CN105552786B - Transmission line of electricity speed governing rope ladder climbing device - Google Patents

Transmission line of electricity speed governing rope ladder climbing device Download PDF

Info

Publication number
CN105552786B
CN105552786B CN201610105770.1A CN201610105770A CN105552786B CN 105552786 B CN105552786 B CN 105552786B CN 201610105770 A CN201610105770 A CN 201610105770A CN 105552786 B CN105552786 B CN 105552786B
Authority
CN
China
Prior art keywords
speed
climbing device
gearbox
string holes
insulating cord
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610105770.1A
Other languages
Chinese (zh)
Other versions
CN105552786A (en
Inventor
郭瑞红
邹伟华
刘平香
李君宏
吴建宁
司振勇
谢贵文
吴杨
杨少宾
杨庭栋
康真
张晓波
崇兴龙
任亦重
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Qunfeng Electric Power Technology Co Ltd
State Grid Corp of China SGCC
State Grid Ningxia Electric Power Co Ltd
Original Assignee
Shaanxi Qunfeng Electric Power Technology Co Ltd
State Grid Corp of China SGCC
State Grid Ningxia Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Qunfeng Electric Power Technology Co Ltd, State Grid Corp of China SGCC, State Grid Ningxia Electric Power Co Ltd filed Critical Shaanxi Qunfeng Electric Power Technology Co Ltd
Priority to CN201610105770.1A priority Critical patent/CN105552786B/en
Publication of CN105552786A publication Critical patent/CN105552786A/en
Application granted granted Critical
Publication of CN105552786B publication Critical patent/CN105552786B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Ladders (AREA)

Abstract

The invention discloses a kind of transmission line of electricity speed governing rope ladder climbing device, DC speed-regulating motor (9) is connect with gearbox (8), and a nylon roller (5) is respectively fixed on two output shafts of gearbox (8);The upper end of two insulating cords (3) is vertically hung on by insulating cord hanger (2) on conducting wire (1), every insulating cord (3) is pierced by from the string holes (11) on lower installation board (13) on the nylon roller (5) of corresponding position after 4 to 6 circles again after passing through the string holes (11) on upper mounting plate (12), and the lower end of every insulating cord (3) is fixed on ground by earth anchor (7) and tensioned lines (6);Control unit (10) includes power switch (14), reversing switch (15) and speed-regulating switch (16);This patent reduces safety requirements and the overall qualities requirement that operating personnel enters operation field, has founded a kind of new method of power transmission lines overhauling operation.

Description

Transmission line of electricity speed governing rope ladder climbing device
Technical field
The invention patent relates to a kind of power transmission lines overhauling tool, especially a kind of transmission line of electricity speed governing rope ladder climbs Device.
Background technology
With the continuous expansion of China's power grid scale, transmission voltage grade and conducting wire distance to the ground are continuously improved, power transmission line The task that road maintenance undertakes is also increasingly heavier, and power transmission lines overhauling operating personnel can only enter conducting wire to distance by climbing rope ladder From 40 meters transmission lines of electricity below are overhauled, and the transmission line of electricity of 40 meters of conducting wire distance to the ground or more cannot then pass through rope ladder method Into site examining and repairing, because not only taking people, laborious but also be extremely unsafe operational method apart from excessively high.In particular with me Building up successively for state's extra-high voltage grid puts into operation, and new requirement is also proposed to the repair method of UHV transmission line, every at present When secondary tangent tower livewire work, it can only enter highfield by swinging in method, and cannot pass through tradition that operating personnel, which enters conducting wire, Method enters by rope ladder, the overall qualities requirement which increases the limitation of operation and to operating personnel.
And the operational method for entering highfield by rope ladder is easy, safe, easy to operation, why cannot be in extra-high crimping Road uses, and main cause is that extra high voltage line distance to the ground is excessively high (minimum 40 meters, 100 meters of highest or more), and operating personnel can not Normal climbing enters operation field, significantly limits the selectivity to extra high voltage line hotline maintenance method.In order to guarantee I The hotline maintenance of state's extra-high voltage grid, it is necessary to design a kind of transmission line of electricity speed governing rope ladder climbing device, be the inspection of extra-high voltage grid It repaiies and livewire work method is improved and provides new operation means.Transmission line of electricity speed governing rope ladder climbing device is still in blank and leads at home Domain needs further to research and develop and test.
Invention content
The purpose of the present invention is exactly to design a kind of transmission line of electricity speed governing rope ladder climbing device, is realized under power failure and electriferous state Transmission line of electricity examines the safe and reliable entrance operation field of operating personnel, can only pass through pendulum to break away from operating personnel to enter tangent tower Enter method, and the quagmire of operation field cannot be entered by rope ladder by conventional method.
The technical scheme is that transmission line of electricity speed governing rope ladder climbing device includes insulating cord, climbing device main body, tensioned lines And earth anchor, it is characterized in that:The climbing device main body includes that climbing device framework, gearbox, DC speed-regulating motor, power supply and control are single Member is vertically disposed with the upper mounting plate and lower installation board being mutually parallel, gearbox and direct current tune in the middle part of the climbing device framework Speed motor is separately fixed on upper mounting plate and lower installation board, and the output shaft of DC speed-regulating motor and the input shaft of gearbox pass through Shaft coupling connects, and perpendicular to ground, two output shafts of gearbox on same level axis and turn to the input shaft of gearbox It is identical, it is respectively fixed with a nylon roller on the overhanging end of two output shafts of gearbox and forms nylon capstan winch;Two thoroughly do away with The upper end of edge rope is vertically hung on by insulating cord hanger on conducting wire, and every insulating cord is after the string holes on upper mounting plate corresponding Be pierced by again from the string holes on lower installation board after 4 to 6 circles on the nylon roller of position, the lower end of every insulating cord by earth anchor and Tensioned lines are fixed on ground;Described control unit and power supply are respectively and fixedly installed to the upper and lower part of climbing device framework, control Unit includes power switch, reversing switch and speed-regulating switch, and reversing switch and speed-regulating switch are used for the steering of DC speed-regulating motor And adjustment of rotational speed;
The gearbox is the turbine and worm reduction box of uniaxial drive twin shaft output;
Upper mounting plate and lower installation board both sides be respectively set there are one for insulating cord by string holes, in upper mounting plate and The string holes of lower installation board homonymy is one group, and the position of every group of string holes is corresponding with the position of the nylon roller of homonymy, every group upper Lower two string holes are located at the upper and lower part of homonymy nylon roller, and lower in vertical direction pair of upper and lower two string holes In;
The tensile force of tensioned lines is adjusted by the tightener in tensioned lines, it is about 40 kilograms to make tension on every insulating cord.
It is an advantage of the invention that:
1) safety requirements and overall qualities requirement that operating personnel enters operation field are reduced, it is intrinsic to break transmission line of electricity The operating type that can only enter straight line pole operation field by swinging in method, founded a kind of the new of power transmission lines overhauling operation Method.
2) present situation that traditional approach relies on talent's climbing has been broken, has ensured that operating personnel enters operation field and there can be abundance Physical efficiency, climbing device used electronic mode, can be entered operation field with most fast speed, significant increase operating efficiency.
3) applicability is wider, can be applicable in all overhead transmission lines.Broken conducting wire distance to the ground more than 40 meters and It cannot directly enter the operational method of site examining and repairing.
4) higher safety and reliability can significantly more efficient reduction operation wind using speed governing rope ladder climbing device equipment Danger promotes the security management and control to operation;Lifting means reliability.
Description of the drawings
Fig. 1:Transmission line of electricity speed governing rope ladder climbing device mounting structure schematic diagram of the present invention;
Fig. 2:Climbing device main body front view;
Fig. 3:The left view of climbing device main body shown in Fig. 2;
Fig. 4:The vertical view of climbing device main body shown in Fig. 2;
Fig. 5:Insulating cord hanging rack structure front view;
Fig. 6:The left view of insulating cord hanging rack structure shown in Fig. 5;
In figure:1- conducting wires;2- insulating cord hangers;3- insulating cords;4- climbing device frameworks;5- nylon rollers;6- tensioned lines;7- Earth anchor;8- gearboxes;9- DC speed-regulating motors;10- control units;11- string holes;12- upper mounting plates;13- lower installation boards;14- Power switch;15- reversing switches;16- speed-regulating switch;17- power supplys.
Specific implementation mode
As shown in Fig. 2 to Fig. 4, climbing device main body be by climbing device framework 4, Double-outputting speed change box 8, DC speed-regulating motor 9, The frame-shaped construction that the power supply 17 and control unit 10 powered to DC speed-regulating motor 9 form, climbing device framework 4 is by high intensity aluminium The cuboid framework structure that alloy profile is constituted, the length size of frame respectively may be about 500mm, 250mm, 1200mm, accord with Close people's standing demand;It is vertically disposed with the upper mounting plate 12 being mutually parallel and lower installation board 13 at the middle part of climbing device framework 4, on Mounting plate 12 and 13 both sides of lower installation board be respectively set there are one for insulating cord 3 by string holes 11, in 12 He of upper mounting plate Two string holes 11 up and down of lower installation board homonymy are one group, the position phase of the position of every group of string holes 11 and the nylon roller 5 of homonymy Corresponding, the string holes 11 per side is located at the upper and lower part of homonymy nylon roller 5, and upper and lower two string holes 11 are in Vertical Square To upper and lower centering;Gearbox 8 and DC speed-regulating motor 9 are separately fixed on upper mounting plate 12 and lower installation board 13, DC speed regulation The output shaft of motor 9 is connect with the input shaft of gearbox 8 by shaft coupling, and gearbox 8 is the turbine of uniaxial drive twin shaft output Worm speed-down case, the input shaft of gearbox 8 perpendicular to ground, two output shafts of gearbox 8 it is vertical with input shaft and also On same level axis, the steering of 8 two output shafts of gearbox is identical, in the babinet overhanging end of two output shafts of gearbox 8 On be respectively fixed with nylon roller 5 and form nylon capstan winch.
As shown in Figure 1, the upper end of two insulating cords 3 is vertically hung on by insulating cord hanger 2 on conducting wire 1, every insulating cord 3 After the string holes 11 on upper mounting plate 12 on the nylon roller 5 of corresponding position after four to six circles again from lower installation board 13 String holes 11 be pierced by, the lower end of every insulating cord 3 is fixed on ground by earth anchor 7 and tensioned lines 6;Described control unit 10 and electricity Source 17 is respectively and fixedly installed to the upper and lower part of climbing device framework 4, and control unit 10 is fixedly mounted on the upper of climbing device framework 4 Portion is conducive to people station operation and control, power supply 17 in the lower platform of climbing device framework 4 and power supply 17 is fixed since weight is larger 4 high-level balance of climbing device framework and stability are increased on the lower raft of climbing device framework 4;Control unit 10 include power switch 14, reversing switch 15 and speed-regulating switch 16, and power supply 17 is connect by cable with DC speed-regulating motor 9 to straight It flows speed regulating motor 9 to power, the main axis direction and rotating speed tune of reversing switch 15 and speed-regulating switch 16 for DC speed-regulating motor 9 Whole, reversing switch 15 includes uplink shelves, downlink shelves and stopping;The rated voltage of DC speed-regulating motor 9 selected by the present embodiment For 24V, rated power 250W;Power supply 17 is 24v/10A/H high-performance lithium ion batteries.It is provided with tightener in tensioned lines 6, The tensile force that tensioned lines 6 are adjusted by the tightener in tensioned lines 6, by testing and testing repeatedly, tension on every insulating cord 3 At about 40 kilograms, using effect is best, and the load of DC speed-regulating motor 9 at this time, the tensioning degree cooperation of insulating cord 3 are best.
As shown in Figure 5, Figure 6, insulating cord hanger 2 is the rigidity hook that high-strength aluminum alloy is made, and two insulating cords 3 are distinguished The both ends that insulating cord links up with 2 crosspieces are tied up to, insulating cord hook 2 is held in by U-shaped hook on conducting wire 1, and insulating cord links up with 2 conducts The terraced head of rope ladder, light-weight, easy to operate, the spacing between two insulating cords 3 is adjustable and keeps constant at work.
The course of work of transmission line of electricity speed governing software climbing device of the present invention is:
1) one end of two insulating cords 3 is securely tied up to the both ends that insulating cord links up with 2 crosspieces, then insulating cord hook 2 is used Tool is hung on the conducting wire 1 for needing work;Every insulating cord 3 is passed through the string holes 11 on the upper mounting plate 12 of climbing device main body Afterwards, it is pierced by again from the string holes 11 on lower installation board 13 after four to six circles on nylon roller 5;
2) two earth anchors 7 are driven into ground and consolidated by the middle part for the other end of every insulating cord 3 being tied up to respective tensioned lines 6 Fixed, the both ends of two tensioned lines 6 securely tie up on the anchoring pile of two earth anchors 7, and the length of adjustment insulating cord 3 makes insulating cord 3 hang down Histogram to stretching substantially;So that insulating cord 3 is further stretched by the tightener of tensioned lines 6 again, and is adjusted and insulated by tightener The tensioning degree of rope 3;
3) operating personnel station is fastened seat belts on the bottom plate of 4 lower part of climbing device framework, the control on operation control unit 10 System switch.14 are turned on the power switch, reversing switch 15 is placed in upshift, rotates speed-regulating switch 16, speed uplink is made to be maintained at 10 To 35 meter per seconds, climbing device main body is along 3 vertical uplink of insulating cord, reversing switch when midway needs to stop and reach operating position 15 are placed in stop position;
4) after the completion of service work, reversing switch 15 is placed in downlink shelves, speed-regulating switch 16 is rotated, downstream rate is made to keep In 10 to 35 meter per seconds, climbing device main body returns to ground along 3 vertical downlink of insulating cord;
5) 14 are turned off the power switch, the tightener in tensioned lines 6 is adjusted, keeps insulating cord 3 fully relaxed, then from conducting wire 1 Remove insulating cord hook 2;Maintenance terminates.

Claims (4)

1. transmission line of electricity speed governing rope ladder climbing device, including insulating cord (3), climbing device main body, tensioned lines (6) and earth anchor (7), special Sign is:The climbing device main body includes climbing device framework (4), gearbox (8), DC speed-regulating motor (9), power supply (17) and control Unit (10) is vertically disposed with the upper mounting plate (12) and lower installation board being mutually parallel in the middle part of the climbing device framework (4) (13), gearbox (8) and DC speed-regulating motor (9) are separately fixed on upper mounting plate (12) and lower installation board (13), direct current tune The output shaft of speed motor (9) is connect with the input shaft of gearbox (8) by shaft coupling, and the input shaft of gearbox (8) is perpendicular to ground Face, two output shafts of gearbox (8) on same level axis and turn to it is identical, in two output shafts of gearbox (8) It is respectively fixed with a nylon roller (5) on overhanging end and forms nylon capstan winch;The upper end of two insulating cords (3) is hung by insulating cord Frame (2) is vertically hung on conducting wire (1), and every insulating cord (3) is after the string holes (11) on upper mounting plate (12) in corresponding position Nylon roller (5) on around 4 to 6 circle after be pierced by again from the string holes (11) on lower installation board (13), the lower end of every insulating cord (3) It is fixed on ground by earth anchor (7) and tensioned lines (6);Described control unit (10) and power supply (17) are respectively and fixedly installed to climb The upper and lower part of device framework (4), control unit (10) include power switch (14), reversing switch (15) and speed-regulating switch (16), the steering and adjustment of rotational speed of reversing switch (15) and speed-regulating switch (16) for DC speed-regulating motor (9).
2. transmission line of electricity speed governing rope ladder climbing device according to claim 1, it is characterized in that:The gearbox (8) is single shaft Input the turbine and worm reduction box of twin shaft output.
3. transmission line of electricity speed governing rope ladder climbing device according to claim 1, it is characterized in that:Upper mounting plate (12) and lower installation Plate (13) both sides be respectively set there are one for insulating cord (3) by string holes (11), in upper mounting plate (12) and lower installation board (13) string holes of homonymy is one group, and two string holes (11) up and down of every group of string holes (11) are located at homonymy nylon roller (5) Upper and lower part, and upper and lower two string holes (11) descend centering in vertical direction.
4. transmission line of electricity speed governing rope ladder climbing device according to claim 1, it is characterized in that:Pass through the receipts in tensioned lines (6) The tensile force of tight device adjustment tensioned lines (6), it is about 40 kilograms to make tension on every insulating cord (3).
CN201610105770.1A 2016-02-25 2016-02-25 Transmission line of electricity speed governing rope ladder climbing device Expired - Fee Related CN105552786B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610105770.1A CN105552786B (en) 2016-02-25 2016-02-25 Transmission line of electricity speed governing rope ladder climbing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610105770.1A CN105552786B (en) 2016-02-25 2016-02-25 Transmission line of electricity speed governing rope ladder climbing device

Publications (2)

Publication Number Publication Date
CN105552786A CN105552786A (en) 2016-05-04
CN105552786B true CN105552786B (en) 2018-09-28

Family

ID=55831807

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610105770.1A Expired - Fee Related CN105552786B (en) 2016-02-25 2016-02-25 Transmission line of electricity speed governing rope ladder climbing device

Country Status (1)

Country Link
CN (1) CN105552786B (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201276407Y (en) * 2008-10-14 2009-07-22 河南送变电建设公司 Manned electric riser
CN201717559U (en) * 2010-07-18 2011-01-19 陈亚安 Lifting aerodyne
CN203813314U (en) * 2014-02-11 2014-09-03 国家电网公司 Elevating device
CN203911362U (en) * 2014-06-25 2014-10-29 国家电网公司 Lifting mechanism for power transmission and transformation installation and maintenance
CN204271532U (en) * 2014-11-20 2015-04-15 中国南方电网有限责任公司超高压输电公司柳州局 Transmit rope lifting device

Also Published As

Publication number Publication date
CN105552786A (en) 2016-05-04

Similar Documents

Publication Publication Date Title
CN103803373B (en) Elevator with multi-stage safety protection
CN108736377B (en) Live crossing system for paying-off construction crossing power line and application method thereof
CN108512115B (en) Screen sealing system crossing power line by auxiliary cross arm and mounting and dismounting method thereof
CN105896379A (en) Hot-line work platform used for overhead transmission line
CN102664358B (en) Live replacement method for static contact of 220 kV flexible busbar
CN112761348A (en) Hanging basket suspension system without counter weight and installation method
CN205681012U (en) Live working platform for overhead transmission line
CN105552786B (en) Transmission line of electricity speed governing rope ladder climbing device
CN207660355U (en) A kind of pylon convenient for Maintenance and Repair
CN206595631U (en) A kind of transmission line of electricity servicing unit
CN206650368U (en) A kind of high-altitude power equipment maintaining of fixation takes sundries
CN109066467A (en) A kind of insulated platform with comprehensive regulatory function
CN106871827B (en) Portable power transmission line arc sag detection device
CN202416171U (en) Stay cable single cable suspension platform
CN205985949U (en) Tension formula transmission line protection system
CN109256721A (en) A kind of helicopter live-line maintenance operation hanging basket
CN104150393A (en) Micro power electric equipment rotating and hoisting device
CN202616663U (en) Damper replacer for overhead ground wire
CN201883932U (en) Hoop-type vertical insulating single ladder
CN201821035U (en) Foreign-matter electrical treatment device for four-bundle conductor of transmission line
CN209127947U (en) A kind of electric pole dismounting auxiliary device
CN202466433U (en) Dual-parallel stay cable cape
CN109205469A (en) A kind of split type structure of electric block and its electric control system
CN201459612U (en) Squirrel-cage repairing device for bridge stay cable
CN105406402A (en) Foldable and lightweight single-string output type strain insulator string device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180928

Termination date: 20190225

CF01 Termination of patent right due to non-payment of annual fee