Prior art keywords
concrete
water
green concrete
parts
mould
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610158059.2A
Other languages
Chinese (zh)
Other versions
CN105839486A (en
Inventor
李仁�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Ding long green concrete Co., Ltd.
Original Assignee
Shanghai Ding Long Green Concrete Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Ding Long Green Concrete Co Ltd filed Critical Shanghai Ding Long Green Concrete Co Ltd
Priority to CN201610158059.2A priority Critical patent/CN105839486B/en
Publication of CN105839486A publication Critical patent/CN105839486A/en
Application granted granted Critical
Publication of CN105839486B publication Critical patent/CN105839486B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G9/00Cultivation in receptacles, forcing-frames or greenhouses; Edging for beds, lawn or the like
    • A01G9/02Receptacles, e.g. flower-pots or boxes; Glasses for cultivating flowers
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving
    • E01C7/142Mixtures or their components, e.g. aggregate
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Abstract

The invention discloses a kind of soilless green concrete construction methods, including the concrete being stirred addition additive is laid in work surface, are evened up according to the thickness of design requirement;Table hole forming is carried out with concrete table hole forming machine, concrete surface is made to form equally distributed hole;Wait for that green concrete has some strength, people that can be sprinkled into Nutrition Soil and water-retaining agent in above-mentioned hole in the case where walking above;According to the kind of required kind of plant, designed desired mould item is placed on the green concrete surface constructed;The cement mortar being stirred is laid on green concrete surface, some strength to be had takes out mould item, and grass seeds maintenance is sprinkled into mould item.Concrete anti-filter effect that the present invention constructs is good, water penetration, good water-retaining property, and can store the carrier that a certain number of multiple nutritional components are grown for grass planting, can afforest but also bank protection.

Description

Soilless green concrete construction method
Technical field
The present invention relates to a kind of soilless green concrete construction methods.
Background technology
The surfaces such as current existing green concrete, eco-concrete, concrete for plant growth must all lay planting soil Grass can be planted, so that navigable river, deserted mountain bank protection, sandy soil, salt-soda soil etc. can not use the above product.
Invention content
It can be afforested but also the soilless green concrete construction method of bank protection the purpose of the present invention is to provide a kind of.
Technical solution of the invention is:
A kind of soilless green concrete construction method, it is characterized in that:Include the following steps:
(1)The concrete being stirred addition additive is laid in work surface, is evened up according to the thickness of design requirement;
(2)Table hole forming is carried out with concrete table hole forming machine, concrete surface is made to form equally distributed hole;
(3)Wait for that green concrete has some strength, people that can be sprinkled into nutrition in above-mentioned hole in the case where walking above Soil and water-retaining agent;
(4)According to the kind of required kind of plant, designed desired mould is placed on the green concrete surface constructed Item;
(5)The cement mortar being stirred is laid on green concrete surface, some strength to be had takes out mould item, in mould item Inside it is sprinkled into grass seeds maintenance.
Step(1)In the component part weight proportion of concrete be:Stone:400-600 parts, water:70-100 parts, water Mud:80-120 parts;Additive addition is 2-6 parts;Cobble-stone diameter is 5-20mm.
Step(2)In concrete table hole forming machine bottom plate mould stick a length of 60-80mm, diameter 25mm, mould stick spacing is 65mm。
Step(3)The specification of middle water-retaining agent is 60-80 mesh;The addition of Nutrition Soil and the mass ratio of water-retaining agent are 1:0.5~ 1.5。
Step(4)In mould specification 15mm(It is long)×25mm(Diameter);Cement mortar group becomes:80 parts of water, sand 600 Part, 100 parts of cement.
Concrete anti-filter effect that the present invention constructs is good, water penetration, good water-retaining property, and can store a certain number of more The carrier that kind of nutritional ingredient is grown for grass planting, can afforest but also bank protection.
With reference to embodiment, the invention will be further described.
Specific implementation mode
A kind of soilless green concrete construction method, includes the following steps:
(1)The concrete being stirred addition additive is laid in work surface, is evened up according to the thickness of design requirement;
(2)Table hole forming is carried out with concrete table hole forming machine, concrete surface is made to form equally distributed hole;
(3)Wait for that green concrete has some strength, people that can be sprinkled into nutrition in above-mentioned hole in the case where walking above Soil and water-retaining agent;
(4)According to the kind of required kind of plant, designed desired mould is placed on the green concrete surface constructed Item;
(5)The cement mortar being stirred is laid on green concrete surface, some strength to be had(Preliminary solidification, but energy When facilitating taking-up mould)Mould item is taken out, grass seeds maintenance is sprinkled into mould item.
Step(1)In the component part weight proportion of concrete be:Stone:400-600 parts, water:70-100 parts, water Mud:80-120 parts;Additive addition is 2-6 parts;Cobble-stone diameter is 5-20mm.
Step(2)In concrete table hole forming machine bottom plate mould stick a length of 60-80mm, diameter 25mm, mould stick spacing is 65mm。
Step(3)The specification of middle water-retaining agent is 60-80 mesh;The addition of Nutrition Soil and the mass ratio of water-retaining agent are 1:0.5~ 1.5。
Step(4)In mould specification 15mm(It is long)×25mm(Diameter);Cement mortar group becomes:80 parts of water, sand 600 Part, 100 parts of cement.

Claims (3)

1. a kind of soilless green concrete construction method, it is characterized in that:It is made of the following steps:
(1) concrete being stirred addition additive is laid in work surface, is evened up according to the thickness of design requirement;
(2) table hole forming is carried out with concrete table hole forming machine, concrete surface is made to form equally distributed hole;The coagulation The a length of 60-80mm of bottom plate mould stick of native table hole forming machine, diameter 25mm, mould stick spacing is 65mm;
(3) waiting for green concrete has a some strength, people can in the case where walking above, be sprinkled into above-mentioned hole Nutrition Soil and Water-retaining agent;The specification of the water-retaining agent is 60-80 mesh;The addition of Nutrition Soil and the mass ratio of water-retaining agent are 1: 0.5~1.5;
(4) according to the kind of required kind of plant, designed desired mould item is placed on the green concrete surface constructed;
(5) cement mortar being stirred is laid on green concrete surface, some strength to be had takes out mould item, spread in mould item Enter grass seeds maintenance.
2. soilless green concrete construction method according to claim 1, it is characterized in that:Concrete in step (1) Component part weight proportion is:Stone:400-600 parts, water:70-100 parts, cement:80-120 parts;Additive addition is 2-6 Part;Cobble-stone diameter is 5-20mm.
3. soilless green concrete construction method according to claim 1, it is characterized in that:Mould specification in step (4) 15mm×25mm;Cement mortar group becomes:80 parts of water, 600 parts of sand, 100 parts of cement.
CN201610158059.2A 2016-03-21 2016-03-21 Soilless green concrete construction method Active CN105839486B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610158059.2A CN105839486B (en) 2016-03-21 2016-03-21 Soilless green concrete construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610158059.2A CN105839486B (en) 2016-03-21 2016-03-21 Soilless green concrete construction method

Publications (2)

Publication Number Publication Date
CN105839486A CN105839486A (en) 2016-08-10
CN105839486B true CN105839486B (en) 2018-10-30

Family

ID=56587577

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610158059.2A Active CN105839486B (en) 2016-03-21 2016-03-21 Soilless green concrete construction method

Country Status (1)

Country Link
CN (1) CN105839486B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108179756A (en) * 2017-12-28 2018-06-19 深圳市铁汉生态环境股份有限公司 A kind of side slope repairs implementation
CN110100694B (en) * 2019-05-06 2022-04-12 福建星原建设工程发展有限公司 Construction method of green concrete
CN110240451B (en) * 2019-07-11 2020-04-07 福建省顺天亿建设有限公司 Greening concrete and construction method thereof
CN114000510A (en) * 2021-12-11 2022-02-01 上海久鼎绿化混凝土有限公司 Construction method of greening concrete on wet soil soft slope

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008054611A (en) * 2006-09-01 2008-03-13 Tankatsu:Kk Wall-surface greening device, and wall-surface greening construction method using the same
JP5799373B2 (en) * 2010-08-10 2015-10-21 株式会社アイ・イー・ジェー Greening method for soilless slope
CN103362132B (en) * 2013-07-26 2016-08-24 六蜂王(石狮)环保建材有限公司 A kind of construction method of cast-in-place greening concrete protective slope
CN105113518B (en) * 2015-08-20 2017-01-18 三峡大学 Construction method for ecological slope protecting base material by arranging slot pits in slope surface
CN105239532A (en) * 2015-10-15 2016-01-13 福建启鹏生态科技有限公司 Ecological concrete building block similar to sponge and preparation method thereof

Also Published As

Publication number Publication date
CN105839486A (en) 2016-08-10

Similar Documents

Publication Publication Date Title
CN105839486B (en) Soilless green concrete construction method
CN104686284B (en) Northern winter big tree transplanting method
CN102839679B (en) Method for protecting vegetation of concrete slope
CN103250536A (en) Method for spraying to green side slope of hard rock with joints being not developed
CN108093729A (en) Side-slope greening and protection method
CN206667272U (en) A kind of slope vegetation protection structure
CN103708776A (en) Ecological recovery method with combination application of planting ecological concrete and high-molecular aggregates
CN105780787A (en) Bottom column and surface hole type cast-in-place planting concrete, and preparation method and device
CN103404422A (en) Water saving planting method for lotus roots
CN105369793A (en) Desertification control method
CN105165461B (en) It is a kind of for the afforestation plant growth block of random-shaping, its preparation method and its application
CN102660958B (en) Method for protecting ecology of slope through sprinkling irrigation of CS (carbon steel) mixed fibers
CN105272513A (en) Environmental-protection type nutritional basal disc and application thereof
CN204626783U (en) A kind of New-type green house concrete column
CN104067799A (en) Method for cultivating plants through sludge
CN106900484A (en) Hybridize the method for transplanting of the big tree of Liriodendron chinense in clay ground
CN204157277U (en) Have slow releasing fertilizer efficiency, water retaining function plant raw lattice
CN203457580U (en) Rock face ecological restoration lifting planting device
CN106234144A (en) Taxus mairei and Lignum nanmu Mixed forestation method
CN204634538U (en) A kind of booth concrete column of mis-collision preventing
CN204000903U (en) Slope protection greening net
CN102677686B (en) Slope protection structure by using plant growing rope to conduct karst side slope nursing
CN203729312U (en) Steep slope greening structure with supporting type thick layer substrate
CN202444866U (en) Device capable of being used for planting trees on vertical banks or abrupt slopes
CN204634540U (en) A kind of convenient booth concrete column hanging thing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20170109

Address after: 201208 Shanghai city Pudong New Area New Road No. 333

Applicant after: Shanghai Ding long green concrete Co., Ltd.

Address before: 226200 Jiangsu city of Nantong province Qidong City East Village 43, room 104

Applicant before: Li Ren

GR01 Patent grant
GR01 Patent grant