CN105821914A - 一种充气折叠式桩基静载检测压重水箱 - Google Patents

一种充气折叠式桩基静载检测压重水箱 Download PDF

Info

Publication number
CN105821914A
CN105821914A CN201610401532.5A CN201610401532A CN105821914A CN 105821914 A CN105821914 A CN 105821914A CN 201610401532 A CN201610401532 A CN 201610401532A CN 105821914 A CN105821914 A CN 105821914A
Authority
CN
China
Prior art keywords
water tank
bottom plate
tank wall
jack
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610401532.5A
Other languages
English (en)
Other versions
CN105821914B (zh
Inventor
彭宝安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Jinhang Computing Technology Research Institute
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610401532.5A priority Critical patent/CN105821914B/zh
Publication of CN105821914A publication Critical patent/CN105821914A/zh
Application granted granted Critical
Publication of CN105821914B publication Critical patent/CN105821914B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明一种充气折叠式桩基静载检测压重水箱主要用于建筑工程领域桩基静荷载检测;它主要由充气水箱壁(1)、立杆(2)、套环(3)、水箱底板(4)、加劲箍(5)、排水管(6)、排水阀(7)、缆风绳(9)、支架(17)组成;本发明的安装方法是:先组装支架(17),将折叠的水箱壁(1)和水箱底板(4)打开并铺放在支架(17)上,给充气水箱壁(1)的空腔(8)充满压缩空气,使充气水箱壁(1)自动立起,再在水箱壁(1)的套环(3)内插入立杆(2),然后在多个立杆(2)的外侧套上加劲箍(5)形成一个水箱圆筒,最后将缆风绳(9)分别与两个对称的立杆(2)的上端固定并成直线排列,缆风绳(9)的两端与地面固定。

Description

一种充气折叠式桩基静载检测压重水箱
技术领域
本发明主要用于建筑工程领域桩基静荷载检测。
背景技术
本人已申请的发明专利:充气折叠式桩基静载检测压重水箱,申请号:2016101457812,该专利仍采用常规的桩基检测的平台,这种桩基检测的平台面积大,安装构件多,吊装费用高,同时水箱放在桩基检测的平台上,重心高,还存在倾覆的危险。
发明内容
本发明解决了上述问题,它主要由充气水箱壁(1)、立杆(2)、套环(3)、水箱底板(4)、加劲箍(5)、排水管(6)、排水阀(7)、缆风绳(9)、支架(17)组成;充气水箱壁(1)有空腔(8),充气水箱壁(1)与水箱底板(4)固定,形成一个上面开口的圆筒形水箱,多个套环(3)与充气水箱壁(1)的外侧固定,多个立杆(2)分别插入套环(3)内,多个加劲箍(5)套在多个立杆(2)的外侧,缆风绳(9)分别与两个对称的立杆(2)的上端固定并成直线排列,缆风绳(9)的两端与地面固定,多个缆风绳(9)沿圆筒形水箱对称布置,水箱底板(4)有排水管(6),排水管(6)上安装有排水阀(7);支架(17)由主梁(11)、次梁(15)、垫梁A(18)、垫梁B(19)、检测千斤顶(12)组成,垫梁A(18)内部有举升千斤顶(20)、次梁(15)布置在主梁(11)上,左右两个主梁(11)的两端放在垫梁A(18),中间主梁(11)的两端放在垫梁B(19)上;水箱底板(4)预埋有分布钢绞线(13)和主钢绞线(14),主钢绞线(14)承受水箱底板(4)的拉应力,主钢绞线(14)较分布钢绞线(13)粗,水箱底板(4)设有套环(3),套环(3)与主钢绞线(14)焊接;本发明的充气水箱壁(1)和水箱底板(4)均是防水的柔性材料制成,可折叠;本发明的安装方法及工作原理是:先组装支架(17),先后安装垫梁A(18)、垫梁B(19)、检测千斤顶(12)、主梁(11)、次梁(15),然后将折叠的充气水箱壁(1)和水箱底板(4)打开并铺放在支架(17)上并将水箱的检测通道(10)套在支架(17)上,给充气水箱壁(1)的空腔(8)充满压缩空气,使充气水箱壁(1)自动立起,然后在充气水箱壁(1)的套环(3)内插入立杆(2)并将立杆(2)打入土层中,然后在多个立杆(2)的外侧套上加劲箍(5)形成一个水箱圆筒,最后将缆风绳(9)分别与两个对称的立杆(2)的上端固定并成直线排列,缆风绳(9)的两端与地面固定,在水箱内注水一定量的水,再启动举升千斤顶(20),将左右两根主梁(11)顶起一定高度,同时读取举升千斤顶(20)的起重量,当举升千斤顶(20)的起重量超过桩基实验承载力的四分之一时,停止举升千斤顶(20)的举升,这一过程是将水箱进行预顶,消除其后检测时水箱底部的变形,从而保证桩基检测能够正常进行,再启动检测千斤顶(12)进行正常的十级荷载检测,检测完毕后,下降检测千斤顶(12)和举升千斤顶(20),打开排水管(6)上的排水阀(7),将水全部排掉。
附图说明
附图标记说明:1-充气水箱壁,2-立杆,3-套环,4-水箱底板,5-加劲箍,6-排水管,7-排水阀,8-空腔,9-缆风绳,10-检测通道,11-主梁,12-检测千斤顶,13-分布钢绞线,14-主钢绞线,15-次梁,16-被检测的桩,17-支架,18-垫梁A,19-垫梁B,20-举升千斤顶,21-地面。
图1是本发明的平面图。
图2是本发明的A-A立面剖面图。
图3是本发明的B-B立面剖面图。
图4是本发明支架(17)的平面布置图。
图5是本发明充气水箱的A-A剖面图。
图6是本发明充气水箱的C-C剖面图。
图7是本发明支架(17)的立面大样图。
图8是本发明水箱底板(4)的局部大样图。
图9是本发明水箱底部被举起的A-A剖面示意图。
图10是本发明垫梁A(18)的大样图。
具体实施方式
发明内容已经详细述说了本发明的具体实施方式,这里不再重复,需说明:一.参见图2,给水箱注水时,只需用水管从水箱上口注水即可;如果工地有多根桩需检测,第一根桩检测完毕后,在第二根桩的检测处安装第二个水箱,用水管将第一个水箱的水抽入第二个水箱内,再拆除第一个水箱并安装到第三根桩的检测处,准备第三根桩的检测,这样可以节约大量的水,当然压载水也可以用废水,排水管(6)和排水阀(7)应安装在水箱底板(4)的最低点处。二.本发明将多个加劲箍(5)套在多个立杆(2)的外侧,主要是为了抵抗水箱的侧压力,水箱越高,侧压力越大;如果水箱底部地面产生不均匀沉降,水箱可能会倾斜,倾斜严重,水箱可能会倾覆,但有了缆风绳(8)的拉结作用,水箱不会倾斜。三.参见图9,当举升千斤顶(20)将左右两根主梁(11)顶起一定高度后,将水箱底板(4)中部顶起,左右两边仍然在地面上,这样支架(17)将承受水箱内的大部分水的重量,以满足桩基检测时压重的需要,同时又使整个水箱重心降低,保证水箱的稳定,水箱底板(4)中部被顶起后,水箱底板(4)将承受很大的拉应力,这个拉应力由水箱底板(4)内埋置的主钢绞线(14)承担,主钢绞线(14)将拉应力传给套环(3),最终由打入地面的立杆(2)承受。四.检测通道(10)的宽度设计应考虑方便检测的需要同时还要考虑支架(17)在受力后能否达到桩基检测时压重的需要,最后也要考虑支架(17)的经济指标,检测通道(10)过宽,支架(17)的宽度加大,不经济;检测通道(10)过窄,不方便检测,同时还有可能在支架(17)在受力后,支架(17)提供的压力不能达到桩基检测时压重的需要。

Claims (1)

1.一种充气折叠式桩基静载检测压重水箱,其特征是:它主要由充气水箱壁(1)、立杆(2)、套环(3)、水箱底板(4)、加劲箍(5)、排水管(6)、排水阀(7)、缆风绳(9)、支架(17)组成;充气水箱壁(1)有空腔(8),充气水箱壁(1)与水箱底板(4)固定,形成一个上面开口的圆筒形水箱,多个套环(3)与充气水箱壁(1)的外侧固定,多个立杆(2)分别插入套环(3)内,多个加劲箍(5)套在多个立杆(2)的外侧,缆风绳(9)分别与两个对称的立杆(2)的上端固定并成直线排列,缆风绳(9)的两端与地面固定,多个缆风绳(9)沿圆筒形水箱对称布置,水箱底板(4)有排水管(6),排水管(6)上安装有排水阀(7);支架(17)由主梁(11)、次梁(15)、垫梁A(18)、垫梁B(19)、检测千斤顶(12)组成,垫梁A(18)内部有举升千斤顶(20)、次梁(15)布置在主梁(11)上,左右两个主梁(11)的两端放在垫梁A(18),中间主梁(11)的两端放在垫梁B(19)上;水箱底板(4)预埋有分布钢绞线(13)和主钢绞线(14),主钢绞线(14)承受水箱底板(4)的拉应力,主钢绞线(14)较分布钢绞线(13)粗,水箱底板(4)设有套环(3),套环(3)与主钢绞线(14)焊接;本发明的充气水箱壁(1)和水箱底板(4)均是防水的柔性材料制成,可折叠;本发明的安装方法及工作原理是:先组装支架(17),先后安装垫梁A(18)、垫梁B(19)、检测千斤顶(12)、主梁(11)、次梁(15),然后将折叠的充气水箱壁(1)和水箱底板(4)打开并铺放在支架(17)上并将水箱的检测通道(10)套在支架(17)上,给充气水箱壁(1)的空腔(8)充满压缩空气,使充气水箱壁(1)自动立起,然后在充气水箱壁(1)的套环(3)内插入立杆(2)并将立杆(2)打入土层中,然后在多个立杆(2)的外侧套上加劲箍(5)形成一个水箱圆筒,最后将缆风绳(9)分别与两个对称的立杆(2)的上端固定并成直线排列,缆风绳(9)的两端与地面固定,在水箱内注水一定量的水,再启动举升千斤顶(20),将左右两根主梁(11)顶起一定高度,同时读取举升千斤顶(20)的起重量,当举升千斤顶(20)的起重量超过桩基实验承载力的四分之一时,停止举升千斤顶(20)的举升,这一过程是将水箱进行预顶,消除其后检测时水箱底部的变形,从而保证桩基检测能够正常进行,再启动检测千斤顶(12)进行正常的十级荷载检测,检测完毕后,下降检测千斤顶(12)和举升千斤顶(20),打开排水管(6)上的排水阀(7),将水全部排掉。
CN201610401532.5A 2016-06-11 2016-06-11 一种充气折叠式桩基静载检测压重水箱 Active CN105821914B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610401532.5A CN105821914B (zh) 2016-06-11 2016-06-11 一种充气折叠式桩基静载检测压重水箱

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610401532.5A CN105821914B (zh) 2016-06-11 2016-06-11 一种充气折叠式桩基静载检测压重水箱

Publications (2)

Publication Number Publication Date
CN105821914A true CN105821914A (zh) 2016-08-03
CN105821914B CN105821914B (zh) 2017-08-25

Family

ID=56532749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610401532.5A Active CN105821914B (zh) 2016-06-11 2016-06-11 一种充气折叠式桩基静载检测压重水箱

Country Status (1)

Country Link
CN (1) CN105821914B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107884280A (zh) * 2017-11-30 2018-04-06 能诚集团有限公司 试压检测装置
CN109056858A (zh) * 2018-09-11 2018-12-21 南昌永祺科技发展有限公司 一种外用压缩空气驱动水介质加载装置及其施工方法
CN109763525A (zh) * 2019-01-24 2019-05-17 胡习兵 装配式桩基静载试验加载装置及方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2145379Y (zh) * 1992-11-26 1993-11-03 沈昌鲁 一种桩基静载试验装置
GB2284673B (en) * 1993-12-08 1997-01-08 Precision Monitoring & Control Pile-testing apparatus
RU2244070C1 (ru) * 2003-04-24 2005-01-10 Хабаровский государственный технический университет Инвентарное устройство для испытания свай-оболочек четырехоболочечной опоры моста статической нагрузкой
CN101644063A (zh) * 2009-09-15 2010-02-10 河海大学 一种pcc桩水囊载荷加载卸载方法
CN201520988U (zh) * 2009-10-10 2010-07-07 中交上海港湾工程设计研究院有限公司 实体群桩竖向抗拔静载荷试验系统
CN103362150A (zh) * 2013-07-20 2013-10-23 江苏久工重型机械股份有限公司 工程基桩静载荷步履检测平台

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2145379Y (zh) * 1992-11-26 1993-11-03 沈昌鲁 一种桩基静载试验装置
GB2284673B (en) * 1993-12-08 1997-01-08 Precision Monitoring & Control Pile-testing apparatus
RU2244070C1 (ru) * 2003-04-24 2005-01-10 Хабаровский государственный технический университет Инвентарное устройство для испытания свай-оболочек четырехоболочечной опоры моста статической нагрузкой
CN101644063A (zh) * 2009-09-15 2010-02-10 河海大学 一种pcc桩水囊载荷加载卸载方法
CN201520988U (zh) * 2009-10-10 2010-07-07 中交上海港湾工程设计研究院有限公司 实体群桩竖向抗拔静载荷试验系统
CN103362150A (zh) * 2013-07-20 2013-10-23 江苏久工重型机械股份有限公司 工程基桩静载荷步履检测平台

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107884280A (zh) * 2017-11-30 2018-04-06 能诚集团有限公司 试压检测装置
CN109056858A (zh) * 2018-09-11 2018-12-21 南昌永祺科技发展有限公司 一种外用压缩空气驱动水介质加载装置及其施工方法
CN109763525A (zh) * 2019-01-24 2019-05-17 胡习兵 装配式桩基静载试验加载装置及方法

Also Published As

Publication number Publication date
CN105821914B (zh) 2017-08-25

Similar Documents

Publication Publication Date Title
CN105673039B (zh) 一种沿空留巷巷旁柔强承载施工结构及其施工方法
US9605401B2 (en) Gravity-based foundation system for the installation of offshore wind turbines and method for the installation of an offshore wind turbine foundation system
CN109024237A (zh) 折叠箱、浮桥及架设方法、桩基加载装置及荷载提供方法
CN105821914A (zh) 一种充气折叠式桩基静载检测压重水箱
CN104452597B (zh) 水中墩超长预应力盖梁施工支撑体系
CN103255752B (zh) 支撑海上风机、海洋建筑物的浮力支撑固定平台
CN110820950B (zh) 大跨度组合式超重偏心坡角钢结构整体同步顶升施工工法
CN103205988A (zh) 适合桩基水下部位修补加固的装置及应用该装置的施工方法
CN100501014C (zh) 单壁钢吊箱及其施工工法
US3483707A (en) Method for reinforcing steel pipe piling in situ and the resultant piling
CN105887918A (zh) 一种塔吊基础及其施工方法
CN105155573A (zh) 海上风机筒中筒基础
CN111549830B (zh) 地铁明挖车站抗拔桩单桩竖向抗拔静荷载试验方法
CN104404885B (zh) 用于水中墩超长预应力盖梁施加预顶力的装置
CN209837060U (zh) 钢板桩围堰
CN209384256U (zh) 一种海上风电钢管桩的加固装置
CN208219623U (zh) 一种可重复利用的基桩桩帽
CN203188257U (zh) 适合桩基水下部位修补加固的装置
EP1116829A2 (en) Foundation raft
JPH0930487A (ja) 半浮遊構造を持つ人工島とその施工法
CN106284397B (zh) 一种斜撑砼柱固护深基坑塔吊基础装置
CN215594146U (zh) 一种新型混凝土抗拔桩及其连接结构
CN2408451Y (zh) 正置式缸体桩身反力静载试验油压装置
CN210369074U (zh) 一种整体式钢结构框架压重堆载体
CN204401463U (zh) 用于水中墩超长预应力盖梁施加预顶力的装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160818

Address after: 430064, Wuhan, Hubei province Hongshan District lion mountain street, school 84, 73, 7, 2 room

Applicant after: WUHAN CHUANGXIAN PATENT TECHNOLOGY SERVICE CO., LTD.

Address before: 430064 Wuhan Institute of education, Hongshan 712 District, Hubei, China

Applicant before: Peng Baoan

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20161017

Address after: Room 2, building 457, Huangpu Road, Huangdao, Shandong, Qingdao, 266555, China

Applicant after: Qingdao Lantian Chuangxian Technology Services Limited

Address before: 430064, Wuhan, Hubei province Hongshan District lion mountain street, school 84, 73, 7, 2 room

Applicant before: WUHAN CHUANGXIAN PATENT TECHNOLOGY SERVICE CO., LTD.

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200917

Address after: 300000 No. 357, free trade road, Airport Economic Zone, Dongli District, Tianjin

Patentee after: TIANJIN JINHANG INSTITUTE OF COMPUTING TECHNOLOGY

Address before: Room 2, building 457, Huangpu Road, Huangdao, Shandong, Qingdao, 266555, China

Patentee before: QINGDAO LANTIAN CHUANGXIAN TECHNOLOGY SERVICE Co.,Ltd.