CN105672208B - 用于拦断沟谷修建渣场的排水结构及其施工方法 - Google Patents
用于拦断沟谷修建渣场的排水结构及其施工方法 Download PDFInfo
- Publication number
- CN105672208B CN105672208B CN201610223338.2A CN201610223338A CN105672208B CN 105672208 B CN105672208 B CN 105672208B CN 201610223338 A CN201610223338 A CN 201610223338A CN 105672208 B CN105672208 B CN 105672208B
- Authority
- CN
- China
- Prior art keywords
- water discharge
- discharge tunnel
- river course
- tunnel
- branch hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B5/00—Artificial water canals, e.g. irrigation canals
- E02B5/02—Making or lining canals
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B5/00—Artificial water canals, e.g. irrigation canals
- E02B5/08—Details, e.g. gates, screens
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Barrages (AREA)
- Revetment (AREA)
Abstract
本发明涉及一种用于拦断沟谷修建渣场的排水结构及一种该排水结构的施工方法。用于拦断沟谷修建渣场的排水结构,包括沿河道宽度方向设置的挡水坝,河道沿岸还设有入口端与挡水坝上游河道连通、出口端与挡水坝下游河道连通的排水隧洞,排水隧洞的底板沿排水隧洞长度方向设有隔墙,使得排水隧洞形成两个过水通道,排水隧洞的入口端设置有闸室,闸室中设置有两道闸门,闸门与过水通道一一相对应,排水隧洞靠近河道一侧设有排水支洞,排水支洞的入口端连通于排水隧洞、出口端连通于河道,排水隧洞内设有可拆除的临时封堵体,临时封堵体配合设于排水支洞入口端的下游。
Description
技术领域
本发明涉及一种用于拦断沟谷修建渣场的排水结构及一种该排水结构的施工方法,属于水利水电工程领域。
背景技术
当前,我国水电建设主要集中在西部高山峡谷地区,修建水电建筑物时,需要大量的弃渣需要存放。在高山峡谷地区,可利用场地及其有限,一般需要存放在小型河道或沟道上,而被占用的河道或沟道一般有水流通过,因此,在存放弃渣之前需要进行沟水处理。在高山峡谷地区,沟水处理主要采取挡水坝拦断沟里的水流,再通过排水隧洞引走沟水的方式。
由于渣场具备堆渣条件之后,水利水电工程主体工程才具备施工条件。当排水隧洞较长,施工时间长时,其工期直接影响到主体工程的工期。如果能实现提前启用部分渣场,使水电项目具备提前局部施工条件,这将节约整个项目建设工期,尤其对建设工期紧迫的工程具有重要的意义。
发明内容
本发明所要解决的技术问题是:提供一种用于拦断沟谷修建渣场的排水结构,当排水隧洞长度长、施工周期过久时,可以提前启动使用渣场。
为解决上述技术问题本发明所采用的技术方案是:用于拦断沟谷修建渣场的排水结构,包括沿河道宽度方向设置的挡水坝,河道沿岸还设有入口端与挡水坝上游河道连通、出口端与挡水坝下游河道连通的排水隧洞,排水隧洞的底板沿排水隧洞长度方向设有隔墙,使得排水隧洞形成两个过水通道,排水隧洞的入口端设置有闸室,闸室中设置有两道闸门,闸门与过水通道一一相对应,排水隧洞靠近河道一侧设有排水支洞,排水支洞的入口端连通于排水隧洞、出口端连通于河道,排水隧洞内设有可拆除的临时封堵体,临时封堵体配合设于排水支洞入口端的下游。
进一步的是:隔墙垂直设置于排水隧洞底板的正中位置。
相应地,本发明还提供一种用于拦断沟谷修建渣场的排水结构施工方法,采用上述的用于拦断沟谷修建渣场的排水结构,施工步骤为:
A、修建排水支洞、排水隧洞设置临时封堵体的上游部分,并在排水隧洞设置临时封堵体,通过排水支洞、排水隧洞设置临时封堵体的上游部分过流;
B、修建挡水坝、排水隧洞设置临时封堵体的下游部分;
C、关闭闸室中远离河道一侧的闸门,使得水流从排水隧洞靠近河道一侧的过水通道及排水支洞通过;拆除排水隧洞中远离河道一侧的临时封堵体,使得排水隧洞远离河道一侧的过水通道连通;然后打开闸室中远离河道一侧的闸门,并关闭闸室中靠近河道一侧的闸门,使得水流从排水隧洞远离河道一侧的过水通道通过,拆除排水隧洞中靠近河道一侧的临时封堵体,使得排水隧洞靠近河道一侧的过水通道连通;在排水隧洞侧壁修建用于封堵排水支洞入口端的封堵体,整条排水隧洞完建,具备过流条件。
步骤C优选在枯水期进行。
本发明的有益效果是:实施时,通过排水支洞、排水隧洞设置临时封堵体的上游部分过流时,挡水坝及排水支洞之间的河道或沟道部分即可堆渣,提前启用该部分渣场;排水支洞前期可以作为施工支洞,加快排水隧洞施工进度,实现一洞多用的效果。
附图说明
图1为本发明的平面图;
图2为排水隧洞入口端的局部视图;
图3为排水支洞入口端的局部视图;
图中标记:1-挡水坝、2-排水隧洞、3-隔墙、4-闸室、5-闸门、6-排水支洞、7-临时封堵体、8-封堵体。
具体实施方式
为便于理解和实施本发明,选本发明的优选实施例结合附图作进一步说明。
如图1~图3所示,本发明包括沿河道宽度方向设置的挡水坝1,河道沿岸还设有入口端与挡水坝1上游河道连通、出口端与挡水坝1下游河道连通的排水隧洞2,排水隧洞2的底板沿排水隧洞2长度方向设有隔墙3,使得排水隧洞2形成两个过水通道,排水隧洞2的入口端设置有闸室4,闸室4中设置有两道闸门5,闸门5与过水通道一一相对应,排水隧洞2靠近河道一侧设有排水支洞6,排水支洞6的入口端连通于排水隧洞2、出口端连通于河道,排水隧洞2内设有可拆除的临时封堵体7,临时封堵体7配合设于排水支洞6入口端的下游。
优选地,隔墙3垂直设置于排水隧洞2底板的正中位置,使得两个过水通道的流量相同,结构更合理。而隔墙2高度可根据枯水期流量确定,应使得隔墙2一侧能满足枯水期过流要求。临时封堵体7设于排水支洞6入口端的下游,距离排水支洞6入口端有一段距离,以调整排水隧洞2进入排水支洞6水流的流态。
排水支洞6布置应满足排水支洞6出口端与挡水坝1之间沟道范围满足前期堆渣要求,并尽量缩短排水隧洞2上半部分长度及排水支洞6长度。排水支洞6在排水隧洞2设置临时封堵体7的上游部分施工时,可以作为施工支洞,加快排水隧洞施工进度,实现一洞多用的效果。
对于该排水结构的施工方法,施工步骤为:
A、修建排水支洞6、排水隧洞2设置临时封堵体7的上游部分,并在排水隧洞2设置临时封堵体7,通过排水支洞6、排水隧洞2设置临时封堵体7的上游部分过流;
B、修建挡水坝1、排水隧洞2设置临时封堵体7的下游部分;
C、关闭闸室4中远离河道一侧的闸门5,使得水流从排水隧洞2靠近河道一侧的过水通道及排水支洞6通过;拆除排水隧洞2中远离河道一侧的临时封堵体7,使得排水隧洞2远离河道一侧的过水通道连通;然后打开闸室4中远离河道一侧的闸门5,并关闭闸室4中靠近河道一侧的闸门5,使得水流从排水隧洞2远离河道一侧的过水通道通过,拆除排水隧洞2中靠近河道一侧的临时封堵体7,使得排水隧洞2靠近河道一侧的过水通道连通;在排水隧洞2侧壁修建用于封堵排水支洞6入口端的封堵体8,整条排水隧洞2完建具备过流条件。
步骤C优选在枯水期进行。这样可以减小隔墙及隧洞规模,节约施工成本。
Claims (4)
1.用于拦断沟谷修建渣场的排水结构,包括沿河道宽度方向设置的挡水坝(1),其特征在于:河道沿岸还设有入口端与挡水坝(1)上游河道连通、出口端与挡水坝(1)下游河道连通的排水隧洞(2),排水隧洞(2)的底板沿排水隧洞(2)长度方向设有隔墙(3),使得排水隧洞(2)形成两个过水通道,排水隧洞(2)的入口端设置有闸室(4),闸室(4)中设置有两道闸门(5),闸门(5)与过水通道一一相对应,排水隧洞(2)靠近河道一侧设有排水支洞(6),排水支洞(6)的入口端连通于排水隧洞(2)、出口端连通于河道,排水隧洞(2)内设有可拆除的临时封堵体(7),临时封堵体(7)配合设于排水支洞(6)入口端的下游。
2.如权利要求1所述的用于拦断沟谷修建渣场的排水结构,其特征在于:隔墙(3)垂直设置于排水隧洞(2)底板的正中位置。
3.用于拦断沟谷修建渣场的排水结构施工方法,其特征在于:采用如权利要求1或2所述的用于拦断沟谷修建渣场的排水结构,施工步骤为:
A、修建排水支洞(6)、排水隧洞(2)设置临时封堵体(7)的上游部分,并在排水隧洞(2)设置临时封堵体(7),通过排水支洞(6)、排水隧洞(2)设置临时封堵体(7)的上游部分过流;
B、修建挡水坝(1)、排水隧洞(2)设置临时封堵体(7)的下游部分;
C、关闭闸室(4)中远离河道一侧的闸门(5),使得水流从排水隧洞(2)靠近河道一侧的过水通道及排水支洞(6)通过;拆除排水隧洞(2)中远离河道一侧的临时封堵体(7),使得排水隧洞(2)远离河道一侧的过水通道连通;然后打开闸室(4)中远离河道一侧的闸门(5),并关闭闸室(4)中靠近河道一侧的闸门(5),使得水流从排水隧洞(2)远离河道一侧的过水通道通过,拆除排水隧洞(2)中靠近河道一侧的临时封堵体(7),使得排水隧洞(2)靠近河道一侧的过水通道连通;在排水隧洞(2)侧壁修建用于封堵排水支洞(6)入口端的封堵体(8),整条排水隧洞(2)完建具备过流条件。
4.如权利要求3所述的用于拦断沟谷修建渣场的排水结构施工方法,其特征在于:步骤C在枯水期进行。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610223338.2A CN105672208B (zh) | 2016-04-12 | 2016-04-12 | 用于拦断沟谷修建渣场的排水结构及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610223338.2A CN105672208B (zh) | 2016-04-12 | 2016-04-12 | 用于拦断沟谷修建渣场的排水结构及其施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105672208A CN105672208A (zh) | 2016-06-15 |
CN105672208B true CN105672208B (zh) | 2017-07-07 |
Family
ID=56310198
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610223338.2A Active CN105672208B (zh) | 2016-04-12 | 2016-04-12 | 用于拦断沟谷修建渣场的排水结构及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105672208B (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107165129A (zh) * | 2017-07-19 | 2017-09-15 | 中国电建集团成都勘测设计研究院有限公司 | 峡谷区高坝水电工程渣场沟水导流系统 |
CN107858990B (zh) * | 2017-12-13 | 2023-09-01 | 中国电建集团成都勘测设计研究院有限公司 | 峡谷区高坝沟水处理工程的布置结构的导流施工方法 |
CN109356097B (zh) * | 2018-11-29 | 2023-09-19 | 中国电建集团成都勘测设计研究院有限公司 | 用于沟水处理的排水隧洞进口结构 |
CN110258476A (zh) * | 2019-06-26 | 2019-09-20 | 中国电建集团成都勘测设计研究院有限公司 | 高山峡谷地区水电站沟水处理用排水洞结构 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105369784A (zh) * | 2015-11-27 | 2016-03-02 | 中国电建集团成都勘测设计研究院有限公司 | 沟水处理排水洞结构和沟水处理排水方法 |
CN105421296A (zh) * | 2015-12-29 | 2016-03-23 | 中国电建集团成都勘测设计研究院有限公司 | 用于沟水处理的排水隧洞及检修方法 |
CN205134292U (zh) * | 2015-11-24 | 2016-04-06 | 中国电建集团成都勘测设计研究院有限公司 | 高拱坝施工导流洞结构 |
CN205501940U (zh) * | 2016-04-12 | 2016-08-24 | 中国电建集团成都勘测设计研究院有限公司 | 用于拦断沟谷修建渣场的排水结构 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3073705B2 (ja) * | 1997-04-04 | 2000-08-07 | 株式会社ホクコン | 排水ブロック |
-
2016
- 2016-04-12 CN CN201610223338.2A patent/CN105672208B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205134292U (zh) * | 2015-11-24 | 2016-04-06 | 中国电建集团成都勘测设计研究院有限公司 | 高拱坝施工导流洞结构 |
CN105369784A (zh) * | 2015-11-27 | 2016-03-02 | 中国电建集团成都勘测设计研究院有限公司 | 沟水处理排水洞结构和沟水处理排水方法 |
CN105421296A (zh) * | 2015-12-29 | 2016-03-23 | 中国电建集团成都勘测设计研究院有限公司 | 用于沟水处理的排水隧洞及检修方法 |
CN205501940U (zh) * | 2016-04-12 | 2016-08-24 | 中国电建集团成都勘测设计研究院有限公司 | 用于拦断沟谷修建渣场的排水结构 |
Also Published As
Publication number | Publication date |
---|---|
CN105672208A (zh) | 2016-06-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105672208B (zh) | 用于拦断沟谷修建渣场的排水结构及其施工方法 | |
CN103410130B (zh) | 一种多用途隧洞布置结构 | |
CN203846465U (zh) | 放空洞或非常泄洪洞布置系统 | |
CN106930262B (zh) | 省水池重叠高水头船闸 | |
CN109356128A (zh) | 一种单引水隧洞水电工程启闭机的布置结构 | |
CN105951689B (zh) | 一种水库预泄兼生态流量下泄结构 | |
CN205712455U (zh) | 市政排水管网或者排水河道中智能冲洗拦蓄液压闸 | |
CN203320497U (zh) | 一种电站的尾水检修闸门 | |
CN205501940U (zh) | 用于拦断沟谷修建渣场的排水结构 | |
CN205501944U (zh) | 适用于高拱坝的向下游供水结构 | |
CN106759161B (zh) | 一种大断面导流洞分期封堵结构及施工方法 | |
CN108677892A (zh) | 导流洞施工支洞用作生态供水洞的改造结构 | |
CN202440787U (zh) | 一种河道导流装置 | |
CN207092033U (zh) | 一种泄洪洞 | |
CN110685256B (zh) | 水电站压力管道施工支洞用作检修通道的结构及施工方法 | |
CN201978546U (zh) | 巷道通过式井下水沉淀系统 | |
CN209836952U (zh) | 一种混凝土坝蓄水期临时下放生态流量的装置 | |
CN104005387A (zh) | 放空洞或非常泄洪洞布置系统及其开启和关闭的方法 | |
CN206189365U (zh) | 用于导流洞封堵体浇筑的导流封堵结构 | |
CN109853490A (zh) | 一种混凝土坝蓄水期临时下放生态流量的方法与装置 | |
CN110258474A (zh) | 可用于特高堆石坝主汛期度汛的生态导流洞结构 | |
CN206680969U (zh) | 一种利用现有封堵闸门下泄生态流量的装置 | |
CN208965520U (zh) | 导流洞施工支洞用作生态供水洞的改造结构 | |
CN102505671B (zh) | 用于多条引水隧洞的上跨式检修通道 | |
CN206157701U (zh) | 一种通航建筑物的输水兼消能结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |