CN105370299B - The buried empty roadway protection processing in high seam thin coal pillar edge of km - Google Patents

The buried empty roadway protection processing in high seam thin coal pillar edge of km Download PDF

Info

Publication number
CN105370299B
CN105370299B CN201510853822.9A CN201510853822A CN105370299B CN 105370299 B CN105370299 B CN 105370299B CN 201510853822 A CN201510853822 A CN 201510853822A CN 105370299 B CN105370299 B CN 105370299B
Authority
CN
China
Prior art keywords
anchor
top plate
supporting
steel band
helped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510853822.9A
Other languages
Chinese (zh)
Other versions
CN105370299A (en
Inventor
孙广京
李爱民
张治高
李志深
卢诗祥
王延辉
徐波
谭文峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG XINJULONG ENERGY CO Ltd
Original Assignee
SHANDONG XINJULONG ENERGY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG XINJULONG ENERGY CO Ltd filed Critical SHANDONG XINJULONG ENERGY CO Ltd
Priority to CN201510853822.9A priority Critical patent/CN105370299B/en
Publication of CN105370299A publication Critical patent/CN105370299A/en
Application granted granted Critical
Publication of CN105370299B publication Critical patent/CN105370299B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/155Laggings made of strips, slats, slabs or sheet piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D15/00Props; Chocks, e.g. made of flexible containers filled with backfilling material
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention discloses a kind of buried empty roadway protection processing in high seam thin coal pillar edge of km, it is characterised in that and first, after gob side entry is excavated according to design section, helped first using anchor+band+net support form supporting roof and two;Second, top plate and two are helped to carry out strengthening supporting;3rd, gob side entry advance support.Due to adding the combined supporting form of anchor cable beam column using anchor band net, roadway deformation can be effectively controlled, meets the production needs of next working face;Advance support is carried out using unit supports formula advance timbering particularly in the gob side entry in front of working face, deformation of the surrounding rock in tunnel amount is obviously reduced, and compared with using individual prop supporting, two help average deformation amount to reduce 566mm, roof to floor convergence reduces 767mm, and pucking amount, which is reduced, reaches 473mm.

Description

The buried empty roadway protection processing in high seam thin coal pillar edge of km
Technical field
The present invention relates to coal mining technology, more particularly to along empty roadway protection processing.
Background technology
At present, coal mining depth reaches km.With coal mining depth, the increase of intensity, and to the big of the energy Amount demand, many Deep Mines are general by the way of thin coal pillar gob side entry driving is stayed in goaf side stope drift active workings.Due to adopting Deep increase year by year, especially in high seam (more than 3.5m) exploitation, gob side entry highlights that surrouding rock deformation is strong, destroys model Enclose greatly, roof fall, wall caving easily occur.So that gob side entry maintenance is more and more difficult, the fltting speed and peace of working face are constrained Full production, has seriously affected the construction in safe and efficient work face although in the past few years scientific research department, colleges and universities and production scene strengthen To deep fractures production practice, the research of roadway support, also achieves certain effect, but for deep-well gob side entry stability Aspect also recognizes deficiency.《Safety regulations in coal mine》Required 20m advance supports are far from meeting gob side entry to advanced branch The demand of shield.At the same time as working face installed power is continuously increased, equipment size is increasing, and supporting is with opening during gob side entry driving Advance support area, height are also bigger during adopting, therefore supporting becomes high yield with advance support during exploitation during gob side entry driving The emphasis and difficult point of working face protection (are put) in efficient fully mechanized mining.For the depth that roof pressure is big, deformation is serious, deformation effect scope is big Portion's big cross section gob side entry, during gob side entry driving frequently with anchor pole and Application of Combined Support with Anchor, in application process there are anchor cable- The problems such as bolt action mismatches and the design method of cable bolting is not suitable with coal roadway support.Advanced branch during working face mining The supporting length that shield distance is longer, supporting intensity is bigger more favourable to roadway maintenance but long will necessarily exist to top plate repeatedly Support causes roof cracking.China's high seam yield accounts for 45% or so of raw coal total output, is a high seam reserves big country, It is the exploitation big country of high seam, therefore, the buried high seam working face thin coal pillar gob side entry support issues of km is worth studying.
The content of the invention
To solve the buried high seam working face thin coal pillar gob side entry supporting difficult problem of km, the present invention proposes one kind Thin coal pillar can effectively control roadway deformation, meet production needs along empty roadway protection processing.
The buried high seam thin coal pillar of km of the present invention is along empty roadway protection processing:
First, after gob side entry is excavated according to design section, first using anchor+band+net support form supporting roof and two Side, i.e., help first paving in top plate and two and hang one layer of bar-mat reinforcement, then pushed down with steel band, then steel band is anchored at top plate with anchor pole On;For the arrangement form of above-mentioned steel band to be arranged along drift section, the spacing of steel band is 1000mm, is set on steel band per spacing 900mm There is a bolthole, anchor pole is arranged as the form of array pitch between 900 × 1000mm;
Second, top plate and two are helped to carry out strengthening supporting
After the completion of anchor+band+net supporting, then plate helps top plate and two to carry out strengthening supporting;
The strengthening supporting of top plate is that anchor cable beam is set between top plate steel band, and anchor cable beam uses the anchoring shape of three rope of a beam Formula, i.e., be respectively equipped with anchor cable hole in the centre of steel channel beam and both ends, with three anchorage cable anchorings on top plate;
The strengthening supporting in portion of side is:Anchor cable column is set on thin coal pillar lateral wall face, anchor cable column uses the anchoring of three rope of a column Form, i.e., be respectively equipped with anchor cable eye in the centre of channel column and upper/lower terminal, with three anchorage cable anchorings on lateral wall country rock;Groove Steel column is arranged between lateral wall steel band, spacing 2m;Upper eye and lower eye use 6.3m anchor cables, and the direction of anchor cable is respectively to top plate Tilted with bottom plate direction;Middle eye uses 4.3m anchor cables;
3rd, gob side entry advance support
With the exploitation of working face, surpassed in the gob side entry in front of working face using unit supports formula advance timbering Preceding supporting;Lame advanced supporting length is not less than 60m;Said units brace type advance timbering structure is by a unjointed beam, double columns Formed with a unsplit bedplate, be needling formula pin shaft joint form between unjointed beam, unsplit bedplate and double columns.
The positive effect of the present invention is, due to the combined supporting form using " anchor band net " plus anchor cable beam column, can effectively to control Roadway deformation processed, meets the production needs of next working face;Particularly, unit is used in the gob side entry in front of working face Brace type advance timbering carries out advance support, and deformation of the surrounding rock in tunnel amount is obviously reduced, and compared with using individual prop supporting, two help Average deformation amount reduces 566mm, and roof to floor convergence reduces 767mm, and pucking amount, which is reduced, reaches 473mm.
Brief description of the drawings
Fig. 1 is embodiment gob side entry supporting sectional drawing;
Fig. 2 is Figure 1A portions enlarged drawing;
Fig. 3 is Figure 1B portions enlarged drawing;
Fig. 4 is unit supports formula advance timbering front view;
Fig. 5 is the side view of Fig. 4.
Marginal data, 1- bar-mat reinforcements, 2- steel bands, 3- anchor poles, 4- anchor rod pallet boards, 5- steel channel beams, 6- anchor cables, 7- channel columns, 8- unjointed beams, the double columns of 9-, 10- unsplit bedplates, 11- hydraulically operated valves.
Embodiment
Referring to the drawings, the buried high seam thin coal pillar of km of the present invention is further illustrated along empty roadway protection processing:
First, as shown in Figure 1, Figure 2, Figure 3 shows, after gob side entry is excavated according to design section, propped up first using " anchor band net " Shield form supporting roof and two is helped, i.e., helps first paving in top plate and two and hang one layer of bar-mat reinforcement 1, then pushed down with steel band 2, then use anchor Steel band 2 is anchored on top plate by bar 3;To be arranged along drift section, the spacing of steel band 2 is the arrangement form of above-mentioned steel band 2 1000mm, is equipped with a bolthole per spacing 900mm on steel band 2, anchor pole 3 is arranged as the form of array pitch between 900 × 1000mm; Anchor pole 3 on top plate uses the MSGLW-600 of 22 × 2500mm of φ without longitudinal rib thread steel type resin anchor, two anchor poles 3 helped The strong thread steel type resin anchor such as MSGLD-335 using 22 × 2500mm of Φ;Above-mentioned bar-mat reinforcement 1 is the bar-mat reinforcement of φ 6.0mm, 1 mesh specification of bar-mat reinforcement is 100 × 100mm;Steel band 2 on top plate is W-shaped steel band, and two steel bands 2 helped are trapezoidal steel band, is used Anchor pole 3 need to be equipped with the anchor rod pallet board 4 that specification is 150 × 150 × 10mm when anchoring trapezoidal steel band;When installing anchor pole, using 2 trees Fat Anchor Agent carries out the extensible bolting.
Second, top plate and two are helped to carry out strengthening supporting
As shown in Figure 1, after the completion of " anchor band net " supporting, then top plate and two are helped to carry out strengthening supporting;
The strengthening supporting of top plate is that anchor cable beam is set between top plate steel band, and anchor cable beam uses the anchoring shape of three rope of a beam Formula, i.e., be respectively equipped with anchor cable hole in the centre of steel channel beam 5 and both ends, is anchored at three anchor cables 6 on top plate;Above-mentioned anchor cable 6 is The high-strength nest anchor ropes of 22 × 10300mm of φ, with 3 resin anchoring agents, anchor cable case bay is 2000mm.
The strengthening supporting in portion of side is:Anchor cable column is set on thin coal pillar lateral wall face, anchor cable column uses the anchoring of three rope of a column Form, i.e., be respectively equipped with anchor cable eye in the centre of channel column 7 and upper/lower terminal, is anchored at three anchor cables 6 on lateral wall country rock; Channel column 7 is arranged between lateral wall steel band 2, spacing 2m;Upper eye and lower eye use 6.3m anchor cables, the direction of anchor cable respectively to Top plate and bottom plate direction tilt;Middle eye uses 4.3m anchor cables.
3rd, gob side entry advance support
With the exploitation of working face, surpassed in the gob side entry in front of working face using unit supports formula advance timbering Preceding supporting;Lame advanced supporting length is not less than 60m;Said units brace type advance timbering structure as shown in Figure 4 and Figure 5, by Unjointed beam 8, double columns 9, unsplit bedplate 10 and hydraulically operated valve 11 form;Between unjointed beam 8, unsplit bedplate 10 and double columns 9 It is needling formula pin shaft joint form;Unjointed beam 8 is designed and sized to long 1600mm, width 600mm, and effectively shield top length is reachable 2000mm, double columns 9 are more than 200mm, integral bottom using double telescopic posts, bearing height 2150mm-4500mm, column cylinder diameter 10 width of seat are not more than 800mm.

Claims (1)

  1. A kind of 1. buried empty roadway protection processing in high seam thin coal pillar edge of km, it is characterised in that
    First, after gob side entry is excavated according to design section, helped first using anchor+band+net support form supporting roof and two, i.e., First paving is helped in top plate and two and hangs one layer of bar-mat reinforcement, is then pushed down with steel band, then steel band is anchored at top plate and two with anchor pole and is helped On;For the arrangement form of above-mentioned steel band to be arranged along drift section, the spacing of steel band be 1000 mm, every 900 mm of spacing on steel band Equipped with a bolthole, anchor pole is set to be arranged as the form of array pitch between 900 × 1000mm;
    Second, top plate and two are helped to carry out strengthening supporting
    After the completion of anchor+band+net supporting, then top plate and two are helped to carry out strengthening supporting;
    The strengthening supporting of top plate is that anchor cable beam is set between top plate steel band, and anchor cable beam uses the anchor type of three rope of a beam, i.e., Anchor cable hole is respectively equipped with the centre of steel channel beam and both ends, with three anchorage cable anchorings on top plate;
    The strengthening supporting in portion of side is:Anchor cable column is set on thin coal pillar lateral wall face, anchor cable column uses the anchor type of three rope of a column, Anchor cable eye is respectively equipped with the centre of channel column and upper/lower terminal, with three anchorage cable anchorings on lateral wall country rock;Channel column cloth Put between lateral wall steel band, spacing 2m;Upper eye and lower eye use 6.3m anchor cables, and the direction of anchor cable is respectively to top plate and bottom plate Direction tilts;Middle eye uses 4.3m anchor cables;
    3rd, gob side entry advance support
    With the exploitation of working face, propped up in advance using unit supports formula advance timbering in the gob side entry in front of working face Shield;Lame advanced supporting length is not less than 60m;Said units brace type advance timbering is overall by a unjointed beam, double columns and one Base forms, and is needling formula pin shaft joint form between unjointed beam, unsplit bedplate and double columns.
CN201510853822.9A 2015-11-27 2015-11-27 The buried empty roadway protection processing in high seam thin coal pillar edge of km Active CN105370299B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510853822.9A CN105370299B (en) 2015-11-27 2015-11-27 The buried empty roadway protection processing in high seam thin coal pillar edge of km

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510853822.9A CN105370299B (en) 2015-11-27 2015-11-27 The buried empty roadway protection processing in high seam thin coal pillar edge of km

Publications (2)

Publication Number Publication Date
CN105370299A CN105370299A (en) 2016-03-02
CN105370299B true CN105370299B (en) 2018-04-20

Family

ID=55372856

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510853822.9A Active CN105370299B (en) 2015-11-27 2015-11-27 The buried empty roadway protection processing in high seam thin coal pillar edge of km

Country Status (1)

Country Link
CN (1) CN105370299B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105736010A (en) * 2016-04-15 2016-07-06 安徽省煤炭科学研究院 Supporting structure for extremely-narrow coal pillar roadway driving along goaf and construction method of supporting structure
CN106089207B (en) * 2016-06-23 2018-06-08 大同煤矿集团有限责任公司 Super high seam working face gob side entry driving thin coal pillar stays equipment, method
CN106050282B (en) * 2016-07-08 2018-08-03 西安科技大学 A kind of anchor structure and reinforcement means of gob side entry retaining thin coal pillar
CN106894833B (en) * 2017-01-23 2018-04-06 山东科技大学 Gob side entry driving unbalanced support structure and construction method under the unstable overlying strata in deep
CN107023311A (en) * 2017-06-08 2017-08-08 刘冲 Roadway repair method below coal column
CN108561159A (en) * 2018-04-10 2018-09-21 淮南矿业(集团)有限责任公司 A kind of anti-wall caving suspension device of the high side in coal seam and method for protecting support
CN110374645A (en) * 2019-08-14 2019-10-25 缪协兴 A kind of super high seam big cross section thin coal pillar gob side entry Equivalent Support method
CN111088989A (en) * 2019-12-12 2020-05-01 大同煤矿集团有限责任公司 Gob-side entry driving surrounding rock control method for fully mechanized caving section of extra-thick coal seam
CN113279795B (en) * 2021-06-29 2023-10-31 辽宁工程技术大学 Drilling, anchoring and repairing rapid tunneling construction process method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1026606C (en) * 1993-07-24 1994-11-16 徐州矿务局庞庄煤矿 Gallery supporting method for underground free digging section in coal mine
RU2168628C1 (en) * 2000-03-20 2001-06-10 Шахтинский институт Южно-Российского государственного технического университета (Новочеркасский политехнический институт) Method of mining of stratified deposits
CN103061806B (en) * 2012-12-28 2014-12-17 山东科技大学 Composite roof thin seam fully-mechanized coal mining face gob-side entry retaining method
CN104061001B (en) * 2014-06-25 2016-09-07 枣庄矿业(集团)有限责任公司滨湖煤矿 Gob side entry retaining exploitation support process method
CN104265295B (en) * 2014-09-11 2017-06-27 四川达竹煤电(集团)有限责任公司铁山南煤矿 Medium Thickness And Medium Slope Angle coal seam prosthetic roadside packing and without coal column gob-side entry retaining method

Also Published As

Publication number Publication date
CN105370299A (en) 2016-03-02

Similar Documents

Publication Publication Date Title
CN105370299B (en) The buried empty roadway protection processing in high seam thin coal pillar edge of km
EP3489459B1 (en) Non-uniform support structure for gob-side entry driving under deep unstable overburden rock and construction method
CN102296976B (en) Asymmetrical bolt-net-cable combined supporting method for special-shaped recovery tunnel of large inclination angle coal bed
CN103410515B (en) It is a kind of that three-soft seam is reciprocating combines mining method without coal column
CN105003288B (en) A kind of method and support system of medium-thickness seam gob side entry retaining
CN205189893U (en) Be used for a lane coal column to wearing reinforced (rfd) supporting construction
CN102268998A (en) Dual-micro-arch span-reducing support method of large-span open-off cut
CN108868833A (en) A method of it carries out cutting gob side entry retaining in the relieving roadway of top in U-shaped steel supported laneway
CN103233748A (en) Anchor mesh cable column combined supporting design method for expanding extra-large span open-off cut brush into lane
CN102900449B (en) Support method for underground goaf roof of coal mine
CN103216244B (en) Roadway soft and weak top plate anchoring beam-arch combined structure support system and support method
CN110529144A (en) A kind of hybrid advanced support method of light section stope drift active workings
EA037966B1 (en) Fractured roof mining method
CN103758529A (en) Coal mine gob-side entry retaining side supporting method
CN109630168A (en) Comprehensive extracting and caving face tunnel is arranged along floor strata and support pattern
CN111425205B (en) Mining support method for steeply inclined extremely thin ore body
CN108049899A (en) A kind of gob side entry driving thin coal pillar breaking surrounding rock reinforcement means
CN104405392B (en) Three soft high seam tunnel jackings are kept on file anchor rete cord active support longwall top coal caving method
CN207018019U (en) The advanced telescopic cantilever suspension device of tunnelling
CN206419050U (en) A kind of alley hydraulic support of supporting variable-width
CN204984458U (en) Medium -thickness seam gob entry's support system
CN110566238A (en) Mud rock roof small coal pillar gob-side roadway supporting structure and method thereof
CN105736027A (en) Support group for gob-side entry retaining
CN104790991A (en) Mining roadway surrounding rock strong and long top anchoring technology
CN210948737U (en) Efficient and rapid tunneling roadway support facility for inclined small-section half-coal-rock roadway with thin coal seam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant