CN105649086B - Deep inverse formula construction method after a kind of underground concrete structure is first shallow - Google Patents

Deep inverse formula construction method after a kind of underground concrete structure is first shallow Download PDF

Info

Publication number
CN105649086B
CN105649086B CN201410628728.9A CN201410628728A CN105649086B CN 105649086 B CN105649086 B CN 105649086B CN 201410628728 A CN201410628728 A CN 201410628728A CN 105649086 B CN105649086 B CN 105649086B
Authority
CN
China
Prior art keywords
shallow
foundation
deep
concrete
base plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410628728.9A
Other languages
Chinese (zh)
Other versions
CN105649086A (en
Inventor
于淼
朱庭贵
姜启元
李朝
刘桥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201410628728.9A priority Critical patent/CN105649086B/en
Publication of CN105649086A publication Critical patent/CN105649086A/en
Application granted granted Critical
Publication of CN105649086B publication Critical patent/CN105649086B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

Deep inverse formula construction method after a kind of underground concrete structure is first shallow, it is characterised in that comprise the following steps:A excavates adjacent shallow foundation hole(2), shallow foundation hole of only constructing(2)The shallow foundations such as concrete foundation base plate, b are cheated(2)Concrete foundation base plate, reaches deep pit excavation after some strength(1), the step absolute altitude of two grades of slopes of deep basal pit is positioned at shallow foundation hole bottom elevation location, c deep basal pits(1)Excavate simultaneously, in the shallow foundation hole constructed(2)Concrete foundation base plate, after the completion of d deep basal pits are poured, starts construction shallow foundation hole(2)The top of concrete foundation base plate, in shallow foundation hole(2)The elements of a fix are remeasured on concrete foundation base plate, then the elements of a fix to deep basal pit top concrete structure remeasure unwrapping wire, correction in time and correction when the elements of a fix of deep basal pit top concrete structure are made.The present invention is perfectly safe with deep basal pit, it is ensured that shallow foundation quality is unaffected and engineering is more economical, more efficiently advantage.

Description

Deep inverse formula construction method after a kind of underground concrete structure is first shallow
Technical field
It is a kind of underground concrete structure specifically the present invention relates to a kind of construction method on buried concrete basis Deep inverse formula construction method after first shallow.
Background technology
Underground concrete structure or Equipment Foundations etc., sequence of construction definitely must be shallow after first depth, i.e., first construct adjacent Deep basal pit, shallower foundation ditch of then constructing again, the main cause of do so is:
1st, because underground water and complicated geology etc. need to take the series of measures such as base pit dewatering, supporting, maintenance, therefore foundation ditch is deeper Construction is more difficult, and foundation ditch is more deep more dangerous, so deep basal pit first arranges construction as usual;
If shallow foundation the 2nd, is first constructed, then deep base of constructing, due to deep basal pit heavy excavation, the shallow foundation constructed certainly will be caused (Structure)It is subjected to displacement and differential settlement, until heavy damage.
Due to above-mentioned main cause, in order to reduce construction risk, arrange shallow after first depth, but due to not going out figure order not Match somebody with somebody, or procedure arrangement is difficult and deep foundation pit support condition is not in place the special circumstances such as needs to wait for, and is accomplished by try to meet the deadline for the project Deep inverse formula construction method after a kind of underground concrete structure is first shallow.
The content of the invention
The purpose of the present invention, is a kind of inverse formula of the first shallow rear depth of underground concrete structure for proposing that deep basal pit is perfectly safe Construction method.
It is another object of the present invention to propose a kind of to ensure that the shallow foundation quality first constructed is unaffected(I.e. center, mark It is high to meet code requirement)Underground concrete structure it is first shallow after deep inverse formula construction method.
A further object of the present invention, be propose it is a kind of more economical, deep after more efficiently underground concrete structure is first shallow Inverse formula construction method.
To achieve the above object, technical solution of the invention is:
Deep inverse formula construction method after a kind of underground concrete structure is first shallow, it is characterised in that comprise the following steps:
The adjacent shallow foundation hole of a, excavation, only construction shallow foundation hole concrete foundation base plate, or column foundation cushion cap is not constructed and is arrived The superstructure in shallow foundation hole;The concrete foundation base plate, or column foundation cushion cap has been poured during conserving after concrete and not torn open Mould, as the stabilising system in deep foundation pit slope, consolidates excavation slope;
B, etc. shallow foundation hole concrete foundation base plate, or column foundation cushion cap poured after 4 angel's concrete reach some strength, Deep pit excavation, shallow foundation hole bottom elevation location is positioned at by the step absolute altitude of two grades of slopes of deep basal pit;
C, deep pit digging simultaneously, cloth on concrete foundation base plate, or column foundation cushion cap are cheated in the shallow foundation constructed If displacement and settlement monitoring point, it is monitored by " the pit retaining monitoring scheme " separately worked out, to control deep pit construction During to shallow foundation hole coordinate influence degree;
After the completion of d, deep basal pit are poured, start the top that construction shallow foundation cheats concrete foundation base plate, or column foundation cushion cap Top, but must first be in shallow foundation hole concrete foundation base plate, or column foundation cushion cap on remeasure the elements of a fix, then The elements of a fix to deep basal pit top concrete structure remeasure unwrapping wire, when with shallow foundation cheat concrete foundation base plate, Huo Zhezhu When the former coordinate of foundation platform has off normal, correction in time and correction when the elements of a fix of deep basal pit top concrete structure are made.
Deep inverse formula construction method can also use following technical measures after underground concrete structure of the invention is first shallow Further to realize.
Foregoing method, wherein the off normal of the former coordinate includes center, absolute altitude deviation.
After adopting the above technical scheme, inverse formula construction method deep after underground concrete structure of the invention is first shallow with Lower advantage:
1st, deep basal pit is perfectly safe;
2nd, ensure that the shallow foundation quality first constructed is unaffected(I.e. center, absolute altitude etc. meet code requirement);
3rd, engineering is more economical, faster.
Brief description of the drawings
Fig. 1 is basic arranged in parallel for two different levels of the embodiment of the present invention, and shallow foundation cushion cap is constructed in advance, with it Bottom surface as deep basal pit classification step structural representation.
In figure:1 deep basal pit, 2 shallow foundations hole, 3 column foundation cushion caps.
Specific embodiment
With reference to embodiments and its accompanying drawing to the present invention illustrate further.
Embodiment 1
Deep inverse formula construction method after underground concrete structure of the invention is first shallow, it is mixed for the underground for having engineering pile load-bearing Xtah Crude Clay structure, it is characterised in that comprise the following steps:
A, first excavate adjacent shallow foundation hole 2, but the substructure that can only construct column foundation cushion cap 3, it is impossible to construction to top Structure, bottom poured during conserving after concrete should not form removal, it is overall as the stabilising system in deep foundation pit slope, consolidate base Hole side slope.
B, treat that 4 days or so concrete reach some strength, piping lane deep basal pit is excavated, by 1 two grades of slopes of piping lane deep basal pit Step absolute altitude is positioned at shallow foundation and cheats 2 bottom elevation locations.
Referring now to Fig. 1, Fig. 1 is basic arranged in parallel, the shallow foundation cushion cap of two different levels of the embodiment of the present invention Construction in advance, using its bottom surface as the structural representation of the classification step of piping lane deep basal pit, so construction makes piping lane deep basal pit The firm safety of one side slope.
C, deep pit digging simultaneously, in the shallow structure constructed(Basis)Displacement is laid on base plate or cushion cap and sedimentation is supervised Measuring point, is monitored by " the pit retaining monitoring scheme " separately worked out, during controlling deep pit construction, to be cheated to shallow foundation Coordinate influence degree.
After the completion of d, deep basal pit are poured, could later start shallow structure of constructing(Basis)Top, but must first be in shallow The elements of a fix are remeasured on foundation platform.This procedure is the key of inverse formula construction method, and reason is:Deep pit construction mistake Cheng Zhong, adjacent shallow foundation(Structure)Different degrees of displacement and sedimentation is had, resulting center, absolute altitude deviation must be upper Portion basis(Structure)Digested, because top is basic(Structure)Other facilities such as electromechanical equipment, steel construction are installed, such as Fruit foundation bolt, rim of a cup thereon etc. produces relatively large deviation, cannot just ensure to install accurate, it is therefore necessary to top basis(Knot Structure)The elements of a fix remeasure unwrapping wire, when the former coordinate with lower raft, cushion cap has off normal, can in time be rectified a deviation on top And correction.
The present invention has substantive distinguishing features and significant technological progress, depth after underground concrete structure of the invention is first shallow Inverse formula construction method when piping lane deep basal pit is adjacent with shallower base for post cushion cap, construct afterwards by the base for post cushion cap for first having constructed shallower Deep base tube corridor.After piping lane construction completion is poured, the rim of a cup on base for post top of later constructing again(For installing steel column)Part.This hair There is deep inverse formula construction method deep basal pit to be perfectly safe after bright underground concrete structure is first shallow, it is ensured that the shallow foundation first constructed Quality is unaffected(I.e. center, absolute altitude etc. meet code requirement), more efficiently advantage more economical with engineering.
Above example is used for illustrative purposes only, rather than limitation of the present invention, about the technology people of technical field Member, without departing from the spirit and scope of the present invention, can also make various conversion or change.Therefore, it is all equivalent Technical scheme should also belong to scope of the invention, should be limited by each claim.

Claims (2)

1. deep inverse formula construction method after a kind of underground concrete structure is first shallow, it is characterised in that comprise the following steps:
The adjacent shallow foundation hole of a, excavation(2), shallow foundation hole of only constructing(2)Concrete foundation base plate, or column foundation cushion cap(3), no Construct to the superstructure in shallow foundation hole;The concrete foundation base plate, or column foundation cushion cap(3)Conserved after having poured concrete Period not form removal, as deep basal pit(1)Stabilising system in side slope, consolidates excavation slope;
B, etc. shallow foundation hole(2)Concrete foundation base plate, or column foundation cushion cap(3)Pour 4 angel's concrete and reach some strength Afterwards, deep pit excavation(1), the step absolute altitude of two grades of slopes of deep basal pit is positioned at shallow foundation hole bottom elevation location;
C, deep basal pit(1)Excavate simultaneously, in the shallow foundation hole constructed(2)Concrete foundation base plate, or column foundation cushion cap(3) It is upper to lay displacement and settlement monitoring point, it is monitored by " the pit retaining monitoring scheme " separately worked out, to control deep pit digging To the coordinate influence degree in shallow foundation hole in work progress;
After the completion of d, deep basal pit are poured, start construction shallow foundation hole(2)The top of concrete foundation base plate, or column foundation cushion cap (3)Top, but must first be in shallow foundation hole(2)Concrete foundation base plate, or column foundation cushion cap(3)On remeasure positioning Coordinate, then the elements of a fix to deep basal pit top concrete structure remeasure unwrapping wire, cheated when with shallow foundation(2)Concrete foundation Base plate, or column foundation cushion cap(3)Former coordinate when having off normal, when the elements of a fix of deep basal pit top concrete structure are made and When rectify a deviation and correct.
2. deep inverse formula construction method after underground concrete structure as claimed in claim 1 is first shallow, it is characterised in that the original The off normal of coordinate includes center, absolute altitude deviation.
CN201410628728.9A 2014-11-11 2014-11-11 Deep inverse formula construction method after a kind of underground concrete structure is first shallow Active CN105649086B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410628728.9A CN105649086B (en) 2014-11-11 2014-11-11 Deep inverse formula construction method after a kind of underground concrete structure is first shallow

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410628728.9A CN105649086B (en) 2014-11-11 2014-11-11 Deep inverse formula construction method after a kind of underground concrete structure is first shallow

Publications (2)

Publication Number Publication Date
CN105649086A CN105649086A (en) 2016-06-08
CN105649086B true CN105649086B (en) 2017-06-30

Family

ID=56483532

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410628728.9A Active CN105649086B (en) 2014-11-11 2014-11-11 Deep inverse formula construction method after a kind of underground concrete structure is first shallow

Country Status (1)

Country Link
CN (1) CN105649086B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978700A (en) * 2018-07-19 2018-12-11 中国十七冶集团有限公司 The construction technology of the proximate building structure basis of different depth
CN109029215A (en) * 2018-09-17 2018-12-18 中国五冶集团有限公司 A kind of mechanism for the measurement of pile foundation hole depth
CN112411555A (en) * 2020-11-16 2021-02-26 上海宝冶集团有限公司 Method for synchronous construction of deep foundation pit and edge foundation process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2254417C1 (en) * 2003-12-15 2005-06-20 Басиев Асхар Николаевич Method and anchor system for securing pit bordering
CN101892668A (en) * 2010-07-30 2010-11-24 中铁四局集团第六工程有限公司 Combined support-excavated geologically solutional deep foundation pit and construction method thereof
CN102031781A (en) * 2009-09-24 2011-04-27 上海市第一建筑有限公司 Foundation pit reinforcing technology from shallow position to deep position for group pit construction
CN102425171A (en) * 2011-09-25 2012-04-25 湖南省勘测设计院 Forward-backward constructing method for central island of deep and large foundation pit
CN203222802U (en) * 2013-03-29 2013-10-02 辽宁工程技术大学 Stepped foundation pit slope supporting structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2254417C1 (en) * 2003-12-15 2005-06-20 Басиев Асхар Николаевич Method and anchor system for securing pit bordering
CN102031781A (en) * 2009-09-24 2011-04-27 上海市第一建筑有限公司 Foundation pit reinforcing technology from shallow position to deep position for group pit construction
CN101892668A (en) * 2010-07-30 2010-11-24 中铁四局集团第六工程有限公司 Combined support-excavated geologically solutional deep foundation pit and construction method thereof
CN102425171A (en) * 2011-09-25 2012-04-25 湖南省勘测设计院 Forward-backward constructing method for central island of deep and large foundation pit
CN203222802U (en) * 2013-03-29 2013-10-02 辽宁工程技术大学 Stepped foundation pit slope supporting structure

Also Published As

Publication number Publication date
CN105649086A (en) 2016-06-08

Similar Documents

Publication Publication Date Title
CN104196034B (en) A kind of utilize steel sheet pile as the foundation ditch construction method in supporting cofferdam
CN102094425B (en) Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam
CN108343102B (en) Pile foundation settlement reinforcement jacking leveling structure and construction method thereof
CN203284791U (en) Independent column basis below column and capable of conducting jacking rectification
CN106013053B (en) A kind of steel sheet pile construction method for supporting for being used to build underground garage open caisson
CN101725357B (en) Construction method for lower section of underground tunnel
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN101666081A (en) Abrupt slope bare rock drilling platform and technology in huge reservoir
CN102430277B (en) Coarse grid sunk well for physically processing waste water and construction method thereof
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN105649086B (en) Deep inverse formula construction method after a kind of underground concrete structure is first shallow
CN106223354B (en) The construction method of shallow foundation stay in place form
CN104153371A (en) Grouting-to-stop-water construction method of underwater rubble bed
CN105714769A (en) Construction method for anti-sliding cast-in-place pile
CN106760620A (en) A kind of utilization open caisson increases the construction method for building the underground space under existing building
CN108951431A (en) Bridge concrete earth cofferdam and bridge pier building technology
CN106609508A (en) Construction technology and construction method for large-particle-size pebble stratum super-deep foundation pit in strong water permeation environment of Yellow River flood plain
CN109706952A (en) Large-scale well-sinking construction method
CN104404979A (en) H-shaped pile slab wall construction method
CN101798823B (en) Construction method of performing remote deviation rectification by passageway method
CN110016919A (en) A kind of aging blocks install the minimally invasive foundation pit structure of elevator and construction method additional
CN201502056U (en) Bare rock drilling platform for steep slope of deep reservoir area
CN103758132B (en) The construction technology of the cantilever soldier pile retaining structure on slope is put in a kind of combination
CN106065628A (en) Based on the major diameter running water pipe security protection construction method forever facing the theory of combination
CN205205832U (en) Structure is propped in trading of underground building

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant