CN105736010A - Supporting structure for extremely-narrow coal pillar roadway driving along goaf and construction method of supporting structure - Google Patents

Supporting structure for extremely-narrow coal pillar roadway driving along goaf and construction method of supporting structure Download PDF

Info

Publication number
CN105736010A
CN105736010A CN201610241124.8A CN201610241124A CN105736010A CN 105736010 A CN105736010 A CN 105736010A CN 201610241124 A CN201610241124 A CN 201610241124A CN 105736010 A CN105736010 A CN 105736010A
Authority
CN
China
Prior art keywords
coal
anchor pole
pole
canopy
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610241124.8A
Other languages
Chinese (zh)
Inventor
杨永刚
何炳银
杨张杰
余大军
王波
王威
王庆牛
王福海
陈康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI PROVINCE COAL SCIENCE RESEARCH INSTITUTE
Original Assignee
ANHUI PROVINCE COAL SCIENCE RESEARCH INSTITUTE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI PROVINCE COAL SCIENCE RESEARCH INSTITUTE filed Critical ANHUI PROVINCE COAL SCIENCE RESEARCH INSTITUTE
Priority to CN201610241124.8A priority Critical patent/CN105736010A/en
Publication of CN105736010A publication Critical patent/CN105736010A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/006Lining anchored in the rock
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • E21D11/22Clamps or other yieldable means for interconnecting adjacent arch members either rigidly, or allowing arch member parts to slide when subjected to excessive pressure

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a supporting structure for extremely-narrow coal pillar roadway driving along a goaf and a construction method of the supporting structure. The supporting structure for extremely-narrow coal pillar roadway driving along the goaf is a structural form that a bolt-beam-net support is adopted on a roadway roof; a roadway solid coal side is supported by utilizing a coal side anchor rod; the side of the roadway goaf is supported by a steel shed leg matched with the anchor rod; the steel shed leg is clamped, fixed and connected by an upper arch section and a lower straight leg section by utilizing a clamping cable; the straight leg section is positioned on the side of a coal pillar; the top end of the arch section extends to the roadway roof. According to the supporting structure disclosed by the invention, not only can the resource recovery rate be improved, but also the roadway space can be effectively maintained to facilitate ventilation and pedestrians.

Description

The supporting construction of a kind of pole thin coal pillar gob side entry driving and construction method thereof
Technical field
The present invention relates to one to be applied to underground coal mine and stay gob side entry driving roadway support structure and construction method thereof when setting 1~2m coal column.
Background technology
Underground coal mine gob side entry driving referred at this stage coal body edge and goaf intersection digging laneway of upper stage, stay and set reasonable coal column, make tunnel be positioned at the stress relaxed area at edge, goaf, to alleviate tunnel pressure, reach a kind of drift support type of the easily purpose of maintenance.Generally individually reserved coal pillar during gob side entry driving, one is to isolate goaf, and two is to support back.Staying the basic principle setting protection pillar is allow tunnel be in the region that a bearing capacity is relatively low as far as possible, and two is reduce coal pillar width as far as possible to increase resource recovery.The width of current reserved coal pillar is promising three classes mainly: first kind coal pillar width is not more than 3m, and the coal column of this kind of width can only play the effect in isolation goaf, and substantially destroys due to it, lose bearing capacity;Equations of The Second Kind coal pillar width 3~8m, this type of coal column is except isolation goaf, although suffer more serious destruction and bigger deformation occurs, still having certain bearing capacity;3rd class coal pillar width is not less than 8m, and this type of coal column generally will not all be damaged, and has higher bearing capacity.
From the viewpoint of improving resource recovery and being prone to roadway maintenance, underground coal mine the 3rd class coal column and the use that coal pillar width is 3~8m are most commonly seen, but mine deficient for part resource, the entrance date of retirement, in order to improve resource recovery, wish that reduction coal column stays as far as possible and set width, but when coal pillar width is down to below 3m, goaf side coal side is crisp by pressure under overburden pressure effect, roof bolting with barand wire mesh conventional while losing bearing capacity loses reliable impetus, lane space cannot be safeguarded, now derives again Air Leakage.Up to now, for staying gob side entry supporting construction when setting 1~3m pole thin coal pillar and construction method thereof not to be publicly reported.
Summary of the invention
The present invention is for avoiding the weak point existing for above-mentioned prior art, a kind of coal pillar width supporting construction at the pole thin coal pillar gob side entry driving of 1~3m and construction method thereof are provided, to resource recovery can be promoted, lane space be can effectively safeguard again, ventilation and pedestrian are beneficial to.
The present invention solves that above-mentioned technical problem adopts the following technical scheme that
The supporting construction of pole of the present invention thin coal pillar gob side entry driving, described pole thin coal pillar gob side entry driving refers to when tunnelling, stays along edge, adjacent sections goaf and sets 1~3m coal column gob side entry driving;Being characterized in that of the supporting construction of described pole thin coal pillar gob side entry driving:
The present invention adopts the version of roof bolting with barand wire mesh at back, top board anchor cable in described roof bolting with barand wire mesh adopts combination of steel rope, described combination of steel rope refers to and with longitudinal ceiling steel channel beam, anchor cable is coordinated supporting, and described longitudinal ceiling steel channel beam refers to the steel channel beam being supported on back along tunnelling direction;
Coal side anchor pole is utilized to carry out supporting for tunnel entity coal side;
Adopting steel canopy lower limb to coordinate anchor pole to carry out supporting at tunnel goaf side, described steel canopy lower limb is to be utilized card cable card to be solidly connected by epimere arcuate segment and hypomere straight legs section;Described straight legs section is positioned at coal column lateral wall, and the top of described arcuate segment is along extending back;The anchor pole coordinated with described steel canopy lower limb includes: be arranged in the top of arcuate segment, in the be vertically anchored at back first solid canopy anchor pole, it is arranged in the middle part of arcuate segment and is anchored at the second solid canopy anchor pole of coal column and back along arcuate surface normal direction, and to the be anchored at coal column and roadway floor the 3rd solid canopy anchor pole under being arranged in the middle part of straight legs section and tilting.
The feature of the supporting construction of pole of the present invention thin coal pillar gob side entry driving lies also in: the length of the described first solid canopy anchor pole, the second solid canopy anchor pole and the 3rd solid canopy anchor pole is all not less than 1500mm.
The feature of the supporting construction of pole of the present invention thin coal pillar gob side entry driving lies also in: the 3rd solid canopy anchor pole is to be anchored in coal column and roadway floor with the angle of depression of 30 °.
The feature of the construction method of the supporting construction of pole of the present invention thin coal pillar gob side entry driving is to carry out as follows:
Step 1, each drilling depth 2m of development machine is utilized to tunnel in tunnel;
Step 2, implementing roof timbering after completing every time pick on back, described roof timbering adopts roof bolting with barand wire mesh, carries out coordinating with longitudinal ceiling steel channel beam by the anchor cable in roof bolting with barand wire mesh and implements strengthening supporting, and the length of described anchor cable is not less than 7.5m;
Step 3, for tunnel entity coal side utilize coal side suspension roof support;
Step 4, implement that coal column is collateral protects, it is adopt the 10# wire netting back of the body to protect coal column lateral wall, at the fillet place, top of coal column reinforcing bar basketry sheet wall supporting, and with Periostracum Serpentis packed coal fillet place tamped and to make it domed, by the first solid canopy anchor pole through the reserved mounting hole in the top of arcuate segment in steel canopy lower limb in being vertically anchored in back, second solid canopy anchor pole through the reserved mounting hole in the middle part of arcuate segment in steel canopy lower limb and is anchored at along arcuate surface normal direction in coal column and back, the 3rd solid canopy anchor pole is anchored in coal column and roadway floor with the angle of depression of 30 °.
Compared with the prior art, the present invention has the beneficial effect that:
1, in the present invention, steel canopy lower limb is utilized card cable card to be solidly connected by epimere arcuate segment and hypomere straight legs section and forms half inverse u shape support, efficiently solve the roadway support issues of the pole thin coal pillar that width is 1~3m, by roadway layout is being propped up the position that bearing capacity is relatively low, be conducive to tunnel safety stable;
2, in the present invention in inverse u shape support steel canopy lower limb have can contracting yielding property energy, can automatically adapt to crush, compared with tunneling boring roof bolting with barand wire mesh, drift section convergency factor reduces by more than 30%, roadway maintenance amount is minimum, does not even keep in repair, and significantly reduces lane and accomplishes this.
3, the present invention stays the coal column setting 1~3m, makes Pillar Recovery rate improve 60~80%;
Accompanying drawing explanation
Fig. 1 is present configuration schematic diagram;
Fig. 2 is steel canopy lower limb structural representation in the present invention;
Number in the figure: 1 tunnel, 11 first solid canopy anchor poles, 12 second solid canopy anchor poles, 13 the 3rd solid canopy anchor poles, 2 coal columns, 21 arcuate segment, 22 straight legs sections, 3 backs, 31 anchor cables, 32 longitudinal ceiling steel channel beams, 33 ceiling anchor poles, 4 entity coal sides, 41 coal side anchor poles, 5 roadway floors.
Detailed description of the invention
Referring to Fig. 1 and Fig. 2, in the present embodiment, pole thin coal pillar gob side entry driving refers to when tunnel 1 is tunneled, and stays along edge, adjacent sections goaf and sets 1~3m coal column 2 gob side entry driving.
In the present embodiment, the supporting construction of pole thin coal pillar gob side entry driving is:
The version of roof bolting with barand wire mesh is adopted at back, top board anchor cable in roof bolting with barand wire mesh adopts combination of steel rope, combination of steel rope refers to and with longitudinal ceiling steel channel beam 32, anchor cable 31 is coordinated supporting, and longitudinal ceiling steel channel beam 32 refers to and is supported on the steel channel beam on back 3 along tunnelling direction;The version of roof bolting with barand wire mesh is: adopts the wire netting back of the body to protect back 3, utilizes ceiling anchor pole 33 to coordinate steel band to carry out initial support, and anchor cable 31 coordinates longitudinal ceiling steel channel beam 32 to make strengthening supporting.Wherein ceiling anchor pole 33 adopts Φ 20 × 2400mm left hand thread steel equal strength anchor rod, and an array pitch is 800 × 800mm;Anchor cable 31 is Φ 22 × 7500mm, and between anchor cable 31, array pitch is 1100 × 800mm.Along tunnel longitudinally and be that decussation is arranged with steel band, every longitudinal ceiling channel-section steel installs three anchor cables, the version of formation " beam three rope " to longitudinal ceiling steel channel beam 32.
4 are helped to utilize coal side anchor pole 41 to carry out supporting for tunnel entity coal;Protecting including adopting 8# wire netting that entity coal side in tunnel is carried out the wire netting back of the body, coal side anchor pole 41 coordinates flat strip steel to carry out supporting.Coal side anchor pole 41 is the left hand thread steel equal strength anchor rod adopting Φ 20 × 2400mm, and between coal side anchor pole 41, array pitch is set to 800 × 800mm;The coal side anchor pole elevation angle and the angle of depression with 20 ° respectively of the top corner and bottom corners place that are positioned at entity coal side 4 anchors into, and the vertical lane side of all the other coals side anchor pole anchors into;Flat strip steel is longitudinally laid along tunnel, and two steel bands that same row is adjacent overlap and compress wire netting mutually, and the coal side anchor pole of steel band lap-joint anchors into entity coal side from overlap joint hole.
As depicted in figs. 1 and 2, adopting steel canopy lower limb to coordinate anchor pole to carry out supporting at tunnel goaf side in the present embodiment, steel canopy lower limb is to be utilized card cable 23 card to be solidly connected by epimere arcuate segment 21 and hypomere straight legs section 22;Straight legs section 22 is positioned at coal column lateral wall, and the top of arcuate segment 21 is along extending back 3;The anchor pole coordinated with steel canopy lower limb includes: be arranged in the top of arcuate segment 21, in the be vertically anchored at back 3 first solid canopy anchor pole 11, it is arranged in the middle part of arcuate segment 21 and is anchored at the second solid canopy anchor pole 12 of coal column 2 and back 3 along arcuate surface normal direction, and to the be anchored at coal column 2 and roadway floor 5 the 3rd solid canopy anchor pole 13 under being arranged in the middle part of straight legs section 22 and tilting.
In being embodied as, the length of the first solid solid canopy anchor pole of canopy anchor pole 11, second 12 and the 3rd solid canopy anchor pole 13 is all not less than 1500mm;3rd solid canopy anchor pole 13 is to be anchored in coal column and roadway floor 5 with the angle of depression of 30 °.
In the present embodiment, the construction method of the supporting construction of pole thin coal pillar gob side entry driving is to carry out as follows:
Step 1, each drilling depth 2m of development machine is utilized to tunnel in tunnel 1;
Step 2, implementing roof timbering after completing every time pick on back 3, roof timbering adopts roof bolting with barand wire mesh, carries out coordinating with longitudinal ceiling steel channel beam 32 by the anchor cable 31 in roof bolting with barand wire mesh and implements strengthening supporting, and the length of anchor cable 31 is not less than 7.5m;
Step 3, for tunnel entity coal help 4 utilize coal side anchor pole 41 supporting;
Step 4, implement that coal column is collateral protects, it is adopt the 10# wire netting back of the body to protect coal column lateral wall, at the fillet place, top of coal column 2 reinforcing bar basketry sheet wall supporting, and with Periostracum Serpentis packed coal fillet place tamped and to make it domed, by the first solid canopy anchor pole 11 through the reserved mounting hole in the top of arcuate segment 21 in steel canopy lower limb in being vertically anchored in back 3, second solid canopy anchor pole 12 is reserved mounting hole through the middle part of arcuate segment 21 in steel canopy lower limb, and it is anchored in coal column 2 and back 3 along arcuate surface normal direction, 3rd solid canopy anchor pole 13 is anchored in coal column 2 and roadway floor 5 with the angle of depression of 30 °.
In being embodied as, a pack support is formed with every steel canopy lower limb, walking upwards along tunnel, spacing between each pack support is set to 600mm, between each pack support, being attached making each pack support be formed as overall structure between steel canopy lower limb with longitudinal reinforcing pull rod, longitudinal reinforcing pull rod has twice, lays respectively at epimere arcuate segment 21 and the middle part of hypomere straight legs section 22.

Claims (4)

1. a supporting construction for pole thin coal pillar gob side entry driving, described pole thin coal pillar gob side entry driving refers to when tunnel (1) is tunneled, and stays along edge, adjacent sections goaf and sets 1~3m coal column (2) gob side entry driving;The supporting construction of described pole thin coal pillar gob side entry driving is characterized by:
The version of roof bolting with barand wire mesh is adopted at back, top board anchor cable in described roof bolting with barand wire mesh adopts combination of steel rope, described combination of steel rope refers to and with longitudinal ceiling steel channel beam (32), anchor cable (31) is coordinated supporting, and described longitudinal ceiling steel channel beam (32) refers to and is supported on the steel channel beam on back (3) along tunnelling direction;
(4) are helped to utilize coal side anchor pole (41) to carry out supporting for tunnel entity coal;
Adopting steel canopy lower limb to coordinate anchor pole to carry out supporting at tunnel goaf side, described steel canopy lower limb is to be utilized card cable (23) card to be solidly connected by epimere arcuate segment (21) and hypomere straight legs section (21);Described straight legs section (22) is positioned at coal column lateral wall, and the top of described arcuate segment (21) is along extending back (3);The anchor pole coordinated with described steel canopy lower limb includes: be arranged in the top of arcuate segment (21), in the be vertically anchored at back (3) first solid canopy anchor pole (11), it is arranged in the middle part of arcuate segment (21) and is anchored at the second solid canopy anchor pole (12) of coal column (2) and back (3) along arcuate surface normal direction, and consolidate canopy anchor pole (13) to the be anchored at coal column (2) and roadway floor (5) the 3rd under being arranged in the middle part of straight legs section (4) and tilting.
2. the supporting construction of pole according to claim 1 thin coal pillar gob side entry driving, is characterized in that: the length of the described first solid canopy anchor pole (11), the second solid canopy anchor pole (12) and the 3rd solid canopy anchor pole (13) is all not less than 1500mm.
3. the supporting construction of pole according to claim 1 thin coal pillar gob side entry driving, is characterized in that: the 3rd solid canopy anchor pole (13) is to be anchored in coal column and roadway floor (5) with the angle of depression of 30 °.
4. the construction method of the supporting construction of the pole thin coal pillar gob side entry driving described in claim 1, is characterized in that carrying out as follows:
Step 1, each drilling depth 2m of development machine is utilized to tunnel in tunnel (1);
Step 2, after completing every time pick, on back (3), implement roof timbering, described roof timbering adopts roof bolting with barand wire mesh, carrying out coordinating enforcement strengthening supporting with longitudinal ceiling steel channel beam (32) by the anchor cable (31) in roof bolting with barand wire mesh, the length of described anchor cable (31) is not less than 7.5m;
Step 3, for tunnel entity coal help (4) utilize coal side anchor pole (41) supporting;
Step 4, implement that coal column is collateral protects, it is adopt the 10# wire netting back of the body to protect coal column lateral wall, at the fillet place, top of coal column (2) reinforcing bar basketry sheet wall supporting, and with Periostracum Serpentis packed coal fillet place tamped and to make it domed, by the first solid canopy anchor pole (11) through the reserved mounting hole in the top of arcuate segment (21) in steel canopy lower limb in being vertically anchored in back (3), second solid canopy anchor pole (12) is reserved mounting hole through the middle part of arcuate segment (21) in steel canopy lower limb, and it is anchored in coal column (2) and back (3) along arcuate surface normal direction, 3rd solid canopy anchor pole (13) is anchored in coal column (2) and roadway floor (5) with the angle of depression of 30 °.
CN201610241124.8A 2016-04-15 2016-04-15 Supporting structure for extremely-narrow coal pillar roadway driving along goaf and construction method of supporting structure Pending CN105736010A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610241124.8A CN105736010A (en) 2016-04-15 2016-04-15 Supporting structure for extremely-narrow coal pillar roadway driving along goaf and construction method of supporting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610241124.8A CN105736010A (en) 2016-04-15 2016-04-15 Supporting structure for extremely-narrow coal pillar roadway driving along goaf and construction method of supporting structure

Publications (1)

Publication Number Publication Date
CN105736010A true CN105736010A (en) 2016-07-06

Family

ID=56254550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610241124.8A Pending CN105736010A (en) 2016-04-15 2016-04-15 Supporting structure for extremely-narrow coal pillar roadway driving along goaf and construction method of supporting structure

Country Status (1)

Country Link
CN (1) CN105736010A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106894833A (en) * 2017-01-23 2017-06-27 山东科技大学 Gob side entry driving unbalanced support structure and construction method under the unstable overlying strata in deep
CN108049898A (en) * 2018-01-16 2018-05-18 湖南科技大学 A kind of support system and its method for protecting support for coal road weak broken top plate
CN108661665A (en) * 2018-05-17 2018-10-16 兖州煤业股份有限公司 A kind of fender gob side entry supporting construction and its method for protecting support
CN114017079A (en) * 2021-10-29 2022-02-08 国能神东煤炭集团有限责任公司 Roadway supporting device for gob-side entry driving under coal mine

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2131038C1 (en) * 1998-01-14 1999-05-27 Сидоренко Николай Викторович Spring lock of yielding support of mine workings
DE10235635A1 (en) * 2002-02-20 2003-08-28 Werner P Berwald Assembly of curved structures, for a tunnel lining, has multi-functional locks at their overlaps to give a variety of bonds using minimum components, with or without anchors
CN101100945A (en) * 2006-06-24 2008-01-09 唐卫东 Mine tunnel U-shaped mulch area fork door support technology
CN102418539A (en) * 2011-10-31 2012-04-18 山西晋城无烟煤矿业集团有限责任公司 Supporting process in soft rock mine roadway rush through construction tunneling
CN105370299A (en) * 2015-11-27 2016-03-02 山东新巨龙能源有限责任公司 Kilometers-deep thick coal seam narrow coal pillar gob-side entry supporting process

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2131038C1 (en) * 1998-01-14 1999-05-27 Сидоренко Николай Викторович Spring lock of yielding support of mine workings
DE10235635A1 (en) * 2002-02-20 2003-08-28 Werner P Berwald Assembly of curved structures, for a tunnel lining, has multi-functional locks at their overlaps to give a variety of bonds using minimum components, with or without anchors
CN101100945A (en) * 2006-06-24 2008-01-09 唐卫东 Mine tunnel U-shaped mulch area fork door support technology
CN102418539A (en) * 2011-10-31 2012-04-18 山西晋城无烟煤矿业集团有限责任公司 Supporting process in soft rock mine roadway rush through construction tunneling
CN105370299A (en) * 2015-11-27 2016-03-02 山东新巨龙能源有限责任公司 Kilometers-deep thick coal seam narrow coal pillar gob-side entry supporting process

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106894833A (en) * 2017-01-23 2017-06-27 山东科技大学 Gob side entry driving unbalanced support structure and construction method under the unstable overlying strata in deep
CN108049898A (en) * 2018-01-16 2018-05-18 湖南科技大学 A kind of support system and its method for protecting support for coal road weak broken top plate
CN108049898B (en) * 2018-01-16 2024-01-26 湖南科技大学 Supporting system and supporting method for weak broken roof of coal roadway
CN108661665A (en) * 2018-05-17 2018-10-16 兖州煤业股份有限公司 A kind of fender gob side entry supporting construction and its method for protecting support
CN114017079A (en) * 2021-10-29 2022-02-08 国能神东煤炭集团有限责任公司 Roadway supporting device for gob-side entry driving under coal mine
CN114017079B (en) * 2021-10-29 2023-10-13 国能神东煤炭集团有限责任公司 Roadway support device for underground gob-side entry driving of coal mine

Similar Documents

Publication Publication Date Title
RU2612427C2 (en) Tunnel self propelled bearing arch
CN103410515B (en) It is a kind of that three-soft seam is reciprocating combines mining method without coal column
CN109763822B (en) Large-dip-angle thick coal seam multi-section coal pillar-free staggered layer roadway protection and inter-section coal pillar-free filling method
CN102661169B (en) Gob-side entry retaining method for anchor bolt network gangue bag wall body for coal mining without pillars
CN101457651B (en) Filling stack advanced support method along empty tunnel in coal-gas co-milling Y-shaped ventilating system
CN104234749B (en) A kind of fully-mechanized mining working big cross section return channel surrounding rock control method
CN105736010A (en) Supporting structure for extremely-narrow coal pillar roadway driving along goaf and construction method of supporting structure
CN105003288B (en) A kind of method and support system of medium-thickness seam gob side entry retaining
CN105370299B (en) The buried empty roadway protection processing in high seam thin coal pillar edge of km
CN103643979A (en) Hydraulic support used for roadway temporary support and erecting and use method of hydraulic support
CN104061001A (en) Gob-side entry retaining mining support process method
CN105201524B (en) A kind of pre- spare anchor net right angle in extremely soft seam tunnel can contracting canopy Support Method
CN104405392B (en) Three soft high seam tunnel jackings are kept on file anchor rete cord active support longwall top coal caving method
CN109630168A (en) Comprehensive extracting and caving face tunnel is arranged along floor strata and support pattern
CN109630171B (en) Method for controlling floor heave by arranging pressure relief lane along bottom plate along top lane
CN215170078U (en) Surrounding rock strengthening and supporting structure of roadway
CN116927809B (en) Roadway support structure and construction method thereof
CN211666747U (en) Coal mine underground crossheading roadway tunneling composite supporting device
CN106930779A (en) A kind of special-shaped canopy method for protecting support of micro- arch of high-dipping three soft coal layer re-exploration laneway battered leg
CN104612728B (en) Roadway supporting method for forming cross point by penetrating through existing roadway
CN102425417A (en) Anchor cable and rough wall combined method for gob-side entry retaining stage under collapsible roof
CN203066986U (en) Composite truss for supporting coal rock roadway top plate
CN115977695A (en) Telescopic coupling support and method for protecting roadway along air in steeply inclined and inclined coal seam
CN108952715A (en) A kind of inclination thickness/super high seam lane top gob side entry driving top coal support reinforcement method
CN205422777U (en) A gob entry support system for roof is unstable

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160706

WD01 Invention patent application deemed withdrawn after publication