CN105839479A - Novel sleeper and manufacturing method thereof - Google Patents

Novel sleeper and manufacturing method thereof Download PDF

Info

Publication number
CN105839479A
CN105839479A CN201610314530.2A CN201610314530A CN105839479A CN 105839479 A CN105839479 A CN 105839479A CN 201610314530 A CN201610314530 A CN 201610314530A CN 105839479 A CN105839479 A CN 105839479A
Authority
CN
China
Prior art keywords
sleeper
billet
lower floor
novel
nut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610314530.2A
Other languages
Chinese (zh)
Other versions
CN105839479B (en
Inventor
韩时捷
王施恩
吴庆飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai International Port Group Co Ltd
CCCC Third Harbor Consultants
Original Assignee
Shanghai International Port Group Co Ltd
CCCC Third Harbor Consultants
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai International Port Group Co Ltd, CCCC Third Harbor Consultants filed Critical Shanghai International Port Group Co Ltd
Priority to CN201610314530.2A priority Critical patent/CN105839479B/en
Publication of CN105839479A publication Critical patent/CN105839479A/en
Application granted granted Critical
Publication of CN105839479B publication Critical patent/CN105839479B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B23/00Easily dismountable or movable tracks, e.g. temporary railways; Details specially adapted therefor
    • E01B23/10Shiftable tracks for heavy loads, e.g. carrying excavators
    • E01B23/12Sleepers

Abstract

The invention discloses a novel sleeper. The novel sleeper comprises a sleeper body. A lower layer steel cushion plate is pre-buried in the sleeper body. Anchor ribs and nuts are welded to the bottom of the lower layer steel cushion plate. The nuts 4 are sleeved with sleeves. An upper layer steel cushion plate is arranged above the lower layer steel cushion plate. Bolts penetrate through the upper layer steel cushion plate and the lower layer steel cushion plate from the upper side to be connected with the nuts. The bolts can be adjusted. The number of the anchor ribs is set according to the requirements of the upper portion of the lower layer steel cushion plate for working loads. The invention further discloses a manufacturing method of the novel sleeper. The novel sleeper is simple in structure and easy to obtain, site installation efficiency and construction quality can be improved, and meanwhile engineering primary investment expenditures and later maintenance and replacement expenditures are saved.

Description

A kind of Novel sleeper and manufacture method thereof
Technical field
The present invention relates to concrete sleeper, specifically, be a kind of Novel sleeper and manufacture method thereof, it can run harbour Harbour automatization fortune loop wheel machine structure.
Background technology
Mountain, ocean Phase IV project will turn domestic largest port district of automatization into, and heap place intends using high-speed cruising Automatization's rail gantry crane carries out handling operation.Big, to track installation accuracy for mountain, ocean Phase IV project land-based area residual settlement amount Require high objective present situation, it is proposed that a kind of novel tie structure, adjustable pedestal is organically combined, to reach with conventional sleeper Ensure that under high accuracy and efficient adjustment premise, initial investment relatively saves and the later stage safeguards, without changing, the purpose adjusted.
Summary of the invention
It is an object of the invention to provide one initial investment under ensureing high accuracy and efficient adjustment premise relatively to save and the later stage Without changing Novel sleeper of maintenance and preparation method thereof.
For achieving the above object, the present invention adopts the technical scheme that:
A kind of Novel sleeper, described Novel sleeper includes a sleeper body, this internal pre-buried lower floor billet of described sleeper, described Lower floor's billet bottom welding dowel and nut, be provided with sleeve pipe outside described nut, described lower floor billet is arranged over upper strata Billet, bolt is from above through described upper strata billet and described lower floor billet and is connected with nut, bolt scalable.
Further, described lower floor's billet is embedded in sleeper, and both connected modes use dowel form.
Further, hard PVC sleeve pipe selected by described sleeve pipe.
Further, described bolt uses hexagonal connecting bolt.
Further, the quantity of described dowel, require configuration according to described lower floor's billet top working load.
The another kind of technical scheme of the present invention, the manufacture method of Novel sleeper, comprise the steps:
(1) at lower floor's billet bottom welding dowel and nut;
(2) nut outer sheath is wrapped up in hard PVC sleeve pipe and fixes;
(3) the lower floor's billet processed is embedded in sleeper;
(4) connect fixing for upper and lower layer billet with hexagonal connecting bolt after the cast-in-place molding of sleeper.
Beneficial effect
Heretofore described lower floor's billet is embedded in sleeper, uses dowel form to replace conventional bolt anchoring;Pre-buried The nut of lower floor's billet bottom welding and the setting of hard PVC sleeve pipe solve the connecting bolt body of rod can only upward, and track is adjusted Whole period is used to affect repeatedly to change by track equipment and is limited.Structural texture of the present invention is simple, easily realizes, and can improve existing Field installation effectiveness and construction quality, save engineering initial investment expense and later maintenance renewal cost simultaneously.
Accompanying drawing explanation
Accompanying drawing 1 is the floor map of a kind of Novel sleeper of the present invention.
Accompanying drawing 2 is the sectional view in direction shown in line A-A in Fig. 1.
The reference and the ingredient that relate in accompanying drawing are as follows:
1. sleeper body 2. lower floor billet
3. hard PVC sleeve pipe 4. nut
5. upper strata billet 6. hexagonal connecting bolt
7. dowel.
Detailed description of the invention
Below in conjunction with example and referring to the drawings the invention will be further described.
Embodiment 1
With reference to Fig. 1, the schematic diagram shown in 2, Fig. 2 is the sectional view in direction shown in line A-A in Fig. 1.This Novel sleeper includes sleeper Body 1, lower floor's billet 2, hard PVC sleeve pipe 3, nut 4, upper strata billet 5, hexagonal connecting bolt 6, dowel 7.
Lower floor's steel pad 2 buttress requires configuration some anchor ribs 7 according to top working load, uses welding manner to carry out even Connect;Simultaneously for meeting the demand that levels billet is connected by hexagonal connecting bolt 6, corresponding connection bottom lower floor's billet The position welding matching nut 4 of bolt aperture, and wrap up in hard PVC sleeve pipe 3 at nut overcoat, to ensure connecting bolt and concrete The isolation of structure.
Embodiment 2
The manufacture method of the present invention, comprises the steps:
(1) at lower floor's billet bottom welding dowel and nut;
(2) nut outer sheath is wrapped up in hard PVC sleeve pipe and fixes;
(3) the lower floor's billet processed is embedded in sleeper;
(4) connect fixing for upper and lower layer billet with hexagonal connecting bolt after the cast-in-place molding of sleeper.
The simple in construction of track foundation of the present invention, easily realizes, and can improve in-site installation efficiency and construction quality.

Claims (6)

1. a Novel sleeper, described Novel sleeper includes a sleeper body, it is characterised in that: described sleeper this most internal pre-buried under Layer billet, described lower floor billet bottom welding dowel and nut, be provided with sleeve pipe, described lower floor billet outside described nut Being arranged over upper strata billet, bolt from above through described upper strata billet and described lower floor billet and is connected with nut, Bolt scalable.
2. Novel sleeper as claimed in claim 1, it is characterised in that: described lower floor's billet is embedded in sleeper, both Connected mode use dowel form.
3. Novel sleeper as claimed in claim 1, it is characterised in that: hard PVC sleeve pipe selected by described sleeve pipe.
4. Novel sleeper as claimed in claim 1, it is characterised in that: described bolt uses hexagonal connecting bolt.
5. Novel sleeper as claimed in claim 1, it is characterised in that: the quantity of described dowel, according to described lower floor steel pad Plate top working load requires configuration.
6., such as the manufacture method of any one Novel sleeper of claim 1-4, comprise the steps:
(1) at lower floor's billet bottom welding dowel and nut;
(2) nut outer sheath is wrapped up in hard PVC sleeve pipe and fixes;
(3) the lower floor's billet processed is embedded in sleeper;
(4) connect fixing for upper and lower layer billet with hexagonal connecting bolt after the cast-in-place molding of sleeper.
CN201610314530.2A 2016-05-13 2016-05-13 A kind of Novel sleeper and its manufacturing method Active CN105839479B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610314530.2A CN105839479B (en) 2016-05-13 2016-05-13 A kind of Novel sleeper and its manufacturing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610314530.2A CN105839479B (en) 2016-05-13 2016-05-13 A kind of Novel sleeper and its manufacturing method

Publications (2)

Publication Number Publication Date
CN105839479A true CN105839479A (en) 2016-08-10
CN105839479B CN105839479B (en) 2018-10-16

Family

ID=56591815

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610314530.2A Active CN105839479B (en) 2016-05-13 2016-05-13 A kind of Novel sleeper and its manufacturing method

Country Status (1)

Country Link
CN (1) CN105839479B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107338687A (en) * 2017-08-28 2017-11-10 华东交通大学 A kind of combined type sleeper

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB132428A (en) *
JP2002309502A (en) * 2001-04-18 2002-10-23 Sekisui Chem Co Ltd Method for redriving screw spike into composite sleeper
CN101014743A (en) * 2004-04-29 2007-08-08 Bwg股份有限两合公司 Fixing for a rail and arrangement for fixing rails
CN201292488Y (en) * 2008-11-12 2009-08-19 铁道第三勘察设计院集团有限公司 Medium low speed magnetic floating line rail fastener
CN201627122U (en) * 2009-06-22 2010-11-10 东守金 Reinforced concrete sleeper for mine
CN204703012U (en) * 2015-05-22 2015-10-14 中交第三航务工程勘察设计院有限公司 Dual adjustable formula track foundation
CN205617162U (en) * 2016-05-13 2016-10-05 中交第三航务工程勘察设计院有限公司 Novel sleeper

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB132428A (en) *
JP2002309502A (en) * 2001-04-18 2002-10-23 Sekisui Chem Co Ltd Method for redriving screw spike into composite sleeper
CN101014743A (en) * 2004-04-29 2007-08-08 Bwg股份有限两合公司 Fixing for a rail and arrangement for fixing rails
CN201292488Y (en) * 2008-11-12 2009-08-19 铁道第三勘察设计院集团有限公司 Medium low speed magnetic floating line rail fastener
CN201627122U (en) * 2009-06-22 2010-11-10 东守金 Reinforced concrete sleeper for mine
CN204703012U (en) * 2015-05-22 2015-10-14 中交第三航务工程勘察设计院有限公司 Dual adjustable formula track foundation
CN205617162U (en) * 2016-05-13 2016-10-05 中交第三航务工程勘察设计院有限公司 Novel sleeper

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107338687A (en) * 2017-08-28 2017-11-10 华东交通大学 A kind of combined type sleeper

Also Published As

Publication number Publication date
CN105839479B (en) 2018-10-16

Similar Documents

Publication Publication Date Title
CN102383418B (en) Anti-seismic prefabricated concrete solid square pile and production method thereof
CN104947603B (en) A kind of rc beam bridge girder reinforcing construction and reinforcement means
CN203755778U (en) Assembly external pre-stress reactive powder concrete wind power tower
CN211517947U (en) Bridge case roof beam is prefabricated with shaped steel pedestal
CN107964979A (en) A kind of transmission line of electricity combining structure assembled cushion cap anchor rod foundation
CN105714678B (en) A kind of combined type gravity anchorage
CN102733307A (en) Method for constructing cast-in-place beam falsework
CN1804238A (en) Combined foundation of backstay type machinery apparatus
CN106381810B (en) With the cast-in-place outstanding method for filling beam of beam-column type bracket
CN105839479A (en) Novel sleeper and manufacturing method thereof
CN205501843U (en) Consolidate rigid framed arch bridge
CN205617162U (en) Novel sleeper
CN204780635U (en) Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures
CN204282388U (en) A kind of pile foundation reinforcement structure adopting compound pile to construct
CN203782670U (en) Floating box platform for over-water construction
CN206052565U (en) A kind of beam-column type bracket
CN202809636U (en) Light steel plant column foundation adapted to filling subgrade settlement
CN203939023U (en) Anti-seismic prefabricated concrete triangle solid pile
CN209523212U (en) Assembled isolated footing
CN114717956A (en) Bridge pier column diaphragm construction umbrella-type support system
CN202672174U (en) Cone-shaped upright foundation of frozen soil region
CN103696611A (en) Base structure for steel tube tower
CN209066196U (en) Railway high-filled embankment box-structure
CN107023029B (en) Hollow circular truncated cone gravity type flexible fan foundation and construction method thereof
CN205997154U (en) The stretching bed seat of the U-shaped beam of track traffic large-tonnage pretensioning prestressed concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: No. 831 zhaojiaman Road, Xuhui District, Shanghai

Applicant after: CCCC Third Harbor Consultants Co., Ltd.

Applicant after: Shanghai International Port (Group) Co., Ltd.

Address before: 200032 831 Zhaojia Bang Road, Xuhui District, Shanghai

Applicant before: CCCC Third Harbor Consultants Co., Ltd.

Applicant before: Shanghai International Port (Group) Co., Ltd.

GR01 Patent grant
GR01 Patent grant