CN105711734A - Manufacturing method of speed boat - Google Patents

Manufacturing method of speed boat Download PDF

Info

Publication number
CN105711734A
CN105711734A CN201610159790.7A CN201610159790A CN105711734A CN 105711734 A CN105711734 A CN 105711734A CN 201610159790 A CN201610159790 A CN 201610159790A CN 105711734 A CN105711734 A CN 105711734A
Authority
CN
China
Prior art keywords
plate
boat
welding
metal plate
hull
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610159790.7A
Other languages
Chinese (zh)
Other versions
CN105711734B (en
Inventor
刘石全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610159790.7A priority Critical patent/CN105711734B/en
Publication of CN105711734A publication Critical patent/CN105711734A/en
Application granted granted Critical
Publication of CN105711734B publication Critical patent/CN105711734B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B2221/00Methods and means for joining members or elements
    • B63B2221/02Methods and means for joining members or elements by welding

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

The invention discloses a manufacturing method of a speed boat and relates to the field of surface ships. The manufacturing method comprises the following steps: cutting the front end of a metal plate along a length direction into three V-shaped notches at intervals; longitudinally folding the metal plate from the tip end of the middle V-shaped notch to the rear section of the metal plate to form a triangular flat plate; longitudinally folding two side edges of the triangular flat plate to form an inclined plate separately; vertically folding the outer side of each inclined plate upwards to form a boat body; welding depressed plates on knuckle lines at two sides of the boat body; welding the V-shaped notches to form a V-shaped boat head; pressing another metal plate to form a tail seal, and welding the tail seal with the tail of the boat body. Compared with the prior art, the manufacturing method of the speed boat has the advantages that a boat hull is formed by cutting and pressing whole plates, so that the boat body is simple and easy to manufacture, and the manufactured speed boat is light in weight, sufficient in strength and rigidity, economical and practical; the boat hull is formed by cutting one metal plate, so that welding points are few, the labor amount is small, and the boat body is difficult to deform.

Description

The manufacture method of speedboat
Technical field
The present invention relates to above water craft technical field, the manufacture method of especially a kind of speedboat.
Background technology
Speedboat is a kind of canoe of high-speed motion on the water surface, all has extensive utilization in military, civilian field, and speedboat is made up of parts such as hull, propeller, steering wheel, electromotors.Present speedboat is all pursuing fast, steady, light and rigidity, and ship speed wants fast, and hull have to be light, but hull is light, then poor stability, and the impact being subject to wave when navigation can produce concussion, situation of jolting, it is easy to cause passenger to fall down, the problem such as dizzy ship;And want hull light, and more Os Draconis, rib and Fu Cang can not be increased, lacked these reinforcing sections, the rigidity of whole hull will reduce, thus, four indexs of fast, steady, light and rigidity of speedboat so that small-sized speedboat becomes a paradox;Due to small-sized speedboat easily manufacture, economical and practical, still meet very much needed for masses;Thus, small-sized speedboat has been carried out various transformation by people, as in order to make small-sized speedboat speed fast, carried out strengthening propeller power to it, but so virtually increase production cost.
Furthermore, existing speedboat, its hull is all that the metallic plate with a piece a piece is assorted to be welded, and manufacturing process is complicated, and pad is many, and hull is easily deformed.
Summary of the invention
Problem to be solved by this invention is to provide the manufacture method of the on-deformable speedboat of speedboat that a kind of manufacturing process is simple and creates.
In order to solve above-mentioned technical problem, the technical solution adopted in the present invention is:
Comprise the steps:
A, first three " V " type breach are determined at the front end edge length direction interval of a rectangular metallic plate;
B, on described metallic plate, go out a triangle flat board along the tip of middle " V " type breach to the back segment longitudinal direction backfin of this metallic plate, again the dual-side of triangle flat board along two other " V " type breach most advanced and sophisticated longitudinally respectively backfin go out a hang plate, two hang plates and triangle flat board constitute the base plate of hull;Then again by the upwards backfin of the outside upright of each hang plate, kayak body is defined;The both sides chine of described kayak body welds water squeezing plate;
C, by the doubling welding of adjacent for described " V " type breach limit, then docking welding is continued on the both sides that will exceed, and forms " V " type deflection arch;
D, another metallic plate is cut into stern transom plate, this stern transom plate is welded on the step B kayak body afterbody prepared.
Owing to adopting technique scheme, the present invention compared with prior art, has the advantages that
Owing to the V-type deflection arch of whole hull, kayak body are compressing by entire plate cutting, as long as welding stern transom plate and V-type deflection arch doubling being welded, namely may make up ship shell, thus the manufacture of hull becomes simple easy, and produced speedboat is light, there are again sufficient intensity and rigidity, economical and practical;Again owing to ship shell is to be formed by one piece of metallic plate cutting, pad is few, and the amount of labour is few, and hull is unlikely to deform.
Accompanying drawing explanation
Fig. 1 is the structural representation before the backfin of the present invention.
Fig. 2 is the upward view forming speedboat of embodiment 1.
Fig. 3 is the A-A cutaway view Amplified image of Fig. 2.
Detailed description of the invention
Below in conjunction with attached Example, the invention will be further described:
Embodiment 1:
Embodiment as shown in Figure 1, Figure 2 and Figure 3, its manufacture method comprises the steps:
A, first three " V " type breach 1,2,3 are determined at the front end edge length direction interval of rectangular metallic plate;
B, the on a metal plate tip of edge " V " type breach 2 go out a triangle flat board 4 to the back segment longitudinal direction backfin of this metallic plate, again the dual-side of triangle flat board along two other " V " type breach 1,3 most advanced and sophisticated longitudinally respectively backfin go out hang plate 5,6, two hang plates and triangle flat board constitute the base plate of hull;Then again by outside 7 and 8 backfin straight up of each hang plate, kayak body is defined;The both sides chine of kayak body welds water squeezing plate 9;
C, by the doubling welding of adjacent for " V " type breach 1,2,3 limit, then docking welding is continued on the both sides that will exceed, and forms " V " type deflection arch;
D, another metallic plate is cut into stern transom plate 10, this stern transom plate is welded on the step B kayak body afterbody prepared.
Owing to the V-type deflection arch of whole hull, kayak body are compressing by entire plate cutting, as long as welding stern transom plate and V-type deflection arch doubling being welded, namely may make up ship shell, thus the manufacture of hull becomes simple easy;Again owing to ship shell is to be formed by one piece of metallic plate cutting, pad is few, and the amount of labour is few, and hull is unlikely to deform.

Claims (1)

1. a manufacture method for speedboat, includes hull, it is characterised in that: its manufacturing step is as follows:
A, first three " V " type breach are determined at the front end edge length direction interval of a rectangular metallic plate;
B, on described metallic plate, go out a triangle flat board along the tip of middle " V " type breach to the back segment longitudinal direction backfin of this metallic plate, again the dual-side of triangle flat board along two other " V " type breach most advanced and sophisticated longitudinally respectively backfin go out a hang plate, two hang plates and triangle flat board constitute the base plate of hull;Then again by the upwards backfin of the outside upright of each hang plate, kayak body is defined;The both sides chine of described kayak body welds water squeezing plate;
C, by the doubling welding of adjacent for described " V " type breach limit, then docking welding is continued on the both sides that will exceed, and forms " V " type deflection arch;
D, another metallic plate is cut into stern transom plate, this stern transom plate is welded on the step B kayak body afterbody prepared.
CN201610159790.7A 2016-03-21 2016-03-21 The manufacture method of speedboat Expired - Fee Related CN105711734B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610159790.7A CN105711734B (en) 2016-03-21 2016-03-21 The manufacture method of speedboat

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610159790.7A CN105711734B (en) 2016-03-21 2016-03-21 The manufacture method of speedboat

Publications (2)

Publication Number Publication Date
CN105711734A true CN105711734A (en) 2016-06-29
CN105711734B CN105711734B (en) 2018-01-23

Family

ID=56159091

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610159790.7A Expired - Fee Related CN105711734B (en) 2016-03-21 2016-03-21 The manufacture method of speedboat

Country Status (1)

Country Link
CN (1) CN105711734B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4282617A (en) * 1977-03-14 1981-08-11 Lundstroem Claes Oe S Boat hull, material or blank for a boat hull, and a method of producing a boat hull
CN101139005A (en) * 2007-10-16 2008-03-12 李跃先 FRP composite material mould-free shipbuilding method
CN101570237A (en) * 2009-06-15 2009-11-04 太阳鸟游艇股份有限公司 Multi-mixture design technique for building ships with composite materials
CN103213650A (en) * 2013-04-13 2013-07-24 王崇高 Skating boat
CN103661796A (en) * 2013-12-20 2014-03-26 苏州澎逸运动用品有限公司 Foldable canoe and manufacturing technology thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4282617A (en) * 1977-03-14 1981-08-11 Lundstroem Claes Oe S Boat hull, material or blank for a boat hull, and a method of producing a boat hull
CN101139005A (en) * 2007-10-16 2008-03-12 李跃先 FRP composite material mould-free shipbuilding method
CN101570237A (en) * 2009-06-15 2009-11-04 太阳鸟游艇股份有限公司 Multi-mixture design technique for building ships with composite materials
CN103213650A (en) * 2013-04-13 2013-07-24 王崇高 Skating boat
CN103661796A (en) * 2013-12-20 2014-03-26 苏州澎逸运动用品有限公司 Foldable canoe and manufacturing technology thereof

Also Published As

Publication number Publication date
CN105711734B (en) 2018-01-23

Similar Documents

Publication Publication Date Title
US8991326B2 (en) Displacement hull form not subject to the limitation of hull speed
US8726823B2 (en) Boat hull
JP5778572B2 (en) Steel ship or light alloy ship
US9567035B2 (en) Means of water surface transport
CN105711734A (en) Manufacturing method of speed boat
US4372240A (en) Surface ship having improved speed and maneuverability
CN105730616A (en) Method for manufacturing wave-suppressing speedboat
CN105836048A (en) Manufacturing method of wave-eliminating yacht
CN113443072B (en) Ship tail post
CN205554529U (en) Yacht
CN105775066B (en) Speedboat and its manufacture method
JP6582296B2 (en) Ship rudder and ship
US3680513A (en) Ship stern fitted with twin-screw propulsion
CN104118531B (en) The not contour fold method of the oblique longitudinal bulkhead of monoshell bulk freighter and monoshell bulk freighter
CN211893551U (en) Simple streamline solid wood structure for ship
JPS6333755Y2 (en)
CN105730615A (en) Manufacturing method of ship buoy
CA2964797A1 (en) Minimum wave bow
CN105836044A (en) Manufacturing method of buoy
CN107303940A (en) Small waterplane area twin hull ship based on bubble drag-reduction
JP2002220082A (en) Wave-propelled ship form
CN105711733A (en) Manufacturing method of marine buoy
JPS5927351Y2 (en) Wave-dissipating catamaran
JPH0224720Y2 (en)
JPH02117491A (en) Small water plane single shell ship equipped with buoyant body on each board

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180123