CN105184011A CN201510626491.5A CN201510626491A CN105184011A CN 105184011 A CN105184011 A CN 105184011A CN 201510626491 A CN201510626491 A CN 201510626491A CN 105184011 A CN105184011 A CN 105184011A
Authority
CN
China
Prior art keywords
web
wiring diagram
transformer station
information
automatic mapping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510626491.5A
Other languages
Chinese (zh)
Inventor
初成刚
文斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rui Rui Technology (tianjin) Co Ltd
Original Assignee
Rui Rui Technology (tianjin) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rui Rui Technology (tianjin) Co Ltd filed Critical Rui Rui Technology (tianjin) Co Ltd
Priority to CN201510626491.5A priority Critical patent/CN105184011A/en
Publication of CN105184011A publication Critical patent/CN105184011A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention provides an automatic transformer substation WEB primary connection diagram forming method and device. Device information depicted in a transformer substation model file can be automatically converted into a transformer substation WEB primary connection diagram, and when the topology relation changes, a system automatically scans the changes of the transformer substation model file and regenerates a connecting diagram. By means of the method and device, the transformer substation WEB primary connection diagram can be automatically formed, and when the system monitors the changes of the transformer substation model file, the connecting diagram can be automatically renewed, and the diagram drawing work of maintainers is greatly reduced. The system automatically links data information with the diagram, manual punctuating is not needed, lots of complicated operation is reduced, and the automation level of the system is improved.

Description

Transformer station WEB primary connection figure automatic mapping method and device
Technical field
The invention belongs to power system automatic field, particularly relate to a kind of transformer station WEB primary connection figure automatic mapping method and device.
Background technology
The primary connection figure of transformer station mainly shows the electrical wiring between major motor, electrical equipment, circuit such as generator, transformer, bus, isolating switch, power circuit in this system, can obtain the finer understanding to this system by wiring diagram.WEB wiring diagram is then be converted to by traditional bus arrangement figure automatically to refresh real-time webpage, enables user check the running status of system anywhere or anytime by browser.Hand drawn WEB wiring diagram, brings huge workload to operation maintenance personnel, particularly when system architecture changes, needs manually to upgrade each figure.This mode can not adapt to the growth requirement of energy internet gradually.
Summary of the invention
In view of this, the object of the invention is to propose a kind of transformer station WEB primary connection figure automatic mapping method and device, effectively reduce the Plot Work of operation maintenance personnel, reduce operation loaded down with trivial details in a large number, improve the automatization level of system.
For achieving the above object, technical scheme of the present invention is achieved in that transformer station WEB primary connection figure automatic mapping method, comprises the following steps:
Step 0:WEB server, by transformer station model file, obtains substation information and facility information; Described transformer station model file instrument generates or hand-coding, for describing the essential information of transformer station;
Step 1:WEB server, by wiring diagram MBM, determines the mode of connection of primary equipment, generates wiring diagram information model;
Step 2:WEB browser is by WEB automatic mapping CMOS macro cell WEB wiring diagram;
Step 3:WEB browser passes through graph data driver module, automatic refresh graphics.
Further, described in step 0, the essential information of transformer station comprises electric pressure, interval, equipment, subset, tie point.
Further, described in step 1, the workflow of wiring diagram MBM is:
Step 10: scanning mode of connection feature database, stores the characteristic information of the typical mode of connection, comprising: line number, bus number, bus connecting line number, primary equipment type etc. in mode of connection feature database;
Step 11: whether mate known type wiring diagram, be: Automatic Optimal layout, no, default algorithm generates layout;
Step 12: generate wiring diagram graphical model, include wiring diagram size information in graphical model, each pel positional information, data binding information.
Further, described in step 2, the workflow of WEB automatic mapping module is:
Step 20: read wiring diagram information model;
Step 21: connect pel storehouse, therefrom extracts required figure meta template;
Step 22: according to graphics template, system draws wiring diagram automatically.
Further, described in step 3, the flow process of graph data driver module is:
Step 30: the web page tag extracting binding data;
Step 31: set up a local Hash array, web page tag is associated with back-end data;
Step 32: when loading for the first time, refreshes total data, afterwards periodic refreshing delta data.
Another aspect of the present invention, transformer station WEB primary connection figure automatic mapping device, comprises the transformer station model file read module of WEB server, for obtaining substation information and facility information; Wiring diagram MBM, for determining the mode of connection of primary equipment, generates wiring diagram information model; And the WEB automatic mapping module of web browser, for generating WEB wiring diagram; Graph data driver module, for automatic refresh graphics.
Further, described transformer station model file read module comprises electric pressure reading unit, interval reading unit, equipment reading unit, subset reading unit, tie point reading unit, for reading the data of electric pressure, interval, equipment, subset, tie point.
Further, described wiring diagram MBM comprises: scanning mode of connection feature database, for storing the characteristic information of the typical mode of connection; Matching judgment unit, for judging whether coupling known type wiring diagram, described matching judgment unit also comprises Automatic Optimal layout units and default algorithm generates layout units; Wiring diagram figure model generation unit, for generating wiring diagram graphical model, includes wiring diagram size information unit in described graphical model, each pel positional information unit, data binding message unit.
Further, described WEB automatic mapping module comprises reading unit, for reading wiring diagram information model; Connecting extraction unit, for connecting pel storehouse, therefrom extracting required figure meta template; Drawing unit, for according to graphics template, system draws wiring diagram automatically.
Further, described graph data driver module comprises extraction unit, for extracting the web page tag of binding data; Hash array location, for setting up a local Hash array, associates web page tag with back-end data; Refresh unit, when loading for the first time, refreshes total data, afterwards periodic refreshing delta data.
Relative to prior art, transformer station WEB primary connection figure automatic mapping method of the present invention and device have following advantage: the application of the invention, the facility information described in transformer station model file can be automatically converted to transformer station WEB primary connection figure, when topological relation changes, the change of system autoscan transformer station model file, regenerates wiring diagram.Use the present invention can complete the automatic mapping of transformer station WEB primary connection figure, when system monitoring is to transformer station model file change, automatically can upgrade wiring diagram, the Plot Work of great less operation maintenance personnel.System is graphic associated data information automatically, without the need to manually adding some points, decreasing operation loaded down with trivial details in a large number, improve the automatization level of system.
Accompanying drawing explanation
The accompanying drawing forming a part of the present invention is used to provide a further understanding of the present invention, and schematic description and description of the present invention, for explaining the present invention, does not form inappropriate limitation of the present invention.
In the accompanying drawings:
Fig. 1 is system flowchart of the present invention.
Fig. 2 is software architecture diagram of the present invention.
Fig. 3 is wiring diagram MBM process flow diagram of the present invention.
Fig. 4 is WEB automatic mapping block flow diagram of the present invention.
Fig. 5 is graph data driver module process flow diagram of the present invention.
Embodiment
It should be noted that, when not conflicting, the embodiment in the present invention and the feature in embodiment can combine mutually.
Below with reference to the accompanying drawings and describe the present invention in detail in conjunction with the embodiments.
As shown in Figure 1, 2, transformer station model file is the text of an XML format, and instrument can be used to generate, also can hand-coding.In transformer station model file, describe the essential information (comprising electric pressure, interval, equipment, subset, tie point etc.) of transformer station, be the important input file of whole system.
Wiring diagram MBM, WEB automatic mapping module, graph data driver module are three large nucleus modules of system, during practical application:
Wiring diagram MBM, for operating in the WEB service in WEB server (as tomcat or jboss), can use relevant database (as: MySQL or Oracle) to carry out data storage;
WEB automatic mapping module, graph data driver module are the js class libraries of WEB page, and WEB graph rendering is responsible for the wiring diagram information model returned on backstage, is plotted on webpage.Graph data driver module is responsible for communicating with WEB service, acquisition number factually time change information, and periodic refreshing.
The main flow of system, as shown in Figure 1:
Step 0: by transformer station model file, obtain substation information and facility information, this file is the text of an XML format, and instrument can be used to generate, also can hand-coding.The essential information (comprising electric pressure, interval, equipment, subset, tie point etc.) of transformer station is described in transformer station model file.
Step 1: by wiring diagram MBM, determines the mode of connection of primary equipment, generates wiring diagram information model;
Step 2: by WEB automatic mapping CMOS macro cell WEB wiring diagram;
Step 3: by graph data driver module, automatic refresh graphics;
The main flow of wiring diagram MBM, as shown in Figure 3:
Step 0: scanning mode of connection feature database, stores the characteristic information of the typical mode of connection, comprising: line number, bus number, bus connecting line number, primary equipment type etc. in mode of connection feature database.
Step 1: whether mate known type wiring diagram, be: Automatic Optimal layout, no, default algorithm generates layout.The wiring diagram type that can identify has: 1. single busbar 2. double-bus 3. triple bus-bar 4. 3/2 wiring 5. 4/3 wiring 6. bus one transformer one genset unit connection 7. Gratz connection 8. angle scheme (or claiming annular).Automatic Optimal layout: according to the difference of the mode of connection, to the position of bus, different settings is carried out in the shape of equipment, direction, position.Default algorithm: in current connecting relation, finds out the longest connection string connected successively, using this string as trunk, according to position from left to right, is arranged in order, supplements entire residual connecting relation on this basis.
Step 2: generate wiring diagram graphical model, include wiring diagram size information in graphical model, each pel positional information, data binding information.
As shown in Figure 4: WEB figure automatic mapping block process is as follows:
Step 0: read wiring diagram information model;
Step 1: connect pel storehouse, therefrom extracts required figure meta template;
Wherein, pel is exactly the elementary cell of composition diagram picture, in the present system, is used for the shape information of a description force device.
Figure meta template, is the template of a description particular type force device shape information, can draws out the display mode of certain force device under different conditions by figure meta template, as when isolating switch closes being green, be red during conjunction, be a shape when handcart closes, timesharing is another shape.
Pel storehouse, is a database storing all types of figure meta template, comprises disconnecting link, handcart, bus, transformer etc.;
Step 2: according to graphics template, system draws wiring diagram automatically.In wiring diagram graphical model, described the position confidence of each pel, figure meta template corresponding in integrating step 1, is plotted in each pel the drafting that assigned address can complete wiring diagram.
As shown in Figure 5, graph data driver module flow process is:
Step 0: the web page tag extracting binding data;
Step 1: set up a local Hash array, web page tag is associated with back-end data;
Step 2: when loading for the first time, refreshes total data, afterwards periodic refreshing delta data.
Use such scheme can complete the automatic mapping of transformer station WEB primary connection figure, when system monitoring is to transformer station model file change, automatically can upgrade wiring diagram, the Plot Work of great less operation maintenance personnel.System is graphic associated data information automatically, without the need to manually adding some points, decreasing operation loaded down with trivial details in a large number, improve the automatization level of system.
The foregoing is only preferred embodiment of the present invention, not in order to limit the present invention, within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (10)

1. transformer station WEB primary connection figure automatic mapping method, is characterized in that, comprise the following steps:
Step 0:WEB server, by transformer station model file, obtains substation information and facility information; Described transformer station model file instrument generates or hand-coding, for describing the essential information of transformer station;
Step 1:WEB server, by wiring diagram MBM, determines the mode of connection of primary equipment, generates wiring diagram information model;
Step 2:WEB browser is by WEB automatic mapping CMOS macro cell WEB wiring diagram;
Step 3:WEB browser passes through graph data driver module, automatic refresh graphics.
2. transformer station WEB primary connection figure automatic mapping method according to claim 1, it is characterized in that, described in step 0, the essential information of transformer station comprises electric pressure, interval, equipment, subset, tie point.
3. transformer station WEB primary connection figure automatic mapping method according to claim 1, it is characterized in that, described in step 1, the workflow of wiring diagram MBM is:
Step 10: scanning mode of connection feature database, stores the characteristic information of the typical mode of connection in mode of connection feature database;
Step 11: whether mate known type wiring diagram, be: Automatic Optimal layout, no, default algorithm generates layout;
Step 12: generate wiring diagram graphical model, include wiring diagram size information in graphical model, each pel positional information, data binding information.
4. transformer station WEB primary connection figure automatic mapping method according to claim 1, it is characterized in that, described in step 2, the workflow of WEB automatic mapping module is:
Step 20: read wiring diagram information model;
Step 21: connect pel storehouse, therefrom extracts required figure meta template;
Step 22: according to graphics template, system draws wiring diagram automatically.
5. transformer station WEB primary connection figure automatic mapping method according to claim 1, it is characterized in that, described in step 3, the flow process of graph data driver module is:
Step 30: the web page tag extracting binding data;
Step 31: set up a local Hash array, web page tag is associated with back-end data;
Step 32: when loading for the first time, refreshes total data, afterwards periodic refreshing delta data.
6. transformer station WEB primary connection figure automatic mapping device, is characterized in that: the transformer station model file read module comprising WEB server, for obtaining substation information and facility information; Wiring diagram MBM, for determining the mode of connection of primary equipment, generates wiring diagram information model; And the WEB automatic mapping module of web browser, for generating WEB wiring diagram; Graph data driver module, for automatic refresh graphics.
7. transformer station WEB primary connection figure automatic mapping device according to claim 6, it is characterized in that: described transformer station model file read module comprises electric pressure reading unit, interval reading unit, equipment reading unit, subset reading unit, tie point reading unit, for reading the data of electric pressure, interval, equipment, subset, tie point.
8. transformer station WEB primary connection figure automatic mapping device according to claim 6, is characterized in that: described wiring diagram MBM comprises: scanning mode of connection feature database, for storing the characteristic information of the typical mode of connection; Matching judgment unit, for judging whether coupling known type wiring diagram, described matching judgment unit also comprises Automatic Optimal layout units and default algorithm generates layout units; Wiring diagram figure model generation unit, for generating wiring diagram graphical model, includes wiring diagram size information unit in described graphical model, each pel positional information unit, data binding message unit.
9. transformer station WEB primary connection figure automatic mapping device according to claim 6, is characterized in that: described WEB automatic mapping module comprises reading unit, for reading wiring diagram information model; Connecting extraction unit, for connecting pel storehouse, therefrom extracting required figure meta template; Drawing unit, for according to graphics template, system draws wiring diagram automatically.
10. transformer station WEB primary connection figure automatic mapping device according to claim 6, is characterized in that: described graph data driver module comprises extraction unit, for extracting the web page tag of binding data; Hash array location, for setting up a local Hash array, associates web page tag with back-end data; Refresh unit, when loading for the first time, refreshes total data, afterwards periodic refreshing delta data.
CN201510626491.5A 2015-09-28 2015-09-28 Automatic transformer substation WEB primary connection diagram forming method and device Pending CN105184011A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510626491.5A CN105184011A (en) 2015-09-28 2015-09-28 Automatic transformer substation WEB primary connection diagram forming method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510626491.5A CN105184011A (en) 2015-09-28 2015-09-28 Automatic transformer substation WEB primary connection diagram forming method and device

Publications (1)

Publication Number Publication Date
CN105184011A true CN105184011A (en) 2015-12-23

Family

ID=54906090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510626491.5A Pending CN105184011A (en) 2015-09-28 2015-09-28 Automatic transformer substation WEB primary connection diagram forming method and device

Country Status (1)

Country Link
CN (1) CN105184011A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106503298A (en) * 2016-09-26 2017-03-15 许继电气股份有限公司 A kind of Topology connection drawing generating method of intelligent substation and device
CN106600742A (en) * 2016-12-12 2017-04-26 浙江知水信息技术有限公司 Hydropower station wiring diagram and unit real-time running condition displaying method
CN107273574A (en) * 2017-05-17 2017-10-20 国网上海市电力公司 A kind of power transmission network automatic mapping technology that system is dispatched based on D5000
CN107292003A (en) * 2017-06-06 2017-10-24 南京南瑞继保电气有限公司 A kind of automatic generating method of electric network station wiring diagram
CN112000831A (en) * 2020-08-13 2020-11-27 贵州电网有限责任公司 Abnormal data identification optimization method based on transformer substation graph transformation
CN112529541A (en) * 2020-12-25 2021-03-19 山东鲁能软件技术有限公司 Method and system for generating equipment measurement label in distribution network line diagram
CN112560132A (en) * 2020-12-24 2021-03-26 山东鲁能软件技术有限公司 Thematic map automatic mapping system, method and device based on automatic mapping algorithm
CN114610927A (en) * 2020-12-09 2022-06-10 南京泓瑞科信息科技有限公司 Method and device for generating distribution network diagram
CN114780186A (en) * 2022-04-02 2022-07-22 国电南瑞科技股份有限公司 Method and system for quickly generating comprehensive information description file based on switching station

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101339503A (en) * 2008-07-08 2009-01-07 江苏方天电力技术有限公司 Electric network wiring scheme on-line editing configuration method
CN102436523A (en) * 2011-10-17 2012-05-02 浙江省电力试验研究院 Method for automatically mapping digital substation interval wiring diagram
CN102760186A (en) * 2012-06-12 2012-10-31 中国电力科学研究院 Method for automatically generating vector graphics of intelligent transformer station
CN103678790A (en) * 2013-12-03 2014-03-26 国家电网公司 Automatic modeling method for power transmission network line loss model based on CIM (common information model)
CN104361184A (en) * 2014-11-21 2015-02-18 贵州电网公司电力调度控制中心 Automatic layout and wiring system and method of power grid

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101339503A (en) * 2008-07-08 2009-01-07 江苏方天电力技术有限公司 Electric network wiring scheme on-line editing configuration method
CN102436523A (en) * 2011-10-17 2012-05-02 浙江省电力试验研究院 Method for automatically mapping digital substation interval wiring diagram
CN102760186A (en) * 2012-06-12 2012-10-31 中国电力科学研究院 Method for automatically generating vector graphics of intelligent transformer station
CN103678790A (en) * 2013-12-03 2014-03-26 国家电网公司 Automatic modeling method for power transmission network line loss model based on CIM (common information model)
CN104361184A (en) * 2014-11-21 2015-02-18 贵州电网公司电力调度控制中心 Automatic layout and wiring system and method of power grid

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
ZHANG L: "Research on Web-based Real-time Monitoring System on SVG and Comet", 《TELKOMNIKA INDONESIAN JOURNAL OF ELECTRICAL ENGINEERING》 *
沙树名 等: "一种基于CIM的厂站接线图自动生成技术", 《电力系统自动化》 *
许杨: "基于SVG的电网实时数据动态显示技术的研究", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106503298A (en) * 2016-09-26 2017-03-15 许继电气股份有限公司 A kind of Topology connection drawing generating method of intelligent substation and device
CN106503298B (en) * 2016-09-26 2019-11-26 许继电气股份有限公司 A kind of Topology connection drawing generating method of intelligent substation and device
CN106600742A (en) * 2016-12-12 2017-04-26 浙江知水信息技术有限公司 Hydropower station wiring diagram and unit real-time running condition displaying method
CN107273574A (en) * 2017-05-17 2017-10-20 国网上海市电力公司 A kind of power transmission network automatic mapping technology that system is dispatched based on D5000
CN107292003A (en) * 2017-06-06 2017-10-24 南京南瑞继保电气有限公司 A kind of automatic generating method of electric network station wiring diagram
CN107292003B (en) * 2017-06-06 2020-09-04 南京南瑞继保电气有限公司 Automatic generation method of power grid station wiring diagram
CN112000831A (en) * 2020-08-13 2020-11-27 贵州电网有限责任公司 Abnormal data identification optimization method based on transformer substation graph transformation
CN112000831B (en) * 2020-08-13 2024-04-19 贵州电网有限责任公司 Abnormal data identification optimization method based on substation graph transformation
CN114610927A (en) * 2020-12-09 2022-06-10 南京泓瑞科信息科技有限公司 Method and device for generating distribution network diagram
CN112560132A (en) * 2020-12-24 2021-03-26 山东鲁能软件技术有限公司 Thematic map automatic mapping system, method and device based on automatic mapping algorithm
CN112560132B (en) * 2020-12-24 2022-11-04 山东鲁能软件技术有限公司 Thematic map automatic mapping system, method and device based on automatic mapping algorithm
CN112529541A (en) * 2020-12-25 2021-03-19 山东鲁能软件技术有限公司 Method and system for generating equipment measurement label in distribution network line diagram
CN114780186A (en) * 2022-04-02 2022-07-22 国电南瑞科技股份有限公司 Method and system for quickly generating comprehensive information description file based on switching station
CN114780186B (en) * 2022-04-02 2023-12-15 国电南瑞科技股份有限公司 Method and system for rapidly generating comprehensive information description file based on switch station

Similar Documents

Publication Publication Date Title
CN105184011A (en) Automatic transformer substation WEB primary connection diagram forming method and device
CN107292003B (en) Automatic generation method of power grid station wiring diagram
CN104376416B (en) Production Managementsystem For Electricpower Network and dispatch automated system graphic interaction method
CN102760186B (en) Method for automatically generating vector graphics of intelligent transformer station
CN106055808B (en) Substation Bus Arrangement figure automatic drafting method based on SCL model file
CN103559355A (en) SVG (Scalable Vector Graphics) technology-based distribution network modeling system
CN104463715A (en) Pattern and model verifying method of distribution automation master station system and geographical information system
CN104462473A (en) Method for automatically generating CIM-G-format plant-station internal wiring diagram based on CIM-E power grid model
CN105335584A (en) Distribution network system single line drawing generation optimization device and method
CN103544352A (en) Virtual terminal connection imaging method based on security coding device (SCD) document
CN108009208A (en) A kind of quick reading of supervisory control of substation information data and analysis method
CN102209108A (en) Method and system for realizing seamless communication between master scheduling station and substation of power grid
CN103715767A (en) Smart power grid information integration and display platform
CN106294562A (en) A kind of electric network information methods of exhibiting and device
CN105046032A (en) Method and system for drawing power distribution network based on CAD
CN104201779A (en) SVG-based automatic integrated monitoring method for online monitoring data
CN102360470A (en) Information matching method and system for electric power system
CN104572153A (en) Update data conversion method for vehicle updating
CN104168138A (en) Electric power communication network system centralized topology generation and display method
CN103632307A (en) Method for checking consistency between SCD and virtual loop table of intelligent substation
CN106910143A (en) Power distribution network artwork multi-edition control method and system
CN109858182B (en) Editing and displaying technology for regulating and controlling cloud station wiring diagram based on B/S framework
CN106503298B (en) A kind of Topology connection drawing generating method of intelligent substation and device
CN106919726A (en) A kind of implementation method of distribution network engineering wiring diagram intelligent Drawing
CN102622415A (en) Synchronous transmission method for multi-platform power quality monitoring data

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Liang Ruidong

Inventor after: Liu Xiaofeng

Inventor after: Luo Zhicheng

Inventor after: Li Dening

Inventor after: Ma Yanqing

Inventor before: Chu Chenggang

Inventor before: Wen Bin

COR Change of bibliographic data
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151223