CN105672143A - 一种更新管线桥架结构的施工方法 - Google Patents

一种更新管线桥架结构的施工方法 Download PDF

Info

Publication number
CN105672143A
CN105672143A CN201610046490.8A CN201610046490A CN105672143A CN 105672143 A CN105672143 A CN 105672143A CN 201610046490 A CN201610046490 A CN 201610046490A CN 105672143 A CN105672143 A CN 105672143A
Authority
CN
China
Prior art keywords
crane span
original
span structure
paragraph
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610046490.8A
Other languages
English (en)
Other versions
CN105672143B (zh
Inventor
周文杰
梁海健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Chenyu Electric Power Technology Co., Ltd.
Original Assignee
Guangdong Chenyu Electric Power Design Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Chenyu Electric Power Design Consulting Co Ltd filed Critical Guangdong Chenyu Electric Power Design Consulting Co Ltd
Priority to CN201610046490.8A priority Critical patent/CN105672143B/zh
Publication of CN105672143A publication Critical patent/CN105672143A/zh
Application granted granted Critical
Publication of CN105672143B publication Critical patent/CN105672143B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D18/00Bridges specially adapted for particular applications or functions not provided for elsewhere, e.g. aqueducts, bridges for supporting pipe-lines

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Jib Cranes (AREA)

Abstract

本发明公开了一种更新管线桥架结构的施工方法。该施工方法通过合理安排施工顺序,采用逐步加长、拖拉和拆除的原理,实现了分步地由新结构构件替换原有桥架的结构构件,最终实现整个桥架结构的替换;在此过程中,无需中断桥架所承载的管线的正常运行,亦无需在桥架下设置临时支架,大大降低了对正常生产和生活的影响,具有良好的社会及经济效益。

Description

一种更新管线桥架结构的施工方法
技术领域
本发明涉及一种施工方法,具体是一种更新管线桥架结构的施工方法。
背景技术
钢桁架结构具有刚度大,重量轻,节省材料等优点,常被应用于承载电缆、管线等设备跨越河道、道路的工程中。但现有桁架结构的桥架在设计时未考虑自身结构的更新问题。若在使用过程中出现结构问题,需要对结构进行替换,只能采用整体更换的办法,即先关停并拆除桥架上承载的管线,再整体拆除旧桥架结构,然后安装新的桥架结构,最后重新安装管线。造成传统桁架结构桥架上述缺点的原因在于通常将桥架结构设计成整体式,包括弦杆、腹杆、节点、横向系杆等均用焊接或螺栓连接成整体,并通过支座固定于基础之上,造成结构只能整体安装、拆卸。在整体更换桥架结构的期间,桥架上的管线自始至终需要停运,对正常生产活动造成严重影响。特别是电网上用于承载电缆的桥架,更换桥架结构期间拆除大量的电缆不但施工极其困难,还将造成长时间、大面积的停电,对社会及经济秩序造成重大影响。
发明内容
本发明的目的在于提供一种更新管线桥架结构的施工方法,以解决上述背景技术中提出的问题。
为实现上述目的,本发明提供如下技术方案:
一种更新管线桥架结构的施工方法,具体步骤如下:
(1)拆除桥架与管线间的连接固定装置;
(2)在原有桥架结构的一侧,安装一段或数段新的桁架下弦杆、上弦杆、腹杆及上部横向系杆;
(3)拆除桥架两侧支座上的约束装置,拆除桥架另一侧的原有桥架第一段的下部横向系杆;
(4)由拖拉设备或顶推设备将桥架整体向另一侧拖拉或顶推,使桥架原有结构的第一段移出结构跨内,而新安装的一段新桁架结构移入到结构跨内;
(5)安装已进入结构跨内的第一段新桥架下部横向系杆;
(6)拆除已移出的原有结构跨内第一段的其他结构杆件,至此完成一个替换循环,如此不断重复,即可在逐步替换原有结构的过程中,最终完成桁架结构整体的替换。
作为本发明进一步的方案:在第一段新桁架结构与旧桁架结构之间增加过度构件。
与现有技术相比,本发明的有益效果是:该发明通过合理安排施工顺序,采用逐步加长、拖拉和拆除的原理,实现了分步地由新结构构件替换原有桥架的结构构件,最终实现整个桥架结构的替换;在此过程中,无需中断桥架所承载的管线的正常运行,亦无需在桥架下设置临时支架,大大降低了对正常生产和生活的影响,具有良好的社会及经济效益。
附图说明
图1为更新管线桥架结构的施工方法的主视图。
图2为更新管线桥架结构的施工方法的侧视图。
其中:1-原有桥架,2-移出后拆除的原有桥架节段,3-原有桥架下部横向系杆,4-新桥架弦杆,5-新桥架腹杆,6-新桥架上部横向系杆,7-新桥架下部横向系杆,8-支座,9-管线,10-桥架与管线间的连接固定装置。
具体实施方式
下面结合具体实施方式对本专利的技术方案作进一步详细地说明。
请参阅图1-2,一种更新管线桥架结构的施工方法,具体步骤如下:
(1)拆除桥架与管线间的连接固定装置10;
(2)在原有桥架1结构的一侧,安装一段或数段新桥架弦杆4、新桥架腹杆5及新桥架上部横向系杆6;
(3)拆除桥架两侧支座8上的约束装置,拆除桥架另一侧的原有桥架下部横向系杆3;
(4)由拖拉设备或顶推设备将桥架整体向另一侧拖拉或顶推,使桥架原有结构的第一段移出结构跨内,而新安装的一段新桁架结构移入到结构跨内;
(5)安装已进入结构跨内的第一段新桥架下部横向系杆7;
(6)拆除已移出的原有结构跨内第一段的其他结构杆件,至此完成一个替换循环,如此不断重复,即可在逐步替换原有结构的过程中,最终完成桁架结构整体的替换。
该施工方法具有以下优点:该发明通过合理安排施工顺序,采用逐步加长、拖拉和拆除的原理,实现了分步地由新结构构件替换原有桥架的结构构件,最终实现整个桥架结构的替换;在此过程中,无需中断桥架所承载的管线9的正常运行,亦无需在桥架下设置临时支架,大大降低了对正常生产和生活的影响,具有良好的社会及经济效益。
上面对本专利的较佳实施方式作了详细说明,但是本专利并不限于上述实施方式,在本领域的普通技术人员所具备的知识范围内,还可以在不脱离本专利宗旨的前提下做出各种变化。

Claims (2)

1.一种更新管线桥架结构的施工方法,其特征在于,具体步骤如下:
(1)拆除桥架与管线间的连接固定装置;
(2)在原有桥架结构的一侧,安装一段或数段新的桁架下弦杆、上弦杆、腹杆及上部横向系杆;
(3)拆除桥架两侧支座上的约束装置,拆除桥架另一侧的原有桥架第一段的下部横向系杆;
(4)由拖拉设备或顶推设备将桥架整体向另一侧拖拉或顶推,使桥架原有结构的第一段移出结构跨内,而新安装的一段新桁架结构移入到结构跨内;
(5)安装已进入结构跨内的第一段新桥架下部横向系杆;
(6)拆除已移出的原有结构跨内第一段的其他结构杆件,至此完成一个替换循环,如此不断重复,即可在逐步替换原有结构的过程中,最终完成桁架结构整体的替换。
2.根据权利要求1所述的更新管线桥架结构的施工方法,其特征在于,在第一段新桁架结构与旧桁架结构之间增加过度构件。
CN201610046490.8A 2016-01-22 2016-01-22 一种更新管线桥架结构的施工方法 Active CN105672143B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610046490.8A CN105672143B (zh) 2016-01-22 2016-01-22 一种更新管线桥架结构的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610046490.8A CN105672143B (zh) 2016-01-22 2016-01-22 一种更新管线桥架结构的施工方法

Publications (2)

Publication Number Publication Date
CN105672143A true CN105672143A (zh) 2016-06-15
CN105672143B CN105672143B (zh) 2017-03-08

Family

ID=56302315

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610046490.8A Active CN105672143B (zh) 2016-01-22 2016-01-22 一种更新管线桥架结构的施工方法

Country Status (1)

Country Link
CN (1) CN105672143B (zh)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200961750Y (zh) * 2006-11-06 2007-10-17 广东省电力设计研究院 电缆桥架敷设用组合式支架
KR20090076593A (ko) * 2008-01-09 2009-07-13 명보산공 주식회사 가교 및 강재교량 구조물의 처짐 방지 구조
CN102747691A (zh) * 2012-08-02 2012-10-24 中铁二十三局集团有限公司 桁架梁整体顶推架设方法
CN202985470U (zh) * 2012-11-21 2013-06-12 上海宝冶集团有限公司 电缆桥架用活动式更换装置
CN203795295U (zh) * 2014-04-02 2014-08-27 中交第二航务工程勘察设计院有限公司 下承式三角桁架外挂带缆通道钢桥
CN104328734A (zh) * 2013-07-22 2015-02-04 中铁工程设计咨询集团有限公司 一种多联多跨连续钢桁梁桥及其施工方法
CN105002836A (zh) * 2015-07-27 2015-10-28 丁洪华 一种原位快速更换拱桥系杆的施工方法
CN105155418A (zh) * 2015-08-16 2015-12-16 腾达建设集团股份有限公司 一种桥梁平移的施工方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200961750Y (zh) * 2006-11-06 2007-10-17 广东省电力设计研究院 电缆桥架敷设用组合式支架
KR20090076593A (ko) * 2008-01-09 2009-07-13 명보산공 주식회사 가교 및 강재교량 구조물의 처짐 방지 구조
CN102747691A (zh) * 2012-08-02 2012-10-24 中铁二十三局集团有限公司 桁架梁整体顶推架设方法
CN202985470U (zh) * 2012-11-21 2013-06-12 上海宝冶集团有限公司 电缆桥架用活动式更换装置
CN104328734A (zh) * 2013-07-22 2015-02-04 中铁工程设计咨询集团有限公司 一种多联多跨连续钢桁梁桥及其施工方法
CN203795295U (zh) * 2014-04-02 2014-08-27 中交第二航务工程勘察设计院有限公司 下承式三角桁架外挂带缆通道钢桥
CN105002836A (zh) * 2015-07-27 2015-10-28 丁洪华 一种原位快速更换拱桥系杆的施工方法
CN105155418A (zh) * 2015-08-16 2015-12-16 腾达建设集团股份有限公司 一种桥梁平移的施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吕国良: "《三桁刚性悬索桁架桥施工控制研究》", 21 September 2009 *

Also Published As

Publication number Publication date
CN105672143B (zh) 2017-03-08

Similar Documents

Publication Publication Date Title
CN106702909A (zh) 一种双幅钢箱梁整体转体结构及施工方法
CN204474178U (zh) 一种缆索起重机
CN110629681A (zh) 一种多跨钢箱梁施工工艺
CN105672143A (zh) 一种更新管线桥架结构的施工方法
CN107297579A (zh) 一塔式脱硫再生塔施工方法
CN203065965U (zh) 一种可自拆换车架的桥梁检查车
CN105714691A (zh) 一种曲线矮塔斜拉桥挂篮交错布置及横移施工方法
CN106185616A (zh) 一种车载便携式卸轨龙门架及其施工方法
CN103825222B (zh) 一种带电更换220kV窄基塔耐张绝缘子串用工具
CN105984821A (zh) 一种按需使用的风电机组舱内起吊装置
CN102877480B (zh) 环形桁架的安装方法
CN205152818U (zh) 一种桥梁整体横移换梁系统
CN205329558U (zh) 一种无拆卸变跨式架板机
CN202643859U (zh) 铝导杆移动升降台车
CN209384030U (zh) 一种地铁龙门吊可拆卸轨道板结构
CN103074849B (zh) 一种可自拆换车架的桥梁检查车
CN205472264U (zh) 一种拆除立式泵联轴器的工具
CN211449868U (zh) 一种用于管道安装的穿管装置
CN204000603U (zh) 一种大桥检修吊篮专用悬挂机构
CN220150180U (zh) 一种渐变格构式背楞防撞墙钢模板
CN210212114U (zh) 一种有轨电车接触网支柱抢修装置
CN213804836U (zh) 一种安全环保型基坑内大跨度悬空管线防护组件
CN108910693B (zh) 一种行车梁及其使用方法
CN203781736U (zh) 辊道的辊子更换装置
CN202559823U (zh) 电力转角塔拉腿主材更换用主材卡具

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 528200 Unit 808, 8th Floor, Building 6, Area A, Hantian Science and Technology City, 17 Shenhai Road, Guicheng Street, Nanhai District, Foshan City, Guangdong Province

Patentee after: Guangdong Chenyu Electric Power Technology Co., Ltd.

Address before: Unit 528000 of Guangdong Province, Nanhai District of Foshan city streets Guicheng deep sea No. 17 Han day science and technology city A District No. 6 Building 804, 808

Patentee before: GUANGDONG CHENYU ELECTRIC POWER DESIGN CONSULTING CO., LTD.

CP03 Change of name, title or address