CN105714683A - Installation and dismantling method of high bent cast-in-situ aqueduct suspension type bailey frames - Google Patents
Installation and dismantling method of high bent cast-in-situ aqueduct suspension type bailey frames Download PDFInfo
- Publication number
- CN105714683A CN105714683A CN201610098392.9A CN201610098392A CN105714683A CN 105714683 A CN105714683 A CN 105714683A CN 201610098392 A CN201610098392 A CN 201610098392A CN 105714683 A CN105714683 A CN 105714683A
- Authority
- CN
- China
- Prior art keywords
- bailey
- aqueduct
- sandbox
- bracket
- bailey bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及一种高排架现浇渡槽悬挂式贝雷架的安装和拆除方法。所述方法利用主体工程排架墩身具有高承载力的优点,以墩帽顶部作为支撑面,采用单独设计的悬挂支撑式贝雷架作为模板支架,利用吊车分组吊装就位,当渡槽混凝土结构施工完成后,需要拆除贝雷支架时,及时在渡槽混凝土结构顶面安装拆除用的上横梁、下托梁、连接上横梁下托梁的钢丝绳和升降螺杆等,最后进行贝雷架的拆除吊装。本发明与现有技术相比,具有安全性能高、节省投资、方案简单、操作方便、施工周期短等特点,解决了现有技术在跨江、跨水田等不利地形条件下进行高大排架式渡槽施工中存在的不足。
The invention relates to a method for installing and dismantling a suspension type Bailey frame of a cast-in-situ aqueduct with a high-bracket frame. The method takes advantage of the high bearing capacity of the bent frame pier body of the main project, uses the top of the pier cap as the supporting surface, and adopts a separately designed suspension support type Bailey frame as the formwork support, and uses a crane to hoist it in place in groups. When the concrete structure of the aqueduct After the construction is completed, when it is necessary to dismantle the Bailey support, install the upper beam, lower joist, wire rope and lifting screw connected to the upper beam and lower joist on the top surface of the concrete structure of the aqueduct in time, and finally remove and lift the Bailey support . Compared with the prior art, the present invention has the characteristics of high safety performance, saving investment, simple scheme, convenient operation, short construction period, etc., and solves the problem that the prior art can carry out tall and large bent structures under unfavorable terrain conditions such as crossing rivers and paddy fields. Deficiencies in the construction of the aqueduct.
Description
技术领域technical field
本发明涉及土建工程大型高位现浇梁板新型支撑技术,具体涉及一种基于高排架现浇渡槽悬挂式贝雷架安装和拆除的施工方法。The invention relates to a new type of support technology for large-scale high-position cast-in-place beams and slabs in civil engineering, and in particular to a construction method for installing and removing suspension-type Bailey frames based on high-bracket cast-in-situ aqueducts.
背景技术Background technique
目前,土建工程大型现浇梁板新型支撑技术包括以下几种:At present, new support technologies for large-scale cast-in-place beams and slabs in civil engineering include the following:
贝雷架钢柱支撑施工法:在两个墩身之间有诸多粗钢管支撑系统,并需要对支撑基础进行地基勘探、专项设计,并必须对支撑系统进行繁重的地基预压。若支撑系统不稳定,会严重影响工程质量。另外,支撑系统的基础施工成本高、周期长。The steel column support construction method of the Bailey frame: there are many thick steel pipe support systems between the two piers, and ground exploration and special design for the support foundation are required, and heavy foundation preloading must be carried out for the support system. If the support system is unstable, it will seriously affect the quality of the project. In addition, the foundation construction cost of the supporting system is high and the period is long.
贝雷架满堂脚手架支撑施工法:与钢柱支撑类似,需要在两墩身之间全面进行地基处理,钢架安装后的预压因高度大、连接件多,满堂架的质量难以得到保证,施工成本高、周期长。The scaffolding construction method of Bailey frame full house scaffolding: similar to steel column support, it is necessary to carry out comprehensive foundation treatment between the two piers. After the steel frame is installed, the preloading is high and there are many connectors, so the quality of the full house frame is difficult to be guaranteed. The construction cost is high and the period is long.
移动模架施工法:模架造价高,只能单向行进,在工程量较大的情况下,不适合多个工作面同时展开施工,对工期影响严重。Mobile formwork construction method: The formwork is expensive and can only travel in one direction. In the case of a large amount of work, it is not suitable for simultaneous construction on multiple working faces, which has a serious impact on the construction period.
预制、大型架桥机安装施工法:必须有大型预制场地、大型梁(渡槽)运输车、大型架桥机,全套设备昂贵。同时,此种施工法不太适合渡槽施工,渡槽与箱梁不同,渡槽顶面是敞开的,不能满足架桥机在上面行走。Prefabricated and large bridge erecting machine installation and construction method: there must be a large prefabricated site, a large beam (aqueduct) transport vehicle, and a large bridge erecting machine, and the complete set of equipment is expensive. At the same time, this construction method is not suitable for aqueduct construction. The aqueduct is different from the box girder, and the top surface of the aqueduct is open, which cannot satisfy the bridge erecting machine to walk on it.
发明内容Contents of the invention
针对现有技术中存在的上述问题,本发明提出一种基于高排架现浇渡槽悬挂式贝雷架安装和拆除的施工方法。利用主体工程排架的墩身具有高承载力的优点,以墩帽顶部作为支撑面,采用单独设计的悬挂支撑式贝雷架作为模板支架,利用吊车分组吊装就位,当渡槽混凝土结构施工完成后,需要拆除贝雷支架时,及时在渡槽混凝土结构顶面安装拆除用的上横梁、下托梁、连接上横梁下托梁的钢丝绳和升降高强螺杆,最后进行贝雷架的拆除吊装。Aiming at the above-mentioned problems existing in the prior art, the present invention proposes a construction method based on the installation and removal of the suspension type Bailey frame of the cast-in-situ aqueduct with high bent frames. The pier body of the bent frame of the main project has the advantage of high bearing capacity. The top of the pier cap is used as the supporting surface, and the separately designed suspension support type Bailey frame is used as the formwork support, and it is hoisted in place by groups of cranes. Finally, when it is necessary to remove the Bailey support, install the upper beam, lower joist, steel wire rope connecting the upper beam and lower joist, and lifting high-strength screw on the top of the concrete structure of the aqueduct in time, and finally remove and lift the Bailey support.
为达到上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:
一种高排架现浇渡槽悬挂式贝雷架安装和拆除方法,包括以下步骤:A method for installing and dismantling a suspension-type Bailey frame of a cast-in-situ aqueduct with high-brackets, comprising the following steps:
步骤1,安装砂箱。Step 1, install the sand box.
在墩帽顶部放置砂箱,在每片贝雷架的两端各设一个砂箱,砂箱的大小一致,砂箱的装砂量经过压实试验和计算获得,使承重后贝雷架的底在同一水平面上。A sand box is placed on the top of the pier cap, and a sand box is set at each end of each piece of Bailey frame. The size of the sand box is the same. bottom on the same level.
步骤2,拼装贝雷架并将拼装后的贝雷架吊装就位。Step 2, assemble the Bailey frame and hoist the assembled Bailey frame in place.
将悬挂式端头支架连接到每榀贝雷架的标准贝雷片(贝雷架由贝雷片和非标准端头支架组成)上,以三榀为一组进行拼装;拼装完成后采用汽车吊吊装就位,安放在相应的砂箱上面。重复所述拼装与吊装就位步骤,直到完成各组的拼装和吊装就位。Connect the hanging terminal bracket to the standard Bailey piece of each Bailey frame (the Bailey frame is composed of Bailey pieces and non-standard terminal brackets), and assemble in groups of three; after the assembly is completed, use a car Hang it in place and place it on the corresponding sand box. Repeat the steps of assembling and hoisting in place until the assembly and hoisting in place of each group is completed.
步骤3,搭设施工马道板。Step 3, build the construction horseway board.
在贝雷梁的上弦杆下面吊铺钢管横托梁,钢管与贝雷梁的上弦杆垂直,采用吊环式螺栓固定钢管,采用十字扣件在钢管两端连接防护栏杆立杆。Hang the steel pipe cross-joist under the upper chord of the Bailey beam. The steel pipe is perpendicular to the upper chord of the Bailey beam. The steel pipe is fixed with ring bolts, and the cross fasteners are used to connect the protective railing poles at both ends of the steel pipe.
步骤4,安装渡槽底模板。Step 4, install the aqueduct bottom template.
采用连接螺栓将渡槽底模板的肋条与贝雷架上弦杆连接在一起,使贝雷架的上弦杆与渡槽底模板的底支架共同形成平直的平面桁架结构。The ribs of the bottom formwork of the aqueduct are connected with the upper chord of the Bailey frame by connecting bolts, so that the upper chord of the Bailey frame and the bottom bracket of the bottom formwork of the aqueduct jointly form a straight plane truss structure.
步骤5,拆除贝雷架。Step 5, remove the Bailey rack.
渡槽混凝土达到设计强度后,拆除渡槽底模板与贝雷梁的连接螺栓,打开砂箱的排沙门,使干砂流出,砂箱顶高程均匀下降,贝雷梁架同时下降,当模板与贝雷梁分离时,拆除渡槽外模和底模。After the concrete of the aqueduct reaches the design strength, remove the connecting bolts between the bottom formwork of the aqueduct and the Bailey beam, and open the sand discharge door of the sand box to allow the dry sand to flow out. When the beam is separated, remove the outer formwork and bottom formwork of the aqueduct.
采用平移装置将贝雷架平移出槽底:先将上横梁安放在渡槽顶部,然后安装下托梁,上横梁和下托梁由钢丝绳和高强螺杆连接,通过紧固或松动升降高强螺杆的螺母控制下托梁的升降。Use a translation device to move the Bailey frame out of the bottom of the tank: first place the upper beam on the top of the aqueduct, and then install the lower joist. The upper beam and the lower joist are connected by a steel wire rope and a high-strength screw, and the nuts of the high-strength screw are tightened or loosened. Controls the raising and lowering of the lower joists.
进一步地,所述方法还包括在墩身一侧搭设施工爬梯的步骤。Further, the method also includes the step of erecting a construction ladder on one side of the pier body.
进一步地,所述砂箱包括砂箱本体、位于砂箱本体顶部的砂箱塞和位于砂箱本体底部的排砂门,砂径小于2mm。Further, the sand box includes a sand box body, a sand box plug at the top of the sand box body and a sand discharge door at the bottom of the sand box body, and the sand diameter is less than 2mm.
进一步地,所述悬挂式端头支架包括悬挂端头和非标准贝雷片。Further, the suspension terminal bracket includes a suspension terminal and non-standard Bailey pieces.
进一步地,步骤3所述紧固螺杆直径不小于14mm;每60cm设置一道钢管横托梁,钢垫片厚度不小于5mm;马道宽度不小于90cm;立杆高度不小于1.2m。Further, the diameter of the fastening screw described in step 3 is not less than 14mm; a steel pipe cross joist is provided every 60cm, and the thickness of the steel gasket is not less than 5mm; the width of the carriageway is not less than 90cm; the height of the pole is not less than 1.2m.
进一步地,步骤4所述连接螺栓直径不小于16mm。Further, the diameter of the connecting bolt in step 4 is not less than 16mm.
进一步地,步骤5所述组合贝雷梁的吊装包括以下步骤:Further, the hoisting of the combined Bailey beam described in step 5 includes the following steps:
在每根下托梁上面,正对组合贝雷梁下面安放一根方木,吊装时,将所述方木移到将要拆除的贝雷架下面。紧固上横梁上的螺栓,将该组贝雷架托起。贝雷架的悬挂端头离开砂箱顶面后,使用千金顶或手拉葫芦向外移动上面的升降螺杆支座,将贝雷梁水平向外移动。中间的贝雷架分多次运送。最后使用吊车进行垂直吊装。一组贝雷梁吊装完成后,重复上述工序,完成所有贝雷架组合梁的拆除。On each lower joist, a square timber is placed directly under the combined Bailey beam, and when hoisting, the square timber is moved under the Bailey frame to be removed. Tighten the bolts on the upper beam to support the group of Baileys. After the hanging end of the Bailey frame leaves the top surface of the sand box, use the jackhammer or a chain hoist to move the upper lifting screw support outwards to move the Bailey beam outwards horizontally. The middle beret is delivered in multiples. Finally, use a crane for vertical lifting. After the hoisting of a group of Bailey beams is completed, the above process is repeated to complete the removal of all Bailey frame composite beams.
与现有技术相比,本发明具有以下优点:Compared with the prior art, the present invention has the following advantages:
(1)本发明应用悬挂式端头,能够在现有贝雷梁结构下部支撑的基础上,增加上部支撑功能,并能充分利用墩台顶面与渡槽底面之间狭小的空间完成贝雷支架结构的安装。(1) The present invention uses a suspension type end, which can increase the upper support function on the basis of the lower support of the existing Bailey beam structure, and can make full use of the narrow space between the pier top surface and the bottom surface of the aqueduct to complete the Bailey support installation of structures.
(2)与贝雷架钢柱支撑施工法相比,本发明无需在两个墩身之间增设诸多粗钢管支撑系统,同时省掉对支撑基础进行地基勘探、专项设计,以及对支撑系统进行繁重的地基预压等工序,既简化了施工程序,又缩短了施工周期,还降低了施工成本。(2) Compared with the steel column support construction method of the Bailey frame, the present invention does not need to add many thick steel pipe support systems between the two pier bodies, and simultaneously saves the foundation exploration and special design of the support foundation, as well as the heavy support system. The foundation preloading and other processes not only simplifies the construction procedure, shortens the construction period, but also reduces the construction cost.
(3)与贝雷架满堂脚手架支撑施工方法相比,本发明无需要在两墩身之间全面进行地基处理,无需搭设满堂架,无需进行预压等施工程序,不但简化了工序,还缩短了施工周期、降低了施工成本。(3) Compared with the supporting construction method of Bailey frame full hall scaffolding, the present invention does not need to carry out comprehensive foundation treatment between the two pier bodies, does not need to set up full hall frames, and does not need to carry out construction procedures such as preloading, which not only simplifies the process, but also shortens the construction time. The construction period is shortened and the construction cost is reduced.
(4)与移动模架施工方法相比,本发明解决了模架造价高、只能单向行进、占用工期太长等问题;另外,采用预制、大型架桥机安装的施工方法,必须有大型预制场地、大型渡槽运输车、大型架桥机等,全套设备昂贵,同时,预制、大型架桥机安装的施工方法不太适合渡槽施工,渡槽与箱梁不同,渡槽顶面是敞开的,不能满足架桥机在上面行走。本发明采用悬挂式贝雷架的安装和拆除方法,避免了上述不利施工条件的制约。(4) Compared with the construction method of mobile formwork, the present invention solves the problems such as high cost of formwork, only one-way travel, and too long construction period; Large prefabricated sites, large aqueduct transport vehicles, large bridge erecting machines, etc., the whole set of equipment is expensive. At the same time, the construction method of prefabrication and large bridge erecting machines is not suitable for aqueduct construction. Aqueducts are different from box girders in that the top surface of the aqueduct is open. It is not enough for the bridge erecting machine to walk on it. The present invention adopts the installation and dismantling method of the suspended bailey frame, which avoids the restriction of the above-mentioned unfavorable construction conditions.
附图说明Description of drawings
图1为砂箱结构示意图;Fig. 1 is a schematic diagram of the sand box structure;
图2为悬挂式贝雷架纵向剖面示意图;Fig. 2 is the schematic diagram of the longitudinal section of the suspended Bailey frame;
图3为悬挂式贝雷架横向剖面示意图;Fig. 3 is a schematic diagram of a transverse section of a suspended Bailey frame;
图4为悬挂式端头支架结构示意图;Fig. 4 is a schematic structural diagram of a suspended end bracket;
图5为悬挑式施工马道板的搭设示意图;Fig. 5 is the schematic diagram of setting up the cantilevered construction curb slab;
图6为渡槽底模板与贝雷梁的连接示意图;Fig. 6 is the connection schematic diagram of aqueduct bottom formwork and Bailey beam;
图7为贝雷架整组拆除示意图。Figure 7 is a schematic diagram of the complete dismantling of the Bailey frame.
具体实施方式detailed description
下面结合附图和实施例对本发明做进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
一种高排架现浇渡槽悬挂式贝雷架安装和拆除方法,包括以下步骤:A method for installing and dismantling a suspension-type Bailey frame of a cast-in-situ aqueduct with high-brackets, comprising the following steps:
1.施工前准备1. Preparation before construction
(1)附属材料准备(1) Preparation of auxiliary materials
在贝雷支架安装和拆除之前,做好所需附件的准备工作,主要包括:用以调节高度的砂箱的设计制作,悬挂式端头支架的设计制作,悬挑式施工马道的固定件(带环的长螺栓)设计和制作,渡槽底模板约束螺栓和垫片的设计制作,拆除时使用的上横梁、下托梁、升降螺杆的选型和购买等。Before the installation and removal of the Bailey bracket, the preparations for the required accessories are done, mainly including: the design and manufacture of the sand box for height adjustment, the design and manufacture of the suspended end bracket, the fixing parts of the cantilevered construction road ( Long bolts with rings) design and manufacture, design and manufacture of aqueduct bottom formwork restraint bolts and gaskets, selection and purchase of upper beams, lower joists, and lifting screws used for dismantling, etc.
砂箱的结构如图1所示,包括砂箱本体、位于砂箱本体顶部的砂箱塞和位于砂箱本体底部的排砂门。砂箱的制作应大小一致,采用细砂,并筛除2mm以上的颗粒,使细砂能够顺利从排砂门排出。每箱的装砂量需经过压实试验,使承重后的渡槽底在同一水平面上。The structure of the sand box is shown in Figure 1, including the sand box body, the sand box plug at the top of the sand box body and the sand discharge door at the bottom of the sand box body. The sand boxes should be made in the same size, use fine sand, and screen out particles over 2mm, so that the fine sand can be smoothly discharged from the sand discharge door. The amount of sand loaded in each box needs to pass a compaction test, so that the bottom of the aqueduct after load-bearing is on the same level.
悬挂式端头支架的结构如图4所示,包括悬挂端头和非标准贝雷片。The structure of the suspended end bracket is shown in Figure 4, including the suspended end and non-standard Bailey pieces.
(2)技术准备(2) Technical preparation
在进行贝雷梁的选用和设计时,参考标准贝雷梁力学特性表、几何特性表和桁架容许内力表,使组合贝雷架能满足施工荷载需要和挠度值需要。在进行端头支座的设计和制作时,使其上弦伸出端的剪切力和弯矩满足要求。When selecting and designing Bailey beams, refer to the standard Bailey beam mechanical property table, geometric property table and truss allowable internal force table, so that the combined Bailey frame can meet the requirements of construction load and deflection value. When designing and manufacturing the end support, the shear force and bending moment at the extended end of the upper chord meet the requirements.
贝雷梁正式吊装就位之前,模拟施工荷载预先进行整体贝雷梁承重后挠度值的验证,找出实际值与理论计算之间的差值,采取正确的修正(或调整)措施,如采取增加或减少贝雷梁的数目、在渡槽顶面与渡槽底模板之间填塞厚度渐变的薄木板措施,使渡槽的槽身预拱度满足设计需要。Before the Bailey beam is formally hoisted in place, simulate the construction load to verify the deflection value of the overall Bailey beam after loading, find out the difference between the actual value and the theoretical calculation, and take correct correction (or adjustment) measures, such as taking The measure of increasing or reducing the number of Bailey beams and filling the thickness of thin wood boards between the top surface of the aqueduct and the bottom formwork of the aqueduct can make the pre-camber of the aqueduct body meet the design requirements.
(3)搭设爬梯(3) Set up a ladder
在抵贴墩身一侧,搭设施工爬梯,供施工人员上下之用。On the side of the pier body, build a construction ladder for construction workers to go up and down.
2.安装砂箱2. Install sand box
在墩帽顶部放置砂箱,在每片贝雷架的两端各设一个砂箱,用以支撑悬挂端头,在拆除模板时降低贝雷支架的高度。A sand box is placed on the top of the pier cap, and a sand box is provided at each end of each bailey to support the suspension end and lower the height of the bailey when the formwork is removed.
3.拼装贝雷架并将拼装后的贝雷架吊装就位3. Assemble the Bailey frame and hoist the assembled Bailey frame in place
将悬挂式端头支架连接到每榀贝雷架的标准贝雷片上,施工过程中按照钢桥安装的施工技术要求进行操作,三榀一组,每组拼装完成经检查无误后,使用汽车吊吊装就位,准确安放在相应的砂箱上面。第一组就位后,重复进行下一组的拼装和吊装就位。就位后的示意图如图2、图3所示。Connect the suspension-type end bracket to the standard Bailey sheet of each Bailey frame. During the construction process, operate according to the construction technical requirements for steel bridge installation. Three groups are used. After each group is assembled and checked, use a car crane Lift it in place and place it accurately on the corresponding sand box. After the first group is in place, repeat the assembly and hoisting of the next group in place. The schematic diagram after being in place is shown in Figure 2 and Figure 3.
4.搭设施工马道板4. Build a construction horseway board
组合贝雷梁的实际宽度仅能满足结构承重需要,需在贝雷梁的两侧增设施工马道板,采用在贝雷梁的上弦杆下面吊铺钢管横托梁,铺设方法如下:The actual width of the combined Bailey beam can only meet the load-bearing requirements of the structure, and it is necessary to add construction slabs on both sides of the Bailey beam. The steel pipe cross-joist is hoisted under the upper chord of the Bailey beam. The laying method is as follows:
用吊环式螺栓将钢管固定在贝雷梁的上弦杆下面,钢管与贝雷梁上弦杆垂直,紧固螺杆直径不小于14mm;约60cm一道,钢垫片厚度不小于5mm,大小以保证不会滑脱为宜,马道宽度不小于90cm。采用十字扣件在钢管两端连接防护栏杆立杆,立杆高度不小于1.2m。简图如图5所示。Fix the steel pipe under the upper chord of the Bailey beam with eyebolts. The steel pipe is perpendicular to the upper chord of the Bailey beam. The diameter of the fastening screw is not less than 14mm; the diameter of the fastening screw is not less than 60cm, and the thickness of the steel gasket is not less than 5mm. It is advisable to slip off, and the width of the horse path is not less than 90cm. Use cross fasteners to connect the protective railing poles at both ends of the steel pipe, and the height of the poles should not be less than 1.2m. The sketch is shown in Figure 5.
5.安装渡槽底模板5. Install the aqueduct bottom formwork
安装渡槽底模板时,将其肋条与贝雷架上弦杆连接在一起,使贝雷架上弦杆与渡槽底模板的支架共同形成稳定的平面桁架结构,以保证组合体不发生侧向弯扭。连接螺栓直径不小于16mm,如图6所示,两根螺栓及配套螺母的直径为16mm;下垫片(夹板)厚10mm、长200mm、宽140mm;上垫片(夹板)厚10mm、长200mm,宽60mm。When installing the bottom formwork of the aqueduct, connect its ribs with the upper chord of the Bailey frame, so that the upper chord of the Bailey frame and the bracket of the bottom formwork of the aqueduct form a stable planar truss structure to ensure that the combination does not occur lateral bending. The diameter of the connecting bolts is not less than 16mm. As shown in Figure 6, the diameter of the two bolts and supporting nuts is 16mm; the lower gasket (splint) is 10mm thick, 200mm long, and 140mm wide; the upper gasket (splint) is 10mm thick and 200mm long , 60mm wide.
6.拆除贝雷架6. Remove the Bailey Rack
当渡槽混凝土达到设计强度后,拆除底模与贝雷梁的连接螺栓,打开砂箱的排沙门,流出干砂,砂箱顶高程下降,使贝雷梁、架均匀下降10cm左右,渡槽底模板与贝雷梁分离时拆除渡槽外模和底模。外模和底模拆除完成后,进行贝雷架的拆除。When the concrete of the aqueduct reaches the design strength, remove the connecting bolts between the bottom formwork and the Bailey beam, open the sand discharge door of the sand box, and let the dry sand flow out. Remove the outer formwork and bottom formwork of the aqueduct when it is separated from the Bailey beam. After the removal of the outer mold and the bottom mold is completed, the Bailey frame is removed.
所有贝雷架均位于渡槽身下面,采用先将贝雷架平移出槽底,然后进行垂直吊装的拆除方法。All Bailey racks are located under the aqueduct body, and the Bailey racks are first moved out of the bottom of the tank, and then vertically hoisted to remove them.
平移装置能进行小范围升降,拆除作业时,先将其上横梁安放在渡槽顶部,然后安装下托梁,上横梁和下托梁由钢丝绳和高强螺杆连接。实施紧固或松动升降高强螺杆的螺母,下托梁便能升降。The translation device can be lifted and lowered in a small range. When dismantling, the upper beam is first placed on the top of the aqueduct, and then the lower joist is installed. The upper beam and the lower joist are connected by steel wire ropes and high-strength screws. Implement fastening or loosening the nuts of the lifting high-strength screw rod, and the lower joist can be lifted.
在每根下托梁上面,正对计划吊装的组合贝雷梁下面,安放一根厚度约10cm左右的方木,方木长度大于三组贝雷架的宽度。吊装时,将方木移动到将要拆除的贝雷架下面,紧固上横梁上的螺栓,将该组贝雷架托起,当贝雷架的悬挂端头离开调节砂箱顶面后,利用千金顶(或手拉葫芦)向外移动上面的升降螺杆支座,将贝雷梁水平向外移动(中间的贝雷架可分多次运送便可满足吊装要求),然后用吊车进行垂直吊装。当一组贝雷架吊装完成后,重复上述工序,完成所有贝雷架的拆除。On each lower joist, directly under the combined Bailey beams that are planned to be hoisted, place a square log with a thickness of about 10cm. The length of the square wood is greater than the width of the three sets of Bailey frames. When hoisting, move the square timber under the Bailey frame to be removed, fasten the bolts on the upper beam, and lift up the group of Bailey frames. When the hanging end of the Bailey frame leaves the top surface of the adjustment sand box, use Qianjinding (or chain hoist) moves the upper lifting screw support outward, moves the Bailey beam outward horizontally (the middle Bailey frame can be transported in multiple times to meet the hoisting requirements), and then vertically hoist with a crane . When a group of Bailey racks is hoisted, repeat the above process to complete the dismantling of all Bailey racks.
贝雷架整组拆除示意图如图7所示。Figure 7 shows the schematic diagram of the entire group of Bailey racks being dismantled.
本发明所述的方法已成功应用于2009-2011年海南省昌化江大广坝水利水电二期(灌区)昌干I标工程1#渡槽跨水田地和2#渡槽跨江的渡槽施工。通过悬挂式贝雷架在33米高排架渡槽成功地实施。The method described in the present invention has been successfully applied to the aqueduct construction of the 1# aqueduct crossing the water field and the 2# aqueduct crossing the river in the second phase of Changhua River Daguangba Water Conservancy and Hydropower (irrigation area) Changqian I standard project in Hainan Province from 2009 to 2011. It was successfully implemented in the 33-meter-high bent aqueduct by hanging Bailey frame.
本发明不限于上述实施方式,本领域技术人员所做出的对上述实施方式任何显而易见的改进或变更,都不会超出本发明的构思和所附权利要求的保护范围。The present invention is not limited to the above-mentioned embodiments, and any obvious improvements or changes made by those skilled in the art to the above-mentioned embodiments will not exceed the concept of the present invention and the scope of protection of the appended claims.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610098392.9A CN105714683A (en) | 2016-02-23 | 2016-02-23 | Installation and dismantling method of high bent cast-in-situ aqueduct suspension type bailey frames |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610098392.9A CN105714683A (en) | 2016-02-23 | 2016-02-23 | Installation and dismantling method of high bent cast-in-situ aqueduct suspension type bailey frames |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN105714683A true CN105714683A (en) | 2016-06-29 |
Family
ID=56157016
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610098392.9A Pending CN105714683A (en) | 2016-02-23 | 2016-02-23 | Installation and dismantling method of high bent cast-in-situ aqueduct suspension type bailey frames |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105714683A (en) |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106759125A (en) * | 2016-12-30 | 2017-05-31 | 黑龙江工程学院 | A kind of one-level aqueduct body construction method |
| CN106812069A (en) * | 2017-03-01 | 2017-06-09 | 杭州市交通工程集团有限公司 | The bottom of mountain area buttress Hanging Basket high stops puts device and method |
| CN108358052A (en) * | 2018-01-12 | 2018-08-03 | 中国葛洲坝集团第工程有限公司 | A kind of fortune tank car trailing type shoulder pole girder conveying device |
| CN110093867A (en) * | 2019-06-12 | 2019-08-06 | 桥致通(武汉)技术有限公司 | A kind of hydraulic swivel head and its application method for bridge rotating free positioning |
| CN110306833A (en) * | 2019-07-15 | 2019-10-08 | 辽宁工程技术大学 | A non-settling sand box for civil engineering |
| CN111576348A (en) * | 2020-06-11 | 2020-08-25 | 浙江世润建创科技发展有限公司 | Aqueduct formwork system supported on Bailey beam and construction method |
| CN111648313A (en) * | 2020-06-11 | 2020-09-11 | 浙江世润建创科技发展有限公司 | Bailey beam dismantling and transporting device and construction method applying same |
| CN112030768A (en) * | 2020-09-08 | 2020-12-04 | 浙江世润建创科技发展有限公司 | Bailey beam suspension structure and construction method applying same |
| CN115418966A (en) * | 2022-09-28 | 2022-12-02 | 中国水利水电第八工程局有限公司 | A kind of cast-in-place support method for aqueduct |
| CN115492390A (en) * | 2022-11-04 | 2022-12-20 | 北京城建北方集团有限公司 | Construction process of overlong overhanging corridor bailey frame support system |
| CN116876353A (en) * | 2023-06-05 | 2023-10-13 | 保利长大工程有限公司 | A construction method for large-span covered beam Bailey supports under 220kv high-voltage line clearance and limited site conditions |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2013149771A1 (en) * | 2012-04-02 | 2013-10-10 | Ulma C Y E, S. Coop | Movable structure suitable for supporting a formwork of a new bridge section in cantilever |
| CN203669362U (en) * | 2013-12-13 | 2014-06-25 | 中建三局第一建设工程有限责任公司 | Connecting device for connecting main truss of bailey frame and jacking stand column |
| CN204781929U (en) * | 2015-05-22 | 2015-11-18 | 武汉凡肯智能装备有限公司 | Convenient intelligent hydraulic pressure jacking die carrier system of standard form shellfish thunder frame of assembling |
| CN105332341A (en) * | 2014-08-08 | 2016-02-17 | 葛洲坝集团第六工程有限公司 | Bailey truss installation and dismounting apparatus |
-
2016
- 2016-02-23 CN CN201610098392.9A patent/CN105714683A/en active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2013149771A1 (en) * | 2012-04-02 | 2013-10-10 | Ulma C Y E, S. Coop | Movable structure suitable for supporting a formwork of a new bridge section in cantilever |
| CN203669362U (en) * | 2013-12-13 | 2014-06-25 | 中建三局第一建设工程有限责任公司 | Connecting device for connecting main truss of bailey frame and jacking stand column |
| CN105332341A (en) * | 2014-08-08 | 2016-02-17 | 葛洲坝集团第六工程有限公司 | Bailey truss installation and dismounting apparatus |
| CN204781929U (en) * | 2015-05-22 | 2015-11-18 | 武汉凡肯智能装备有限公司 | Convenient intelligent hydraulic pressure jacking die carrier system of standard form shellfish thunder frame of assembling |
Non-Patent Citations (1)
| Title |
|---|
| 宋维侠等: "关于悬挂式贝雷架在高架渡槽施工中的应用", 《城市建设理论研究(电子版)》 * |
Cited By (15)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106759125A (en) * | 2016-12-30 | 2017-05-31 | 黑龙江工程学院 | A kind of one-level aqueduct body construction method |
| CN106759125B (en) * | 2016-12-30 | 2018-11-02 | 黑龙江工程学院 | A kind of level-one aqueduct body construction method |
| CN106812069A (en) * | 2017-03-01 | 2017-06-09 | 杭州市交通工程集团有限公司 | The bottom of mountain area buttress Hanging Basket high stops puts device and method |
| CN106812069B (en) * | 2017-03-01 | 2019-04-12 | 杭州市交通工程集团有限公司 | The bottom basket downward putting device and method of the high buttress Hanging Basket in mountain area |
| CN108358052A (en) * | 2018-01-12 | 2018-08-03 | 中国葛洲坝集团第工程有限公司 | A kind of fortune tank car trailing type shoulder pole girder conveying device |
| CN110093867A (en) * | 2019-06-12 | 2019-08-06 | 桥致通(武汉)技术有限公司 | A kind of hydraulic swivel head and its application method for bridge rotating free positioning |
| CN110306833A (en) * | 2019-07-15 | 2019-10-08 | 辽宁工程技术大学 | A non-settling sand box for civil engineering |
| CN111576348A (en) * | 2020-06-11 | 2020-08-25 | 浙江世润建创科技发展有限公司 | Aqueduct formwork system supported on Bailey beam and construction method |
| CN111648313A (en) * | 2020-06-11 | 2020-09-11 | 浙江世润建创科技发展有限公司 | Bailey beam dismantling and transporting device and construction method applying same |
| CN112030768A (en) * | 2020-09-08 | 2020-12-04 | 浙江世润建创科技发展有限公司 | Bailey beam suspension structure and construction method applying same |
| CN115418966A (en) * | 2022-09-28 | 2022-12-02 | 中国水利水电第八工程局有限公司 | A kind of cast-in-place support method for aqueduct |
| CN115418966B (en) * | 2022-09-28 | 2025-04-01 | 中国水利水电第八工程局有限公司 | A cast-in-place support method for aqueduct |
| CN115492390A (en) * | 2022-11-04 | 2022-12-20 | 北京城建北方集团有限公司 | Construction process of overlong overhanging corridor bailey frame support system |
| CN115492390B (en) * | 2022-11-04 | 2024-03-15 | 北京城建北方集团有限公司 | Construction process of support system of ultra-long overhanging corridor bailey frame |
| CN116876353A (en) * | 2023-06-05 | 2023-10-13 | 保利长大工程有限公司 | A construction method for large-span covered beam Bailey supports under 220kv high-voltage line clearance and limited site conditions |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105714683A (en) | Installation and dismantling method of high bent cast-in-situ aqueduct suspension type bailey frames | |
| CN103291076B (en) | Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame | |
| CN101922143B (en) | Cover beam construction method | |
| CN104963301B (en) | The dilatory translation downward putting device and method removed for pier top beam section and bridge pier | |
| CN205025086U (en) | Strength nature skeleton concrete beam construction suspend template in midair | |
| CN104695337B (en) | Self-lifting sliding and turnover construction system and construction method | |
| WO2022142999A1 (en) | Hoisting device for bridge water surface pile tie beam and construction method therefor | |
| CN108360380B (en) | A kind of bridge pier column construction work platform and construction method thereof | |
| CN109457814B (en) | Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure | |
| CN106592438B (en) | Twin shaft pier and middle binder truss move integrally construction method | |
| CN111005324B (en) | Support-free suspension and locking construction method for assembled type segmental box girder | |
| CN101781878A (en) | Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof | |
| CN102561690A (en) | Construction method for supporting structures on two sides of post-cast strip by use of brick column | |
| CN105463997A (en) | Erecting method for segmental beam | |
| CN104032967A (en) | Hoisting construction method for prefabricated assembly-type frame structure members | |
| CN110468743B (en) | A mobile hanger and construction method for the renovation of old bridge pier caps | |
| CN112324131B (en) | One-frame dual-purpose large-span stiff beam construction structure and construction method thereof | |
| CN103993739B (en) | The construction method of granulation tower spraying layer stiff beam | |
| CN211420881U (en) | Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam | |
| CN115162165B (en) | Construction method for closing middle tower column of highway-railway dual-purpose river-crossing A-type cable-stayed bridge | |
| CN214939311U (en) | Integrated bridge erection machine for prefabricated bridge piers and beams | |
| CN222990595U (en) | Multifunctional portal for suspension bridge construction | |
| CN114277672A (en) | Large-span prestressed concrete bent cap structure and construction method thereof | |
| CN113699898A (en) | Side-hanging type full-suspension cover beam combined support platform and mounting method thereof | |
| CN112960566A (en) | Construction method of built-in tower crane of super high-rise building |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160629 |