CN209523212U - Assembled isolated footing - Google Patents

Assembled isolated footing Download PDF

Info

Publication number
CN209523212U
CN209523212U CN201822217276.1U CN201822217276U CN209523212U CN 209523212 U CN209523212 U CN 209523212U CN 201822217276 U CN201822217276 U CN 201822217276U CN 209523212 U CN209523212 U CN 209523212U
Authority
CN
China
Prior art keywords
reinforcing bar
cylinder
pedestal
bolt
isolated footing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822217276.1U
Other languages
Chinese (zh)
Inventor
尚志海
李家富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ceri Architects & Engineers Co Ltd
MCC Capital Engineering and Research Incorporation Ltd
Zhongye Jingcheng Engineering Technology Co Ltd
Original Assignee
Ceri Architects & Engineers Co Ltd
Zhongye Jingcheng Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ceri Architects & Engineers Co Ltd, Zhongye Jingcheng Engineering Technology Co Ltd filed Critical Ceri Architects & Engineers Co Ltd
Priority to CN201822217276.1U priority Critical patent/CN209523212U/en
Application granted granted Critical
Publication of CN209523212U publication Critical patent/CN209523212U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of assembled isolated footings, it is related to construction engineering technical field, the assembled isolated footing includes: pedestal, multiple first bolts are embedded in the pedestal, first bolt is embedded in the pedestal close to the part on head, first bolt protrudes the upper surface of the pedestal close to the part of screw rod, and the upper end of the pedestal offers the first groove;Cylinder on the base is set, the lower end of the cylinder is embedded with the shear key that can be embedded in first groove, multiple through holes are offered on the cylinder along the vertical direction, the screw portion of first bolt is inserted into the through hole and is screwed into nut so that the cylinder is fixedly connected with the pedestal.The application on the basis of proof strength, firmness are met the requirements its can be assembled to form the higher cylinder of band and heavier-weight isolated footing.

Description

Assembled isolated footing
Technical field
The utility model relates to construction engineering technical field, in particular to a kind of assembled isolated footing.
Background technique
Prefabricated concrete structure is to be formed by prefabricated components through assembly connection, and prefabricated components are wherein main stress structure Part.Prefabricated concrete structure is one of the important directions of China's building structure development, it is conducive to China's building industrialization Development, raising production efficiency is energy saving, develops Green environmental-protection building, and is conducive to improve and guarantee construction engineering quality. Compared with cast-in-situ construction method, fabricated construction is conducive to green construction, because fabricated construction can more meet in green construction Save land, energy conservation, section material, water-saving and environmental protection etc. require, the negative effect to environment can be reduced, including reduce noise, It fugitive dust is prevented, reduces environmental pollution, cleans transport, reduce place interference, save resources and the energy such as water power material, it then follows can The principle of sustainable development.
The work progress of isolated footing of the cast-in-place concrete with cylinder is digging in-situ foundation trench, construction cushion coat, formwork, binding Reinforcing bar, placing concrete.Have the shortcomings that in entire work progress many: 1, long construction period, work progress are easy to make environment At pollution, it is unfavorable for environmentally protective;2, basis is used only once, and is resulted in waste of resources;3, Foundation Fieldbus field is constructed, coagulation soil property Amount is not easy to guarantee.The shortcomings that for above-mentioned construction, someone be layered to step isolated footing prefabricated, then on-site consolidation, Or whole prefabrication being carried out to small in size, light-weight basis, then transport to building site installation, both methods addresses only certain The problem of prefabricated installation on basis.But for higher, heavier-weight the isolated footing with cylinder, there is presently no assembly Therefore the solution of formula needs a kind of assembled isolated footing to solve the above problems.
Utility model content
In order to overcome the drawbacks described above of the prior art, the technical problem to be solved is that provide for the utility model embodiment A kind of assembled isolated footing, it can be assembled to form band compared with Gao Zhu on the basis of proof strength, firmness are met the requirements Body and heavier-weight isolated footing.
The specific technical solution of the utility model embodiment is:
A kind of assembled isolated footing, the assembled isolated footing include:
Pedestal is embedded with multiple first bolts in the pedestal, and first bolt is embedded in institute close to the part on head It states in pedestal, first bolt protrudes the upper surface of the pedestal close to the part of screw rod, and the upper end of the pedestal offers First groove;
Cylinder on the base is set, and the lower end of the cylinder is embedded with the shearing resistance that can be embedded in first groove Key, multiple through holes are offered on the cylinder along the vertical direction, and the screw portion of first bolt is inserted into the through hole In and be screwed into nut so that the cylinder is fixedly connected with the pedestal.
Preferably, the cylinder is internally provided with obturator, and the obturator is made of polyurethane material.
Preferably, the shear key uses I-steel.
Preferably, cement mortar can be injected in the through hole.
Preferably, first bolt is arranged along the vertical direction, and first bolt is distributed around first groove.
Preferably, horizontally extending the first reinforcing bar and the second reinforcing bar, first spiral shell are provided in the pedestal The position on the head of bolt is between first reinforcing bar and second reinforcing bar.
Preferably, the channel for being connected to first groove is offered in the pedestal, the channel is used for the shearing resistance Grouting material is injected in the gap of key and first groove.
Preferably, the lower end of the cylinder has the stage portion protruded to horizontal direction, and the through hole is located at described Rank portion.
Preferably, the horizontally extending bottom-up third reinforcing bar being sequentially distributed, are provided in the cylinder Four reinforcing bars and the 5th reinforcing bar, are provided with the 6th reinforcing bar and the 7th reinforcing bar extended along the vertical direction in the cylinder, and the described 5th The both ends of reinforcing bar connection the 6th reinforcing bar and the 7th reinforcing bar, the third reinforcing bar and the 4th reinforcing bar are more than institute respectively It states at through hole, the 6th reinforcing bar and the 7th reinforcing bar are located at the surrounding of the cylinder, the 6th reinforcing bar and institute The lower end for stating the 7th reinforcing bar extends at the third reinforcing bar.
Preferably, the upper end of the cylinder is embedded with the second bolt or L-type steel muscle.
The technical solution of the utility model have it is following significant the utility model has the advantages that
For traditional free band cylinder integral cast-in-situ basis, either rim of a cup formula, anchor bolt type or direct-burried reinforcing bar formula It is both needed to live formwork, ties up reinforcing bar, placing concrete needs to conserve concrete, needs to reach design strength in concrete The construction of superstructure can be carried out afterwards.And the assembled isolated footing in the application can save live formwork, concrete pours It builds and curing time, assembly can quickly carry out subsequent construction after the completion, save the duration, work progress is environmentally protective.This is practical Novel the shortcomings that overcoming the construction of Foundation Fieldbus field placing concrete, meets the needs that China pushes assembled architecture energetically, have There are major and immediate significance and engineering application value.
Referring to following description and accompanying drawings, the particular implementation of the utility model is disclosed in detail, specifies practical Novel principle can be in a manner of adopted.It should be understood that the embodiments of the present invention in range not thus by Limitation.In the range of the spirit and terms of appended claims, the embodiments of the present invention includes many changes, modifications With it is equivalent.The feature for describing and/or showing for a kind of embodiment can be in a manner of same or similar one or more It uses in a other embodiment, is combined with the feature in other embodiment, or the feature in substitution other embodiment.
Detailed description of the invention
Attached drawing described here is only used for task of explanation, and is not intended to limit in any way disclosed by the utility model Range.In addition, shape and proportional sizes of each component in figure etc. are only schematically, to be used to help the reason to the utility model Solution is not the specific shape and proportional sizes for limiting each component of the utility model.Those skilled in the art is practical new at this Under the introduction of type, various possible shapes and proportional sizes can be selected to implement the utility model as the case may be.
Fig. 1 is the general assembly drawing of assembled isolated footing in the utility model embodiment;
Fig. 2 is the first structural schematic diagram of the utility model embodiment middle column body;
Fig. 3 is second of structural schematic diagram of the utility model embodiment middle column body;
Fig. 4 is the third structural schematic diagram of the utility model embodiment middle column body;
Fig. 5 is the front view of pedestal in the utility model embodiment;
Fig. 6 is the top view of pedestal in the utility model embodiment;
Fig. 7 is the structural schematic diagram of the first bolt in the utility model embodiment.
The appended drawing reference of the figures above:
1, pedestal;2, the first bolt;3, the first groove;4, channel;5, hanging ring;6, bed course;7, cylinder;8, shear key;9, Through hole;10, stage portion;11, obturator;12, the first reinforcing bar;13, the second reinforcing bar;14, third reinforcing bar;15, the 4th reinforcing bar; 16, the 5th reinforcing bar;17, the 6th reinforcing bar;18, the 7th reinforcing bar;19, the second bolt;20, L-type steel muscle;21, nut;22, washer.
Specific embodiment
In conjunction with the description of attached drawing and specific embodiment of the present invention, the utility model can be clearly understood Details.But specific embodiment of the present utility model described herein, it is only used for explaining the purpose of this utility model, without It can be understood as being limitations of the present invention in any way.Under the introduction of the utility model, technical staff is contemplated that Any possible deformation based on the utility model, these are regarded as belonging to the scope of the utility model.It needs to illustrate It is that when element is referred to as " being set to " another element, it can directly on the other element or there may also be placed in the middle Element.When an element is considered as " connection " another element, it can be directly to another element or can Centering elements can be existed simultaneously.Term " installation ", " connected ", " connection " shall be understood in a broad sense, for example, it may be mechanical connection or Electrical connection, the connection being also possible to inside two elements can be directly connected, can also indirectly connected through an intermediary, For the ordinary skill in the art, the concrete meaning of above-mentioned term can be understood as the case may be.Made herein Term " vertical ", " horizontal ", "upper", "lower", "left", "right" and similar statement simply to illustrate that mesh , it is not meant to be the only embodiment.
Unless otherwise defined, all technical and scientific terms used herein and the technical field for belonging to the application The normally understood meaning of technical staff is identical.The term used in the description of the present application is intended merely to description tool herein The purpose of the embodiment of body, it is not intended that in limitation the application.Term as used herein "and/or" includes one or more Any and all combinations of relevant listed item.
For be assembled to form band higher cylinder on the basis of proof strength, firmness are met the requirements and heavier-weight Isolated footing, propose a kind of assembled isolated footing in the embodiment of the present application, Fig. 1 is to fill in the utility model embodiment General assembly drawing with formula isolated footing is embedded with multiple as shown in Figure 1, assembled isolated footing may include: pedestal 1 in pedestal 1 First bolt 2, the first bolt 2 are embedded in pedestal 1 close to the part on head, and the first bolt 2 protrudes bottom close to the part of screw rod The upper surface of seat 1, the upper end of pedestal 1 offers the first groove 3;Cylinder 7 on pedestal 1 is set, and the lower end of cylinder 7 is embedded with It can be embedded in the shear key 8 of the first groove 3, offer multiple through holes 9, the threaded shank of the first bolt 2 on cylinder 7 along the vertical direction Divide and is inserted through in hole 9 and is screwed into nut 21 so that cylinder 7 is fixedly connected with pedestal 1.
Fig. 5 is the front view of pedestal in the utility model embodiment, and Fig. 6 is the vertical view of pedestal in the utility model embodiment Figure, as shown in Figure 5 and Figure 6, pedestal 1 is horizontally extending, with certain thickness with proof strength.Pedestal 1 is in factory Prefabricated to form, size, thickness and amount of reinforcement after Force Calculation specifically by determining.It the cross section of pedestal 1 can be in rectangle, just Rectangular, round or other irregular shapes etc. do not do any restrictions to it in this application, and the transversal mask body of pedestal 1 can To be determined according to actual needs.
As shown in figure 5, being embedded with multiple first bolts 2 in pedestal 1, the first bolt 2 is arranged along the vertical direction.First bolt 2 are embedded in pedestal 1 close to the part on head, and the first bolt 2 protrudes the upper surface of pedestal 1 close to the part of screw rod, pedestal 1 Upper end offers the first groove 3.It is provided with horizontally extending the first reinforcing bar 12 and the second reinforcing bar 13 in pedestal 1, first It the position on the head of bolt 2 can be between the first reinforcing bar 12 and the second reinforcing bar 13, so in the first bolt 2 under tension Or more can uniformly share pulling force or torque to this pedestal 1 when torque, to guarantee the first bolt 2 and pedestal 1 Between the secured intensity that connects.The arrangement of reinforcement quantity of first reinforcing bar 12 and the second reinforcing bar 13 is carried with specific reference to 1 top of pedestal in pedestal 1 Lotus is determined.
As shown in Figure 5 and Figure 6, the upper center of pedestal 1 offers the first groove 3, and the first groove 3 is used for 8 energy of shear key It is enough embedded, the first bolt 2 is distributed around the first groove 3.The concrete shape of first bolt 2 distribution can be according to the water of cylinder 7 Flat cross-sectional shape is determined that the surrounding for meeting cylinder 7 has the first bolt 2 to pass through.The particular number of first bolt 2, material Matter and diameter can be determined according to the Calculation and Analysis of Force between pedestal 1 and cylinder 7.The material of first bolt 2 can choose The models such as Q235 or Q345.
As shown in figure 5, handling and assembly in order to facilitate pedestal 1 in assembly, it can in the prefabrication process of pedestal 1 To hold setting hanging ring 5 on it, hanging ring 5 can be distributed in the surrounding of pedestal 1 to be multiple.
As shown in Figure 1, offering the channel 4 of the first groove 3 of connection in pedestal 1, which can prolong in the horizontal direction It stretches, is connected to the side wall of pedestal 1.After shear key is embedded in the first groove 3, channel 4 is used between shear key and the first groove 3 Gap injects grouting material, so that being securely attached to together between shear key and pedestal 1.
As shown in Figure 1, the top of pedestal 1 can be arranged in cylinder 7.Cylinder 7 extends substantially in the vertical direction, pre- in factory It makes, size, shape and amount of reinforcement after Force Calculation specifically by determining.During being prefabricated in the factory, the lower end of cylinder 7 Medium position at be embedded with the shear key 8 that can be embedded in the first groove 3.8 top of shear key is embedded in cylinder 7, under shear key 8 Portion's protrusion.When cylinder 7 and pedestal 1 link together, the cutting in the horizontal direction that can be subject to cylinder 7 by shear key 8 Shear force is transferred on pedestal 1, to guarantee the firmness connected between cylinder 7 and pedestal 1.In the present embodiment, shearing resistance Key uses I-steel.
As shown in Figure 1, multiple through holes 9 are offered on cylinder 7 along the vertical direction.When cylinder 7 is arranged on pedestal 1, The screw portion of first bolt 2 is inserted through in hole 9 and is screwed into nut 21 so that cylinder 7 is fixedly connected with pedestal 1, by above-mentioned Mode achievees the purpose that cylinder 7 and pedestal 1 assemble.In a kind of feasible embodiment, the lower end of cylinder 7 has to level side The stage portion 10 protruded around, that is to say, that the cross-sectional area of 7 lower end of cylinder is greater than the cross-sectional area of 7 upper end of cylinder. Through hole 9 is located at stage portion 10, and through hole 9 has can be set in the surrounding of stage portion 10.The cross-sectional shape of stage portion 10 with The concrete shape of first bolt 2 distribution matches.When the screw portion of the first bolt 2 is inserted through in hole 9, the first bolt 2 Upper end exceeds the upper surface of stage portion 10, and Fig. 7 is the structural schematic diagram of the first bolt in the utility model embodiment, such as Fig. 7 institute Show, then the washer 22 being relatively large in diameter is set on the first bolt 2, be finally screwed into nut 21 and is tightened.21 pine of nut in order to prevent It is de-, two nuts 21 can be screwed on the first bolt 2.After the first bolt 2 is tightened with nut 21, can be to the first bolt 2 outside Dew part and nut 21 smear pitch to achieve the purpose that anti-corrosion protection.
As shown in Figure 1, being fit into through hole 9 in order to protect the first bolt 2 in through hole 9 in the first bolt 2 and inciting somebody to action Cylinder 7 can inject cement mortar in through hole 9 after adjusting in place.
As shown in Figure 1, the middle part of cylinder 7 is internally provided with obturator 11, obturator 11 by lightweight polyurethane material system At, the whole weight of cylinder 7 can be mitigated under the premise of guaranteeing that cylinder 7 has enough support loads, consequently facilitating cylinder 7 Transport and the assembly between cylinder 7 and pedestal 1.
Fig. 2 is the first structural schematic diagram of the utility model embodiment middle column body, as shown in Fig. 2, being provided in cylinder 7 The horizontally extending bottom-up third reinforcing bar 14 being sequentially distributed, the 4th reinforcing bar 15 and the 5th reinforcing bar 16 is set in cylinder 7 It is equipped with the 6th reinforcing bar 17 and the 7th reinforcing bar 18 extended along the vertical direction, the 5th reinforcing bar 16 connects the 6th reinforcing bar 17 and the 7th reinforcing bar 18, the 5th reinforcing bar 16 is for improving the tensile property of cylinder 7 in the horizontal direction.The both ends of third reinforcing bar 14 and the 4th reinforcing bar 15 It is respectively more than that at through hole 9, can so guarantee that there is enough intensity at through hole 9, and then be conducive to the connection of the first bolt 2 The firmness of cylinder 7 and pedestal 1.6th reinforcing bar 17 and the 7th reinforcing bar 18 are located at the surrounding of cylinder 7,17 He of the 6th reinforcing bar The lower end of 7th reinforcing bar 18 extends at third reinforcing bar 14, and the 6th reinforcing bar 17 and the 7th reinforcing bar 18 are for improving cylinder 7 in vertical side Upward tensile property.
As shown in Fig. 2, handling and assembly in order to facilitate cylinder 7 in assembly, it can in the prefabrication process of cylinder 7 To bury hanging ring 5 on its side wall, hanging ring 5 can be distributed on different side walls to be multiple.
As shown in Fig. 2, the upper end of cylinder 7 can be in rim of a cup formula, to be connected for the other components prefabricated with top.? In second of embodiment, Fig. 3 is second of structural schematic diagram of the utility model embodiment middle column body, as shown in figure 3, cylinder 7 upper end can be embedded with the second bolt 19 being vertically arranged, and the head of the second bolt 19 is located inside cylinder 7, the second bolt 19 half of screw exposes the upper surface of cylinder 7, by the second bolt 19 to realize cylinder 7 top and prefabricated other structures Part is connected.In the third embodiment, Fig. 4 is the third structural schematic diagram of the utility model embodiment middle column body, such as Shown in Fig. 4, the upper end of cylinder 7 can be embedded with L-type steel muscle 20, using reserved joint bar mode and top cast-in-place concrete structure phase Connection.
It also proposed a kind of assembly method using any of the above-described assembled isolated footing in this application, may include Following steps:
Cylinder 7 is sling by loop wheel machine, so that the through hole 9 of the first bolt 2 and cylinder 7 on pedestal 1 aligns.
Cylinder 7 is transferred, so that the first bolt 3 on pedestal 2 passes through the through hole 9 of cylinder 7, the insertion first of shear key 8 is recessed Slot 3.
Cement mortar is injected into through hole 9 to fill the gap between the first bolt 2 and cylinder 7.
Washer 22 is inserted in the first bolt 2, then is screwed into nut 21 so that pedestal 1 is fixedly connected with 7 phase of cylinder.
There is the channel 4 of the first groove 3 of connection in pedestal 1, grouting material is injected into the first groove 3 by channel 4.
After being screwed into nut 21 on the first bolt 2, leakage part and nut 21 to the first bolt 2 carry out smearing pitch work Industry is to reach corrosion-resistant purpose.
Assembled isolated footing passes through segment design in the application, and pedestal 1 and cylinder 7 is prefabricated in factory's segmentation progress, To which assembly can be carried out on bed course 6 at the construction field (site).The assembled isolated footing pre-buried first bolt 2 in pedestal 1, Through hole 9 is offered on cylinder 7, when cylinder 7 is arranged on pedestal 1, is penetrated in through hole 9 and is screwed by the first bolt 2 Nut 21 is to realize that short column and pedestal 1 assemble stress performance that is integral, and reaching cast-in-place mass-type foundation.Meanwhile in 7 He of cylinder It is additionally provided with shear key between pedestal 1, to be further ensured that the shearing force born on cylinder 7 in the horizontal direction can be passed effectively To pedestal 1.
For traditional free band cylinder integral cast-in-situ basis, either rim of a cup formula, anchor bolt type or direct-burried reinforcing bar formula It is both needed to live formwork, ties up reinforcing bar, placing concrete needs to conserve concrete, needs to reach design strength in concrete The construction of superstructure can be carried out afterwards.And the assembled isolated footing in the application can save live formwork, concrete pours It builds and curing time, assembly can quickly carry out subsequent construction after the completion, save the duration, work progress is environmentally protective.This is practical Novel the shortcomings that overcoming the construction of Foundation Fieldbus field placing concrete, meets the needs that China pushes assembled architecture energetically, have There are major and immediate significance and engineering application value.
All articles and reference disclosed, including patent application and publication, for various purposes by quoting knot Together in this.Describing combined term " substantially by ... constitute " should include identified element, ingredient, component or step and reality Other elements, ingredient, component or the step of the basic novel feature of the combination are not influenced in matter.Using term "comprising" or " comprising " describes the combination of element here, ingredient, component or step it is also contemplated that substantially by these elements, ingredient, component Or the embodiment that step is constituted.Here by using term " can with ", it is intended to illustrate that " can with " includes described any Attribute is all optional.Multiple element, ingredient, component or step can be mentioned by single integrated component, ingredient, component or step For.Alternatively, single integrated component, ingredient, component or step can be divided into multiple element, ingredient, component or the step of separation Suddenly.For describe the open "a" or "an" of element, ingredient, component or step do not say in order to exclude other elements, at Point, component or step.
All the embodiments in this specification are described in a progressive manner, the highlights of each of the examples are with The difference of other embodiments, the same or similar parts between the embodiments can be referred to each other.Above-described embodiment is only Illustrate the technical ideas and features of the present invention, it is practical new its object is to allow person skilled in the art that can understand this The content of type is simultaneously implemented accordingly, does not limit the protection scope of the present invention.It is all real according to the spirit of the present invention Equivalent change or modification made by matter, should be covered within the scope of the utility model.

Claims (10)

1. a kind of assembled isolated footing, which is characterized in that the assembled isolated footing includes:
Pedestal is embedded with multiple first bolts in the pedestal, and first bolt is embedded in the bottom close to the part on head In seat, first bolt protrudes the upper surface of the pedestal close to the part of screw rod, and the upper end of the pedestal offers first Groove;
Cylinder on the base is set, and the lower end of the cylinder is embedded with the shear key that can be embedded in first groove, institute It states and offers multiple through holes on cylinder along the vertical direction, the screw portion of first bolt is inserted into the through hole and twists Enter nut so that the cylinder is fixedly connected with the pedestal.
2. assembled isolated footing according to claim 1, which is characterized in that the cylinder is internally provided with filling Body, the obturator are made of polyurethane material.
3. assembled isolated footing according to claim 1, which is characterized in that the shear key uses I-steel.
4. assembled isolated footing according to claim 1, which is characterized in that cement bonded sand can be injected in the through hole Slurry.
5. assembled isolated footing according to claim 1, which is characterized in that first bolt is set along the vertical direction It sets, first bolt is distributed around first groove.
6. assembled isolated footing according to claim 1, which is characterized in that be provided in the horizontal direction in the pedestal The first reinforcing bar and the second reinforcing bar extended, the position on the head of first bolt is located at first reinforcing bar and second steel Between muscle.
7. assembled isolated footing according to claim 1, which is characterized in that offer connection described the in the pedestal The channel of one groove, the channel are used to inject grouting material to the gap of the shear key and first groove.
8. assembled isolated footing according to claim 1, which is characterized in that the lower end of the cylinder has to level side To the stage portion of protrusion, the through hole is located at the stage portion.
9. assembled isolated footing according to claim 1, which is characterized in that be provided in the horizontal direction in the cylinder The bottom-up third reinforcing bar being sequentially distributed, the 4th reinforcing bar and the 5th reinforcing bar extended is provided with along vertical side in the cylinder To the 6th reinforcing bar of extension and the 7th reinforcing bar, the 5th reinforcing bar connects the 6th reinforcing bar and the 7th reinforcing bar, and described the The both ends of three reinforcing bars and the 4th reinforcing bar are more than the 6th reinforcing bar and the 7th reinforcing bar difference at the through hole respectively Positioned at the surrounding of the cylinder, the lower end of the 6th reinforcing bar and the 7th reinforcing bar extends at the third reinforcing bar.
10. assembled isolated footing according to claim 1, which is characterized in that the upper end of the cylinder is embedded with second Bolt or L-type steel muscle.
CN201822217276.1U 2018-12-27 2018-12-27 Assembled isolated footing Active CN209523212U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822217276.1U CN209523212U (en) 2018-12-27 2018-12-27 Assembled isolated footing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822217276.1U CN209523212U (en) 2018-12-27 2018-12-27 Assembled isolated footing

Publications (1)

Publication Number Publication Date
CN209523212U true CN209523212U (en) 2019-10-22

Family

ID=68228621

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822217276.1U Active CN209523212U (en) 2018-12-27 2018-12-27 Assembled isolated footing

Country Status (1)

Country Link
CN (1) CN209523212U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111379269A (en) * 2018-12-27 2020-07-07 北京京诚华宇建筑设计研究院有限公司 Assembly type independent foundation and assembly method
CN114855861A (en) * 2021-02-03 2022-08-05 内蒙古电力(集团)有限责任公司 Novel power transmission line fabricated foundation and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111379269A (en) * 2018-12-27 2020-07-07 北京京诚华宇建筑设计研究院有限公司 Assembly type independent foundation and assembly method
CN114855861A (en) * 2021-02-03 2022-08-05 内蒙古电力(集团)有限责任公司 Novel power transmission line fabricated foundation and construction method thereof

Similar Documents

Publication Publication Date Title
CN103924711B (en) The construction technology of assembling grillage shear wall structural system
CN106988483B (en) A kind of assembled steel reinforced Concrete U Vierendeel girder and its connection steelframe
CN106284655B (en) Precast concrete beam stud connects connecting node and connection method
CN206941858U (en) Band is encorbelmented the structure of attached prestressing force assembled power consumption frame strengthening outside plate framework
CN108678218B (en) Assembly type concrete shear wall based on multipurpose thin-wall steel pipe and construction method thereof
CN205894291U (en) Assemble integral precast prestressed reinforced concrete roof beam and frame support connnection structure
CN105781010A (en) Compound wallboard and integrated precast structure thereof
CN209523212U (en) Assembled isolated footing
CN106930436B (en) Reinforced concrete shear wall with built-in prestressed steel diagonal bracing
CN106958259B (en) A kind of concrete towers column foundation and its construction method
CN205637239U (en) Completely assembling formula steel pipe concrete frame compound shear wall structure
CN208534081U (en) A kind of reconstruction structure of old building constructional column
CN214459538U (en) Solid-web arch bridge system assembled by UHPC prefabricated corrugated plate segments
CN209523213U (en) Assembled isolated footing
CN206829416U (en) A kind of prefabricated assembled double steel pipe concrete shear force wall
CN203546955U (en) Superposed plate type concrete shear wall
CN108532625A (en) A kind of foundation of wind-driven generator unit
CN105951987B (en) Node and construction method are poured after the secondary external permanent aluminium sheet external mold of frame
CN107938499A (en) A kind of prefabricated assembled bridge pier
CN209468856U (en) A kind of assembly concrete column beam connecting node
CN108729541B (en) Connect beam type Building block construction method
CN206359882U (en) A kind of assembled solid steel tube constrains reinforced column squat pier
CN207003719U (en) A kind of prefabricated steel faced wall with steel bar girder
CN115821972A (en) Assembled rock anchor rod foundation of power transmission line and construction method
CN108678164A (en) Connect beam type Building block structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant