CN105591318B - A kind of block method of U-shaped net - Google Patents

A kind of block method of U-shaped net Download PDF

Info

Publication number
CN105591318B
CN105591318B CN201511023550.6A CN201511023550A CN105591318B CN 105591318 B CN105591318 B CN 105591318B CN 201511023550 A CN201511023550 A CN 201511023550A CN 105591318 B CN105591318 B CN 105591318B
Authority
CN
China
Prior art keywords
rope
netting
bearing
bearing rope
selvage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201511023550.6A
Other languages
Chinese (zh)
Other versions
CN105591318A (en
Inventor
孟庆强
苏秀成
王小松
张甲雷
邹新梧
黄磊
左韬
刘波
杨怀伟
曹正
郑茂堂
姬广彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Ac Engineering Construction Co
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Tianjin Electric Power Transmission and Transformation Engineering Corp
Original Assignee
State Grid Ac Engineering Construction Co
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Tianjin Electric Power Transmission and Transformation Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Ac Engineering Construction Co, State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd, Tianjin Electric Power Transmission and Transformation Engineering Corp filed Critical State Grid Ac Engineering Construction Co
Priority to CN201511023550.6A priority Critical patent/CN105591318B/en
Publication of CN105591318A publication Critical patent/CN105591318A/en
Application granted granted Critical
Publication of CN105591318B publication Critical patent/CN105591318B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • H02G1/04Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables for mounting or stretching

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The present invention provides a kind of block method of U-shaped net, and each U-shaped net includes:The first netting of side rope, the second netting of side rope, bottom surface the first netting rope and the second netting of bottom surface rope;U-shaped net is built on bearing rope, and bearing rope includes:The upper bearing rope of cross-arm first, the bearing rope of upper cross-arm second, the bearing rope of selvage first, the bearing rope of selvage second and middle bearing rope, including:Using circulating the bearing rope of cross-arm first and the bearing rope of upper cross-arm second on wire saws;Utilize endless rope traction selvage first bearing rope, the bearing rope of selvage second and middle bearing rope;Seating side the first netting rope between the upper bearing rope of cross-arm first and selvage first bearing rope, seating side the second netting rope between the upper bearing rope of cross-arm second and selvage second bearing rope;The first netting of bottom surface rope is installed between the bearing rope of selvage first and middle bearing rope, the second netting of bottom surface rope is installed between the bearing rope of selvage second and middle bearing rope.The critical facility below power transmission line is protected not smashed by power transmission line or pull rope.

Description

A kind of block method of U-shaped net
Technical field
The present invention relates to high-voltage transmission equipment technical field, more particularly to a kind of block method of U-shaped net.
Background technology
With the fast development of extra high voltage line construction, it is commonly encountered in UHV transmission line work progress across important The situation of facility, and show the features such as spanning height more and more higher, number are more and more, operating mode becomes increasingly complex.
In order to ensure the security of newly-built power line crossing, it is desirable to provide a kind of block method, built in high voltage transmission line During if, carry out block and build power transmission line, prevent power transmission line or pull rope from breaking, drop on critical facility, damage.
The content of the invention
In order to solve prior art, the present invention provides a kind of block method of U-shaped net, can prevent high voltage transmission line construction During occur dropping on the critical facility of lower section when wire or pull rope broken string situation, it is important below power transmission line so as to ensure The safety of facility.
The present invention provides a kind of block method of U-shaped net, and applied in high voltage transmission line work progress, each U-shaped net wraps Include following three kinds of netting ropes:The first netting of side rope, the second netting of side rope, bottom surface the first netting rope and the netting of bottom surface second Rope;The U-shaped net is built on bearing rope, and the bearing rope includes:The upper bearing rope of cross-arm first, the bearing rope of upper cross-arm second, The bearing rope of selvage first, the bearing rope of selvage second and middle bearing rope, this method comprise the following steps:
Using circulating the bearing rope of cross-arm first and the bearing rope of upper cross-arm second on wire saws;
Utilize endless rope traction selvage first bearing rope, the bearing rope of selvage second and middle bearing rope;
The first netting of seating side rope between the bearing rope of cross-arm first and the bearing rope of selvage first on described, on described The second netting of seating side rope between the bearing rope of cross-arm second and the bearing rope of selvage second;
The first netting of bottom surface rope is installed between the bearing rope of selvage first and middle bearing rope, in the selvage The second netting of bottom surface rope is installed between the second bearing rope and middle bearing rope.
Preferably, in addition to:Is installed between the bearing rope of selvage first and middle bearing rope spaced a predetermined distance One supports insulative bar, it is spaced the preset distance and the second support is installed between the bearing rope of selvage second and middle bearing rope Insulating bar.
Preferably, bottom surface the first netting rope sets one every two meters, and bottom surface the second netting rope is every two meters Set one.
Preferably, the first supports insulative bar sets one every six meters, and the second supports insulative bar is every six meters Set one.
Preferably, the preset distance is six meters.
Preferably, side the first netting rope sets one every four meters, and side the second netting rope is every four meters Set one.
Preferably, also include before the first netting of side rope is installed:
A pull rope is mounted on the every bearing rope, the pull rope is used to draw the netting rope.
Compared with prior art, the present invention at least has advantages below:
The method that the present embodiment provides, below power transmission line and U-shaped net has been built in side, due to two sides of the U-shaped net Face and bottom surface constitute web frame.Even if power transmission line or traction fracture of rope fall down, and fall in the inside of the U-shaped net, no It can fall on the critical facility below power transmission tower.The critical facility below power transmission line can so be protected not by power transmission line or traction Rope smashes, so as to protect the critical facility below power transmission line.
Brief description of the drawings
, below will be to embodiment or existing in order to illustrate more clearly of the embodiment of the present application or technical scheme of the prior art There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments described in application, for those of ordinary skill in the art, on the premise of not paying creative work, Other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the flow chart of block embodiment of the method one of U-shaped net provided by the invention;
Fig. 2 is U-shaped block device side view corresponding to method provided by the invention;
Fig. 3 is the front view of U-shaped block device provided by the invention;
Fig. 4 is the flow chart of block embodiment of the method two of U-shaped net provided by the invention.
Embodiment
In order that those skilled in the art more fully understand the present invention program, below in conjunction with the embodiment of the present invention Accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is only this Invention part of the embodiment, rather than whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art exist The every other embodiment obtained under the premise of creative work is not made, belongs to the scope of protection of the invention.
Embodiment of the method one:
Referring to Fig. 1, the figure is the flow chart of block embodiment of the method one of U-shaped net provided by the invention.
The block method for the U-shaped net that the present embodiment provides, applied in high voltage transmission line work progress, each U-shaped net wraps Include following three kinds of netting ropes:The first netting of side rope, the second netting of side rope, bottom surface the first netting rope and the netting of bottom surface second Rope;The U-shaped net is built on bearing rope, and the bearing rope includes:The upper bearing rope of cross-arm first, the bearing rope of upper cross-arm second, The bearing rope of selvage first, the bearing rope of selvage second and middle bearing rope, this method comprise the following steps:
S101:Using circulating the bearing rope of cross-arm first and the bearing rope of upper cross-arm second on wire saws;
S102:Utilize endless rope traction selvage first bearing rope, the bearing rope of selvage second and middle bearing rope;
It should be noted that the both ends of all bearing ropes are fixed on bottom surface by corner block respectively, described turn to is slided Car is articulated on the cross-arm of power transmission tower.
S103:The first netting of seating side rope between the bearing rope of cross-arm first and the bearing rope of selvage first on described, Seating side the second netting rope between the bearing rope of upper cross-arm second and selvage second bearing rope;
S104:The first netting of bottom surface rope is installed between the bearing rope of selvage first and middle bearing rope, in institute State and the second netting of bottom surface rope is installed between the bearing rope of selvage second and middle bearing rope.
In order to facilitate method provided by the invention is understood, Fig. 2 and Fig. 3 are may refer to, i.e., method provided by the invention is corresponding U-shaped block device.
It is understood that S101-S104 introduce be a U-shaped net build process, two adjacent power transmission towers it Between need to build multiple U-shaped nets, multiple U-shaped nets form U-shaped block device, so can just prevent from transmitting electricity thread breakage when, avoid Fall on the critical facility below power transmission line.
The method that the present embodiment provides, below power transmission line and U-shaped net has been built in side, due to two sides of the U-shaped net Face and bottom surface constitute web frame.Even if power transmission line or traction fracture of rope fall down, and fall in the inside of the U-shaped net, no It can fall on the critical facility below power transmission tower.The critical facility below power transmission line can so be protected not by power transmission line or traction Rope smashes.
In order to facilitate the U-shaped net for understanding that the present invention is built, Fig. 2 and Fig. 3 may refer to.
Referring to Fig. 2, the figure is the side view of U-shaped net corresponding to method provided by the invention.
It should be noted that U-shaped net provided by the invention is applied on high voltage transmission line, the power transmission tower adjacent positioned at two Between.Between two adjacent power transmission towers include two U-shaped block devices, it is necessary to explanation be U-shaped block device include it is more Individual U-shaped net.The corresponding U-shaped packaging system 100 of power transmission tower left horizontal stretcher as shown in Figure 2, i.e., U-shaped shown in dotted line are U-shaped net. Similarly, a U-shaped block device corresponding to right horizontal stretcher.
Referring to Fig. 3, for the front view of U-shaped block device provided by the invention.
The U-shaped block device that the present embodiment provides, applied in high voltage transmission line work progress, including five kinds of bearing ropes: Upper the first bearing rope of cross-arm A1, the second bearing rope of upper cross-arm A2, the first bearing rope of selvage B1, selvage the second bearing rope B2 and centre Bearing rope B3, in addition to multiple U-shaped nets, each U-shaped net include following three kinds of netting ropes:Side the first netting rope C1, side Two netting rope C2, bottom surface the first netting rope D1 and bottom surface the second netting rope D2;
The first bearing rope of upper cross-arm A1, the second bearing rope of upper cross-arm A2, the first bearing rope of selvage B1, selvage second are held Support rope B2 and middle bearing rope B3 is all connected between two adjacent power transmission towers;Power transmission tower is located at Fig. 3 left and right sides respectively, Two power transmission towers are not shown in Fig. 3.
The first end of side the first netting rope C1 connects upper the first bearing rope of cross-arm A1, and the side first is compiled Nettle C1 the second end connects the first bearing rope of selvage B1;
The first end of side the second netting rope C2 connects upper the second bearing rope of cross-arm A2, and the side second is compiled Nettle C2 the second end connects the second bearing rope of selvage B2;
The first end of bottom surface the first netting rope D1 connects the first bearing rope of selvage B1, the netting of bottom surface first Rope D1 the second end connects the middle bearing rope B3, and the first end of bottom surface the second netting rope D2 connects the selvage second Bearing rope B2, bottom surface the second netting rope D2 the second end connect the middle bearing rope B3.
It should be noted that it is only the U-shaped net for illustrating two laid out in parallel to understand for convenience in Fig. 3, it is defeated at two The U-shaped net shown in multiple Fig. 3 is placed between electric tower, for example, bottom surface the first netting rope D1 and bottom surface the second netting rope D2 are every One is set every two meters, side the first netting rope C1 and side the second netting rope C2 set one every four meters.It is appreciated that , the distance at two D1 intervals can set as needed, and the smaller effect of distance at interval is better, but D1 set it is too close It is more to collect the material needed, and setting up procedure is also relatively time-consuming, can be taken into account between effect and cost to consider interval Distance.The same D1 of D2 and C1, C2 setting principle, will not be repeated here.
With reference to Fig. 2 as can be seen that the U-shaped block device can be prevented during power transmission line is built, thread breakage of transmitting electricity Or dropped to during traction fracture of rope on the critical facility below power transmission tower.Because two sides of the U-shaped net device and bottom surface are equal Constitute web frame.Even if power transmission line or traction fracture of rope fall down, and fall in the inside of the U-shaped packaging system, will not fall On the critical facility below power transmission tower.So the critical facility below power transmission line can be protected not pounded by power transmission line or pull rope It is bad.
Embodiment of the method two:
Referring to Fig. 4, the figure is the flow chart of block embodiment of the method two of U-shaped net provided by the invention.
The block method for the U-shaped net that the present embodiment provides, S401-S402 is identical with S101-S102 respectively, S404-S405 It is identical with S103-S104 respectively, it will not be repeated here.
S403:Also include before the first netting of side rope is installed:
A pull rope is mounted on the every bearing rope, the pull rope is used to draw the netting rope.
S406:The first supports insulative is installed between the bearing rope of selvage first and middle bearing rope spaced a predetermined distance Bar, it is spaced the preset distance and the second supports insulative bar is installed between the bearing rope of selvage second and middle bearing rope.
With continued reference to Fig. 3, the U-shaped net spaced a predetermined distance also includes:Supports insulative bar;For example, every 6 meters of settings One group of supports insulative bar.One group of supports insulative bar is two.It is understood that the spacing distance of supports insulative bar can also join Examine D1 setting principle.
The supports insulative bar is two, is respectively:First supports insulative bar E1 and the second supports insulative bar E2;
The first end of the first supports insulative bar E1 connects the bearing rope of selvage first, the first supports insulative bar E1 the second end connects the middle bearing rope B3;
The first end of the second supports insulative bar E2 connects the bearing rope of selvage second, the second supports insulative bar E2 the second end connects the middle bearing rope B3.
In addition, the U-shaped block device, can also include:Single pole coaster and double-rod coaster, not shown in figure;
The first end of the first supports insulative bar E1 is held by a single pole pulley suspension in the selvage first Support rope B1;
The first end of the second supports insulative bar E2 is held by a single pole pulley suspension in the selvage second Support rope B2;
The second end of the first supports insulative bar E1 and the second end of the second supports insulative bar E2 are by same The individual double-rod pulley suspension is in the middle bearing rope B3.
U-shaped block device similar with bearing rope, that the present embodiment provides, in addition to following five kinds of danish seine ropes:Upper cross-arm One danish seine rope, the second danish seine of upper cross-arm rope, the first danish seine of selvage rope, selvage the second danish seine rope and middle danish seine rope;Danish seine rope figure Not shown in.
The first danish seine of upper cross-arm rope is articulated in the first bearing rope of upper cross-arm A1, for drawing the side first Netting rope C1 first end;
The second danish seine of upper cross-arm rope is articulated in the second bearing rope of upper cross-arm A2, for drawing the side second Netting rope C2 first end;
The first danish seine of selvage rope is articulated in the first bearing rope of selvage B1, for drawing the netting of bottom surface first Rope D1 first end;
The second danish seine of selvage rope is articulated in the second bearing rope of selvage B2, for drawing the netting of bottom surface second Rope D2 first end;
The middle danish seine rope is articulated in the middle bearing rope, for drawing the second of bottom surface the first netting rope D1 End and bottom surface the second netting rope D2 the second end are moved on the middle bearing rope.
The above described is only a preferred embodiment of the present invention, any formal limitation not is made to the present invention.Though So the present invention is disclosed above with preferred embodiment, but is not limited to the present invention.It is any to be familiar with those skilled in the art Member, without departing from the scope of the technical proposal of the invention, all using the methods and technical content of the disclosure above to the present invention Technical scheme makes many possible changes and modifications, or is revised as the equivalent embodiment of equivalent variations.Therefore, it is every without departing from The content of technical solution of the present invention, the technical spirit according to the present invention is to any simple modification made for any of the above embodiments, equivalent Change and modification, still fall within technical solution of the present invention protection in the range of.

Claims (7)

  1. A kind of 1. block method of U-shaped net, it is characterised in that applied in high voltage transmission line work progress, each U-shaped net includes Three kinds of netting ropes below:The first netting of side rope, the second netting of side rope, bottom surface the first netting rope and the second netting of bottom surface rope; The U-shaped net is built on bearing rope, and the bearing rope includes:The upper bearing rope of cross-arm first, the bearing rope of upper cross-arm second, selvage First bearing rope, the bearing rope of selvage second and middle bearing rope, this method comprise the following steps:
    Using circulating the bearing rope of cross-arm first and the bearing rope of upper cross-arm second on wire saws;
    Utilize endless rope traction selvage first bearing rope, the bearing rope of selvage second and middle bearing rope;
    The first netting of seating side rope, the cross-arm on described between the bearing rope of cross-arm first and the bearing rope of selvage first on described The second netting of seating side rope between second bearing rope and the bearing rope of selvage second;
    The first netting of bottom surface rope is installed between the bearing rope of selvage first and middle bearing rope, in the selvage second The second netting of bottom surface rope is installed between bearing rope and middle bearing rope.
  2. 2. the block method of U-shaped net according to claim 1, it is characterised in that also include:Spaced a predetermined distance described First supports insulative bar is installed between the bearing rope of selvage first and middle bearing rope, is spaced the preset distance in the selvage Second supports insulative bar is installed between two bearing ropes and middle bearing rope.
  3. 3. the block method of U-shaped net according to claim 2, it is characterised in that the first netting of bottom surface rope is every two Rice sets one, and bottom surface the second netting rope sets one every two meters.
  4. 4. the block method of U-shaped net according to claim 2, it is characterised in that the first supports insulative bar is every six Rice sets one, and the second supports insulative bar sets one every six meters.
  5. 5. the block method of U-shaped net according to claim 3, it is characterised in that the preset distance is six meters.
  6. 6. the block method of U-shaped net according to claim 1, it is characterised in that the first netting of side rope is every four Rice sets one, and side the second netting rope sets one every four meters.
  7. 7. the block method of U-shaped net according to claim 1, it is characterised in that installing the first netting of side rope Also include before:
    A pull rope is mounted on the every bearing rope, the pull rope is used to draw the netting rope.
CN201511023550.6A 2015-12-30 2015-12-30 A kind of block method of U-shaped net Active CN105591318B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511023550.6A CN105591318B (en) 2015-12-30 2015-12-30 A kind of block method of U-shaped net

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511023550.6A CN105591318B (en) 2015-12-30 2015-12-30 A kind of block method of U-shaped net

Publications (2)

Publication Number Publication Date
CN105591318A CN105591318A (en) 2016-05-18
CN105591318B true CN105591318B (en) 2018-04-03

Family

ID=55930668

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511023550.6A Active CN105591318B (en) 2015-12-30 2015-12-30 A kind of block method of U-shaped net

Country Status (1)

Country Link
CN (1) CN105591318B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111181066B (en) * 2020-01-20 2021-01-26 广东电网能源发展有限公司 Construction method of net sealing protection device of three-phase two-split conductor

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201315444Y (en) * 2008-11-20 2009-09-23 四川电力送变电建设公司 Suspended cable basket blocking net charged crossing support
CN103236656B (en) * 2013-04-08 2017-02-08 国家电网公司 Column suspension type crossing structure and operating method thereof
CN203645249U (en) * 2014-01-10 2014-06-11 葛洲坝集团电力有限责任公司 Hook-net-plane-type charged crossing device

Also Published As

Publication number Publication date
CN105591318A (en) 2016-05-18

Similar Documents

Publication Publication Date Title
CN201315444Y (en) Suspended cable basket blocking net charged crossing support
CN203377546U (en) High speed railway spanning construction apparatus
CN108736377A (en) A kind of payingoff construction spanning the transmission line road lives across system and its application process
CN105591318B (en) A kind of block method of U-shaped net
CN203039298U (en) A safety protective net used for replacing an overhead ground wire under a special spanning condition
CN104410005A (en) Operation method for replacing overhead conductor and ground wire
CN110401137A (en) Transmission line wire replacing options
CN105790156A (en) Transmission line construction new net-blocking construction method
CN206401811U (en) A kind of leap net of crossing live-line Poling Construction
CN103944104B (en) A kind of charged dismounting Bird's Nest method
CN104466857B (en) A kind of preformed strain hardware fitting of Great span
CN105514867A (en) Method for replacing V-shaped insulator string of power transmission line pole
CN205355752U (en) U type block device
CN205355669U (en) Power transmission line construction is with supplementary cross arm
CN102611057A (en) Crossing mesh
CN205911713U (en) Overhead ground wire splint for overhead line
CN203445520U (en) Live spanning device
CN206646424U (en) A kind of express highway intelligent speed limit direction board
CN107947029A (en) A kind of distribution line crosses over shelves thread-changing coaster and its thread-changing method
CN106129898B (en) One kind changes ground wire and crosses over servicing unit
CN204689233U (en) A kind of actinobacillus device of enamelling machine
CN204919488U (en) A damping formula block a river line for blocking superelevation ship
CN104393524B (en) Avoid setting up using aerial earth wire extension pulley group job and cross over frame construction method
CN207098439U (en) Tumble card component and conductor load transfer device
CN206886511U (en) A kind of 110KV line sides install the special hoisting bar of arrester additional

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant