CN105550256A - Power grid planning oriented automatic diluting method of geographical wiring diagram - Google Patents

Power grid planning oriented automatic diluting method of geographical wiring diagram Download PDF

Info

Publication number
CN105550256A
CN105550256A CN201510901827.4A CN201510901827A CN105550256A CN 105550256 A CN105550256 A CN 105550256A CN 201510901827 A CN201510901827 A CN 201510901827A CN 105550256 A CN105550256 A CN 105550256A
Authority
CN
China
Prior art keywords
circuit
vacuate
point
line
wiring diagram
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510901827.4A
Other languages
Chinese (zh)
Other versions
CN105550256B (en
Inventor
刘志松
孙皓
马亮
刘行波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUBEI CENTRAL CHINA TECHNOLOGY DEVELOPMENT OF ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Wuhan Power Supply Co of State Grid Hubei Electric Power Co Ltd
Original Assignee
HUBEI CENTRAL CHINA TECHNOLOGY DEVELOPMENT OF ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Wuhan Power Supply Co of State Grid Hubei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUBEI CENTRAL CHINA TECHNOLOGY DEVELOPMENT OF ELECTRIC POWER Co Ltd, State Grid Corp of China SGCC, Wuhan Power Supply Co of State Grid Hubei Electric Power Co Ltd filed Critical HUBEI CENTRAL CHINA TECHNOLOGY DEVELOPMENT OF ELECTRIC POWER Co Ltd
Priority to CN201510901827.4A priority Critical patent/CN105550256B/en
Publication of CN105550256A publication Critical patent/CN105550256A/en
Application granted granted Critical
Publication of CN105550256B publication Critical patent/CN105550256B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/29Geographical information databases
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Databases & Information Systems (AREA)
  • Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Data Mining & Analysis (AREA)
  • Remote Sensing (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a power grid planning oriented automatic diluting method of a geographical wiring diagram. The power grid planning oriented automatic diluting method comprises the following steps: 1) data preparation: according to an area range or an attribute condition, comparing the spatial range or the attribute contents of lines to screen the lines which meet the condition, and caching the electric transmission lines into a list; 2) setting a decision rule of feature points; 3) setting a line diluting factor d; and 4) storing a diluted coordinate point between every two feature points into one coordinate point array according to a line trend, forming a new line according to the line trend after the line finishes diluting, and updating the coordinate point sequence of the original line to form a diluted power grid wiring diagram. Before the power grid wiring diagram is subjected to diluting processing, a feature point constraint condition is set for the power grid wiring diagram, the diluting processing which considers the feature points is carried out, the required feature points and lines are retained, a data size is reduced to a largest extent, and the power grid planning oriented automatic diluting method has the advantages of being high in diluting speed and high in efficiency.

Description

A kind of automatic vacuate method of geographical wiring diagram towards Electric Power Network Planning
Technical field
The present invention relates to power electronics areas of information technology, specifically a kind of automatic vacuate method of geographical wiring diagram towards Electric Power Network Planning.
Background technology
Geographical wiring diagram is the basic data of administration of power networks and Electric Power Network Planning, and the drafting of geographical wiring diagram is an arduousness and the work of complexity, its conventional drafting method take general map as background, AutoCAD Software on Drawing is used to go out geographic position, the path of power circuit and their mutual annexations of generating plant, transformer station.
Traditional evacuating algorithm is the linear vacuate carried out according to geometric algorithm, and the evacuating algorithm that GIS software uses is normally towards the overall situation, processes all data of vacuate that need.But the unique point that traditional evacuating algorithm can not exist in identification data, the data of some key are deleted, cause loss of learning.
Summary of the invention
The invention provides a kind of automatic vacuate method of geographical wiring diagram towards Electric Power Network Planning, the Redundant Control point in circuit can be reduced greatly, simplify circuit, reduce data volume to greatest extent, and reduce data redundancy when transmission of information, and the performance of key message can be made more outstanding, automatic vacuate speed is fast, and efficiency is high.
The automatic vacuate method of geographical wiring diagram towards Electric Power Network Planning, is characterized in that comprising the steps:
Step one, data encasement: by regional extent or attribute conditions, screened the circuit satisfied condition by the spatial dimension of comparison circuit or property content, and be cached in list by these transmission lines of electricity;
Step 2, the decision rule of setting unique point: by setting minimum detection range r, for the vertical range of the transformer station to circuit that judge every bar circuit both sides in transmission line of electricity list, if hang down apart from being less than r, then judge that there is a unique point at this place, judge on this basis to be set to the center of circle so that substation is in place, with r be radius circular scope in whether there is the geometric coordinate point of circuit, if existed, then this geometric coordinate point is unique point, if there is no, then calculate the intersection point of transformer station to circuit, getting intersection point point is unique point, according to the trend of circuit, the head and the tail point of circuit and unique point do not carry out vacuate, on circuit, remaining geometric coordinate point all can fall by vacuate,
Step 3, setting circuit vacuate factor d, vacuate factor d is a parameter of control line vacuate density degree, its value represents the maximum deflection difference value between the circuit coordinate point after vacuate and former center line, line segment in circuit after every 2 unique points connection forms the center line of whole circuit, the vertical range of all non-unique points and center line on computational scheme, and determine the maximum normal distance dmax between every 2 unique points, with dmax compared with vacuate factor d given in advance: if dmax<d, then the point between these 2 unique points is all cast out; If dmax >=d, the reference mark retaining dmax corresponding forms new unique point, and with this point for separation, circuit is cut to two parts, reuses the method, until the equal <d of all dmax, the i.e. vacuate of complete paired transmission line to these two parts;
Coordinate points between step 4, every 2 unique points after vacuate is stored in a coordinate points array according to line alignment, a new circuit is formed according to line alignment after circuit completes vacuate, and upgrade the coordinate point sequence of original circuit, form the electric network wiring scheme after vacuate.
As above towards the automatic vacuate method of geographical wiring diagram of Electric Power Network Planning, it is characterized in that: the regional extent in step one comprises administrative region or electric pressure specifies the transmission line of electricity scope needing to carry out vacuate process.
The present invention can arrange several feature points constraint conditions towards the automatic evacuating algorithm of geographical wiring diagram of Electric Power Network Planning on electric network wiring scheme, the unique point needed for user can be made to remain after vacuate, simultaneously after vacuate process, the Redundant Control point in circuit can be greatly reduced, simplify circuit, thus reduce data volume.Decrease data redundancy when transmission of information, the performance of key message can be made more outstanding, make performing content more short and sweet.
Accompanying drawing explanation
Fig. 1 is the schematic flow sheet of the present invention towards the automatic vacuate method of geographical wiring diagram of Electric Power Network Planning;
Schematic diagram when Fig. 2 is unique point of the present invention judgement;
Fig. 3 is center line of the present invention and evacuating algorithm;
Fig. 4 is the geographical wiring diagram before vacuate;
Geographical wiring diagram after Fig. 5 uses traditional vacuate method to carry out vacuate;
Fig. 6 is the geographical wiring diagram after using vacuate method of the present invention to carry out vacuate.
Embodiment
Below in conjunction with the accompanying drawing in the present invention, the technical scheme in the present invention is clearly and completely described.
Figure 1 shows that the schematic flow sheet of the present invention towards the automatic vacuate method of geographical wiring diagram of Electric Power Network Planning, the automatic vacuate method of the described geographical wiring diagram towards Electric Power Network Planning comprises the steps:
Step one, data encasement: by regional extent or attribute conditions, comprise administrative region, electric pressure etc. and specify the transmission line of electricity scope needing to carry out vacuate process, by the spatial dimension of comparison circuit or property content, the circuit satisfied condition is screened, and these transmission lines of electricity are cached in list.
Step 2, the decision rule of setting unique point: as shown in Figure 2, by setting minimum detection range r, for the vertical range of the transformer station's (point) to circuit that judge every bar circuit both sides in transmission line of electricity list, if hang down apart from being less than r, then judge that there is a unique point at this place, judge on this basis to be set to the center of circle so that substation is in place, with r be radius circular scope in whether there is the geometric coordinate point of circuit, if existed, then this geometric coordinate point is unique point, if there is no, then calculate the intersection point of transformer station to circuit, getting intersection point point is unique point, according to the trend of circuit, the head and the tail point of circuit and unique point do not carry out vacuate, on circuit, remaining geometric coordinate point all can fall by vacuate,
Step 3, setting circuit vacuate factor d.The vacuate factor is a parameter of control line vacuate density degree, its value represents the maximum deflection difference value between the circuit coordinate point after vacuate and former center line, line segment in circuit after every 2 unique points connection forms the center line (as shown in Figure 3) of whole circuit, the vertical range of all non-unique points and center line on computational scheme, and determine the maximum normal distance dmax between every 2 unique points, with dmax compared with vacuate factor d given in advance: if dmax<d, then the point between these 2 unique points is all cast out; If dmax >=d, the reference mark retaining dmax corresponding forms new unique point, and with this point for separation, circuit is cut to two parts, reuses the method, until the equal <d of all dmax, the i.e. vacuate of complete paired transmission line to these two parts.
Coordinate points between step 4, every 2 unique points after vacuate is stored in a coordinate points array according to line alignment, a new circuit is formed according to line alignment after circuit completes vacuate, and upgrade the coordinate point sequence of original circuit, electric network wiring scheme more short and sweet after forming vacuate.
Before carrying out vacuate to the geographical wiring diagram of electrical network, flex point is many, emphasis is not outstanding and data volume is large, and geographical wiring diagram as shown in Figure 4.
Traditional vacuate belongs to linear vacuate, and the result figure utilizing such vacuate method to carry out vacuate can to obtain as shown in Figure 5, can see from figure is, the some disconnection that power network line and transformer station etc. must retain after carrying out vacuate, causes loss of learning.
After utilizing the automatic evacuating algorithm of the geographical wiring diagram towards Electric Power Network Planning invented to carry out vacuate to wiring diagram herein, result as shown in Figure 6.By arranging the unique point rule constrains such as dotted line on electric network wiring scheme, the unique point needed for user being remained after vacuate, decreases data volume to greatest extent, make wiring diagram more intuitively readable.
The above; be only the specific embodiment of the present invention, but protection scope of the present invention is not limited thereto, anyly belongs to those skilled in the art in the technical scope that the present invention discloses; the change that can expect easily or replacement, all should be encompassed within protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with the protection domain of claim.

Claims (2)

1., towards the automatic vacuate method of geographical wiring diagram of Electric Power Network Planning, it is characterized in that comprising the steps:
Step one, data encasement: by regional extent or attribute conditions, screened the circuit satisfied condition by the spatial dimension of comparison circuit or property content, and be cached in list by these transmission lines of electricity;
Step 2, the decision rule of setting unique point: by setting minimum detection range r, for the vertical range of the transformer station to circuit that judge every bar circuit both sides in transmission line of electricity list, if hang down apart from being less than r, then judge that there is a unique point at this place, judge on this basis to be set to the center of circle so that substation is in place, with r be radius circular scope in whether there is the geometric coordinate point of circuit, if existed, then this geometric coordinate point is unique point, if there is no, then calculate the intersection point of transformer station to circuit, getting intersection point point is unique point, according to the trend of circuit, the head and the tail point of circuit and unique point do not carry out vacuate, on circuit, remaining geometric coordinate point all can fall by vacuate,
Step 3, setting circuit vacuate factor d, vacuate factor d is a parameter of control line vacuate density degree, its value represents the maximum deflection difference value between the circuit coordinate point after vacuate and former center line, line segment in circuit after every 2 unique points connection forms the center line of whole circuit, the vertical range of all non-unique points and center line on computational scheme, and determine the maximum normal distance dmax between every 2 unique points, with dmax compared with vacuate factor d given in advance: if dmax<d, then the point between these 2 unique points is all cast out; If dmax >=d, the reference mark retaining dmax corresponding forms new unique point, and with this point for separation, circuit is cut to two parts, reuses the method, until the equal <d of all dmax, the i.e. vacuate of complete paired transmission line to these two parts;
Coordinate points between step 4, every 2 unique points after vacuate is stored in a coordinate points array according to line alignment, a new circuit is formed according to line alignment after circuit completes vacuate, and upgrade the coordinate point sequence of original circuit, form the electric network wiring scheme after vacuate.
2. as claimed in claim 1 towards the automatic vacuate method of geographical wiring diagram of Electric Power Network Planning, it is characterized in that: the regional extent in step one comprises administrative region or electric pressure specifies the transmission line of electricity scope needing to carry out vacuate process.
CN201510901827.4A 2015-12-08 2015-12-08 A kind of geographical wiring diagram towards Electric Power Network Planning vacuates method automatically Active CN105550256B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510901827.4A CN105550256B (en) 2015-12-08 2015-12-08 A kind of geographical wiring diagram towards Electric Power Network Planning vacuates method automatically

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510901827.4A CN105550256B (en) 2015-12-08 2015-12-08 A kind of geographical wiring diagram towards Electric Power Network Planning vacuates method automatically

Publications (2)

Publication Number Publication Date
CN105550256A true CN105550256A (en) 2016-05-04
CN105550256B CN105550256B (en) 2018-07-31

Family

ID=55829445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510901827.4A Active CN105550256B (en) 2015-12-08 2015-12-08 A kind of geographical wiring diagram towards Electric Power Network Planning vacuates method automatically

Country Status (1)

Country Link
CN (1) CN105550256B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108205565A (en) * 2016-12-19 2018-06-26 北京四维图新科技股份有限公司 Electronic map element vacuates method, apparatus and terminal
CN110750556A (en) * 2019-10-26 2020-02-04 武汉中海庭数据技术有限公司 Method and device for thinning and gap filling of geographic data and storage medium
CN112163330A (en) * 2020-09-23 2021-01-01 武汉大学 Power distribution network planning graph visibility optimization method
CN115630181A (en) * 2022-11-04 2023-01-20 中科星图数字地球合肥有限公司 Data thinning method, device and related equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101458818A (en) * 2008-09-26 2009-06-17 深圳市路畅科技有限公司 Graphic data compression processing method based on folding line evacuating algorithm
CN101493330A (en) * 2008-01-23 2009-07-29 厦门雅迅网络股份有限公司 Map vector data vacuating method in network navigation of mobile phone
CN102542901A (en) * 2010-12-17 2012-07-04 上海博泰悦臻电子设备制造有限公司 Line segment vacuating device for electronic map and method thereof
CN102568009A (en) * 2010-12-17 2012-07-11 上海博泰悦臻电子设备制造有限公司 Line segment reducing device and method for electronic map
CN103839228A (en) * 2012-11-23 2014-06-04 厦门雅迅网络股份有限公司 Data rarefying and smooth processing method based on vector map

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101493330A (en) * 2008-01-23 2009-07-29 厦门雅迅网络股份有限公司 Map vector data vacuating method in network navigation of mobile phone
CN101458818A (en) * 2008-09-26 2009-06-17 深圳市路畅科技有限公司 Graphic data compression processing method based on folding line evacuating algorithm
CN102542901A (en) * 2010-12-17 2012-07-04 上海博泰悦臻电子设备制造有限公司 Line segment vacuating device for electronic map and method thereof
CN102568009A (en) * 2010-12-17 2012-07-11 上海博泰悦臻电子设备制造有限公司 Line segment reducing device and method for electronic map
CN103839228A (en) * 2012-11-23 2014-06-04 厦门雅迅网络股份有限公司 Data rarefying and smooth processing method based on vector map

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘晓红 等: "矢量数据压缩的角度分段道格拉斯算法研究", 《四川测绘》 *
卢英水 等: "基于特征点的高程点自动抽稀法", 《测绘与空间地理信息》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108205565A (en) * 2016-12-19 2018-06-26 北京四维图新科技股份有限公司 Electronic map element vacuates method, apparatus and terminal
CN110750556A (en) * 2019-10-26 2020-02-04 武汉中海庭数据技术有限公司 Method and device for thinning and gap filling of geographic data and storage medium
CN112163330A (en) * 2020-09-23 2021-01-01 武汉大学 Power distribution network planning graph visibility optimization method
CN115630181A (en) * 2022-11-04 2023-01-20 中科星图数字地球合肥有限公司 Data thinning method, device and related equipment
CN115630181B (en) * 2022-11-04 2024-03-15 中科星图数字地球合肥有限公司 Data thinning method and device and related equipment

Also Published As

Publication number Publication date
CN105550256B (en) 2018-07-31

Similar Documents

Publication Publication Date Title
KR101354627B1 (en) Engineering topology generating method of the digital substation and the apparatus thereof
CN105550256A (en) Power grid planning oriented automatic diluting method of geographical wiring diagram
CN103218398B (en) Intelligent substation SCL (substation configuration description language) file difference comparison method
CN103762591A (en) Power distribution network topology layout method
CN102044869A (en) Special topology analysis method and device for distribution network
CN107527112B (en) Method and equipment for determining shortest path between power equipment
CN103218478B (en) Depth Priority Searching and the search system of topological isolated island is eliminated for power distribution network
CN104463715A (en) Pattern and model verifying method of distribution automation master station system and geographical information system
CN106940706A (en) The system and method for creating the geographical space network model in simultaneously managing customer environment
CN106685736B (en) Determine the method and device for the failure base station that association is broken down
CN105184011A (en) Automatic transformer substation WEB primary connection diagram forming method and device
CN105138777A (en) Pole tower model selection method and device
CN109933634B (en) Power system graph drawing method based on power radiation range
CN112560862A (en) Text recognition method and device and electronic equipment
CN104102790A (en) GIS (Geographic Information System)-based automatic diagram forming system and method of power supply diagram
CN111027746A (en) Intelligent distribution network system ring network diagram automatic generation method and device
CN111953072B (en) Low-voltage distribution area topology identification method, device, equipment and storage medium
CN102185706A (en) Method for generating IEEE1394 (Institute of Electrical and Electronics Engineers 1394) network topological graph
CN103646116A (en) Method and device for creating graphical interface of equipment in distribution network
CN108829959B (en) Service-driven-oriented distribution network thematic map automatic generation method
WO2013026178A1 (en) Orthogonal layout generation
CN113743057A (en) Object recognition redrawing-based power grid OCS drawing conversion method
CN103441988A (en) Data migration method crossing GIS platforms
CN104363612B (en) Piecemeal wireless sensor network restorative procedure based on mobile relay scheduling
CN109830954A (en) The topological hierarchy recognition methods automatically generated suitable for power grid visualization simulation model

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant