranged in described entrance hole and the gag lever post of Horizontal limiting through hole (392) connect.
Described a kind of high firm building stake the most according to claim 5, it is characterised in that: described gag lever post (392) two Side is provided with the limited block for preventing described gag lever post (392) from skidding off from described entrance hole.
A kind of high firm building the most according to claim 6 stake, it is characterised in that: described central hollow column (31) is upper flat Row is symmetrically arranged with two groups of adjustment structures of a shared described down-pressed pole (39), two middle tones of described two groups of adjustment structures Connecting between pole (38) and have even power lower platen (41), described down-pressed pole (39) is fixed in described even power lower platen (41) The heart, described down-pressed pole (39) is the most removably arranged with even power weight bucket post (394), in described even power weight bucket post (394) by Upper downwards at least provided with two spacing guiding collars (395), the described spacing guiding collar and even power weight bucket post (394) inwall Between connected by some spokes (396).
A kind of high firm building the most according to claim 7 stake, it is characterised in that: the following pressure in described down-pressed pole (39) bottom Some firm stiffeners (393) it are provided with radially, the upper corresponding institute of described even power weight bucket post (394) centered by bar axle center The position stating entrance hole offers connecting hole.
9. according to the arbitrary described a kind of high firm building stake of claim 1-8, it is characterised in that: described left pile crown (21) and the right side Pile crown (22) bottom is connected by axis of rotation, and described left pile crown (21) relative position upper with right pile crown (22) is provided with screw, Be provided with regulation screw (6) in described screw, described regulation screw (6) is positioned at described left pile crown (21) and right pile crown (22) it Between be arranged with back-moving spring (8).
A kind of high firm building the most according to claim 9 stake, it is characterised in that: described left pile body (11) or right pile body (12) top is provided with adjusting rod, and described adjusting rod includes that rear end is articulated with opening on described left pile body (11) or right pile body (12) Be provided with first adjusting rod (71) in hole, multiple location (711) and rear end is socketed in described first adjusting rod (71) can be along first The second adjusting rod (72) that adjusting rod (71) slides, described second adjusting rod (72) front end be arranged on described right pile body (12) or The contiguous block on left pile body (11) top is spirally connected;It is provided with multiple groove (721), in described groove on described second adjusting rod (72) Being provided with locating piece (722), described locating piece (722) bottom is connected with described groove bottom land by spring.
CN201610350949.3A 2016-05-25 2016-05-25 High firm building stake Active CN105839617B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610350949.3A CN105839617B (en) 2016-05-25 2016-05-25 High firm building stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610350949.3A CN105839617B (en) 2016-05-25 2016-05-25 High firm building stake

Publications (2)

Publication Number Publication Date
CN105839617A true CN105839617A (en) 2016-08-10
CN105839617B CN105839617B (en) 2024-03-22

Family

ID=56593287

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610350949.3A Active CN105839617B (en) 2016-05-25 2016-05-25 High firm building stake

Country Status (1)

Country Link
CN (1) CN105839617B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190734A (en) * 2017-06-22 2017-09-22 成都赋阳技术开发有限公司 The roadbed supporting pile for repairing construction is built for road and bridge
CN110409428A (en) * 2019-07-01 2019-11-05 东莞市建安集团有限公司 Tube pile structure and its construction method
CN113550299A (en) * 2021-09-06 2021-10-26 芜湖宝正新型材料科技有限公司 Assembled unwrapping wire tubular pile of steel-wood structure

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63277318A (en) * 1987-05-01 1988-11-15 Yukio Matsumoto Specific inner drilling pile work closing hollow part of pile
CN1057082A (en) * 1990-06-04 1991-12-18 俞晓 The dry type steel basket soil basketing method and the device thereof of castinplace pile
CN1141988A (en) * 1996-06-24 1997-02-05 王艳琳 Horizontal-separation type treatment method for extruding enlarging diameter of pile and formation device thereof
WO2000003113A1 (en) * 1998-07-10 2000-01-20 Dexin He A hydraulic pushing-expanding device
GB0103163D0 (en) * 2001-02-08 2001-03-28 Cementation Found Skanska Ltd Improvements relating to piles
JP2004197397A (en) * 2002-12-18 2004-07-15 Kubota Corp Longitudinal joining device for columnar body
JP2004300662A (en) * 2003-03-28 2004-10-28 Hitachi Metals Techno Ltd Pile head joint structure
CN102817357A (en) * 2011-06-10 2012-12-12 上海万德风力发电股份有限公司 Load-bearing foundation piles for offshore large wind driven generators and towers and construction method of load-bearing foundation piles
CN203403406U (en) * 2013-08-23 2014-01-22 梁峰 Tool-type spiral expansion head pull and press pile
CN203795414U (en) * 2014-04-30 2014-08-27 陈佳 Telescopic building pile
CN203834468U (en) * 2014-05-12 2014-09-17 黄丽华 Internal expansion type miniature concrete pile
CN203947481U (en) * 2014-06-30 2014-11-19 中国建筑第二工程局有限公司 Combined type section steel pile transverse baffle plate supporting structure
CN204703153U (en) * 2015-05-23 2015-10-14 上海绿地建设(集团)有限公司 A kind of barb type construction pile
CN204753568U (en) * 2015-07-29 2015-11-11 黄河科技学院 Transverse orientation building stake of difficult wearing and tearing of locating pin
CN204825858U (en) * 2015-07-29 2015-12-02 黄河科技学院 Convenient transverse orientation building stake of retrieving
CN204898663U (en) * 2015-06-17 2015-12-23 浙江水利水电学院 Cutting edge type flap valve stake point with lateral extension function
CN204919532U (en) * 2015-09-07 2015-12-30 浙江宝龙建设有限公司 Novel building stake
CN105544525A (en) * 2015-12-11 2016-05-04 陈明 Uplift pile with unfolding barb and construction method thereof
CN205653778U (en) * 2016-05-25 2016-10-19 浙江乔兴建设集团有限公司 High firm building pile

Patent Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63277318A (en) * 1987-05-01 1988-11-15 Yukio Matsumoto Specific inner drilling pile work closing hollow part of pile
CN1057082A (en) * 1990-06-04 1991-12-18 俞晓 The dry type steel basket soil basketing method and the device thereof of castinplace pile
CN1141988A (en) * 1996-06-24 1997-02-05 王艳琳 Horizontal-separation type treatment method for extruding enlarging diameter of pile and formation device thereof
WO2000003113A1 (en) * 1998-07-10 2000-01-20 Dexin He A hydraulic pushing-expanding device
GB0103163D0 (en) * 2001-02-08 2001-03-28 Cementation Found Skanska Ltd Improvements relating to piles
JP2004197397A (en) * 2002-12-18 2004-07-15 Kubota Corp Longitudinal joining device for columnar body
JP2004300662A (en) * 2003-03-28 2004-10-28 Hitachi Metals Techno Ltd Pile head joint structure
CN102817357A (en) * 2011-06-10 2012-12-12 上海万德风力发电股份有限公司 Load-bearing foundation piles for offshore large wind driven generators and towers and construction method of load-bearing foundation piles
CN203403406U (en) * 2013-08-23 2014-01-22 梁峰 Tool-type spiral expansion head pull and press pile
CN203795414U (en) * 2014-04-30 2014-08-27 陈佳 Telescopic building pile
CN203834468U (en) * 2014-05-12 2014-09-17 黄丽华 Internal expansion type miniature concrete pile
CN203947481U (en) * 2014-06-30 2014-11-19 中国建筑第二工程局有限公司 Combined type section steel pile transverse baffle plate supporting structure
CN204703153U (en) * 2015-05-23 2015-10-14 上海绿地建设(集团)有限公司 A kind of barb type construction pile
CN204898663U (en) * 2015-06-17 2015-12-23 浙江水利水电学院 Cutting edge type flap valve stake point with lateral extension function
CN204753568U (en) * 2015-07-29 2015-11-11 黄河科技学院 Transverse orientation building stake of difficult wearing and tearing of locating pin
CN204825858U (en) * 2015-07-29 2015-12-02 黄河科技学院 Convenient transverse orientation building stake of retrieving
CN204919532U (en) * 2015-09-07 2015-12-30 浙江宝龙建设有限公司 Novel building stake
CN105544525A (en) * 2015-12-11 2016-05-04 陈明 Uplift pile with unfolding barb and construction method thereof
CN205653778U (en) * 2016-05-25 2016-10-19 浙江乔兴建设集团有限公司 High firm building pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190734A (en) * 2017-06-22 2017-09-22 成都赋阳技术开发有限公司 The roadbed supporting pile for repairing construction is built for road and bridge
CN110409428A (en) * 2019-07-01 2019-11-05 东莞市建安集团有限公司 Tube pile structure and its construction method
CN110409428B (en) * 2019-07-01 2021-04-27 东莞市建安集团有限公司 Tubular pile structure and construction method thereof
CN113550299A (en) * 2021-09-06 2021-10-26 芜湖宝正新型材料科技有限公司 Assembled unwrapping wire tubular pile of steel-wood structure

Also Published As

Publication number Publication date
CN105839617B (en) 2024-03-22

Similar Documents

Publication Publication Date Title
CN105839617A (en) High-stability building pile
CN201186838Y (en) Vertical type coil holder
CN105862857A (en) Width-adjustable building pile
CN205653778U (en) High firm building pile
CN205653779U (en) Building pile with side stake
CN205653783U (en) Width adjustable building pile
CN105862726A (en) Building pile with side piles
CN206289940U (en) A kind of building construction support for shuttering
CN210128186U (en) Adjustable crane base
CN204825858U (en) Convenient transverse orientation building stake of retrieving
CN206233535U (en) Lifting scaffold
CN206834000U (en) A kind of strand winder
CN210992821U (en) Sports is with multi-functional training aid
CN205167620U (en) Press dehydrator
CN210728520U (en) Horizontal bar convenient to altitude mixture control
CN203097251U (en) Adjustable anti-displacement device of overhanging type discharging platform
CN113922278A (en) Adjustable electric power cable hoisting device
CN206934662U (en) A kind of screw mandrel lifts basketball stands
CN207058174U (en) A kind of adjustable stainless steel welded pipe device for discharging
CN205944880U (en) Car wiring harness preassembles platform
CN110145128B (en) High-rise public building construction is with platform of unloading
CN220848639U (en) Curtain construction slope hanging flower basket equipment
CN205202236U (en) Korean ginseng forming machine
CN212141282U (en) Children climbing device
CN218563019U (en) A template subassembly for clear water concrete construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A highly stable building pile

Granted publication date: 20240322

Pledgee: Zhejiang Tailong Commercial Bank Co.,Ltd. Huzhou balidian small and micro enterprise franchise sub branch

Pledgor: ZHEJIANG QIAOXING CONSTRUCTION GROUP Co.,Ltd.

Registration number: Y2024980032684

PE01 Entry into force of the registration of the contract for pledge of patent right