CN105672308B CN201610075607.5A CN201610075607A CN105672308B CN 105672308 B CN105672308 B CN 105672308B CN 201610075607 A CN201610075607 A CN 201610075607A CN 105672308 B CN105672308 B CN 105672308B
Authority
CN
China
Prior art keywords
pile
eye
broken
nut
bushing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610075607.5A
Other languages
Chinese (zh)
Other versions
CN105672308A (en
Inventor
郭志敏
鲁勤松
金惠良
顾利君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HAIYAN HUARUISI FASTENER Co.,Ltd.
Original Assignee
Dongyang Ju Ran Electronic Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongyang Ju Ran Electronic Technology Co Ltd filed Critical Dongyang Ju Ran Electronic Technology Co Ltd
Priority to CN201610075607.5A priority Critical patent/CN105672308B/en
Publication of CN105672308A publication Critical patent/CN105672308A/en
Application granted granted Critical
Publication of CN105672308B publication Critical patent/CN105672308B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a kind of pile pile Quick connection parts, including big nut, primary nut, it is characterized in that setting bushing, locking device inside big nut, eye-splice pin is set on primary nut, it eye-splice pin lower hollow and is broken equipped with several buttons with step surface along the circumferential direction uniformly configured, the lower face cooperation of the step surface and bushing broken is detained, locking device is clamped with the internal face that button is broken.The bushing is threadedly attached on big nut, and the eye-splice pin is threadedly attached on primary nut, and eye-splice pin automatic fastening and can lock after being inserted into bushing, to be connected as an entirety.The Quick connection part have it is compact-sized, connection quickly, it is reliable, bearing capacity is strong, advantage easy to use.

Description

A kind of pile pile Quick connection part
Technical field
The present invention relates to a kind of Quick connection parts, in particular for concrete square pile and the Quick connection part of pile pile.
Background technology
Chinese pile pile was started to walk since 1987, by the development of more than ten years, had formed the tubulose production of more than 260, the whole nation Enterprise.Recent years, tubular pile industry was quickly grown.At present the country pile pile be mainly used in 60 layers of a variety of skyscrapers below with And industry and civil buildings embedded footing on piles, low capped pile foundation plinth, railway, highway and bridge, harbour, harbour, water conservancy, municipal administration, construction and big The engineering foundations construction field such as type equipment.The application percentage of wherein real estate domain accounts for 80% or so, and road and rail accounts for 15% left side The right side, annual demand reach more than one hundred million meters of scale.
A length of 10 meters of the standard knot of pile pile, by its end, iron plate welds together in traditional work progress.According to On-the-spot investigation, construction site need the registration for adjusting two connected pile piles to be increased since the quality of stake is big before welding Adjust degree of difficulty.It is not easy clean welds when welding, is susceptible to rosin joint, phenomena such as solder skip, welding quality is not easy to ensure. It requires weld seam welding to complete postcooling certain time in design, ensures weld strength, however often principal security is applied for construction site Work progress, it is difficult to control, be easy that weld seam is made to generate crack when no completely cooling in this way, greatly destroy the intensity of connection. Due to that can not be detected after indentation ground, to cause certain risk.Patent publication No. is the patent Shen of CN104948554A Please file disclose a kind of bolt-type connector, structure easy tos produce disengaging, it cannot be guaranteed that the reliability being vertically connected with.
Invention content
In order to solve the technical issues of weldquality is unreliable, and working efficiency is low, long construction period in above-mentioned work progress, The present invention devises a kind of quick mechanical connection component, after two pile piles are connected through, can ensure that its is heavy automatically It is right, and the intensity connected is ensured by the actual strength of its own.Further, since eliminating the link of welding, greatly carry The high efficiency of construction, it is cost-effective, avoid electric welding itself may caused by environmental pollution and to the straight of operator's health Connect damage.
In order to solve the above technical problems, the present invention adopts the following technical scheme that:
A kind of pile pile Quick connection part, including big nut, primary nut, it is characterised in that setting bushing, lock inside big nut Determine device, eye-splice pin is set on primary nut, eye-splice pin lower hollow and has equipped with what several were along the circumferential direction uniformly configured The button of step surface is broken, and the lower face cooperation of the step surface and bushing broken is detained, and locking device is clamped with the internal face that button is broken, locking dress The maximum periphery set coordinates with the internal face that button is broken so that the lower face clamping for detaining the step surface and bushing broken is reliable, is not easy It is detached from.
After eye-splice pin is inserted into the bushing being connected on big nut, with the push-in of eye-splice pin, the button of its underpart It breaks and is pressed together under radial force effect and pushes locking mandrel that spring is pressed onto on spring base, when the step surface that button is broken Be inserted into more than after bush end face, button breaks automatic distending and is anchored to bush end face, then lock mandrel under spring force by It bounces, is inserted into inside eye-splice pin, avoid button from breaking makes eye-splice pin and bushing separate under the action of pulling force into bushing.
The locking device is made of spring base, spring, locking mandrel, and spring base is mounted on big nut, locks mandrel It is flexibly connected with spring base, locks and be provided with spring between mandrel and spring base, locked the maximum periphery of mandrel and button is broken Internal face coordinates, and fit clearance is less than the radial width that button breaks terrace of appearing on the stage.
On the eye-splice pin there are 2 to 10 buttons to break, button, which breaks interior outer bottom, to be had into a chamfering, and the separation trough between breaking is detained Width is 0.5mm to 8mm, and separation slot length is 0.5mm to 40mm.
The locking mandrel has into a guide section, lock segments and flexible guide section, it is described enter guide section top have down Angle, the lock segments periphery are spherical surface or the conical surface, and the flexible guide section is flexibly connected with spring base, and spring pocket, which is mounted in, to be stretched On contracting guide section.
The bushing is threadedly attached on big nut, and the eye-splice pin is threadedly attached on primary nut, eye-splice Pin automatic fastening and can lock after being inserted into bushing, to be connected as an entirety.
The present invention has the following advantages:
(1)Whole process does not need artificial intervention, high degree of automation.
(2)The pilot process such as welding are avoided, construction efficiency is greatly improved.
(3)Connecting-piece structure design itself ensure that the registration of connection, intensity and reliability.
(4)Modularized design, it is at low cost, use simplicity.
Description of the drawings
Fig. 1 is the structural schematic diagram of the embodiment of the present invention.
Specific implementation mode
The following describes the present invention in detail with reference to the accompanying drawings and specific embodiments.
As shown in Figure 1, the pile pile Quick connection part of the embodiment of the present invention, including big nut 100, it is mounted on inside big nut Spring base 200, be sequentially arranged at compressed spring 300 on spring base 200, locking mandrel 400, be mounted in big nut 100 The bushing 500 in portion, primary nut 700 and the eye-splice pin 600 on primary nut 700.Wherein, if being provided on eye-splice pin 600 600 lower part of eye-splice pin is divided into the button equipped with step surface and breaks 602, and breaks 602 interior outer bottom in each button by dry separation trough 601 Portion be respectively equipped with it is outer enter a chamfering 603 and it is interior enter a chamfering 604.Locking mandrel 400 is equipped with into guide section 401, lock segments 403 and flexible guide section 404,403 top of lock segments is spherical surface 402 or may be designed in the conical surface.
In pile pile fabrication, one end of reinforcing bar is inserted into the hole 101 on big nut 100, another reinforcing bar One end is inserted into the hole 701 on primary nut 700, and big nut 100 is connected by both ends after distinguishing pier nose with primary nut 700.Using with The tooling that big nut 100, primary nut 700 coordinate is by certain amount(Particular number is different and different according to the size of pile pile)It is big Primary nut is connected and stretches(So that the connection of big nut 100,700 reliable fit of primary nut), ensure the quality of production of pile pile.Pile pile Production technology is identical with current process engineering, it is thus only necessary to change the connecting tooling at both ends.
In the work progress of piling, that end equipped with primary nut 700 is downward, and eye-splice pin 600 is tightened to primary nut 700 Interior, by nut seat 200, spring 300 and locking mandrel 400 are sequentially loaded into big nut 100, and bushing 500 is tightened to big spiral shell In mother 100.During two root canal piles enter position, when eye-splice pin 600 enters in position to the bushing 500 being connected on big nut 100 After, with the push-in of eye-splice pin 600, the button of its underpart breaks 602 and is pressed under radial force effect and together, push locking core Spring 300 is pressed onto on spring base 200 by axis 400, after button, which breaks the step surface on 602, is inserted into the lower face more than bushing 500, Button breaks 602 automatic distendings and is anchored to 500 lower face of bushing, then locks mandrel 400 and is bounced under spring force, is inserted into and inserts Inside pin buckle 600, avoids button from breaking 602 and detached into bushing 500 under the action of pulling force.This is arrived, the connection of two pile piles is completed.
It is the preferred forms of patent of the present invention above, by those skilled in the art according to the revealed spirit of this patent The various change or remodeling made each fall within the range that this patent includes.

Claims (4)

1. a kind of pile pile Quick connection part, including big nut, primary nut, it is characterised in that setting bushing, locking inside big nut Device, is arranged eye-splice pin on primary nut, eye-splice pin lower hollow and has platform equipped with what several were along the circumferential direction uniformly configured The button of terrace is broken, and the lower face cooperation of the step surface and bushing broken is detained, and locking device is clamped with the internal face that button is broken, the locking Device is made of spring base, spring, locking mandrel, and spring base is mounted on big nut, and locking mandrel is flexibly connected with spring base, It is provided with spring between locking mandrel and spring base, locks the internal face cooperation that the maximum periphery of mandrel is broken with button.
2. pile pile Quick connection part according to claim 1, it is characterised in that:There are 2 to 10 buttons on the eye-splice pin It breaks, button, which breaks interior outer bottom, to be had into a chamfering, and the separation groove width between button is broken is 0.5mm to 8mm, and separation slot length is 0.5mm To 40mm.
3. pile pile Quick connection part according to claim 1, it is characterised in that:The locking mandrel has to be oriented into position Section, lock segments and flexible guide section, it is described enter to have chamfering, the lock segments periphery be spherical surface or cone on guide section top Face, the flexible guide section are flexibly connected with spring base, and spring pocket is mounted on flexible guide section.
4. pile pile Quick connection part according to claim 1, it is characterised in that:The bushing is threadedly attached in big spiral shell On mother, the eye-splice pin is threadedly attached on primary nut.
CN201610075607.5A 2016-02-03 2016-02-03 A kind of pile pile Quick connection part Active CN105672308B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610075607.5A CN105672308B (en) 2016-02-03 2016-02-03 A kind of pile pile Quick connection part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610075607.5A CN105672308B (en) 2016-02-03 2016-02-03 A kind of pile pile Quick connection part

Publications (2)

Publication Number Publication Date
CN105672308A CN105672308A (en) 2016-06-15
CN105672308B true CN105672308B (en) 2018-11-02

Family

ID=56303471

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610075607.5A Active CN105672308B (en) 2016-02-03 2016-02-03 A kind of pile pile Quick connection part

Country Status (1)

Country Link
CN (1) CN105672308B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759942B (en) * 2017-03-01 2022-07-01 邓剑涛 Integrally-cured welding-free pin lock connecting structure and construction method thereof
CN111851483A (en) * 2020-08-14 2020-10-30 海盐华瑞斯紧固件有限公司 Steel ball formula tubular pile quick connector
CN112746614B (en) * 2021-02-05 2023-08-18 单良 Quick-connection tensile-pulling prestressed square pile and connection method
CN116695695B (en) * 2023-08-08 2023-12-19 连云港市源通水泥制品有限公司 Concrete pipe pile convenient to connect fixedly

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2890173Y (en) * 2005-05-17 2007-04-18 周兆弟 Splicing type pile-splicing buckle and precast products
CN201033871Y (en) * 2005-05-17 2008-03-12 周兆弟 Elastic expanding joggle joint pile end plate, precast member and butt-jointing structure between the members
CN101787699A (en) * 2009-11-07 2010-07-28 广东三和管桩有限公司 Bolt fastening structure of pipe die
CN201581396U (en) * 2009-11-07 2010-09-15 广东三和管桩有限公司 Pipe die bolt connecting structure
CN104895052A (en) * 2015-06-25 2015-09-09 袁江 Rapid joint of precast concrete pile
CN204728315U (en) * 2015-06-25 2015-10-28 袁江 A kind of precast concrete pile snap joint

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5749228B2 (en) * 2012-07-26 2015-07-15 勇平 八百板 Steel pipe pile for small buildings and its construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2890173Y (en) * 2005-05-17 2007-04-18 周兆弟 Splicing type pile-splicing buckle and precast products
CN201033871Y (en) * 2005-05-17 2008-03-12 周兆弟 Elastic expanding joggle joint pile end plate, precast member and butt-jointing structure between the members
CN101787699A (en) * 2009-11-07 2010-07-28 广东三和管桩有限公司 Bolt fastening structure of pipe die
CN201581396U (en) * 2009-11-07 2010-09-15 广东三和管桩有限公司 Pipe die bolt connecting structure
CN104895052A (en) * 2015-06-25 2015-09-09 袁江 Rapid joint of precast concrete pile
CN204728315U (en) * 2015-06-25 2015-10-28 袁江 A kind of precast concrete pile snap joint

Also Published As

Publication number Publication date
CN105672308A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN105672308B (en) A kind of pile pile Quick connection part
CN103556624B (en) Adapter sleeve, to produce and method of attachment containing the prefabricated units of this adapter sleeve and prefabricated units
CN204266193U (en) Pile foundation steel bar cage locator
CN203569582U (en) Connecting structure of concrete pipe pile and bearing platform
CN103590414B (en) A kind of attachment structure of concrete tubular pile and cushion cap
CN106087984B (en) A kind of deformed bar cage and a kind of construction method of special-shaped uplift pile
CN102021908A (en) Mechanical connection structure and construction method for splicing precast square piles
CN104790388B (en) A kind of prefabricated pile mechanical connecting structure and attaching method thereof
CN205444968U (en) Bar planting anchor structure
CN111827279A (en) Sawtooth-shaped tubular pile quick connector
CN206957185U (en) External corner shear wall set buries screw rod and fixes suspension scaffold shaped steel connector
CN204626393U (en) For the pile extension assembly of concrete pile
CN205530240U (en) Tubular pile rapid connection means
CN104196023B (en) A kind of using method of the concrete precast pipe pile pile top of band mechanical connecting device
CN204385731U (en) Prestressed concrete pipe pile X-type pin connector
CN104372793A (en) Anti-floating method used for existing basement by adopting pre-stressed anchor cables in jet grouting pile method
CN104594343B (en) A kind of assembled stake and its construction method
CN207749816U (en) A kind of upright bar fixing piece
CN205530241U (en) From locking -type rapid connection means
CN109372284A (en) A kind of means to save the situation of broken stone bolt
CN211143495U (en) Connecting and fixing device for concrete filled steel tube column
CN107724384B (en) A pile-to-pile connection construction method
CN104975710A (en) Connecting method and connecting structure of scaffold and main body structure
CN203879398U (en) Drill rod of rotary drilling rig adopting threaded connection between core section rod pipe body and square head
CN206887936U (en) A kind of prefabricated pile and foundation connection structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20180918

Address after: 322100, 3, Chaoyang Road, Wu Ning street, Dongyang, Jinhua, Zhejiang, 3

Applicant after: Dongyang Ju ran Electronic Technology Co., Ltd.

Address before: 314300 three layers of 2 seawall Industrial Park, Xitang Bridge Street, Haiyan County, Jiaxing, Zhejiang.

Applicant before: JIAXING FAST HARDWARE CO., LTD.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190603

Address after: 314033 Zhenxing Road 796-2, Jiabei Street, Xiuzhou District, Jiaxing City, Zhejiang Province

Patentee after: Jiaxing Hangtai Precision Engineering Technology Co., Ltd.

Address before: 322100, 3, Chaoyang Road, Wu Ning street, Dongyang, Jinhua, Zhejiang, 3

Patentee before: Dongyang Ju ran Electronic Technology Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210409

Address after: 314300 Tuanjie group, xuyouche village, Qinshan street, Haiyan County, Jiaxing City, Zhejiang Province

Patentee after: HAIYAN HUARUISI FASTENER Co.,Ltd.

Address before: 314033 Zhenxing Road 796-2, Jiabei Street, Xiuzhou District, Jiaxing City, Zhejiang Province

Patentee before: Jiaxing Hangtai Precision Engineering Technology Co.,Ltd.

TR01 Transfer of patent right