CN105719049B - Method and system for realizing intelligent log - Google Patents

Method and system for realizing intelligent log Download PDF

Info

Publication number
CN105719049B
CN105719049B CN201610017675.6A CN201610017675A CN105719049B CN 105719049 B CN105719049 B CN 105719049B CN 201610017675 A CN201610017675 A CN 201610017675A CN 105719049 B CN105719049 B CN 105719049B
Authority
CN
China
Prior art keywords
log
default
construction
construction project
type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610017675.6A
Other languages
Chinese (zh)
Other versions
CN105719049A (en
Inventor
邱海燕
乐铁毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Dashang construction Digital Technology Co.,Ltd.
Original Assignee
Shenzhen Dashang Network Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Dashang Network Technology Co ltd filed Critical Shenzhen Dashang Network Technology Co ltd
Priority to CN201610017675.6A priority Critical patent/CN105719049B/en
Publication of CN105719049A publication Critical patent/CN105719049A/en
Application granted granted Critical
Publication of CN105719049B publication Critical patent/CN105719049B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/10File systems; File servers
    • G06F16/18File system types
    • G06F16/1805Append-only file systems, e.g. using logs or journals to store data
    • G06F16/1815Journaling file systems
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F21/00Security arrangements for protecting computers, components thereof, programs or data against unauthorised activity
    • G06F21/60Protecting data
    • G06F21/62Protecting access to data via a platform, e.g. using keys or access control rules
    • G06F21/6218Protecting access to data via a platform, e.g. using keys or access control rules to a system of files or objects, e.g. local or distributed file system or database
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention provides a method and a system for realizing an intelligent log. The method comprises the following steps: customizing log types according to the requirements of construction projects, wherein the log types comprise default logs and non-default logs, establishing log models of different versions for the default logs, and setting applicable areas for the log models; receiving work diaries sent by managers of each construction department of the construction project by adopting a communication terminal; and calling a log model matched with the default log type and the area where the construction project is located according to the default log type in the working diary, and filling the construction content in the working diary into a corresponding log content classification position in the log model according to the construction content category in the working diary to generate the construction project log of the default type. The method and the system can reduce heavy manual recording work, update the construction project log in time, ensure the accuracy of log content, quickly search target data, share the log to participating parties and enable the participating parties to know the project progress in real time.

Description

Method and system for realizing intelligent log
Technical Field
The invention belongs to the technical field of construction management, and particularly relates to a method and a system for realizing an intelligent log.
Background
In the construction industry, supervision and construction logs are indispensable files in project data of each unit, and related departments in different regions have different requirements on the format of the logs and the content of the logs. The supervision and construction log is also called a working diary, is a real comprehensive record of construction organization management, construction technology and other related construction activities and field condition changes in the whole construction stage, and is a memorandum for processing construction problems and a basic material for summarizing construction management experience. The work diary has a very important position in the whole project archive. At present, the logs are manually filled by related personnel appointed by a project principal, then the manual logs provided by different people are collected and counted to obtain the current construction project log, the condition that information deviation is inconsistent with the reality can occur in the recording process by the manual construction project log recording mode, and the problems that information is not updated timely, information is omitted, data is difficult to search after filing, the project cannot be traced back timely when the project has problems, and the project progress cannot be mastered by a manager in real time exist.
Disclosure of Invention
The embodiment of the invention aims to provide a method and a system for realizing an intelligent log, and aims to solve the problems that information deviation is inconsistent with reality in the recording process by the manual construction project log recording mode, information updating is not timely, information is omitted, searching is difficult after data filing, a project cannot be traced back timely when encountering problems, and a manager cannot master project progress in real time.
The embodiment of the invention is realized in such a way that an implementation method of an intelligent log comprises the following steps:
defining log types according to the requirements of construction projects, wherein the log types comprise default logs and non-default logs, defining different log content classification versions for the default logs, generating log models of different versions according to the different log content classification versions, and then respectively setting applicable areas for the log models of different versions;
receiving a work diary transmitted by each construction department manager of the construction project by using a communication terminal, the work diary including: the method comprises the steps of obtaining a default log type, a region where a construction project is located, construction content and a construction content category;
and calling a log model matched with the working diary according to the default log type in the working diary and the area where the construction project is located, and filling the construction content in the working diary into a corresponding log content classification position in the log model according to the construction content category in the working diary to generate the construction project log of the default type.
In the method for implementing an intelligent log according to the embodiment of the present invention, after the calling a log model matched with the work diary according to the default log type in the work diary and the area where the construction project is located, and filling the construction content in the work diary in the corresponding position in the log model according to the construction content category in the work diary to generate the construction project log of the default type, the method further includes:
and receiving and storing the construction project logs of the non-default type, which are filled by the managers of each construction department of the construction project by adopting a communication terminal.
In the method for implementing an intelligent log according to the embodiment of the present invention, after receiving and storing the construction project logs of the non-default type, which are filled by the managers of each construction department of the construction project using the communication terminal, the method further includes:
and setting the browsing permission of the construction project log of the default type and/or the construction project log of the non-default type, and sharing the construction project log of the default type and/or the construction project log of the non-default type to other participants.
In the method for implementing an intelligent log according to the embodiment of the present invention, before setting the browsing permission of the construction project log of the default type and/or the construction project log of the non-default type, and sharing the construction project log of the default type and/or the construction project log of the non-default type to other participating parties, the method further includes:
and checking whether the construction project log of the default type and/or the construction project log of the non-default type are complete, and if not, performing supplementary modification on the construction project log of the default type and/or the construction project log of the non-default type.
In the implementation method of the intelligent log according to the embodiment of the invention, the construction content includes characters and/or pictures input by managers of each construction department of the construction project by adopting a communication terminal.
Another objective of the embodiments of the present invention is to provide an implementation system of an intelligent log, including a log model building module, a receiving module, and a default log generating module, where the default log generating module is connected to the log model building module and the receiving module, respectively, where:
the log model establishing module is used for customizing log types according to requirements of construction projects, wherein the log types comprise default logs and non-default logs, defining different log content classification versions for the default logs, generating log models of different versions according to the different log content classification versions, and then setting applicable areas for the log models of different versions respectively;
the receiving module is configured to receive a work diary sent by a communication terminal by a manager of each construction department of the construction project, where the work diary includes: the method comprises the steps of obtaining a default log type, a region where a construction project is located, construction content and a construction content category;
the default log generation module is used for calling a log model matched with the working diary according to the default log type in the working diary and the area where the construction project is located, and filling the construction content in the working diary in a corresponding log content classification position in the log model according to the construction content category in the working diary so as to generate the construction project log of the default type.
In the system for implementing an intelligent log according to the embodiment of the present invention, the system further includes a non-default log generating module connected to the receiving module, where the non-default log generating module is configured to:
and receiving and storing the construction project logs of the non-default type, which are filled by the managers of each construction department of the construction project by adopting a communication terminal.
In the system for implementing an intelligent log according to the embodiment of the present invention, the system further includes a storage module and an authority setting module, the storage module is connected to the default log generation module and the non-default log generation module, and the authority setting module is connected to the storage module, wherein:
the storage module is used for storing the construction project log of the default type generated by the default log generation module and the construction project log of the non-default type generated by the non-default log generation module;
the permission setting module is used for setting the browsing permission of the construction project log of the default type and/or the construction project log of the non-default type, and sharing the construction project log of the default type and/or the construction project log of the non-default type to other participating parties.
In the system for implementing the intelligent log according to the embodiment of the present invention, the system further includes a log checking and modifying module connected to the storage module, wherein:
and the log checking and modifying module is used for checking whether the construction project log of the default type and/or the construction project log of the non-default type are complete or not, and if not, performing supplementary modification on the construction project log of the default type and/or the construction project log of the non-default type.
In the system for implementing the intelligent log according to the embodiment of the present invention, the construction content includes characters and/or pictures input by managers of each construction department of the construction project by using a communication terminal.
The implementation of the method and the system for realizing the intelligent log provided by the embodiment of the invention has the following beneficial effects:
according to the method, the log types are customized according to the requirements of construction projects, the log types comprise default logs and non-default logs, different log content classification versions are defined for the default logs, different log models of different versions are generated according to the different log content classification versions, and then applicable areas are set for the log models of different versions respectively; receiving a work diary transmitted by each construction department manager of the construction project by using a communication terminal, the work diary including: the method comprises the steps of obtaining a default log type, a region where a construction project is located, construction content and a construction content category; finally, a log model matched with the work diary is called according to the default log type in the work diary and the area where the construction project is located, the construction content in the work diary is filled in the corresponding log content classification position in the log model according to the construction content category in the work diary to generate a construction project log of the default type, so that the heavy work of manually recording the construction project log in the prior art is reduced, the construction project log can be updated in time, the accuracy of the log content is ensured, a manager of the construction project can master the progress of the project, target data can be searched in real time and quickly, and the root of the problem can be tracked quickly when the construction project has problems; the construction project logs of the default type and/or the construction project logs of the non-default type are set to have browsing permission, and the construction project logs of the default type and/or the construction project logs of the non-default type are shared with other participating parties, so that the logs can be shared with other participating parties, managers of other participating parties can view the project logs in real time and know the project progress.
Drawings
Fig. 1 is a flowchart illustrating a specific implementation of a method for implementing an intelligent log according to a first embodiment of the present invention;
fig. 2 is a flowchart illustrating a specific implementation of a method for implementing an intelligent log according to a second embodiment of the present invention;
fig. 3 is a schematic structural diagram of an implementation system of an intelligent log according to a third embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Fig. 1 shows a specific implementation flow of an implementation method of an intelligent log according to a first embodiment of the present invention. Referring to fig. 1, an implementation flow of the implementation method of the intelligent log provided by this embodiment is detailed as follows:
in S101, defining log types according to requirements of construction projects, wherein the log types comprise default logs and non-default logs, defining different log content classification versions for the default logs, generating log models of different versions according to the different log content classification versions, and then respectively setting applicable regions for the log models of different versions.
In this embodiment, a user may customize a plurality of different default logs and non-default logs according to own needs, and establish corresponding log models for the different default logs respectively, and since the requirements of each region on log formats may be different, the same default log may correspond to a plurality of different log models, and each log model corresponds to an applicable region. As a specific implementation example, in this embodiment, a default log and a non-default log are defined, where the default log is a construction log, and the non-default log is a security log. It should be noted that in other implementation examples, the user may add multiple default logs in a customized manner and/or add multiple non-default logs in a customized manner according to the needs of the user.
At S102, a work diary transmitted by each construction department manager of the construction project using a communication terminal is received, the work diary including: default log type, area of construction project, construction content and construction content category.
In this embodiment, the communication terminal is a mobile phone, a computer, or an IPD, and a manager of each construction department of a construction project can send a work diary to an implementation system of an intelligent log in the form of a short message, a multimedia message, or a short message through a public wireless communication network or a self-established local wireless communication network through the mobile phone, the computer, or the IPD at any time, and then the implementation system of the intelligent log receives and processes the work diary.
In S103, a log model matched with the work diary is called according to the default log type in the work diary and the area where the construction project is located, and the construction content in the work diary is filled in the corresponding log content classification position in the log model according to the construction content category in the work diary, so as to generate a construction project log of the default type.
In this embodiment, after receiving the work diaries sent by the managers of each construction department of the construction project, the system for implementing the intelligent logs analyzes and counts the work diaries sent by each construction department of the current construction project, so as to generate only one construction project log for the same default log type. For example: if the default log types in the work logs sent by managers of three different construction departments of the same current construction project are construction logs and the construction project is in the area A, the implementation system of the intelligent log firstly searches for a proper log model according to the default log types and the area to which the construction project belongs, and then fills the construction contents in the three work logs into corresponding log content classification positions in the log model according to the construction content types, so that the construction project log of the default type can be generated.
It should be noted that, in this embodiment, the construction content includes characters and/or pictures input by managers of each construction department of the construction project through a communication terminal, so that the construction condition of the construction project on the same day can be recorded more vividly, vividly and truly in a mode of combining pictures and texts, and the authenticity and traceability of the log are improved.
Optionally, after S103 in this embodiment, the method may further include:
in S104, a non-default type of construction project log filled by each construction department manager of the construction project using a communication terminal is received and stored.
In this embodiment, the construction project logs of the non-default type are filled by managers of construction departments of the construction project directly by using communication terminals, information aggregation is not required, and each construction project log of the non-default type only has one log per day.
As can be seen from the above, in the implementation method of the intelligent log provided by this embodiment, firstly, the log types are customized according to the requirements of the construction project, where the log types include a default log and a non-default log, different log content classification versions are defined for the default log, log models of different versions are generated according to the different log content classification versions, and then, applicable regions are respectively set for the log models of different versions; receiving a work diary transmitted by each construction department manager of the construction project by using a communication terminal, the work diary including: the method comprises the steps of obtaining a default log type, a region where a construction project is located, construction content and a construction content category; finally, a log model matched with the work diary is called according to the default log type in the work diary and the area where the construction project is located, the construction content in the work diary is filled in the corresponding log content classification position in the log model according to the construction content category in the work diary to generate a construction project log of the default type, so that the heavy work of manually recording the construction project log in the prior art is reduced, the construction project log can be updated in time, the accuracy of the log content is ensured, and a manager of the construction project masters the progress of the project; in addition, target data can be searched quickly in real time, and the root of a problem can be tracked quickly when the construction project has the problem.
Fig. 2 shows a specific implementation flow of an implementation method of an intelligent log according to a second embodiment of the present invention. Referring to fig. 2, in the implementation method of the two types of intelligent logs provided by this embodiment, with respect to the embodiment shown in fig. 1, after receiving and storing the construction project logs of the non-default type filled by the managers of the construction departments of the construction project by using the communication terminal, the method further includes:
in S205, it is checked whether the construction project log of the default type and/or the construction project log of the non-default type are complete, and if not, the construction project log of the default type and/or the construction project log of the non-default type are modified in a supplementary manner.
In this embodiment, after the system for implementing the intelligent log automatically generates the electronic version of the construction project log according to the received work diary, a preview interface of the construction project log may be displayed for a user to check whether the log is wrong or complete, if the log is wrong or incomplete, a modification operation instruction input by the user is received under the preview interface to modify the log, and then the modified construction project log meeting the requirements is stored in a storage module of the recording system for subsequent query and use.
In S206, the browsing permission of the construction project log of the default type and/or the construction project log of the non-default type is set, and the construction project log of the default type and/or the construction project log of the non-default type are shared to other participating parties.
In this embodiment, after the construction project log is saved, a manager can also customize the browsing permission of the log so as to conveniently share the log to other participating parties, and similarly, logs recorded by other participating parties can also be shared with each other by setting the permission of the log. Therefore, each participating party can master the construction progress of the construction project in real time.
Steps S201 to S204 in the present embodiment are completely the same as steps S101 to S104 in the embodiment shown in fig. 1, and therefore, the description thereof will not be repeated here.
As can be seen from the above, compared with the previous embodiment, in the implementation method of the intelligent log provided in this embodiment, because the browsing permission of the default type of construction project log and/or the non-default type of construction project log is set, the default type of construction project log and/or the non-default type of construction project log is shared with other participating parties, so that the log can be shared with other participating parties, and a manager of the other participating parties can also view the project log in real time to know the project progress.
Fig. 3 is a schematic structural diagram of an implementation system of an intelligent log according to a third embodiment of the present invention, where the system is configured to execute the methods provided in the embodiments shown in fig. 1 to fig. 2. Only the portions related to the present embodiment are shown for convenience of explanation.
Referring to fig. 3, the present embodiment provides an implementation system of an intelligent log, including a log model building module 1, a receiving module 2, and a default log generating module 3, where the default log generating module 3 is connected to the log model building module 1 and the receiving module 2, respectively, and where:
the log model establishing module 1 is used for customizing log types according to requirements of construction projects, wherein the log types comprise default logs and non-default logs, defining different log content classification versions for the default logs, generating log models of different versions according to the different log content classification versions, and then respectively setting applicable areas for the log models of different versions;
the receiving module 2 is configured to receive a work diary sent by a communication terminal by a manager of each construction department of the construction project, where the work diary includes: the method comprises the steps of obtaining a default log type, a region where a construction project is located, construction content and a construction content category;
the default log generating module 3 is configured to call a log model matched with the work diary according to the default log type in the work diary and the area where the construction project is located, and fill the construction content in the work diary in a corresponding log content classification position in the log model according to the construction content category in the work diary, so as to generate the construction project log of the default type.
Optionally, the system for implementing the smart log further includes a non-default log generating module 4 connected to the receiving module 2, where the non-default log generating module 4 is configured to:
and receiving and storing the construction project logs of the non-default type, which are filled by the managers of each construction department of the construction project by adopting a communication terminal.
Optionally, the system for implementing the intelligent log further includes a storage module 5 and an authority setting module 6, the storage module 5 is connected to the default log generating module 3 and the non-default log generating module 4, the authority setting module 6 is connected to the storage module 5, wherein:
the storage module 5 is configured to store the construction project log of the default type generated by the default log generation module 3 and the construction project log of the non-default type generated by the non-default log generation module 4;
the permission setting module 6 is configured to set a browsing permission of the construction project log of the default type and/or the construction project log of the non-default type, and share the construction project log of the default type and/or the construction project log of the non-default type to other participating parties.
Optionally, the system for implementing the intelligent log further includes a log checking and modifying module 7 connected to the storage module 5, wherein:
the log checking and modifying module 7 is configured to check whether the construction project log of the default type and/or the construction project log of the non-default type are complete, and if not, perform supplementary modification on the construction project log of the default type and/or the construction project log of the non-default type.
Optionally, the construction content includes characters and/or pictures input by managers of each construction department of the construction project by using a communication terminal.
It should be noted that, since each module in the system provided in the embodiment of the present invention is based on the same concept as that of the embodiment of the method of the present invention, the technical effect brought by the embodiment of the method of the present invention is the same as that of the embodiment of the method of the present invention, and specific contents may be referred to the description in the embodiment of the method of the present invention, and are not described herein again.
Therefore, it can be seen that the implementation system of the intelligent log provided by the embodiment can also reduce the heavy work of manually recording the construction project log in the prior art, and can update the construction project log in time, so as to ensure the accuracy of the log content, enable a construction project manager to master the project progress, and also can quickly find target data in real time, and quickly track the root of the problem when the construction project has a problem; in addition, the log can be shared with other participating parties, so that managers of the other participating parties can view the project log in real time and know the project progress.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (6)

1. An implementation method of an intelligent log is characterized by comprising the following steps:
the implementation system of the intelligent log self-defines log types according to the requirements of construction projects, wherein the log types comprise default log types and non-default log types, different log content classification versions are defined for the default log types, log models of different versions are generated according to the different log content classification versions, and then application areas are set for the log models of different versions respectively; the default log comprises a construction log, the non-default log comprises a safety log, and the same default log can correspond to a plurality of different log models;
the implementation system of the intelligent log receives a work diary sent by each construction department manager of the construction project by adopting a communication terminal, wherein the work diary comprises: the method comprises the steps of obtaining a default log type, a region where a construction project is located, construction content and a construction content category;
the implementation system of the intelligent log calls a log model matched with the working diary according to the default log type in the working diary and the area where the construction project is located, and fills the construction content in the working diary in a corresponding log content classification position in the log model according to the construction content category in the working diary so as to generate the construction project log of the default log type; generating only one construction project log aiming at the same default log type of the same construction project; if the default log types in the working diaries sent by the managers of three different construction departments of the same current construction project are construction logs and the construction project is in the area A, the implementation system of the intelligent log firstly searches a proper log model according to the default log types and the area to which the construction project belongs, and then fills the construction contents in the working diaries sent by the managers of the three different construction departments to the corresponding log content classification positions in the log model according to the construction content classes, so that the construction project log of the default type can be generated;
the method for generating the construction project log of the default log type comprises the following steps of calling a log model matched with a work diary according to the default log type in the work diary and the area where the construction project is located, filling construction contents in the work diary to a corresponding position in the log model according to the construction content type in the work diary, and generating the construction project log of the default log type, wherein the method further comprises the following steps: receiving and storing construction project logs of a non-default log type, which are filled by construction department managers of the construction project by adopting a communication terminal; the construction project logs of the non-default type do not need to be subjected to information gathering, and each construction project log of the same type can only have one log every day;
wherein, after receiving and storing the construction project log of the non-default log type filled by the managers of each construction department of the construction project by adopting the communication terminal, the method further comprises the following steps: and setting the browsing authority of the construction project log of the default log type and/or the construction project log of the non-default log type, and sharing the construction project log of the default log type and/or the construction project log of the non-default log type to other participating parties.
2. The method for implementing intelligent logs according to claim 1, wherein before setting the browsing permission of the construction project logs of the default log type and/or the construction project logs of the non-default log type and sharing the construction project logs of the default log type and/or the construction project logs of the non-default log type to other participating parties, the method further comprises:
and checking whether the construction project log of the default log type and/or the construction project log of the non-default log type are complete, and if not, performing supplementary modification on the construction project log of the default log type and/or the construction project log of the non-default log type.
3. The method for implementing the intelligent log according to claim 1, wherein the construction content comprises characters and/or pictures input by managers of each construction department of the construction project by adopting a communication terminal.
4. The system for realizing the intelligent log is characterized by comprising a log model establishing module, a receiving module and a default log type generating module, wherein the default log type generating module is respectively connected with the log model establishing module and the receiving module, and the method comprises the following steps:
the log model establishing module is used for customizing log types according to requirements of construction projects, wherein the log types comprise default log types and non-default log types, defining different log content classification versions for the default log types, generating log models of different versions according to the different log content classification versions, and then setting applicable areas for the log models of different versions respectively; the default log comprises a construction log, the non-default log comprises a safety log, and the same default log can correspond to a plurality of different log models;
the receiving module is configured to receive a work diary sent by a communication terminal by each construction department manager of the construction project, where the work diary includes: the method comprises the steps of obtaining a default log type, a region where a construction project is located, construction content and a construction content category;
the default log type generating module is used for calling a log model matched with the working diary according to the default log type in the working diary and the area where the construction project is located, and filling the construction content in the working diary in a corresponding log content classification position in the log model according to the construction content category in the working diary so as to generate the construction project log of the default log type; generating only one construction project log aiming at the same default log type of the same construction project; if the default log types in the working diaries sent by the managers of three different construction departments of the current same construction project are construction logs and the construction project is in the area A, the implementation system of the intelligent log firstly searches a proper log model according to the default log types and the area to which the construction project belongs, then fills the construction contents in the working diaries sent by the managers of the three different construction departments into corresponding log content classification positions in the log model according to the construction content classes, and can generate a construction project log of the default type;
the device further comprises a non-default log type generation module connected with the receiving module, wherein the non-default log type generation module is used for: receiving and storing construction project logs of a non-default log type, which are filled by construction department managers of the construction project by adopting a communication terminal; the construction project logs of the non-default type do not need to be subjected to information gathering, and each construction project log of the same type can only have one log every day;
the device further comprises a storage module and an authority setting module, wherein the storage module is connected with the default log type generation module and the non-default log type generation module, the authority setting module is connected with the storage module, and the device further comprises:
the storage module is used for storing the construction project log of the default log type generated by the default log type generation module and the construction project log of the non-default log type generated by the non-default log type generation module;
the permission setting module is used for setting the browsing permission of the construction project log of the default log type and/or the construction project log of the non-default log type, and sharing the construction project log of the default log type and/or the construction project log of the non-default log type to other participating parties.
5. The system for implementing intelligent logging of claim 4, further comprising a log check and modification module connected to the storage module, wherein:
and the log checking and modifying module is used for checking whether the construction project log of the default log type and/or the construction project log of the non-default log type are complete or not, and if the construction project log of the default log type and/or the construction project log of the non-default log type are incomplete, performing supplementary modification on the construction project log of the default log type and/or the construction project log of the non-default log type.
6. The system for implementing the intelligent log according to claim 4, wherein the construction content comprises characters and/or pictures input by managers of each construction department of the construction project by using a communication terminal.
CN201610017675.6A 2016-01-12 2016-01-12 Method and system for realizing intelligent log Active CN105719049B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610017675.6A CN105719049B (en) 2016-01-12 2016-01-12 Method and system for realizing intelligent log

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610017675.6A CN105719049B (en) 2016-01-12 2016-01-12 Method and system for realizing intelligent log

Publications (2)

Publication Number Publication Date
CN105719049A CN105719049A (en) 2016-06-29
CN105719049B true CN105719049B (en) 2020-04-24

Family

ID=56147664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610017675.6A Active CN105719049B (en) 2016-01-12 2016-01-12 Method and system for realizing intelligent log

Country Status (1)

Country Link
CN (1) CN105719049B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109344311A (en) * 2018-12-04 2019-02-15 北京诺士诚国际工程项目管理有限公司 A kind of generation method of work diary, the generation method of supervision diary and system
CN109598442A (en) * 2018-12-04 2019-04-09 北京诺士诚国际工程项目管理有限公司 A kind of methods of marking and device of supervision behavior
CN110084536B (en) * 2019-05-15 2021-06-29 北京创鑫旅程网络技术有限公司 Method and device for processing work logs
CN110263008B (en) * 2019-06-20 2022-02-01 江苏满运软件科技有限公司 Terminal off-line log management system, method, device and storage medium
CN111932202A (en) * 2020-07-31 2020-11-13 中建八局第二建设有限公司 Construction log compiling system and method based on cloud service
CN115511474B (en) * 2022-11-09 2023-01-24 四川公路桥梁建设集团有限公司 Application method of engineering project standard library, electronic equipment and readable medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101753971A (en) * 2008-12-22 2010-06-23 中兴通讯股份有限公司 Journal system and journal recording method in content management system in uniform video management platform
CN103064905A (en) * 2012-12-18 2013-04-24 武汉华中数控股份有限公司 Log management method of numerical control system
CN104933077A (en) * 2014-03-20 2015-09-23 上海宝信软件股份有限公司 Rule-based multi-file information analysis method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7010726B2 (en) * 2001-03-01 2006-03-07 International Business Machines Corporation Method and apparatus for saving data used in error analysis

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101753971A (en) * 2008-12-22 2010-06-23 中兴通讯股份有限公司 Journal system and journal recording method in content management system in uniform video management platform
CN103064905A (en) * 2012-12-18 2013-04-24 武汉华中数控股份有限公司 Log management method of numerical control system
CN104933077A (en) * 2014-03-20 2015-09-23 上海宝信软件股份有限公司 Rule-based multi-file information analysis method

Also Published As

Publication number Publication date
CN105719049A (en) 2016-06-29

Similar Documents

Publication Publication Date Title
CN105719049B (en) Method and system for realizing intelligent log
CN110839104B (en) Group communication method, device and equipment
US9977788B2 (en) Methods and systems for managing files in an on-demand system
CN103118140B (en) By sharing files to the method, system and device of relation loop other user terminals outer
US10354080B2 (en) Facilitating offline or other contemporaneous editing of tabular data
US20140372369A1 (en) Managing Changes to Shared Electronic Documents Using Change History
US20220342518A1 (en) Card-based information management method and system
CN105574167A (en) Mobile terminal-based automatic photograph naming processing method and system
CN114124861A (en) Message group sending method and device, computer equipment and storage medium
KR20200046769A (en) Method for providing business process management system based on automatic report generation
CN103533169A (en) Method for positioning and linking field of electronic business card based on mobile terminal
CN107436785B (en) Revit software information interaction system and interaction method based on information system
CN110738038A (en) Contract text generation method, device, equipment and computer readable storage medium
CN105094768A (en) Application interface generation method and application interface generation device
US20230374095A1 (en) Inter-application workflow performance analytics
CN110020414A (en) A kind of electronic contract document creation method, system
US7849056B2 (en) System and method for managing databases associated with respective personal information manager service accounts
CN107357887B (en) Two-dimensional code-based traceable report generation method
CN109684620A (en) Change to the contract information recording method, device and computer readable storage medium
US8671078B2 (en) Sharing parts of a document using search framework
CN102780714B (en) A kind of information management cloud system and the method realizing information sharing thereof
US9922053B1 (en) System for image capture, notation and distribution
US10147061B2 (en) Integrating a construction jobsite system with external tools
US11431590B2 (en) Method and device to update contacts
CN114493185A (en) Approval processing method, device, system, electronic equipment, storage medium and product

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Qiu Haiyan

Inventor after: Le Tieyi

Inventor before: Le Tieyi

Inventor before: Qiu Haiyan

Inventor before: Liu Jun

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220104

Address after: 518000 1103, Yaohua Building, No. 6023, Shennan Avenue, Tian'an community, Shatou street, Futian District, Shenzhen, Guangdong Province

Patentee after: Shenzhen Dashang construction Digital Technology Co.,Ltd.

Address before: 518000 room 2011, west block, Zhuzilin Qiushi building, Shennan Middle Road, Futian District, Shenzhen, Guangdong Province

Patentee before: SHENZHEN DASHANG NETWORK TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right