CN105625178A - Y-shaped pier column construction process - Google Patents

Y-shaped pier column construction process Download PDF

Info

Publication number
CN105625178A
CN105625178A CN201410584959.4A CN201410584959A CN105625178A CN 105625178 A CN105625178 A CN 105625178A CN 201410584959 A CN201410584959 A CN 201410584959A CN 105625178 A CN105625178 A CN 105625178A
Authority
CN
China
Prior art keywords
vibrating
pier stud
reinforcing steel
building
advance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410584959.4A
Other languages
Chinese (zh)
Inventor
董伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 14th Bureau Group Co Ltd
Original Assignee
China Railway 14th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 14th Bureau Group Co Ltd filed Critical China Railway 14th Bureau Group Co Ltd
Priority to CN201410584959.4A priority Critical patent/CN105625178A/en
Publication of CN105625178A publication Critical patent/CN105625178A/en
Pending legal-status Critical Current

Links

Abstract

The invention provides a Y-shaped pier column construction process. According to the structural condition and the standard requirement, tumbling barrels are arranged; the tumbling barrels are placed in advance in the reinforcing steel bar binding process and then reinforcing steel bar binding is carried out; due to the fact that reinforcing steel bars are criss-cross in a # shape, in the binding process, technicians give the priority to inspection of the interval accuracy of the reinforcing steel bars, and offline inspection is carried out when it is necessary so as to guarantee the vertical through condition; and according to the structural size and the vibrating radius of vibrating rods, the technicians distribute vibrating points, insertion tests are conducted on vibrating holes in advance, and if the vibrating rods are stuck, the reinforcing steel bars are adjusted according to the standard requirement, so that a smooth channel is guaranteed. The Y-shaped pier column construction process has the beneficial effects that 50 kilograms of cement is saved for each square, a construction period is shortened, time cost is saved, and inherent quality of a solid structure is guaranteed; the appearance quality is remarkably improved; and a viaduct double-column type Y-shaped pier is solid inside and attractive outside, the solid strength meets the design requirement after the pier is detected by various organizations, no honeycombs, pitted surfaces or cracks exist, bar leakage is completely eradicated, and the process is accepted by various parties.

Description

Y type pier stud construction technology
Technical field
The present invention relates to a kind of pier stud construction technology, specifically Y type pier stud construction technology.
Background technology
Overpass except 1# pier stud, all the other posts high at more than 3m, 7#, 8#, 9#, 12#, 13#, 14# pier stud in 7m level above, and require that pier stud is with binder one-time-concreting molding; Pier shaft reinforcing bar is intensive, and bar diameter is big, and stirrup is crisscross, and in groined type, reinforcing bar clear spacing is little, and concrete vibrates difficulty, deals with improperly and can produce honeycomb, leak.
Summary of the invention
For solving the problems referred to above, it is an object of the invention to provide a kind of Y type pier stud construction technology.
The present invention is for achieving the above object, it is achieved through the following technical solutions: Y type pier stud construction technology, according to structure situation, code requirement, tumbling barrel is set, when reinforcing bar binding, tumbling barrel is placed in advance, then reinforcing bar binding is being carried out, invar muscle is crisscross, in groined type, in process of binding, technical staff focuses on the examination of bar spacing precision, and go offline inspection if desired; To ensure up/down perforation; Vibrating radins according to physical dimension and vibrating spear, technical staff carries out vibrating layouting, and to vibrating, examination is inserted in hole in advance, as blocked vibrating spear, reinforcing bar is pressed code requirement adjustment, to ensure channels open.
For realizing the purpose of the present invention further, can also be by the following technical solutions: testing crew is according to the performance of blender, in conjunction with previous experiences and code requirement, determine mixing time, during stirring, often dish must estimate mixture situation, concrete mixture carries out workability detection before dispatching from the factory, before concrete placings, testing crew carries out workability detection equally, time undesirable, return mixing station and processes. When building pier stud, though workability is controlled effectively, because pier stud is high, sandstone segregation phenomenon is unavoidably there is in concrete mixture after beating to pier stud, in order to ensure that portion occurs without " rotten ", honeycomb, first building the same label mortar of about 10cm, when building, layer and section is constructed, every layer controls at about 30cm, join 2 workmans for every section, at 2m and following, template is knocked, cavity is determined whether with sound, vibrate again in the position that shakes of leakage, if desired can tapping template, but dynamics wants light. According to weather condition, form removal after building 12 hours, note the template collision to entity during form removal, carry out maintenance after form removable immediately, it is contemplated that the construction features of Y type pier stud, therefore adopt covered rearing with plastic film maintenance, curing time is 14 days.
It is an advantage of the current invention that: in the present invention, every side saves cement 50 kilograms, shortens construction period, has saved time cost, and entity structure inherent quality is guaranteed. Presentation quality is obviously improved. In overpass queen post Y type, real outer U.S., detects solid strength through each mechanism and meets designing requirement, without honeycomb, pitted skin, crackle, stopped leakage muscle, obtains each side certainly.
Accompanying drawing explanation
Fig. 1 is one of present configuration schematic diagram; Fig. 2 is the two of present configuration schematic diagram.
Detailed description of the invention
Y type pier stud construction technology, according to structure situation, code requirement, arranges tumbling barrel, is placed in advance by tumbling barrel when reinforcing bar binding, then carrying out reinforcing bar binding, invar muscle is crisscross, in groined type, in process of binding, technical staff focuses on the examination of bar spacing precision, and go offline inspection if desired; To ensure up/down perforation; Vibrating radins according to physical dimension and vibrating spear, technical staff carries out vibrating layouting, and to vibrating, examination is inserted in hole in advance, as blocked vibrating spear, reinforcing bar is pressed code requirement adjustment, to ensure channels open.
Testing crew is according to the performance of blender, in conjunction with previous experiences and code requirement, determine mixing time, during stirring, often dish must estimate mixture situation, concrete mixture carries out workability detection before dispatching from the factory, before concrete placings, testing crew carries out workability detection equally, time undesirable, return mixing station and process.
When building pier stud, though workability is controlled effectively, because pier stud is high, sandstone segregation phenomenon is unavoidably there is in concrete mixture after beating to pier stud, in order to ensure that portion occurs without " rotten ", honeycomb, first building the same label mortar of about 10cm, when building, layer and section is constructed, every layer controls at about 30cm, join 2 workmans for every section, at 2m and following, template is knocked, cavity is determined whether with sound, vibrate again in the position that shakes of leakage, if desired can tapping template, but dynamics wants light.
According to weather condition, form removal after building 12 hours, note the template collision to entity during form removal, carry out maintenance after form removable immediately, it is contemplated that the construction features of Y type pier stud, therefore adopt covered rearing with plastic film maintenance, curing time is 14 days.
Construction control
1. the adjustment of match ratio and optimization
According to construction features, build mode, have two kinds of methods available for match ratio: one adopts self-compacting concrete or high throwing to exempt from the concrete that shakes; Existing mix-proportion adjustment is optimized by the two. In line with the principle of " economical rationality ", namely starting existing match ratio is optimized the bimester that project management department's testing crew shifting to an earlier date, concrete condition is as follows:
1.1 according to distance of reinforcing bar, in conjunction with current material, selects 5mm-26.5mm rubble;
1.2 according to pier stud height, slump-loss amount, vibrating has dead angle, and the slump determines 140mm-180mm;
1.3 according to the local situation that entity detection is focused on resilience in Wuxi, and sand coarse aggregate ratio determines 36%-38%;
1.4 according to practical experience, and water consumption is low, suitably increases additional dosage;
1.5 according to design strength, life requirement, it is determined that cement consumption scope;
According to conditions above, testing crew repetition test, in conjunction with the bounce situations of concrete sample, it is proposed that the theoretical match ratio of pier stud construction targetedly;
2. the setting of passage during reinforcing bar binding
According to structure situation, code requirement, tumbling barrel is set, when reinforcing bar binding, tumbling barrel is placed in advance, then carrying out reinforcing bar binding, invar muscle is crisscross, in groined type, in process of binding, technical staff focuses on the examination of bar spacing precision, and go offline inspection if desired. To ensure up/down perforation. Vibrating radins according to physical dimension and vibrating spear, technical staff carries out vibrating layouting, and to vibrating, examination is inserted in hole in advance, as blocked vibrating spear, reinforcing bar is pressed code requirement adjustment, to ensure channels open.
3. the control of concrete workability
Testing crew is according to the performance of blender, in conjunction with previous experiences and code requirement, determine mixing time, during stirring, often dish must estimate mixture situation, concrete mixture carries out workability detection before dispatching from the factory, before concrete placings, testing crew carries out workability detection equally, time undesirable, return mixing station and process.
4. the building of concrete
When building pier stud, though workability is controlled effectively, because pier stud is high, sandstone segregation phenomenon is unavoidably there is in concrete mixture after beating to pier stud, in order to ensure that portion occurs without " rotten ", honeycomb, first building the same label mortar of about 10cm, when building, layer and section is constructed, every layer controls at about 30cm, join 2 workmans for every section, at 2m and following, template is knocked, cavity is determined whether with sound, vibrate again in the position that shakes of leakage, if desired can tapping template, but dynamics wants light.
5. the maintenance of concrete
According to weather condition, form removal after building 12 hours, note the template collision to entity during form removal, carry out maintenance after form removable immediately, it is contemplated that the construction features of Y type pier stud, therefore adopt covered rearing with plastic film maintenance, curing time is 14 days.
Advantage
Every side saves cement 50 kilograms, shortens construction period, has saved time cost, and entity structure inherent quality is guaranteed. Presentation quality is obviously improved.
Technical scheme is not restricted in the scope of embodiment of the present invention. The technology contents of the not detailed description of the present invention is known technology.

Claims (4)

1.Y type pier stud construction technology, it is characterized in that: according to structure situation, code requirement, tumbling barrel is set, being placed in advance by tumbling barrel when reinforcing bar binding, then carrying out reinforcing bar binding, invar muscle is crisscross, in groined type, in process of binding, technical staff focuses on the examination of bar spacing precision, and go offline inspection if desired; To ensure up/down perforation; Vibrating radins according to physical dimension and vibrating spear, technical staff carries out vibrating layouting, and to vibrating, examination is inserted in hole in advance, as blocked vibrating spear, reinforcing bar is pressed code requirement adjustment, to ensure channels open.
2. Y type pier stud construction technology according to claim 1, it is characterized in that: testing crew is according to the performance of blender, in conjunction with previous experiences and code requirement, determine mixing time, during stirring, often dish must estimate mixture situation, concrete mixture carries out workability detection before dispatching from the factory, before concrete placings, testing crew carries out workability detection equally, time undesirable, return mixing station and processes.
3. Y type pier stud construction technology according to claim 1, it is characterized in that: when building pier stud, though workability is controlled effectively, because pier stud is high, sandstone segregation phenomenon is unavoidably there is in concrete mixture after beating to pier stud, in order to ensure that portion occurs without " rotten ", honeycomb, first build the same label mortar of about 10cm, when building, layer and section is constructed, every layer controls at about 30cm, join 2 workmans for every section, at 2m and following, template is knocked, cavity is determined whether with sound, vibrate again in the position that leakage is shaken, if desired can tapping template, but dynamics wants light.
4. Y type pier stud construction technology according to claim 3, it is characterized in that: according to weather condition, form removal after building 12 hours, the template collision to entity is noted during form removal, maintenance is carried out immediately after form removable, considering the construction features of Y type pier stud, therefore adopt covered rearing with plastic film maintenance, curing time is 14 days.
CN201410584959.4A 2014-10-28 2014-10-28 Y-shaped pier column construction process Pending CN105625178A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410584959.4A CN105625178A (en) 2014-10-28 2014-10-28 Y-shaped pier column construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410584959.4A CN105625178A (en) 2014-10-28 2014-10-28 Y-shaped pier column construction process

Publications (1)

Publication Number Publication Date
CN105625178A true CN105625178A (en) 2016-06-01

Family

ID=56040489

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410584959.4A Pending CN105625178A (en) 2014-10-28 2014-10-28 Y-shaped pier column construction process

Country Status (1)

Country Link
CN (1) CN105625178A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108277777A (en) * 2017-12-08 2018-07-13 中交烟台环保疏浚有限公司 Wave wall substep pouring construction process
CN111455858A (en) * 2020-04-23 2020-07-28 安徽省路港工程有限责任公司 Integral pouring construction method for column pier
CN112144417A (en) * 2020-10-12 2020-12-29 中建八局第一建设有限公司 Construction device and construction method for hollow coping of special-shaped pier gem

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108277777A (en) * 2017-12-08 2018-07-13 中交烟台环保疏浚有限公司 Wave wall substep pouring construction process
CN111455858A (en) * 2020-04-23 2020-07-28 安徽省路港工程有限责任公司 Integral pouring construction method for column pier
CN112144417A (en) * 2020-10-12 2020-12-29 中建八局第一建设有限公司 Construction device and construction method for hollow coping of special-shaped pier gem

Similar Documents

Publication Publication Date Title
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN104405123B (en) Cast-in-situ reinforced concrete thin-wall rectangular small bore open tubular column template assembly and construction method thereof
CN109208921A (en) The localization method of building element assembled sleeve embedded bar
CN105625178A (en) Y-shaped pier column construction process
CN110230394A (en) The construction method of constructional column
ATE523305T1 (en) METHOD AND SYSTEM FOR PRODUCING HOLLOW, PRISMATIC, MODULAR REINFORCED CONCRETE ELEMENTS AND ELEMENT OBTAINED THEREFROM
CN106351376B (en) Shed deckhead construction method
CN205134392U (en) Chemistry electric osmose method is united pile foundation and is consolidated side slope model test device
CN104831862B (en) Fiber-reinforced concrete composite thermal insulation permanent template
CN103938649B (en) A kind of construction method on high-rise building cavity basis
CN203022222U (en) Wholly-cast ring beam of brick-concrete building support
CN105201204B (en) A kind of method and structure of rotten when preventing pouring reinforcement concrete column suspension column
CN202945741U (en) Non-vibrating concrete column of steel tube
CN101845797A (en) One-step molding method of vase-shaped columnar pier for urban viaduct bridges
CN205713091U (en) A kind of diagonal column mold plate system
CN205712565U (en) A kind of prefabricated two-sided wall
CN104947853B (en) A kind of Inner standpipe formula cast-in-situ reinforced concrete column and construction method
CN107724384B (en) Pile-to-pile connection construction method
JP6424045B2 (en) Manufacturing method of reinforced structure
CN103882836A (en) Method and filling device for controlling sluice pier cracks
CN203938971U (en) Prefabricated concrete hollow slab termination integral mold plate
CN209179203U (en) Column and basic connection component and frame structure system
CN205296849U (en) Letter storehouse concrete funnel structure
CN110820990B (en) Embedded steel bar positioning and grouting method for PC component construction
CN105804321B (en) Steel pipe gypsum mortar discarded concrete coupled column and preparation method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160601