CN105672137A - Bridge pier body reinforcement construction method and reinforcement frameworks - Google Patents
Bridge pier body reinforcement construction method and reinforcement frameworks Download PDFInfo
- Publication number
- CN105672137A CN105672137A CN201610163800.4A CN201610163800A CN105672137A CN 105672137 A CN105672137 A CN 105672137A CN 201610163800 A CN201610163800 A CN 201610163800A CN 105672137 A CN105672137 A CN 105672137A
- Authority
- CN
- China
- Prior art keywords
- steel reinforcement
- framework
- pier body
- reinforcing bar
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610163800.4A CN105672137B (en) | 2016-03-22 | 2016-03-22 | A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610163800.4A CN105672137B (en) | 2016-03-22 | 2016-03-22 | A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105672137A true CN105672137A (en) | 2016-06-15 |
CN105672137B CN105672137B (en) | 2018-04-13 |
Family
ID=56311331
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610163800.4A Active CN105672137B (en) | 2016-03-22 | 2016-03-22 | A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105672137B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109322248A (en) * | 2018-10-12 | 2019-02-12 | 中铁隧道集团二处有限公司 | A kind of Bridge Piers bar reinforcement positioning device and installation method |
CN113668387A (en) * | 2021-07-08 | 2021-11-19 | 中交路桥建设有限公司 | Modularized construction method for pier body reinforcing steel bars |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003239455A (en) * | 2002-02-18 | 2003-08-27 | Kyushu Univ | Concrete support |
CN101929249A (en) * | 2010-08-10 | 2010-12-29 | 中铁一局集团有限公司 | Double line stream-line type round end entity pier cap steel bar overall binding construction method |
CN203420229U (en) * | 2013-09-05 | 2014-02-05 | 中铁上海工程局有限公司 | Positioner for reinforcement framework of round-ended solid pier body |
CN104404883A (en) * | 2014-11-19 | 2015-03-11 | 中交四航局第三工程有限公司 | Inner working platform for rapid construction of bridge pier and construction method using inner working platform |
CN204266115U (en) * | 2014-12-03 | 2015-04-15 | 中铁上海工程局有限公司 | Round end type entity pier shaft clad steel muscle colligation auxiliary positioning mould |
CN105220619A (en) * | 2015-10-12 | 2016-01-06 | 中铁城建集团第二工程有限公司 | A kind of method of quick manufacture two-wire nose circle solid pier |
-
2016
- 2016-03-22 CN CN201610163800.4A patent/CN105672137B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003239455A (en) * | 2002-02-18 | 2003-08-27 | Kyushu Univ | Concrete support |
CN101929249A (en) * | 2010-08-10 | 2010-12-29 | 中铁一局集团有限公司 | Double line stream-line type round end entity pier cap steel bar overall binding construction method |
CN203420229U (en) * | 2013-09-05 | 2014-02-05 | 中铁上海工程局有限公司 | Positioner for reinforcement framework of round-ended solid pier body |
CN104404883A (en) * | 2014-11-19 | 2015-03-11 | 中交四航局第三工程有限公司 | Inner working platform for rapid construction of bridge pier and construction method using inner working platform |
CN204266115U (en) * | 2014-12-03 | 2015-04-15 | 中铁上海工程局有限公司 | Round end type entity pier shaft clad steel muscle colligation auxiliary positioning mould |
CN105220619A (en) * | 2015-10-12 | 2016-01-06 | 中铁城建集团第二工程有限公司 | A kind of method of quick manufacture two-wire nose circle solid pier |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109322248A (en) * | 2018-10-12 | 2019-02-12 | 中铁隧道集团二处有限公司 | A kind of Bridge Piers bar reinforcement positioning device and installation method |
CN113668387A (en) * | 2021-07-08 | 2021-11-19 | 中交路桥建设有限公司 | Modularized construction method for pier body reinforcing steel bars |
Also Published As
Publication number | Publication date |
---|---|
CN105672137B (en) | 2018-04-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105113389B (en) | Assembled type bridge pier column member with steel-concrete composite structure | |
CN104746422B (en) | A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method | |
CN102767141B (en) | Construction method for huge capping beam utilizing reinforced concrete thin wall as permanent formwork | |
CN103850363B (en) | Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall | |
WO2020001156A1 (en) | Bridge and bridge pier thereof | |
CN108049305A (en) | The splicing construction and joining method of a kind of precast pier and prefabricated cushion cap | |
CN203270457U (en) | Suspension bar anchoring structure capable of initiatively reinforcing concrete tied-arch bridge | |
CN202466845U (en) | Middle-layer node connecting structure for steel tube concrete column and steel reinforced concrete beam | |
CN103726589A (en) | H-shaped steel and steel pipe framework assembly shear wall with protruding interfaces and bent steel bars and manufacturing method | |
CN103603435A (en) | Assembled concrete seismic beam-column frame and construction method thereof | |
CN103410090B (en) | A kind of suspension rod anchoring structure of active enforcement concrete bowstring arch bridge and construction method thereof | |
CN105672137A (en) | Bridge pier body reinforcement construction method and reinforcement frameworks | |
CN103938871A (en) | Method for constructing concrete-filled steel tube column and bonded prestressed frame beam structure adopting reinforced concrete ring beam joints | |
CN103924676B (en) | Prestressing force connects beams of concrete concrete-filled circular steel tube column node | |
CN103422436B (en) | Construction method for utilizing corrugated steel webs to bear construction load | |
CN201972095U (en) | Chain block lifting platform for thin-walled hollow piers of bridges | |
CN109267489B (en) | Construction method for cable-stayed bridge cable tower anchoring area | |
CN208668249U (en) | A kind of connecting structure of prefabricated bent cap and Precast Pier Columns | |
CN206646392U (en) | A kind of modular bridge structure | |
CN205369005U (en) | Joint construction of annular cross -section prefabricating bridge pier and cushion cap | |
CN103921347A (en) | Thrusting type fixing and mounting formwork for prefabricated T-beam ribbed plate rebars and prestressed pipes | |
CN205382595U (en) | Integral shear force wall of steel pipe concrete edge constraint coincide | |
CN205501803U (en) | Framework of steel reinforcement of pier pier shaft reinforcing bar | |
CN104453013A (en) | Prefabricated wall component and fabricated reinforced concrete shear wall | |
CN203765784U (en) | Fixed drawing-inserting type installing mould frame for prefabricated T-beam rib plate reinforcing steel bar and pre-stressed pipeline |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information |
Inventor after: Yan Lizhong Inventor after: Zhang Guangping Inventor after: Li Jinbao Inventor after: Pang Xihai Inventor after: Ren Hongzhuan Inventor after: Guo Zhaohui Inventor after: Wang Hongjin Inventor after: Zhong Gaojie Inventor after: Hu Xiaojun Inventor after: Cao Jianqiu Inventor before: Li Jinbao Inventor before: Ren Hongzhuan Inventor before: Guo Zhaohui Inventor before: Wang Hongjin Inventor before: Zhong Gaojie Inventor before: Hu Xiaojun Inventor before: Cao Jianqiu Inventor before: He Lei Inventor before: Wang Yong |
|
COR | Change of bibliographic data | ||
GR01 | Patent grant | ||
GR01 | Patent grant |