Summary of the invention
It is contemplated that one of technical problem solved the most to a certain extent in correlation technique.To this end, the purpose of the present invention
One of be to propose a kind of pyrolysis of coal reactor-recirculating fluidized bed combined system and utilize its method processing coal.
Concrete, the present invention is directed to recirculating fluidized bed and be provided with a kind of New type coal plug technique, produce combustible gas and pyrolysis oil also
Co-producing power, and utilize the induction system of existing recirculating fluidized bed, it is achieved semicoke heat is sent, and ensures the burning of semicoke, and reduces
Coal plug process costs.The combined system of the present invention solves the problem that coal plug leading portion pyrolytic process is complicated, and thermal decomposition product
Appropriate application, reduces cost of electricity-generating.
In view of this, in one aspect of the invention, the invention provides a kind of pyrolysis of coal reactor-recirculating fluidized bed combination is
System.According to embodiments of the invention, this pyrolysis of coal reactor-recirculating fluidized bed combined system includes:
Pyrolysis of coal reactor, described pyrolysis of coal reactor has coal entrance, semicoke outlet and gas mixture and exports, wherein,
Described coal entrance is arranged at the top of described pyrolysis of coal reactor, and the outlet of described gas mixture is arranged at described pyrolysis of coal reaction
On the roof of device and/or sidewall, the outlet of described semicoke is arranged at the bottom of described pyrolysis of coal reactor;
It is provided with many oil gas in described pyrolysis reactor and derives pipeline, gas gathering manifold, many gas-collecting branch pipes, heat accumulating type radiation
Pipe and cyclone separator,
Wherein, described gas gathering manifold is adjacent to the internal perisporium of described pyrolysis of coal reactor and is vertically arranged,
One end of described gas-collecting branch pipe is connected with described gas gathering manifold, and the other end is communicated to described oil gas and derives pipeline;
Described cyclone separator has gas-solid mixture entrance, gas vent and a solid outlet, wherein, described gas vent with
The outlet of described gas mixture is connected, and one end of described gas gathering manifold extends the gas-solid mixing being communicated to described cyclone separator
Thing entrance;
Described heat accumulation type radiant tube is along the short transverse multi-tier arrangement of described pyrolysis reactor, and every layer has many in level side
Heat accumulation type radiant tube the most parallel to each other;
Recirculating fluidized bed, described recirculating fluidized bed is provided with semicoke entrance, bunker coal entrance and air intake, described semicoke
Entrance is connected with the outlet of described semicoke.
Inventor finds, the pyrolysis of coal reactor of the present invention directly can be combined with existing recirculating fluidized bed, and without to existing
Some recirculating fluidized beds are transformed, with existing pyrolysis of coal plug technique-recirculating fluidized bed generating set associated with compared with system,
In the pyrolysis of coal reactor-recirculating fluidized bed combined system of the present invention, pyrolysis of coal reactor and recirculating fluidized bed can be relatively independent
Ground runs, and the two interferes with each other relatively small.Further, since pyrolysis of coal reactor uses heat accumulation type radiant tube for being pyrolyzed
Journey carries supplying heat source, can realize the accurate temperature controlling to pyrolytic process by the flow of the combustion gas that adjustment is passed through heat accumulation type radiant tube,
And this heat accumulation type radiant tube can be by realizing quickly commutation and heat storage type combustion at two ends, it is ensured that pyrolysis of coal reactor
The uniformity in middle temperature field, such that it is able to significantly improve the fast pyrogenation efficiency of coal charge, with more traditional use gas heat carrier
Or solid thermal carriers compare as the pyrolytic reaction device of pyrolysis thermal source, the pyrolysis of coal reaction unit of the present invention need not to arrange pre-
Hot cell and carrier separative element, can greatly simplify fast pyrogenation reaction process flow process, thus significantly reduce the fault of device
In rate and gained tar, dust content is relatively low, and then it is complicated to solve existing coal plug leading portion pyrolytic process, and existing heat
The problem solving the fluctuation of service that reactor causes with CFBB coupling height.The pyrolysis of coal reactor of the present invention-follow
Ring fluid bed combined system can be effective to produce combustible gas and pyrolysis oil co-production electric power, and utilizes existing recirculating fluidized bed
Induction system, it is achieved semicoke heat is sent, and ensures the burning of semicoke, and reduces coal plug process costs.Coal heat as the present invention
When solution reactor-recirculating fluidized bed combined system is used for generating electricity, it can be ensured that the stability of electricity generation system.Of particular note
It is that pyrolysis of coal inside reactor is provided with cyclone separator, greatly reduces whirlwind insulation cost and tar condensing blocking pipeline
Possibility.
In one embodiment of the invention, every layer of described heat accumulation type radiant tube includes multiple parallel and equally distributed storage
Hot type radiant tube, and each described heat accumulation type radiant tube and each the heat accumulating type spoke in adjacent upper and lower two-layer heat accumulation type radiant tube
Penetrate and manage parallel and be in staggered distribution in the short transverse of described pyrolysis of coal reactor.Thus, it is possible to significantly improve the fast of coal charge
Speed pyrolysis efficiency, and then improve the productivity of tar.
In one embodiment of the invention, described gas-collecting branch pipe is arranged parallel to each other along the length direction of described gas gathering manifold.
In one embodiment of the invention, described gas-collecting branch pipe is perpendicular to described gas collecting main pipe.
In one embodiment of the invention, described oil gas derives the pipeline short transverse laminates along described pyrolysis reactor
Putting, every layer has many oil gas the most parallel to each other and derives pipeline.
In one embodiment of the invention, oil gas described in same layer is derived pipeline and is communicated to same described gas-collecting branch pipe.
In one embodiment of the invention, described oil gas is derived pipeline and is arranged in parallel with described heat accumulation type radiant tube, and institute
State the respective left and right sides of heat accumulation type radiant tube and be symmetrically arranged with two oil gas derivation pipelines.
In one embodiment of the invention, described oil gas derive pipeline and neighbouring described heat accumulation type radiant tube tube wall it
Spacing is 1/2-3 times that described oil gas derives pipe diameter d.
In one embodiment of the invention, described oil gas is derived and is provided with multiple through hole on the tube wall of pipeline.
In one embodiment of the invention, the plurality of through hole uniformly divides on the length direction that described oil gas derives pipeline
Cloth.
In one embodiment of the invention, the outer wall of described cyclone separator and the described heat accumulation type radiant tube being adjacent
Between be welded with support bar.
In one embodiment of the invention, described pyrolysis of coal reactor-recirculating fluidized bed combined system farther includes: oil
Gas mixture after-treatment device, described gas mixture after-treatment device is connected with the outlet of described gas mixture.
In one embodiment of the invention, described gas mixture after-treatment device includes: Oil-gas Separation assembly, described
Oil-gas Separation assembly has gas mixture import, pyrolysis gas outlet and tar outlet, and described gas mixture import is with described
Gas mixture outlet is connected;Pyrolysis gas purification assembly, described pyrolysis gas purification assembly has pyrolysis gas import and combustible gas goes out
Mouthful, described pyrolysis gas import is connected with described pyrolysis gas outlet, tar refining assembly, and described tar refining assembly has tar
Entrance and oil product outlet, described tar entrance is connected with described tar outlet.
In another aspect of this invention, the invention provides one and utilize foregoing pyrolysis of coal reactor-recirculating fluidized bed connection
The method processing coal by system.According to embodiments of the invention, the method comprises the following steps:
(1) coal is delivered to described pyrolysis of coal reactor and carries out pyrolysis processing, in order to obtain semicoke and gas mixture;
(2) described semicoke is delivered to described recirculating fluidized bed, makes described semicoke carry out combustion power generation;And
(3) described gas mixture is delivered to described gas mixture after-treatment device post-process, thus obtains flammable
Gas and oil product.
Surprisingly, it was found that in the method, it is possible to use pyrolysis of coal reactor is direct with existing recirculating fluidized bed
Combination, and without transforming existing recirculating fluidized bed, pyrolysis of coal reactor and recirculating fluidized bed can relatively independently
Running, the two interferes with each other relatively small.The method can be effective to produce combustible gas and pyrolysis oil co-production electric power, and
Utilize the induction system of existing recirculating fluidized bed, it is achieved semicoke heat is sent, ensure the burning of semicoke, and reduce coal plug technique
This.And, in the method, the gas mixture that pyrolysis of coal produces is before discharging pyrolysis of coal reactor, through cyclonic separation
Device carries out dedusting, can greatly reduce pyrolysis of coal reactor to the insulation of pipeline between pyrolysis oil gas mixture rapid condensation device
Facility, reduce equipment thermal insulation area and reduce system heat tracing energy consumption, greatly reduce simultaneously tar condensing blocking pipeline can
Energy.
In one embodiment of the invention, step (3) including: described gas mixture is carried out Oil-gas Separation by (3-1)
Process, obtain tar and pyrolysis gas;(3-2) described pyrolysis gas is carried out purified treatment, obtain combustible gas;(3-3) by described
Tar carries out refinement treatment, obtains oil product.
The present invention at least has the advantages that
1) radiant tube heating downstriker pyrolysis of coal reactor be combined with recirculating fluidized bed, the pyrolysis reactor of the present invention have employed
Heat accumulation type radiant tube combines descending reactor, belongs to heating indirectly, and such pyrolysis reactor allows ciculation fluidized with existing
Bed directly combination, and without existing recirculating fluidized bed is transformed on a large scale.
2) hot semicoke is sent into recirculating fluidized bed, it is possible to increase the capacity usage ratio of electricity generation system.
3) in pyrolysis of coal reactor, cyclone separator is set, greatly reduces the dustiness of the gas mixture of the pyrolysis reactor that produces coal
And pyrolysis of coal reactor is to the lagging facility of pipeline between pyrolysis oil gas mixture rapid condensation device, reduces the insulation face of equipment
Amass and reduce system heat tracing energy consumption, greatly reducing the possibility of tar condensing blocking pipeline simultaneously, reduce the place of follow-up tar
Reason cost.
The additional aspect of the present invention and advantage will part be given in the following description, and part will become bright from the following description
Aobvious, or recognized by the practice of the present invention.
Detailed description of the invention
Embodiments of the invention are described below in detail.The embodiments described below is exemplary, is only used for explaining the present invention,
And be not considered as limiting the invention.Unreceipted concrete technology or condition in embodiment, according to the document in this area
Described technology or condition or carry out according to product description.Agents useful for same or instrument unreceipted production firm person, be
Can by city available from conventional products.
In describing the invention, it is to be understood that term " " center ", " longitudinally ", " laterally ", " length ", " width ",
" thickness ", " on ", D score, "front", "rear", "left", "right", " vertically ", " level ", " top ", " end ", " interior ", " outward ",
Orientation or the position relationship of the instruction such as " clockwise ", " counterclockwise ", " axially ", " radially ", " circumferential " are based on shown in the drawings
Orientation or position relationship, be for only for ease of describe the present invention and simplify describe rather than instruction or hint indication device or
Element must have specific orientation, with specific azimuth configuration and operation, be therefore not considered as limiting the invention.
Additionally, term " first ", " second " are only used for describing purpose, and it is not intended that instruction or hint relative importance or
Person implies the quantity indicating indicated technical characteristic.Thus, define " first ", the feature of " second " can express or
Implicitly include at least one this feature.In describing the invention, " multiple " are meant that at least two, such as two,
Three etc., unless otherwise expressly limited specifically.
In the present invention, unless otherwise clearly defined and limited, term " install ", " being connected ", " connection ", the art such as " fixing "
Language should be interpreted broadly, and connects for example, it may be fixing, it is also possible to be to removably connect, or integral;Can be machinery
Connect, it is also possible to be electrical connection;Can be to be joined directly together, it is also possible to be indirectly connected to by intermediary, can be two units
Connection within part or the interaction relationship of two elements, unless otherwise clear and definite restriction.Ordinary skill for this area
For personnel, above-mentioned term concrete meaning in the present invention can be understood as the case may be.
In the present invention, unless otherwise clearly defined and limited, fisrt feature second feature " on " or D score can be
One directly contacts with second feature, or the first and second features are by intermediary mediate contact.And, fisrt feature is
Two features " on ", " top " and " above " but fisrt feature directly over second feature or oblique upper, or be merely representative of first
Characteristic level height is higher than second feature.Fisrt feature second feature " under ", " lower section " and " below " can be fisrt feature
Immediately below second feature or obliquely downward, or it is merely representative of fisrt feature level height less than second feature.
In one aspect of the invention, the invention provides a kind of pyrolysis of coal reactor-recirculating fluidized bed combined system.According to this
Inventive embodiment, with reference to Fig. 2, this pyrolysis of coal reactor-recirculating fluidized bed combined system include pyrolysis of coal reactor 100 with
And recirculating fluidized bed 200.
According to embodiments of the invention, pyrolysis of coal reactor 100 has coal entrance 110, semicoke outlet 120 and air-fuel mixture
Thing outlet 130.Wherein, coal entrance 110 is arranged at the top of pyrolysis of coal reactor 100, is suitable to fine coal supply to coal heat
Solve in reactor 100;Gas mixture outlet 130 is arranged on roof and/or the sidewall of pyrolysis of coal reactor 100, is suitable to
Gas mixture pyrolysis of coal produced discharges pyrolysis of coal reactor 100;Semicoke outlet 120 is arranged at pyrolysis of coal reactor 100
Bottom, be suitable to by pyrolysis of coal produce semicoke discharge pyrolysis of coal reactor 100.
According to embodiments of the invention, it is provided with many oil gas in pyrolysis of coal reactor 100 and derives pipeline 140, gas gathering manifold
150, many gas-collecting branch pipes 160, heat accumulation type radiant tube 170 and cyclone separator 180.
According to a particular embodiment of the invention, heat accumulation type radiant tube 160 in the inside of pyrolysis of coal reactor 100 along pyrolysis of coal
The short transverse multi-tier arrangement of reactor 100, every layer has many heat accumulation type radiant tubes the most parallel to each other.
According to a particular embodiment of the invention, every layer of heat accumulation type radiant tube 160 includes multiple parallel and equally distributed heat accumulating type spoke
Penetrate pipe and each heat accumulation type radiant tube is parallel with each heat accumulation type radiant tube in adjacent upper and lower two-layer heat accumulation type radiant tube.Root
According to the concrete example of the present invention, heat accumulation type radiant tube can be the circle of DN200~300mm or semicircle radiant tube.Thus,
The pyrolysis efficiency of pyrolysis material can be significantly improved, and then improve pyrolysis oil yield.
According to a particular embodiment of the invention, the concrete set-up mode of heat accumulation type radiant tube 160 is not particularly limited, this area
Technical staff can carry out appropriate design according to the temperature field that actual pyrolytic reaction needs.In some embodiments of the invention,
The concrete set-up mode of heat accumulation type radiant tube 160 includes but not limited to: adjacent heat accumulation type radiant tube about 160 center distance can
Thinking 300~500mm, adjacent heat accumulation type radiant tube vertical centre spacing can be 400~800mm, multilayer heat accumulation type radiant tube
The number of plies can be 10-30 layer.It is to be understood that adjacent heat accumulation type radiant tube left and right center distance can be understood as same
Distance in the heart in heat accumulation type radiant tube on layer, and adjacent heat accumulation type radiant tube vertical centre spacing can be understood as adjacent up and down
Distance in the heart in the adjacent heat accumulation type radiant tube of two interlayers.Inventor finds, this kind of structure is arranged so that in reactor
Uniform distribution of temperature field, such that it is able to significantly improve the pyrolysis efficiency of material, and then improves the yield of pyrolysis oil.
According to a particular embodiment of the invention, heat accumulation type radiant tube can be unidirectional, gas heat-accumulated type radiant tube, i.e. by storing
The heat that combustion gas is produced by hot type radiant tube body carries out heat supply in the way of radiation.According to a particular embodiment of the invention,
Gas control valve (not shown) can be provided with on heat accumulation type radiant tube.Thus, it is possible to adjust by adjusting gas control valve
The flow of the combustion gas that joint is passed through heat accumulation type radiant tube realizes the accurate temperature controlling to pyrolytic process, such that it is able to significantly improve material
Pyrolysis efficiency, and then improve pyrolysis oil yield.
Concrete, the flow etc. that can be passed through the combustion gas of heat accumulation type radiant tube by adjustment realizes the accurate temperature controlling to pyrolytic process,
The every independent temperature control of heat accumulation type radiant tube, and the combustion system of heat accumulation type radiant tube employing periodically commutation so that single accumulation of heat
The temperature field of formula radiant tube is more or less the same in 30 DEG C, thus ensures the uniformity of reactor temperature field, such as logical by adjusting
The flow of the combustion gas entering heat accumulation type radiant tube makes pyrolysis reactor be divided into three districts, i.e. drying and dehydrating district, pyrolysis from top to bottom
Reaction zone, semicoke maturation zone, can be by existing to the temperature range in the control realization drying and dehydrating district of heat accumulation type radiant tube
680-730 degree Celsius, it is possible to quickly slough the moisture contained by pyrolysis material, drying and dehydrating district temperature is slightly higher simultaneously, can subtract
Few drying and dehydrating section length.Pyrolysis reaction region temperature range can control at 500-650 degree Celsius, to ensure the abundant of material
Pyrolysis, semicoke maturation zone temperature can control at 500-600 degree Celsius, thus a heating part is pyrolyzed the most completely further
Material.
According to embodiments of the invention, gas gathering manifold 150 is adjacent to the internal perisporium of pyrolysis of coal reactor 100 and is vertically arranged, collection
One end of gas branch pipe 160 is connected with gas gathering manifold 150, and the other end is communicated to oil gas and derives pipeline 140.Gas-collecting branch pipe 160
Concrete set-up mode be not particularly limited, such as include but not limited to the length direction cloth parallel to each other along gas gathering manifold 150
Put.Every gas-collecting branch pipe 160 can individually be connected with gas gathering manifold 150, it is also possible to two or many gas-collecting branch pipes 160
It is communicated to gas gathering manifold 150 by same connection pipeline 161 near one end of gas-collecting branch pipe.According to embodiments of the invention,
Can have certain angle between gas-collecting branch pipe 160 and gas gathering manifold 150, in some concrete examples, gas-collecting branch pipe 160 hangs down
Directly arrange in gas collecting main pipe 150.Thus, beneficially the quick of gas mixture is derived.
According to embodiments of the invention, oil gas is derived pipeline 140 and is connected with one end of gas-collecting branch pipe 160, and oil gas is led
Go out and be provided with through hole on the tube wall of pipe 140.Thus, by arranging oil gas derivation pipeline so that the heat produced in pyrolytic process
Solve oil gas quickly to derive, thus effectively suppression oil gas second pyrolysis, improve pyrolysis oil yield.According to embodiments of the invention,
The quantity of through hole is not particularly limited, and in some concrete examples, oil gas is derived and is provided with multiple leading on the tube wall of pipeline 140
Hole, it is preferable that the plurality of through hole is derived at oil gas and is uniformly distributed on the length direction of pipeline 140.Thus, beneficially oil gas
Mixture is quickly derived.
According to embodiments of the invention, oil gas derives the pipeline 140 short transverse multi-tier arrangement along pyrolysis reactor 100, often
Layer has many oil gas the most parallel to each other derives pipeline.According to a particular embodiment of the invention, same layer oil
Gas delivery line road 140 is communicated to same gas-collecting branch pipe 160.Thereby, it is possible to gas mixture is concentrated, is derived rapidly.
According to embodiments of the invention, oil gas is derived pipeline 140 and is arranged in parallel with heat accumulation type radiant tube 170, and heat accumulating type spoke
The left and right sides penetrating pipe 170 is symmetrically arranged with two oil gas derivation pipelines 140.Inventor finds, by every heat accumulating type
Radiant tube both sides are installed oil gas and are derived pipeline, and the gas mixture that pyrolysis produces is derived rapidly by deriving pipeline, thus has
Inhibit to effect the second pyrolysis of oil gas, and then the yield of raising pyrolysis oil, good in economic efficiency.
According to embodiments of the invention, as it is shown on figure 3, oil gas derives pipeline 140 and neighbouring heat accumulation type radiant tube 170
Spacing L of tube wall is 1/2-3 times that oil gas derives pipe diameter d.The pyrolysis oil gas that thus can derive generation at once mixes
Compound, it is to avoid pyrolysis oil cracks, improves pyrolysis oil productivity.
According to embodiments of the invention, cyclone separator 180 has gas-solid mixture entrance 181, gas vent 182 and solid
Outlet 183, wherein, gas vent 182 is connected with gas mixture outlet 120, and the end of gas gathering manifold 150 extends
It is communicated to the gas-solid mixture entrance 181 of this cyclone separator 180.Inventor finds, by pyrolysis of coal inside reactor
Cyclone separator is set, thermal decomposition product is carried out gas solid separation process, it is possible to effectively reduce the oil gas discharging pyrolysis of coal reactor
The produce coal pyrolysis oil gas of pyrolysis reactor of the dustiness of mixture, effectively suppression mixes dust condensation blocking subsequent pipeline and relevant
Equipment;Meanwhile, in cyclone separator built-in pyrolysis of coal reactor, pyrolysis reactor can be reduced to gas mixture condensing unit
Between the lagging facility of pipeline, reduce the thermal insulation area of equipment and reduce system heat tracing energy consumption.
According to embodiments of the invention, weld between outer wall and the heat accumulation type radiant tube 170 being adjacent of cyclone separator 180
It is connected to support bar 181, it is possible to be firmly fixed to inside pyrolysis reactor this cyclone separator.Generally, whirlwind divides
It is arranged at the top of pyrolysis reactor 100 from device 180, therefore, it can in cyclone separator 180 outer wall and ground floor accumulation of heat
Support bar 181 is welded between formula radiant tube 170.
According to embodiments of the invention, pyrolysis of coal reactor 100 is additionally provided with the combustion needed for heat accumulation type radiant tube burning simultaneously
Smoke entrance (not shown) after material, air and burning, fuel gas inlet and air intake are respectively and heat accumulation type radiant tube
170 are connected.The heat smoke produced that burns in heat accumulation type radiant tube may be used for treating the fine coal raw material of pyrolysis be dried and
The pre-heat treatment, thus further increases pyrolysis of coal reactor efficiency and efficiency of combustion, and achieves comprehensive utilization resource, fall
The purpose of low energy consumption.
According to embodiments of the invention, the height of pyrolysis of coal reactor 100 and width are preferably suitable, and width can be 2-6 rice,
Highly can control by controlling the quantity and spacing of every layer of heat accumulation type radiant tube 170, the height of usual pyrolysis of coal reactor can
Think 5~20m.Thus, it is possible to realize the pyrolysis completely to material.It will be understood by those skilled in the art that pyrolysis of coal is reacted
The height of device 100 and width are not limited to above-mentioned scope, and those skilled in the art can select the most flexibly.
According to embodiments of the invention, recirculating fluidized bed 200 is provided with semicoke entrance 210, bunker coal entrance 220 and sky
Gas entrance 230, wherein, semicoke entrance 210 is connected with semicoke outlet 120, is suitable to half will produced in pyrolysis of coal reactor
Burnt supply is respectively adapted in recirculating fluidized bed 200 to recirculating fluidized bed 200, bunker coal entrance 220 and air intake 230
Supply bunker coal and air, be beneficial to carry out combustion power generation.Specifically, recirculating fluidized bed 200 can be using semicoke as only
One fuel carries out combustion power generation, i.e. bunker coal entrance 220 and closes, and only supplies semicoke by semicoke entrance 210 and carries out burning
Electricity;Recirculating fluidized bed 200 can also carry out combustion power generation using the mixture of semicoke and coal as fuel, passes through fuel the most simultaneously
Coal entrance 220 and semicoke entrance 210 carry out mixed combustion generating for coal supply and semicoke respectively in recirculating fluidized bed 200.Send out
A person of good sense finds, burns by the hot semicoke directly heat produced in pyrolysis of coal reactor 100 is delivered to recirculating fluidized bed 200
Generating, can not only guarantee the combustion stability of recirculating fluidized bed 200, and can significantly improve capacity usage ratio, and
When the stability utilizing this pyrolysis of coal reactor-recirculating fluidized bed combined system to be able to ensure that electricity generation system when carrying out combustion power generation.
According to embodiments of the invention, with reference to Fig. 4 and Fig. 5, this pyrolysis of coal reactor-recirculating fluidized bed combined system can enter
One step includes: gas mixture after-treatment device 400, this gas mixture after-treatment device 400 and pyrolysis of coal reactor 100
Gas mixture outlet 130 be connected.Specifically, gas mixture after-treatment device 400 may include that Oil-gas Separation group
Part 410, pyrolysis gas purification assembly 420 and tar refining assembly 430.Gas mixture after-treatment device 400 is suitable to pyrolysis
The gas mixture obtained post-processes, and carries out Oil-gas Separation, pyrolysis gas purification and tar refining etc. successively and processes, with
To purified gas and high added value oil product.
According to embodiments of the invention, Oil-gas Separation assembly 410 has gas mixture import 411, pyrolysis gas outlet 412
With tar outlet 413, gas mixture import 411 exports 130 with the gas mixture of pyrolysis of coal reactor and is connected, tar
Outlet 413 is connected with the tar entrance 431 of tar refining assembly 430, and this Oil-gas Separation assembly 410 is suitable to antipyretic product
Raw gas mixture separates and obtains pyrolysis gas and tar, and Oil-gas Separation assembly 410 carries out the concrete mode of Oil-gas Separation not to be subject to
Limit especially, it may for example comprise but it is not limited to condensation, spray etc..
According to embodiments of the invention, pyrolysis gas purification assembly 420 has pyrolysis gas import 421 and combustible gas outlet 422,
Wherein, pyrolysis gas import 421 is connected with pyrolysis gas outlet 412, and pyrolysis gas purification assembly 420 is suitable to carry out pyrolysis gas
The operation such as desulfurization, deamination carries out purified treatment to obtain clean combustible gas.In certain embodiments, pyrolysis gas purification assembly
420 can be provided with two combustible gases exports 422 (not shown)s, one of them and the heat accumulating type in pyrolysis of coal reactor
Radiant tube is connected, for providing the fuel of heat accumulation type radiant tube combustion heating, it is achieved the Appropriate application of thermal decomposition product, and another
Individual pyrolysis gas outlet 422 is as product gas outlet.
According to embodiments of the invention, tar refining assembly 430 have tar entrance 431 and oil product outlet 432, wherein,
Tar entrance 431 is connected with tar outlet 413.The tar that this tar refining assembly 430 is suitable to separating acquisition refines
Process, to obtain high added value oil product, such as, include but not limited to that the tar to isolated carries out hydrofinishing.
Pyrolysis of coal reactor-recirculating fluidized bed the combined system of the present invention arranges coal plug technique, efficient solution for recirculating fluidized bed
The problem that coal plug leading portion pyrolytic process of having determined is complicated, in the combined system of the present invention, pyrolysis of coal reactor can follow with existing
Ring fluid bed is directly combined, and send hot semicoke by First air, it is not necessary to transform existing recirculating fluidized bed, with existing
System associated with pyrolysis of coal plug technique-recirculating fluidized bed generating set is compared, the pyrolysis of coal reactor-recirculating fluidized bed of the present invention
In combined system, pyrolysis of coal reactor and recirculating fluidized bed can run relatively independently, and the two interferes with each other relatively small,
Thermal decomposition product Appropriate application, cost of electricity-generating is substantially reduced.Pyrolysis of coal reactor-recirculating fluidized bed the combined system of the present invention is permissible
It is effective to produce combustible gas and pyrolysis oil co-production electric power, and utilizes the induction system of existing recirculating fluidized bed, it is achieved semicoke
Heat delivers to recirculating fluidized bed, and retains the combustion system of original recirculating fluidized bed, it is achieved in pyrolysis char and recirculating fluidized bed
Coal mix burning, ensure the stability of CFBC, pyrolysis gas and pyrolytic tar processed simultaneously, produce flammable
Gas and prepared tar are as major product, it is achieved the economic benefit of coal plug.Pyrolysis of coal reactor-recirculating fluidized bed as the present invention
When combined system is used for generating electricity, it can be ensured that the stability of electricity generation system.Special needs to be pointed out is, in pyrolysis of coal reactor
Portion is provided with cyclone separator, can reduce the temperature of pyrolysis of coal gas mixture, reduce the oil of the pyrolysis reactor that produces coal simultaneously
The dustiness of gas mixture, reduces the dust content in subsequent high temperature coal pyrolysis gas Quench tar, and tar condensing blocks pipeline
May, reduce whirlwind insulation cost simultaneously.
In order to reduce the impact on coal powder boiler combustion of the coal plug, the combined system of the present invention takes the descending fast pyrogenation of heat accumulating type
Stove, it is only necessary to be delivered to recirculating fluidized bed hot for the semicoke produced, be effectively utilized the sensible heat that pyrolysis char is self-contained,
Pyrolysis gas and pyrolytic tar are processed simultaneously, produce combustible gas and high added value oil product as major product, it is achieved coal plug
Economic benefit.Pyrolysis primary dust removing system (i.e. cyclone separator) is built in pyrolysis reactor simultaneously, effectively reduces
Go out the dustiness of the pyrolysis gas of pyrolysis reactor, it is to avoid the problem that tar condenses blocking pipeline.
In another aspect of this invention, the invention provides one and utilize foregoing pyrolysis of coal reactor-recirculating fluidized bed connection
The method processing coal by system.According to embodiments of the invention, with reference to Fig. 6, the method comprises the following steps:
S100: coal is delivered to described pyrolysis of coal reactor and carries out pyrolysis processing, in order to obtain semicoke and gas mixture.
According to embodiments of the invention, the particle diameter supplying the coal to pyrolysis of coal reactor can be less than 3 millimeters, thus, and heat
Solving material to be heated evenly in pyrolysis reactor, pyrolytic reaction efficiency is higher, and pyrolytic tar yield is higher.
According to a particular embodiment of the invention, the temperature on pyrolysis reactor top is 680-730 degree Celsius, and the temperature at middle part is
500-650 degree Celsius, the temperature of bottom is 500-600 degree Celsius.Specifically, pyrolysis is expected in pyrolysis reactor by up to
Lower motion, sequentially passes through drying and dehydrating district, top, pyrolysis reaction region, middle part and semicoke maturation zone, bottom, in drying and dehydrating district heat
Solve material and quickly slough moisture, then carry out pyrolytic reaction in pyrolysis reaction region, obtain gas mixture and semicoke, air-fuel mixture
Thing is derived pipeline by oil gas and is quickly derived, and collects through gas-collecting branch pipe, gas gathering manifold and supply to the second cyclone separator,
Discharging pyrolysis reactor after removing dust, the semicoke obtained is continued to move downwardly into semicoke maturation zone, is then exported by semicoke
Discharge pyrolysis of coal reactor.
S200: semicoke is delivered to described recirculating fluidized bed, makes semicoke carry out combustion power generation.
According to embodiments of the invention, in this step, the pyrolysis high-temperature semi-coke of 400-600 degree Celsius is discharged from semicoke outlet,
Deliver to recirculating fluidized bed through First air, carry out combustion power generation.
S300: described gas mixture is delivered to described gas mixture after-treatment device and post-processes, thus obtain can
Combustion gas and oil product.
According to embodiments of the invention, with reference to Fig. 7, step S300 may further include following steps: S310: by oil gas
Mixture carries out Oil-gas Separation process, obtains tar and pyrolysis gas;S320: pyrolysis gas is carried out purified treatment, obtains flammable
Gas;And S330: tar is carried out refinement treatment, obtains oil product.Thus, it is possible to effectively thermal decomposition product is fitted
Suitable post processing, obtains combustible gas and the high added value oil product of cleaning.
Inventor finds, in the method, it is possible to use pyrolysis of coal reactor is directly combined with existing recirculating fluidized bed, and
Without transforming existing recirculating fluidized bed, pyrolysis of coal reactor and recirculating fluidized bed can run relatively independently, and two
Person interferes with each other relatively small.The method can be effective to produce combustible gas and pyrolysis oil co-production electric power, and utilizes existing
The induction system of recirculating fluidized bed, it is achieved semicoke heat is sent, ensures the burning of semicoke, and reduces coal plug process costs.And,
In the method, the gas mixture that pyrolysis of coal produces, before discharging pyrolysis of coal reactor, carries out dedusting through cyclone separator,
Can greatly reduce pyrolysis of coal reactor to the lagging facility of pipeline between pyrolysis oil gas mixture rapid condensation device, minimizing sets
Standby thermal insulation area and reduction system heat tracing energy consumption, greatly reduce the possibility of tar condensing blocking pipeline simultaneously.
Referring to Fig. 5 and Fig. 7, describe pyrolysis of coal reactor-recirculating fluidized bed combined system and the utilization of the present invention in detail
The duty of its method processing coal is described.
Specifically, by coal entrance 110, the fine coal that particle diameter is crushed to less than 3 millimeters in advance is supplied to pyrolysis of coal reactor
100, fine coal from top to bottom moves in pyrolysis of coal reactor 100, is pyrolyzed under the temperature field that heat accumulation type radiant tube provides
Reaction, produces gas mixture and semicoke.On the one hand, the gas mixture obtained derives the through hole of pipeline 140 by oil gas
Enter oil gas and derive pipeline 140, derive pipeline 140 by oil gas and be directed into gas-collecting branch pipe 160, be then collected to gas gathering manifold
150, and be supplied to cyclone separator 180 carry out gas solid separation process by gas-solid mixture entrance 181, consolidating of isolated
Body is discharged through solid outlet 183, enters in pyrolysis of coal reactor 100, the gas mixture of isolated through gas vent 182,
Gas mixture outlet 130 is also entered carried out Oil-gas Separation in Oil-gas Separation assembly 410 by gas mixture entrance 411
Processing, the pyrolysis gas of isolated is discharged through pyrolysis gas outlet 412, then enters pyrolysis gas through pyrolysis gas import 421 and purifies
Assembly 420, in pyrolysis gas purification assembly 420, pyrolysis gas carries out the operation such as desulfurization, deamination and carries out purified treatment, obtains
Purified gas part through combustible gas outlet 422 discharge, obtain combustible gas product, a part can be exported by another combustible gas
422 supply the heat accumulation type radiant tube to pyrolysis of coal reactor, separate in combustion heating, Oil-gas Separation assembly 410
To tar enter tar refining assembly 430 through tar outlet 413 and tar import 431 successively, at tar refining assembly 430
In tar is carried out hydrotreating, the high added value oil product obtained through oil product outlet 432 discharge.On the other hand, pyrolysis produces
Semicoke through semicoke outlet 120 discharge pyrolysis of coal reactors 100, then enter recirculating fluidized bed 200 through semicoke entrance 210,
In recirculating fluidized bed 200, supply bunker coal and air by bunker coal entrance 220 and air intake 230, in circulation simultaneously
In fluid bed 200, semicoke and coal carry out mixing burning generating.