CN105696791A - Embedded die for bolt hole used for installing building construction cropping platform - Google Patents

Embedded die for bolt hole used for installing building construction cropping platform Download PDF

Info

Publication number
CN105696791A
CN105696791A CN201610217460.9A CN201610217460A CN105696791A CN 105696791 A CN105696791 A CN 105696791A CN 201610217460 A CN201610217460 A CN 201610217460A CN 105696791 A CN105696791 A CN 105696791A
Authority
CN
China
Prior art keywords
square frame
bar
bolt hole
vertical bar
vertical pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610217460.9A
Other languages
Chinese (zh)
Other versions
CN105696791B (en
Inventor
李蓉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Industry Co Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201610217460.9A priority Critical patent/CN105696791B/en
Publication of CN105696791A publication Critical patent/CN105696791A/en
Application granted granted Critical
Publication of CN105696791B publication Critical patent/CN105696791B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • E04G15/04Cores for anchor holes or the like around anchors embedded in the concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明公开了一种房屋建筑施工切料平台安装用螺栓孔的预埋模具,改善了现有预埋方式过于复杂,精度较低的问题。本发明包括方形框体,所述方形框体两端分别设有一根横杆,且在所述方体框体一侧设有一根纵杆;所述横杆、纵杆均位于方形框体的内侧;所述横杆的两端分别与方体框体两侧相连,所述纵杆的两端分别与方体两端相连,且纵杆还与两根横杆相连;所述方形框体四个角、纵杆与方形框体相连点、横杆与方形框体相连点和横杆与纵杆相连点处分别设有一个竖杆。本发明可一次性预埋十二个螺纹孔,效率高;而且位置精度高;同时本发明的设备能够重复使用,大大地降低了模具成本。

The invention discloses a pre-embedded mold for bolt holes used for installing a material cutting platform for building construction, which improves the problems that the existing pre-embedded methods are too complicated and have low precision. The present invention comprises a square frame body, a horizontal bar is provided at both ends of the square frame body, and a longitudinal bar is provided on one side of the square frame body; Inside; the two ends of the horizontal bar are respectively connected with the two sides of the square frame, the two ends of the vertical bar are respectively connected with the two ends of the square body, and the vertical bar is also connected with two horizontal bars; the square frame A vertical bar is respectively arranged at the four corners, the connecting points of the vertical bar and the square frame, the connecting points of the horizontal bar and the square frame, and the connecting points of the horizontal bar and the vertical bar. The present invention can pre-embed twelve threaded holes at one time, with high efficiency and high position accuracy; meanwhile, the device of the present invention can be used repeatedly, which greatly reduces the mold cost.

Description

一种房屋建筑施工切料平台安装用螺栓孔的预埋模具A pre-embedded mold for bolt holes for installation of building construction material cutting platform

技术领域 technical field

本发明涉及一种房屋建筑施工切料平台安装用螺栓孔的预埋模具。 The invention relates to a pre-embedded mold for bolt holes used for installing a material cutting platform for building construction.

背景技术 Background technique

在房屋建筑工程施工中,安装施工卸料平台,进行施工用料机等部件的上下,其平台使用型钢支撑架进行支撑,型钢在楼板上的固体需要使用U型螺栓孔,故而需在楼板上预埋螺栓孔,现有的预埋方式过于复杂,精度较低。 In the construction of housing construction, the construction unloading platform is installed to carry out the up and down of the construction material machine and other components. The platform is supported by the steel support frame. Pre-embedded bolt holes, the existing pre-embedded method is too complicated and the precision is low.

发明内容 Contents of the invention

为了改善上述问题,本发明的目的在于提供一种房屋建筑施工切料平台安装用螺栓孔的预埋模具。 In order to improve the above-mentioned problems, the object of the present invention is to provide a pre-embedded mold for bolt holes for installation of a building construction material cutting platform.

为了实现上述目的,本发明采用的技术方案如下: In order to achieve the above object, the technical scheme adopted in the present invention is as follows:

一种房屋建筑施工切料平台安装用螺栓孔的预埋模具,包括方形框体,所述方形框体两端分别设有一根横杆,且在所述方体框体一侧设有一根纵杆;所述横杆、纵杆均位于方形框体的内侧;所述横杆的两端分别与方体框体两侧相连,所述纵杆的两端分别与方体两端相连,且纵杆还与两根横杆相连;所述方形框体四个角、纵杆与方形框体相连点、横杆与方形框体相连点和横杆与纵杆相连点处分别设有一个竖杆。 A pre-embedded mold for bolt holes for installing a material cutting platform for house construction, comprising a square frame, a horizontal bar is provided at both ends of the square frame, and a longitudinal bar is provided on one side of the square frame. bar; the cross bar and the vertical bar are all located inside the square frame; the two ends of the horizontal bar are respectively connected with the two sides of the square frame, and the two ends of the vertical bar are respectively connected with the two ends of the square body, and The vertical bar is also connected with two horizontal bars; the four corners of the square frame, the connecting points of the vertical bar and the square frame, the connecting points of the horizontal bar and the square frame, and the connecting points of the horizontal bar and the vertical bar are respectively provided with a vertical pole.

进一步地,每个竖杆外均套接有预埋套管。 Further, each vertical bar is sleeved with a pre-embedded casing.

再进一步地,所述预埋套管底部封闭,顶部开口。 Still further, the embedded casing is closed at the bottom and open at the top.

更进一步地,所述预埋套管顶部侧壁设有通孔,且顶部边沿向外翻转。 Furthermore, the top side wall of the pre-embedded casing is provided with a through hole, and the top edge is turned outward.

另外,所述方形框体由四根杆围成。 In addition, the square frame is surrounded by four rods.

此外,所述横杆、纵杆和方形框体之间均焊接相连。 In addition, the cross bar, the longitudinal bar and the square frame are all connected by welding.

本发明与现有技术相比,具有以下优点及有益效果: Compared with the prior art, the present invention has the following advantages and beneficial effects:

本发明可一次性预埋十二个螺纹孔,效率高;而且位置精度高;同时本发明的设备能够重复使用,大大地降低了模具成本。 The present invention can pre-embed twelve threaded holes at one time, with high efficiency and high position accuracy; meanwhile, the device of the present invention can be used repeatedly, greatly reducing the mold cost.

附图说明 Description of drawings

图1为本发明的结构示意图。 Fig. 1 is a structural schematic diagram of the present invention.

其中,附图中标记对应的零部件名称为:1-方形框体,2-横杆,3-纵杆,4-竖杆,5-预埋套管。 Among them, the names of parts corresponding to the marks in the drawings are: 1-square frame, 2-horizontal bar, 3-longitudinal bar, 4-vertical bar, 5-embedded casing.

具体实施方式 detailed description

下面结合附图和实施例对本发明作进一步说明,本发明的实施方式包括但不限于下列实施例。 The present invention will be further described below with reference to the accompanying drawings and examples, and the embodiments of the present invention include but not limited to the following examples.

实施例 Example

如图1所示,一种房屋建筑施工切料平台安装用螺栓孔的预埋模具,包括方形框体1,所述方形框体两端分别设有一根横杆2,且在所述方体框体一侧设有一根纵杆3;所述横杆、纵杆均位于方形框体的内侧;所述横杆的两端分别与方体框体两侧相连,所述纵杆的两端分别与方体两端相连,且纵杆还与两根横杆相连;所述方形框体四个角、纵杆与方形框体相连点、横杆与方形框体相连点和横杆与纵杆相连点处分别设有一个竖杆4。其中,所述方形框体由四根杆围成。所述横杆与方形框体两端的杆相平行;所述纵杆与方形框体两侧的杆相平行。这样设置能够确保设置于各个相连点和四个角上的竖杆满足施工要求,从而预留出供“U”型螺栓穿过的螺栓孔。另外,每个竖杆外均套接有预埋套管5。 As shown in Figure 1, a pre-embedded mold for bolt holes for installing a material cutting platform for building construction, comprising a square frame body 1, a cross bar 2 is provided at both ends of the square frame body, and One side of the frame body is provided with a vertical bar 3; the horizontal bar and the vertical bar are all positioned at the inner side of the square frame; the two ends of the horizontal bar are respectively connected with the two sides of the square frame body, They are respectively connected to two ends of the square body, and the vertical bar is also connected to two horizontal bars; the four corners of the square frame, the connecting points of the vertical bar and the square frame, the connecting points of the horizontal bar and the square frame, and the connection points of the horizontal bar and the vertical A vertical rod 4 is respectively arranged at the connecting points of the rods. Wherein, the square frame is surrounded by four rods. The horizontal bar is parallel to the bars at both ends of the square frame; the vertical bar is parallel to the bars on both sides of the square frame. This setting can ensure that the vertical bars arranged at each connection point and four corners meet the construction requirements, thereby reserving bolt holes for "U" bolts to pass through. In addition, each vertical bar is sleeved with a pre-embedded casing 5 .

在实际施工时,将预埋套管套在竖杆上,然后将本发明放置于施工位置,然后进行浇筑混凝土,当混凝土浇筑完成后,只需将方形框体取下,然后再将预埋套管从混凝土中取出即可,这样就形成了螺栓孔。当然如果预埋较深,可以无需取出预埋套管,只需将方形框体取出即可。由于有竖杆的存在,能够确保每一个预埋套管垂直,不会发生倾斜,而且能够限定每个预埋套管之间的距离,从而满足施工需求。 In actual construction, put the pre-embedded casing on the vertical bar, then place the present invention at the construction position, and then pour concrete. The casing is simply removed from the concrete so that the bolt holes are formed. Of course, if the pre-embedding is deep, it is not necessary to take out the pre-embedded casing, just take out the square frame. Due to the existence of the vertical bar, it can ensure that each embedded casing is vertical without inclination, and the distance between each embedded casing can be limited, so as to meet the construction requirements.

具体地,所述预埋套管底部封闭,顶部开口。通过上述设置,可以防止混凝土在浇筑过程中流入预埋套管,避免无法形成螺栓孔。 Specifically, the embedded casing is closed at the bottom and open at the top. Through the above arrangement, it is possible to prevent the concrete from flowing into the embedded casing during the pouring process, so as to prevent the bolt holes from being unable to be formed.

当需要将预埋套管取下时,预埋套管顶部侧壁设有通孔,且顶部边沿向外翻转。这样设置,能够通过通孔安装相应的吊钩等部件,将预埋套管从混凝土中取出,值得说明的是,混凝土上沿低于通孔;若不需要将预埋套管从混凝土中取出,那么就无需设置通孔。由于预埋套管顶部边沿向外翻转,这样设置也能够利用突出的部分采用部件将预埋套管从混凝土中取出。 When the embedded casing needs to be removed, the top side wall of the embedded casing is provided with a through hole, and the top edge is turned outward. In this way, the corresponding hook and other components can be installed through the through hole, and the embedded casing can be taken out of the concrete. It is worth noting that the upper edge of the concrete is lower than the through hole; , then no vias are required. Since the top edge of the pre-embedded casing is turned outwards, such an arrangement can also utilize the protruding part to take the pre-embedded casing out of the concrete.

为了使本发明的结构更加稳定、牢固。所述横杆、纵杆和方形框体之间均焊接相连。通过焊接使得各部件之间连接的更加牢固,从而更好的实现预埋螺栓孔的作用,再取出时,也能够很好的将竖杆直接从预埋套管内取出。 In order to make the structure of the present invention more stable and firm. The cross bar, the vertical bar and the square frame are all connected by welding. Welding makes the connection between the parts more firm, so as to better realize the function of the embedded bolt hole, and when it is taken out again, the vertical bar can also be taken out directly from the embedded casing.

值得说明的是,本发明结构简单,制造成本低,而且非常实用,能够一次性预埋十二个螺栓孔,同时能够确保“U”型螺栓刚好穿过进行固定型钢支撑架。 It is worth noting that the present invention is simple in structure, low in manufacturing cost, and very practical. It can pre-embed twelve bolt holes at one time, and at the same time, it can ensure that the "U" bolts just pass through to fix the steel support frame.

按照上述实施例,便可很好地实现本发明。值得说明的是,基于上述结构设计的前提下,为解决同样的技术问题,即使在本发明上做出的一些无实质性的改动或润色,所采用的技术方案的实质仍然与本发明一样,故其也应当在本发明的保护范围内。 According to the above-mentioned embodiments, the present invention can be well realized. It is worth noting that, based on the premise of the above-mentioned structural design, in order to solve the same technical problem, even if some insubstantial changes or polishes are made on the present invention, the essence of the adopted technical solution is still the same as the present invention. Therefore, it should also be within the protection scope of the present invention.

Claims (6)

1. the pre-buried mould of a housing construction blank stage+module bolt hole, it is characterised in that include square framework (1), described square framework is respectively arranged at two ends with a cross bar (2), and is provided with a vertical pole (3) in described cube framework side;Described cross bar, vertical pole are respectively positioned on the inner side of square framework;The two ends of described cross bar are connected with cube framework both sides respectively, and the two ends of described vertical pole are connected with cube two ends respectively, and vertical pole is also connected with two cross bars;Be connected with square framework point, cross bar of four angles of described square framework, vertical pole is connected a little with square framework and cross bar some places that is connected with vertical pole are respectively equipped with a montant (4)。
2. the pre-buried mould of a kind of housing construction blank stage+module bolt hole according to claim 1, it is characterised in that be all socketed with service sleeve (5) outside each montant。
3. the pre-buried mould of a kind of housing construction blank stage+module bolt hole according to claim 2, it is characterised in that described service sleeve bottom lock, open top。
4. the pre-buried mould of a kind of housing construction blank stage+module bolt hole according to claim 3, it is characterised in that described service sleeve top sidewall is provided with through hole, and top sides is along outwards overturning。
5. the pre-buried mould of a kind of housing construction blank stage+module bolt hole according to claim 4, it is characterised in that described square framework is surrounded by four bars。
6. the pre-buried mould of a kind of housing construction blank stage+module bolt hole according to claim 5, it is characterised in that be all weldingly connected between described cross bar, vertical pole and square framework。
CN201610217460.9A 2016-04-08 2016-04-08 A kind of pre-buried mould of housing construction blank stage+module bolt hole Active CN105696791B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610217460.9A CN105696791B (en) 2016-04-08 2016-04-08 A kind of pre-buried mould of housing construction blank stage+module bolt hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610217460.9A CN105696791B (en) 2016-04-08 2016-04-08 A kind of pre-buried mould of housing construction blank stage+module bolt hole

Publications (2)

Publication Number Publication Date
CN105696791A true CN105696791A (en) 2016-06-22
CN105696791B CN105696791B (en) 2018-01-02

Family

ID=56219450

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610217460.9A Active CN105696791B (en) 2016-04-08 2016-04-08 A kind of pre-buried mould of housing construction blank stage+module bolt hole

Country Status (1)

Country Link
CN (1) CN105696791B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050012540A (en) * 2003-07-25 2005-02-02 김대현 Fixing way of subsidiary materials for a building and the structure
CN203238953U (en) * 2012-12-10 2013-10-16 中国建筑第八工程局有限公司 Embedded sleeve positioning device
CN204199180U (en) * 2014-10-23 2015-03-11 田文 A kind of bridge pad bolt integral built-in mould
CN204781959U (en) * 2015-05-25 2015-11-18 中国五冶集团有限公司 Ring location auxiliary device
CN205476470U (en) * 2016-04-08 2016-08-17 中国五冶集团有限公司 Pre -buried mould of housing construction construction blank bolt hole for platform installation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050012540A (en) * 2003-07-25 2005-02-02 김대현 Fixing way of subsidiary materials for a building and the structure
CN203238953U (en) * 2012-12-10 2013-10-16 中国建筑第八工程局有限公司 Embedded sleeve positioning device
CN204199180U (en) * 2014-10-23 2015-03-11 田文 A kind of bridge pad bolt integral built-in mould
CN204781959U (en) * 2015-05-25 2015-11-18 中国五冶集团有限公司 Ring location auxiliary device
CN205476470U (en) * 2016-04-08 2016-08-17 中国五冶集团有限公司 Pre -buried mould of housing construction construction blank bolt hole for platform installation

Also Published As

Publication number Publication date
CN105696791B (en) 2018-01-02

Similar Documents

Publication Publication Date Title
CN204298825U (en) Foundation ditch builds elephant trunk supporting and regulating device
CN107700533B (en) A kind of construction technology of box-type quick assembly and disassembly mould pipe gallery
CN205348212U (en) Prefabricated assembled combination column base
CN104453224A (en) Formwork support structure of basement exterior wall and construction method of formwork support structure
CN102561695A (en) Construction method for building buildings by aluminum templates
CN205476470U (en) Pre -buried mould of housing construction construction blank bolt hole for platform installation
CN207526100U (en) Wall is poured with aluminum alloy pattern plate leveling and ruggedized construction
CN212027123U (en) Tool for fixing wire box
CN103031892A (en) Steel truss brace and manufacturing method for steel truss platform
CN105696791B (en) A kind of pre-buried mould of housing construction blank stage+module bolt hole
CN204491564U (en) A kind of jacket for offshore structure
CN204680514U (en) Transformer oil storage
CN203603465U (en) Novel descending plate lifting die
CN107012952A (en) A kind of concrete frame node
CN108775147A (en) A kind of wall body casting template supporting construction device
CN206859675U (en) A kind of station bottom plate and side wall chamfering punching block positioning instrument
CN208718374U (en) A kind of steel framework wooden model combination unit
CN205791363U (en) A kind of electrical engineering positioning installation apparatus
CN211320855U (en) Prefabricated wall junction box tooling rack
CN203188223U (en) Bottomless double-wall steel sleeve box for achieving dry operation 100% recycle
CN204199691U (en) A kind of handrail formwork for placing structure of spiral stairs
CN203008232U (en) Steel truss strut
CN220150883U (en) Formwork support base
CN108868125A (en) A kind of support jacking and roof plate-girder fast assembling-disassembling system
CN216543870U (en) Light current case mould and wallboard in assembled precast concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201124

Address after: No.28 Shuguang Xili, Chaoyang District, Beijing 100020

Patentee after: China Metallurgical Industry Co., Ltd

Address before: Jinjiang District mcc5 610000 Chengdu Road, Sichuan province No. 9

Patentee before: CHINA MCC5 GROUP Corp.,Ltd.

TR01 Transfer of patent right