CN105630861B - A kind of the operating parameter management method and system of distributed data acquisition system - Google Patents
A kind of the operating parameter management method and system of distributed data acquisition system Download PDFInfo
- Publication number
- CN105630861B CN105630861B CN201510811134.6A CN201510811134A CN105630861B CN 105630861 B CN105630861 B CN 105630861B CN 201510811134 A CN201510811134 A CN 201510811134A CN 105630861 B CN105630861 B CN 105630861B
- Authority
- CN
- China
- Prior art keywords
- operating parameter
- data
- file
- current
- parameter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000007726 management method Methods 0.000 title claims abstract description 27
- 238000012423 maintenance Methods 0.000 claims abstract description 34
- 238000012795 verification Methods 0.000 claims abstract description 28
- 238000012360 testing method Methods 0.000 claims abstract description 21
- 230000001360 synchronised effect Effects 0.000 claims abstract description 11
- 230000004913 activation Effects 0.000 claims description 5
- 230000010354 integration Effects 0.000 claims description 5
- 241000208340 Araliaceae Species 0.000 claims description 3
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 claims description 3
- 235000003140 Panax quinquefolius Nutrition 0.000 claims description 3
- 238000012790 confirmation Methods 0.000 claims description 3
- 235000008434 ginseng Nutrition 0.000 claims description 3
- 230000004044 response Effects 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 11
- 238000004891 communication Methods 0.000 abstract description 3
- 230000006870 function Effects 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 5
- 230000008569 process Effects 0.000 description 5
- 238000012986 modification Methods 0.000 description 4
- 230000004048 modification Effects 0.000 description 4
- 238000010276 construction Methods 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 2
- 238000013480 data collection Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000007246 mechanism Effects 0.000 description 2
- 230000008859 change Effects 0.000 description 1
- 230000000739 chaotic effect Effects 0.000 description 1
- 238000013524 data verification Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 235000012054 meals Nutrition 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 238000004321 preservation Methods 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 230000000153 supplemental effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/10—File systems; File servers
- G06F16/13—File access structures, e.g. distributed indices
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/10—File systems; File servers
- G06F16/11—File system administration, e.g. details of archiving or snapshots
- G06F16/122—File system administration, e.g. details of archiving or snapshots using management policies
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/10—File systems; File servers
- G06F16/17—Details of further file system functions
- G06F16/178—Techniques for file synchronisation in file systems
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/10—File systems; File servers
- G06F16/18—File system types
- G06F16/182—Distributed file systems
Abstract
The present invention relates to the operating parameter management methods and system of a kind of distributed data acquisition system, this method comprises: acquiring the more new data in current CIM/E file when detecting has the more new data of operating parameter in current CIM/E file;The operational parameter data of other control centres is obtained, and whether the operational parameter data for detecting other control centres has update;The corresponding operational parameter data in other control centres prestored is updated according to the more new data of the operating parameter of other control centres;The operating parameter of more new data and other the updated control centres prestored to the operating parameter in the current CIM/E file of acquisition is integrated, and current maintenance state operating parameter is formed;Checksum test is carried out to current operating parameter;The current maintenance state operating parameter of verification and test passes is synchronized in the operating parameter file of run mode.The present invention carries out real-time update and management to the operating parameter of distributed data acquisition system, realizes the purpose of link configuration and communication index efficiently managed.
Description
Technical field
The present invention relates to technical field of data administration, adopt more particularly, to a kind of distributed data based on CIM/E file
The operating parameter management method and system of collecting system.
Background technique
With moving forward steadily for China's extra-high voltage alternating current-direct current mixed connection bulk power grid construction in recent years, power grid feature and operation characteristic
Significant changes occur, it is meant that " big operation ", " general overhaul " System Construction needs deepen constantly.China's power grid will show completely newly
Network morphology so that the operation and control of power grid are increasingly complicated, there is an urgent need to develop smart grid scheduling adaptable therewith
Support system further promotes the intelligent level of dispatching of power netwoks, realizes multi-stage scheduling Collaboration and bulk power grid total tune
Control enhances the accident risk prevention ability of power grid, improves the ability that bulk power grid is controlled in scheduling.
Since the power grid scale of smart grid supporting system technology monitoring is increasing, real time data to be treated
It measures increasing, needs real time data to be sharing also more and more between multiple control centres.The construction of big operation architecture is so that intelligence
Can dispatching of power netwoks technology support system acquisition range, service object and in terms of have very big expansion.It is existing
Some data acquisition functions are all no longer satisfied the demand of future development in service mode, acquisition capacity and management mode,
The research for needing to carry out in a deep going way data acquisition technology promotes the data-handling capacity of acquisition, carries out data acquisition function into one
The planning and designing of step.Using distributed data acquisition function, make data acquisition is more convenient to increase function, it is easier to expand scale,
It is more simply safeguarded, more efficient acquisition data.Then, the smart grid dispatching technique branch based on distributed data acquisition system
The system of holding is come into being.
But in actual use, the operation of each control centre in distributed data acquisition system is joined
Number is inconsistent, but the data between control centre are unified and cooperated, therefore, when in one of them or several scheduling
When the operating parameter of the heart updates, the operating parameter of each control centre needs correspondingly to be adjusted, but currently running ginseng
Number way to manages it is more chaotic, cannot the operating parameter in time to each control centre be updated, to cause distribution
The accuracy and real-time of data acquisition are affected.
Summary of the invention
In view of the above-mentioned problems, the present invention provides a kind of operation ginseng of distributed data acquisition system based on CIM/E file
Number management method and system carry out real-time update and management to the operating parameter of distributed data acquisition system, realize that link is matched
Set and communicate the purpose of index efficiently managed.
Based on above-mentioned purpose, one aspect of the present invention proposes a kind of operating parameter pipe of distributed data acquisition system
Reason method characterized by comprising
When detecting has the more new data of operating parameter in current CIM/E file, acquire in current CIM/E file
More new data;
The operational parameter data of other control centres is obtained, and the operational parameter data for detecting other control centres is
It is no to have update;
Other control centres pair described in prestoring are updated according to the more new data of the operating parameter of other control centres
The operational parameter data answered;
To in the more new data of the operating parameter in the current CIM/E file of acquisition and other the updated scheduling prestored
The operating parameter of the heart is integrated, and current maintenance state operating parameter is formed;
Checksum test is carried out to the current operating parameter;
The current maintenance state operating parameter of verification and test passes is synchronized in the operating parameter file of run mode.
Wherein, the more new data is deposited into the current CIM/E file by man-machine interface HMI.
Wherein, the operational parameter data of other control centres is the operational parameter data under run mode.
Wherein, the operational parameter data of other control centres described in the acquisition specifically includes:
Selection needs to obtain the control centre of operating parameter;
Establish the network connection with the server of the control centre of selection;
Request activation message is sent to the server;
After the confirmation activation message for receiving the server response, receive where the server that server is sent
The operational parameter data of control centre;
After the operational parameter data of control centre where receiving the server, the file that the server is sent is received
Check code;
Received operational parameter data is verified according to the file verification code, if verified successfully, receives number
According to completion, the server is otherwise notified to retransmit data.
Wherein, described that the current operating parameter is carried out to verify the file format school specifically included to current operating parameter
It tests, the verification of content authentication and correctness.
Wherein, it is described according to the more new data of the operating parameter of other control centres update prestore described in other scheduling in
The corresponding operational parameter data of the heart, specifically includes:
The more new data of the operating parameter of other control centres is added to the corresponding fortune in other described control centres
In row Parameter File.
According to another aspect of the present invention, a kind of operating parameter management system of distributed data acquisition system is provided,
It is characterised by comprising:
Data acquisition module, for acquiring when detecting has the more new data of operating parameter in current CIM/E file
More new data in current CIM/E file;
Data acquisition module for obtaining the operational parameter data of other control centres, and detects in other described scheduling
Whether the operational parameter data of the heart has update;
Data update module, the more new data for the operating parameter according to other control centres update the institute prestored
State the corresponding operational parameter data in other control centres;
Data Integration module, for operating parameter in the current CIM/E file to acquisition more new data and prestore
The operating parameter of other updated control centres is integrated, and current maintenance state operating parameter is formed;
Data check and test module, for carrying out checksum test to the current operating parameter;
Data simultaneous module, for the current maintenance state operating parameter of verification and test passes to be synchronized to the fortune of run mode
In row Parameter File.
Wherein, the system also includes display module, for showing the data collecting module collected of the operating parameter
Data, other control centres obtained operational parameter data and current maintenance state operational parameter data.
Wherein, the system also includes operating parameter memory modules, for being synchronized to by current maintenance state operating parameter
When in the operating parameter file of run mode, original operating parameter file of the run mode is stored.
The operating parameter management method and system of a kind of distributed data acquisition provided by the invention, by operating parameter
Acquisition, transmission, integration and the verification of data, and using the storage of CIM/E file offer, shared, administrative mechanism, to distributed number
The efficient management of link configuration and communication index is realized according to function classification according to the operating parameter of acquisition system, and can
The maintenance process of data acquisition is reduced, file service efficiency is improved.Meanwhile under the premise of authority data acquires file content,
It is transmitted by the exchange of file, improves access and the exchange efficiency of data.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to make one simply to introduce, it should be apparent that, the accompanying drawings in the following description is this hair
Bright some embodiments for those of ordinary skill in the art without creative efforts, can be with root
Other attached drawings are obtained according to these attached drawings.
Fig. 1 is a kind of flow chart of the operating parameter management method of distributed data acquisition system of the invention;
Fig. 2 shows the structural block diagrams of the operating parameter management system of distributed data acquisition system of the invention.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention
In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is
A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art
Every other embodiment obtained without creative efforts, shall fall within the protection scope of the present invention.
Fig. 1 is a kind of flow chart of the operating parameter management method of distributed data acquisition system of the invention.
Referring to Fig.1, the operating parameter management method of a kind of distributed data acquisition system of one embodiment of the present of invention,
It specifically includes:
S1, when detecting has the more new data of operating parameter in current CIM/E file, acquire current CIM/E file
In more new data;
In the present embodiment, the more new data in current CIM/E file be deposited by man-machine interface HMI it is described current
CIM/E file in.
Operational parameter data of the invention is stored in CIM/E file, and CIM/E file is a kind of with specific format
File is in itself the same with the other kinds of file in file system.The model of data collection system all saves
In CIM/E file.And there are two types of states for operating parameter, are maintenance state and run mode respectively.CIM/E file is in both states
It is lower to have different entities respectively.The management of operating parameter of the invention is mainly completed in the case where safeguarding state, and access is maintenance state
Under CIM/E file.After user confirms that maintenance state file is errorless, the CIM/E file synchronization under state will be safeguarded to run mode.And
Data collection system obtains model and completes under run mode, and access is CIM/E file under run mode.
S2, the operational parameter data for obtaining other control centres, and detect the operating parameter number of other control centres
According to whether having update;
Above-mentioned steps S2 is specifically included:
S211, selection need to obtain the control centre of operating parameter;
The network connection of the server of S212, foundation and the control centre of selection;
S213, Xiang Suoshu server send request activation message;
After S214, the confirmation for receiving the server response activate message, the service sent from server is received
The operational parameter data of control centre where device;
After the operational parameter data of control centre where S215, the reception server, receives the server and send
File verification code;
S216, received operational parameter data is verified according to the file verification code, if verified successfully, is connect
It receives data to complete, the server is otherwise notified to retransmit data.
In the present embodiment, the operational parameter data of other control centres is the operational parameter data under run mode.
S3, other the described control centres prestored are updated according to the more new data of the operating parameter of other control centres
Corresponding operational parameter data;
In the embodiment of the present invention, after getting the operating parameter of other control centres, detect whether the operating parameter has
It updates, if do not updated, the operational parameter data for other the original control centres that then be used directly carries out the data of next step
Processing then updates corresponding operational parameter data, more new data is added to corresponding operating parameter file if there is updating
In.As newly increased a reference record when some control centre, after getting the reference record, which is protected
It is stored in the file of corresponding control centre's supplemental characteristic.
S4, to the more new data of the operating parameter in the current CIM/E file of acquisition and other the updated tune prestored
The operating parameter at degree center is integrated, and current maintenance state operating parameter is formed.
S5 carries out checksum test to the current operating parameter;
In order to guarantee CIM/E file content safety and correctness, need to carry out current operating parameter verification and
Test, in the present embodiment, current operating parameter is stored in CIM/E file, and verification includes 3 aspects: file authentication
Verification, file format verification and file content verification.
Firstly, file authentication verification refers to whether file content is to read and write by CIM/E file standard interface, have not
There is the write operation for carrying out non-standard interface.CIM/E file calculates one 16 MD5 codes by using MD5 algorithm, by making
With the comparison of MD5 code, to check whether file illegally or is accidentally modified.
The verification of CIM/E file format refers to the verification of distributed data acquisition system CIM/E file label and criteria check,
It is written and read file by standard CIM/E file interface, a series of file label and fixed format can be generated.Pass through these
Label and the correct resolution file content of format ability, so criteria check and label verification are to guarantee CIM/E file content just
True essential step.
The verification of CIM/E file content refers to whether file content accords with as the operating parameter of distributed data acquisition system
Logical, whether operating parameter is reasonable.It can lead to distributed data by file content verification to avoid because of unreasonable configuration
Acquisition leads to the problem of mistake.
The present embodiment tests CIM/E file by being tested current operating parameter, if sent out in test
After existing problem, current operating parameter is regenerated, so that the recovery process of configuration error is simplified, so that management process is more square
Just, safer.
S6, the current maintenance state operating parameter of verification and test passes is synchronized in the operating parameter file of run mode.
In the embodiment of the present invention, maintenance state file is for managing, and run mode file is for running.Distributed data acquisition
The synchronization of the CIM/E file of system includes 2 aspects, first is that from maintenance state file to the synchronization of run mode file, the other is
The synchronization of state file, run mode file is safeguarded between node.It is the dimension from file server host first when carrying out file synchronization
Run mode file synchronization of the state file to file server host is protected, carries out judgement synchronization by comparing MD5 code after synchronously completing
Whether succeed.If it is successful, being synchronized again from file server host to each file server standby host, then pass through again
MD5 code carries out file synchronization judgement.This time file synchronization success, otherwise fails if each node all success, needs weight
It is new to carry out file synchronization.
The operating parameter management method of distributed data acquisition of the invention passes through the acquisition to operational parameter data, biography
Defeated, integration and verification, and using the storage of CIM/E file offer, shared, administrative mechanism, to distributed data acquisition system
Operating parameter realizes the efficient management of link configuration and communication index according to function classification, and can reduce data acquisition
Maintenance process, improve file service efficiency.Meanwhile under the premise of authority data acquires file content, pass through the friendship of file
Transmission is changed, access and the exchange efficiency of data are improved.
Fig. 2 shows the structural block diagrams of the operating parameter management system of distributed data acquisition system of the invention.
In another embodiment of the present invention, a kind of operating parameter management system of distributed data acquisition system is provided
System, as shown in Fig. 2, the system specifically includes:
Data acquisition module 10, for adopting when detecting has the more new data of operating parameter in current CIM/E file
Collect the more new data in current CIM/E file;
Data acquisition module 20 for obtaining the operational parameter data of other control centres, and detects other described scheduling
Whether the operational parameter data at center has update;
Data update module 30, what the more new data update of the operating parameter for other control centres according to prestored
The corresponding operational parameter data in described other control centres;
Data Integration module 40, for the operating parameter in the current CIM/E file to acquisition more new data and prestore
The operating parameters of other updated control centres integrated, form current maintenance state operating parameter;
Data check and test module 50, for carrying out checksum test to the current operating parameter;
Data simultaneous module 60, for the current maintenance state operating parameter of verification and test passes to be synchronized to run mode
In operating parameter file.
In above-mentioned system, acquisition or the data updated can be shown by interface, therefore further
In embodiment, the system also includes display modules, the data of the data collecting module collected for showing the operating parameter,
The operational parameter data of other control centres obtained and current maintenance state operational parameter data.
In addition, the display module also provides displaying and the maintenance interface of operating parameter for user, it is connection user and system
Tie.Human machine interface realizes the reading and change of operation meal South Lake data by basic platform file service, then realizes
The displaying and maintenance of data.
In addition, being not easy in order to prevent in generation modification mistake, accidental damage etc. extensive when being operated to CIM/E file
After multiple situation, it can be restored from old version before.I.e. in a further embodiment, the system also includes fortune
Row parameter memory module, for when current maintenance state operating parameter to be synchronized in the operating parameter file of run mode, by institute
The original operating parameter file for stating run mode is stored.
Above-mentioned operating parameter memory module can efficiently solve the difficulty of unexpected CIM/E file access pattern when occurring, and improve
The safety and reliability of maintenance.What the old version of CIM/E file saved is to carry out the file before file modification each time
Content, as long as memory space is supported, the old version of CIM/E file can almost support the preservation of all old versions and extensive
It is multiple.
Although the embodiments of the invention are described in conjunction with the attached drawings, but those skilled in the art can not depart from this hair
Various modifications and variations are made in the case where bright spirit and scope, such modifications and variations are each fallen within by appended claims
Within limited range.
In specification of the invention, numerous specific details are set forth.It is to be appreciated, however, that the embodiment of the present invention can be with
It practices without these specific details.In some instances, well known method, structure and skill is not been shown in detail
Art, so as not to obscure the understanding of this specification.
It will be understood by those skilled in the art that can be adaptively changed to the module in the equipment in embodiment
And they are provided in the different one or more equipment of the embodiment.Can in embodiment module or unit or
Component is combined into a module or unit or component, and furthermore they can be divided into multiple submodule or subelement or subgroups
Part.In addition to such feature and/or at least some of process or unit are mutually exclusive places, any combination can be used
To all features disclosed in this specification (including adjoint claim, abstract and attached drawing) and so disclosed any side
All process or units of method or equipment are combined.Unless expressly stated otherwise, this specification (is wanted including adjoint right
Ask, make a summary and attached drawing) disclosed in each feature can be replaced with an alternative feature that provides the same, equivalent, or similar purpose.
In addition, it will be appreciated by those of skill in the art that although some embodiments described herein include other embodiments
In included certain features rather than other feature, but the combination of the feature of different embodiments mean it is of the invention
Within the scope of and form different embodiments.For example, in the following claims, embodiment claimed is appointed
Meaning one of can in any combination mode come using.
Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent
Pipe present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: its according to
So be possible to modify the technical solutions described in the foregoing embodiments, or to some or all of the technical features into
Row equivalent replacement;And these are modified or replaceed, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution
The range of scheme should all cover within the scope of the claims and the description of the invention.
Claims (7)
1. a kind of operating parameter management method of distributed data acquisition system characterized by comprising
When detecting has the more new data of operating parameter in current CIM/E file, the update number in current CIM/E file is acquired
According to;
The operational parameter data of other control centres is obtained, and whether the operational parameter data for detecting other control centres has
It updates;
It is corresponding that other control centres described in prestoring are updated according to the more new data of the operating parameter of other control centres
Operational parameter data;
To the more new data of the operating parameter in the current CIM/E file of acquisition and other the updated control centres prestored
Operating parameter is integrated, and current maintenance state operating parameter is formed;
Checksum test is carried out to the current maintenance state operating parameter;
The current maintenance state operating parameter of verification and test passes is synchronized in the operating parameter file of run mode;
The operational parameter data of other control centres described in the acquisition specifically includes:
Selection needs to obtain the control centre of operating parameter;
Establish the network connection with the server of the control centre of selection;
Request activation message is sent to the server;
After the confirmation activation message for receiving the server response, the scheduling where the server that server is sent is received
The operational parameter data at center;
After the operational parameter data of control centre where receiving the server, the file verification that the server is sent is received
Code;
Received operational parameter data is verified according to the file verification code, if verified successfully, it is complete to receive data
At otherwise notifying the server to retransmit data.
2. management method according to claim 1, which is characterized in that the more new data is stored in by man-machine interface HMI
Into the current CIM/E file.
3. management method according to claim 1, which is characterized in that the operational parameter data of other control centres is
Operational parameter data under run mode.
4. management method according to claim 1, which is characterized in that described to be carried out to the current maintenance state operating parameter
Verification specifically includes the file format verification to current maintenance state operating parameter, content authentication and correctness verification.
5. management method according to claim 1, which is characterized in that the operating parameter according to other control centres
More new data updates the corresponding operational parameter data in other described control centres prestored, specifically includes:
The more new data of the operating parameter of other control centres is added to the corresponding operation ginseng in other described control centres
In number file.
6. a kind of operating parameter management system of distributed data acquisition system characterized by comprising
Data acquisition module, for when detecting has the more new data of operating parameter in current CIM/E file, acquisition to be current
More new data in CIM/E file;
Data acquisition module is updated, for obtaining the operational parameter data of other control centres, and is detected in other described scheduling
Whether the operational parameter data of the heart has update;
Data update module, for according to the update of the more new data of the operating parameter of other control centres prestore described in its
The corresponding operational parameter data in his control centre;
Data Integration module, the more new data for the operating parameter in the current CIM/E file to acquisition and the update that prestores
The operating parameter of other control centres afterwards is integrated, and current maintenance state operating parameter is formed;
Data check and test module, for carrying out checksum test to the current maintenance state operating parameter;
Data simultaneous module, the operation for the current maintenance state operating parameter of verification and test passes to be synchronized to run mode are joined
In number file;
The system also includes display modules, and the data of the data collecting module collected for showing the operating parameter obtain
Other control centres operational parameter data and current maintenance state operational parameter data.
7. system according to claim 6, which is characterized in that the system also includes operating parameter memory modules, are used for
When current maintenance state operating parameter to be synchronized in the operating parameter file of run mode, by original operation of the run mode
Parameter File is stored.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510811134.6A CN105630861B (en) | 2015-11-20 | 2015-11-20 | A kind of the operating parameter management method and system of distributed data acquisition system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510811134.6A CN105630861B (en) | 2015-11-20 | 2015-11-20 | A kind of the operating parameter management method and system of distributed data acquisition system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105630861A CN105630861A (en) | 2016-06-01 |
CN105630861B true CN105630861B (en) | 2019-05-14 |
Family
ID=56045799
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510811134.6A Active CN105630861B (en) | 2015-11-20 | 2015-11-20 | A kind of the operating parameter management method and system of distributed data acquisition system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105630861B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106534272A (en) * | 2016-10-21 | 2017-03-22 | 江苏方天电力技术有限公司 | System and method for processing parameters of coal-fired unit |
CN107257373A (en) * | 2017-06-15 | 2017-10-17 | 国电南瑞科技股份有限公司 | A kind of grid model data maintenance management method based on CIM/E files |
CN107301078B (en) * | 2017-07-25 | 2023-08-01 | 欣旺达电动汽车电池有限公司 | Method and device for automatically updating parameters of energy storage system |
CN107463487B (en) * | 2017-08-03 | 2020-12-29 | 国网江苏省电力有限公司信息通信分公司 | Distributed host performance acquisition system and performance acquisition method |
CN108572845B (en) * | 2018-03-15 | 2022-05-31 | 华为技术有限公司 | Upgrading method of distributed micro-service cluster and related system |
CN108761258A (en) * | 2018-03-29 | 2018-11-06 | 深圳众厉电力科技有限公司 | Transformer short period overload capability assessment system based on artificial intelligence and big data technology |
CN109712386A (en) * | 2018-12-06 | 2019-05-03 | 中国南方电网有限责任公司 | A kind of Distributed Modeling System metric data method of calibration based on E format |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103577938A (en) * | 2013-11-15 | 2014-02-12 | 国家电网公司 | Power grid dispatching automation main-and-standby system model synchronizing method and synchronizing system thereof |
CN104134163A (en) * | 2014-07-11 | 2014-11-05 | 国家电网公司 | Power distribution network graph and model management system and power distribution network graph and model management method based on CIM/E and CIM/G |
CN104866943A (en) * | 2015-03-19 | 2015-08-26 | 国家电网公司 | CIM/E file-based distributed data acquisition system main and standby dispatch synchronization method |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8402068B2 (en) * | 2000-12-07 | 2013-03-19 | Half.Com, Inc. | System and method for collecting, associating, normalizing and presenting product and vendor information on a distributed network |
US20110078291A1 (en) * | 2009-09-30 | 2011-03-31 | International Business Machines Corporation | Distributed performance monitoring in soft real-time distributed systems |
-
2015
- 2015-11-20 CN CN201510811134.6A patent/CN105630861B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103577938A (en) * | 2013-11-15 | 2014-02-12 | 国家电网公司 | Power grid dispatching automation main-and-standby system model synchronizing method and synchronizing system thereof |
CN104134163A (en) * | 2014-07-11 | 2014-11-05 | 国家电网公司 | Power distribution network graph and model management system and power distribution network graph and model management method based on CIM/E and CIM/G |
CN104866943A (en) * | 2015-03-19 | 2015-08-26 | 国家电网公司 | CIM/E file-based distributed data acquisition system main and standby dispatch synchronization method |
Also Published As
Publication number | Publication date |
---|---|
CN105630861A (en) | 2016-06-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105630861B (en) | A kind of the operating parameter management method and system of distributed data acquisition system | |
CN109474977A (en) | A kind of monitoring method of equipment, apparatus and system | |
CN107453925A (en) | Remote firmware updating method and cloud platform based on multistage communication platform | |
CN103560279B (en) | Based on the diagnosis maintaining method of the battery management system diagnostic system of CAN | |
CN103095518A (en) | Coverage rate test processing method and device and coverage rate test server and system | |
CN107992321A (en) | ECU software update method, device, vehicle-mounted T-BOX and vehicle | |
KR101256944B1 (en) | System and method for data recovery for automatic meter reading system | |
CN103166773A (en) | Method and system for monitoring operation state of server | |
CN105653329A (en) | Application management method, apparatus and system | |
CN109165170B (en) | Method and system for automatic request test | |
CN102625339A (en) | Monitoring system for using state of integrated wireless communication equipment of railway locomotive | |
CN102859505B (en) | The management method of management system and computer system | |
CN102006204B (en) | Distributed resolution system for monitoring data stream in real time | |
CN103500400A (en) | Multi-application mobile payment system and safety method | |
CN107943497A (en) | A kind of ETC electronic tags bluetooth upgrading management system | |
CN109510744A (en) | Internet of Things device intelligence cut-in method and device | |
CN106532931B (en) | A kind of electric power system dispatching boss station intelligent batch is to point methods | |
CN106992916A (en) | A kind of electric power dispatching system and implementation method based on virtual private cloud | |
CN107481503A (en) | A kind of kilowatt meter reading-out system and meter register method | |
CN107463476A (en) | The acquisition methods and device of information | |
CN110049027A (en) | A kind of transmission platform for block chain network information | |
CN107977467A (en) | Database monitoring device | |
CN114201336A (en) | Configuration checking control method, system and equipment for online monitoring control function of master station | |
CN106354863A (en) | System and method for managing rail-transit electronic map | |
CN109461226A (en) | A kind of intelligent inspection system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |